CN102116157A - 一种相邻盾构由水平并行转为上下并行掘进的施工方法 - Google Patents

一种相邻盾构由水平并行转为上下并行掘进的施工方法 Download PDF

Info

Publication number
CN102116157A
CN102116157A CN2009102477387A CN200910247738A CN102116157A CN 102116157 A CN102116157 A CN 102116157A CN 2009102477387 A CN2009102477387 A CN 2009102477387A CN 200910247738 A CN200910247738 A CN 200910247738A CN 102116157 A CN102116157 A CN 102116157A
Authority
CN
China
Prior art keywords
tunnel
grouting
driving
tunneled
slurry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2009102477387A
Other languages
English (en)
Other versions
CN102116157B (zh
Inventor
秦灏
蔡怡众
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Co Ltd
Original Assignee
Shanghai Mechanized Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Co Ltd filed Critical Shanghai Mechanized Construction Co Ltd
Priority to CN200910247738.7A priority Critical patent/CN102116157B/zh
Publication of CN102116157A publication Critical patent/CN102116157A/zh
Application granted granted Critical
Publication of CN102116157B publication Critical patent/CN102116157B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本发明涉及一种相邻盾构由水平并行转为上下并行掘进的施工方法。先进行下面一条隧道的掘进,下面一条隧道掘进完成后,用置换注浆方法,将下部隧道掘进过程中注射的惰性浆液置换成硬性浆液;然后在进行上面一条隧道的掘进,掘进时设定掘进速度,控制掘进机的前仓土压力和盾尾注浆量,盾尾注浆用惰性浆液,在隧道推进完成后再置换成硬性浆液,在上、下两条隧道掘进完成后,对交叉段及重叠段隧道的分层注浆。本发明的优点使隧道施工能够更好适应当前城市轨道交通网络化的要求,更合理的利用地下空间资源,使轨道交通各车站实现更多的“零换乘”;降低重叠段隧道施工时二次扰动对周边环境的影响,确保施工及将来地铁运营过程中上下两条隧道的安全及稳定。

