CN102074921B - Method for inserting electric tubes into case in concrete wall - Google Patents

Method for inserting electric tubes into case in concrete wall Download PDF

Info

Publication number
CN102074921B
CN102074921B CN 201010571106 CN201010571106A CN102074921B CN 102074921 B CN102074921 B CN 102074921B CN 201010571106 CN201010571106 CN 201010571106 CN 201010571106 A CN201010571106 A CN 201010571106A CN 102074921 B CN102074921 B CN 102074921B
Authority
CN
China
Prior art keywords
chamber
case
fulgurite
cover plate
concrete walls
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201010571106
Other languages
Chinese (zh)
Other versions
CN102074921A (en
Inventor
赵德珺
盛浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai No2 Building Co Ltd
Original Assignee
Shanghai No2 Building Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai No2 Building Co Ltd filed Critical Shanghai No2 Building Co Ltd
Priority to CN 201010571106 priority Critical patent/CN102074921B/en
Publication of CN102074921A publication Critical patent/CN102074921A/en
Application granted granted Critical
Publication of CN102074921B publication Critical patent/CN102074921B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a method for inserting electric tubes into a case in a concrete wall. The method comprises the steps: the case is put in a hole on the concrete wall and fixed with the electric tubes