Description

一种相邻盾构由水平并行转为上下并行掘进的施工方法
技术领域
本发明涉及一种相邻盾构由水平并行转为上下并行掘进的施工方法。
背景技术
随着我国城市建设步伐的加快,地铁施工正在上海、广州、深圳、南京、北京等城市如火如荼的进行,而且全国其他多个城市都在计划或准备修建地铁。像在上海这样一座大城市中,轨道交通已成为市民出行必不可少的交通工具。因此上海已加快了轨道交通建设的步伐,至2010年,将建成11条轨道交通线路,形成400公里以上的运营网络,轨道交通的日均客流量占全市公交客流总量的比重将从目前的12%增加到35%左右。这将大力缓解中心城区交通拥堵状况,确保2010年世博会的大客流量得到及时运送和疏解。由于轨道交通建设的深入,越来越多的站点将形成同站换乘,实现网络化覆盖。通过合理的利用地下空间资源,提供更加便利的换乘条件,实现真正意义上的“零换乘”,研究相邻区间隧道由水平并行转为上下并行掘进的施工技术尤为重要。
发明内容:
本发明的目的是解决同一车站同一站台实现不同线路之间的换乘在施工过程中的出现的技术难题,即二条隧道由水平并行掘进逐渐转为上下并行,并最终上下竖向进洞。本发明设计一种相邻盾构由水平并行转为上下并行掘进的施工方法,包括中间上下重叠段,两边的交叉段,其特征在于:先进行下面一条隧道的掘进,下面一条隧道掘进完成后,用置换注浆方法,将下部隧道掘进过程中注射的惰性浆液置换成硬性浆液;然后在进行上面一条隧道的掘进,掘进时设定掘进速度,控制掘进机的前仓土压力和盾尾注浆量,在上、下两条隧道掘进完成后,对交叉段及重叠段隧道的分层注浆,控制住两条隧道的后期沉降直至稳定。其特征在于:所述的置换注浆方法为待一条隧道推进完成后,先将隧道推进过程中注射的同步浆液进行置换,置换注浆采用双液浆,其中甲液为水、水泥、粉煤灰、膨润土,按重量配比100∶100∶66∶5,乙液为水玻璃,掺入比为30~50kg。置换注浆加固孔深为管片外0.5米,采用BW250泵送跳环注浆,即每两环注浆一环,每环施工5孔,每孔注浆量为400L。置换注浆的目的是让已建隧道整体趋于稳定,降低对隧道后期沉降的影响。其特征在于:上部隧道逐渐进入交叉段时,控制盾构推进速度在1cm/min,盾构掘进前仓土压力按P=k0γh进行控制,P:平衡压力(包括地下水);γ:土体的平均重度(KN/m3);h:隧道埋深(m);k0:土的侧向静止平衡压力系数。为确保盾尾间隙及时得到填充,在盾构推进过程中进行同步注浆,同步注浆采用惰性浆液,由膨润土、粉煤灰、黄砂和水组成,按重量配比为100∶400∶680∶430。其特征在于:在上、下两条隧道掘进完成后,对交叉段及重叠段隧道的分层注浆,分层注浆加固在两条隧道推进结束并完成置换注浆后进行,其加固的深度为隧道外壁1.5米范围,其目的是加强交叉及重叠段隧道周边土体强度,减少隧道的后期沉降,确保将来隧道运营的安全。重叠段隧道采用预留15个注浆孔的特殊衬砌管片,垂直加固区段,下面隧道施工15孔,上面隧道施工下半部7孔。交叉区段,上面隧道施工下半区7孔,下面隧道施工上半区8孔,分层注浆采用置换注浆法进行。本发明的优点是本发明的优点使隧道施工能够更好适应当前城市轨道交通网络化的要求,更合理的利用地下空间资源,使轨道交通各车站实现更多的“零换乘”;降低重叠段隧道施工时二次扰动对周边环境的影响,确保施工及将来地铁运营过程中上下两条隧道的安全及稳定。
附图说明
附图1-1,1-2为隧道交叉、重叠和平行段的俯视和正视示意图,附图2-1,2-2,2-3为隧道交叉、重叠段剖面图,附图3-1为对下层隧道注浆加固图,图3-2对上层隧道注浆加固图,图3-3对上下层隧道进行分层注浆加固,图中1为上隧道,2为下隧道,3为注浆层,4为分层注浆层。
下面结合实例对本发明作详细使用说明。
具体实施方式:
包括中间上下重叠段,两边的交叉段,其特征在于:先进行下面一条隧道的掘进,下面一条隧道掘进完成后,用置换注浆方法,将下部隧道掘进过程中注射的惰性浆液置换成硬性浆液;然后在进行上面一条隧道的掘进,掘进时设定掘进速度,控制掘进机的前仓土压力和盾尾注浆量,在上、下两条隧道掘进完成后,对交叉段及重叠段隧道的分层注浆,控制住两条隧道的后期沉降直至稳定。其特征在于:所述的置换注浆方法为待一条隧道推进完成后,先将隧道推进过程中注射的同步浆液进行置换,置换注浆采用双液浆,其中甲液为水、水泥、粉煤灰、膨润土,按重量配比100∶100∶66∶5,乙液为水玻璃,掺入比为30~50kg。置换注浆加固孔深为管片外0.5米,采用BW250泵送跳环注浆,即每两环注浆一环,每环施工5孔,每孔注浆量为400L。置换注浆的目的是让已建隧道整体趋于稳定,降低对隧道后期沉降的影响。其特征在于:上部隧道逐渐进入交叉段时,控制盾构推进速度在1cm/min,盾构掘进前仓土压力按P=k0γh进行控制,P:平衡压力(包括地下水);γ:土体的平均重度(KN/m3);h:隧道埋深(m);k0:土的侧向静止平衡压力系数。为确保盾尾间隙及时得到填充,在盾构推进过程中进行同步注浆,同步注浆采用惰性浆液,由膨润土、粉煤灰、黄砂和水组成,按重量配比为100∶400∶680∶430。其特征在于:在上、下两条隧道掘进完成后,对交叉段及重叠段隧道的分层注浆,分层注浆加固在两条隧道推进结束并完成置换注浆后进行,其加固的深度为隧道外壁1.5米范围,其目的是加强交叉及重叠段隧道周边土体强度,减少隧道的后期沉降,确保将来隧道运营的安全。重叠段隧道采用预留15个注浆孔的特殊衬砌管片,垂直加固区段,下面隧道施工15孔,上面隧道施工下半部7孔。交叉区段,上面隧道施工下半区7孔,下面隧道施工上半区8孔,分层注浆采用置换注浆法进行。在施工过程中,先行掘进下面一条隧道。在下面一条隧道掘进完成后,先通过置换注浆技术,将下部隧道推进过程中注射的“惰性浆液”置换成“硬性浆液”,使土体强度达到0.2~0.3Mpa,确保下面已建隧道稳定。在上部隧道隧道掘进由水平逐渐转为交叉并最终上下并行的施工过程中,通过对盾构姿态的控制、设定合理的推进速度、严格控制前仓土压力、盾尾注浆量,并辅以信息化监测,使得上部隧道在推进过程中,对周边环境的二次扰动影响降低到最低,将在建施工隧道的轴线控制在合理范围内,同时控制好下部已建隧道的变形及轴线要求在合理范围内。

Claims (4)

1.一种相邻盾构由水平并行转为上下并行掘进的施工方法,包括中间上下重叠段,两边的交叉段,其特征在于:先进行下面一条隧道的掘进,下面一条隧道掘进完成后,用置换注浆方法,将下部隧道掘进过程中注射的惰性浆液置换成硬性浆液;然后在进行上面一条隧道的掘进,掘进时设定掘进速度,控制掘进机的前仓土压力和盾尾注浆量,盾尾注浆用惰性浆液,在隧道推进完成后再置换成硬性浆液,在上、下两条隧道掘进完成后,对交叉段及重叠段隧道的分层注浆。
2.按权利要求1所述的一种相邻盾构由水平并行转为上下并行掘进的施工方法,其特征在于:所述的置换注浆方法为待一条隧道推进完成后,先将隧道推进过程中注射的同步浆液进行置换,置换注浆采用双液浆,其中甲液为水、水泥、粉煤灰、膨润土,按重量配比100∶100∶66∶5,乙液为水玻璃,掺入比为30~50kg。置换注浆加固孔深为管片外0.5米,采用泵送跳环注浆,即每两环注浆一环,每环施工5孔,每孔注浆量为400L。
3.按权利要求1所述的一种相邻盾构由水平并行转为上下并行掘进的施工方法,其特征在于:上部隧道逐渐进入交叉段时,控制盾构推进速度在1cm/min,盾构掘进前仓土压力按P=k0γh进行控制,P:平衡压力(包括地下水);γ:土体的平均重度(KN/m3);h:隧道埋深(m);k0:土的侧向静止平衡压力系数。为确保盾尾间隙及时得到填充,在盾构推进过程中进行同步注浆,同步注浆采用惰性浆液,由膨润土、粉煤灰、黄砂和水组成,按重量配比为100∶400∶680∶430。
4.按权利要求1所述的一种相邻盾构由水平并行转为上下并行掘进的施工方法,其特征在于:在上、下两条隧道掘进完成后,对交叉段及重叠段隧道的分层注浆,分层注浆加固在两条隧道推进结束并完成置换注浆后进行,其加固的深度为隧道外壁1.5米范围,重叠段隧道采用预留15个注浆孔的特殊衬砌管片,垂直加固区段,下面隧道施工15孔,上面隧道施工下半部7孔。交叉区段,上面隧道施工下半区7孔,下面隧道施工上半区8孔,分层注浆采用置换注浆法进行。
CN200910247738.7A 2009-12-30 2009-12-30 一种相邻盾构由水平并行转为上下并行掘进的施工方法 Expired - Fee Related CN102116157B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910247738.7A CN102116157B (zh) 2009-12-30 2009-12-30 一种相邻盾构由水平并行转为上下并行掘进的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910247738.7A CN102116157B (zh) 2009-12-30 2009-12-30 一种相邻盾构由水平并行转为上下并行掘进的施工方法

Publications (2)

Publication Number Publication Date
CN102116157A true CN102116157A (zh) 2011-07-06
CN102116157B CN102116157B (zh) 2014-07-30

Family

ID=44215070

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910247738.7A Expired - Fee Related CN102116157B (zh) 2009-12-30 2009-12-30 一种相邻盾构由水平并行转为上下并行掘进的施工方法

Country Status (1)

Country Link
CN (1) CN102116157B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106223969A (zh) * 2016-08-30 2016-12-14 中铁隧道勘测设计院有限公司 一种近距离上下重叠或近距离交叉盾构隧道施工方法
CN109458185A (zh) * 2018-11-22 2019-03-12 重庆大学 上下重叠交叉并行隧道盾构施工方法
CN110578525A (zh) * 2019-10-08 2019-12-17 中铁开发投资集团有限公司 重叠盾构隧道穿越运营地铁隧道微扰动施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101144384A (zh) * 2007-11-01 2008-03-19 中铁二局股份有限公司 隧道工程非爆破弱扰动开挖施工方法
WO2009002199A1 (en) * 2007-06-25 2008-12-31 Silvino Pompeu Santos Tunnel multi gallery
CN101539023A (zh) * 2008-03-21 2009-09-23 中铁二局股份有限公司 盾构机带压开仓作业施工方法
CN101603426A (zh) * 2009-07-08 2009-12-16 广东华隧建设股份有限公司 一种盾构施工中软弱地层加固的施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2009002199A1 (en) * 2007-06-25 2008-12-31 Silvino Pompeu Santos Tunnel multi gallery
CN101144384A (zh) * 2007-11-01 2008-03-19 中铁二局股份有限公司 隧道工程非爆破弱扰动开挖施工方法
CN101539023A (zh) * 2008-03-21 2009-09-23 中铁二局股份有限公司 盾构机带压开仓作业施工方法
CN101603426A (zh) * 2009-07-08 2009-12-16 广东华隧建设股份有限公司 一种盾构施工中软弱地层加固的施工方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106223969A (zh) * 2016-08-30 2016-12-14 中铁隧道勘测设计院有限公司 一种近距离上下重叠或近距离交叉盾构隧道施工方法
CN109458185A (zh) * 2018-11-22 2019-03-12 重庆大学 上下重叠交叉并行隧道盾构施工方法
CN110578525A (zh) * 2019-10-08 2019-12-17 中铁开发投资集团有限公司 重叠盾构隧道穿越运营地铁隧道微扰动施工方法

Also Published As

Publication number Publication date
CN102116157B (zh) 2014-07-30

Similar Documents

Publication Publication Date Title
CN104612698B (zh) 一种浅埋暗挖隧道上台阶中隔壁施工方法
CN110080781A (zh) 一种盾构隧道多区间、小净距、交叠下穿高架桥施工方法
CN107725060B (zh) 含复杂地质且无盾构始发场地的地铁隧道施工方法
CN103882854B (zh) 盾构连续下穿铁路与立交桥的施工方法
CN204644799U (zh) 一种四线无砟轨道路基桩板结构
CN104500082B (zh) 矿山法隧道内盾构接收施工方法
CN102606167B (zh) 浅埋暗挖隧道横向注浆导管沉降控制施工方法
CN103046933B (zh) 一种盾构过站掘进与车站平行施工方法
CN106567718B (zh) 一种复合地层单拱超大跨地铁车站拉槽支撑代换的施工方法
CN106223967B (zh) 一种大埋深矩形或类矩形隧道盾构施工装置及方法
CN102071941B (zh) 一种基于综采沿空留巷的砼块错缝纵码成墙方法
CN105019475A (zh) 预制装配整体式混凝土综合管廊及施工工法
CN108868778A (zh) 一种大型地下结构非开挖修建方法
CN103277110A (zh) 叠落式盾构隧道的施工方法
CN106703828A (zh) 采用预制装配式衬砌结合pba建造地铁车站的施工方法
CN106499417B (zh) 特大断面浅埋地铁车站预留t字岩梁岩柱施工工法
CN107905114A (zh) 一种特大跨径连续刚构拱桥的施工方法
CN104564101A (zh) 单管双层隧道同步施工方法
CN106812134A (zh) 预留远期线穿越既有线条件的素桩加固体系及其构建方法
CN103670446B (zh) 圆形引水隧洞2/3圆砼衬砌施工方法
CN108868814A (zh) 湿陷性黄土结合卵石土地层暗挖风道接盾构隧道的风井
CN109707388A (zh) 防止盾构机始发即下穿既有盾构隧道时地面塌陷的方法
CN104481555A (zh) 一种穿过软弱围岩进行钻注注浆施工的方法
CN107476351A (zh) 拼装车站预制侧墙拼装施工缝的防水方法
CN102116157B (zh) 一种相邻盾构由水平并行转为上下并行掘进的施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 201802 Shanghai City, Jiading District Nanxiang Town, Shanghai Yi Road No. 1255

Applicant after: Shanghai Mechanized Construction Group Co., Ltd.

Address before: 201802 Shanghai City, Jiading District Nanxiang Town, Shanghai Yi Road No. 1255

Applicant before: Shanghai Mechanized Construction Co., Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: SHANGHAI CITY MACHINERY CONSTRUCTION CO., LTD. TO: SHANGHAI MECHANIZED CONSTRUCTION CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140730

Termination date: 20201230

CF01 Termination of patent right due to non-payment of annual fee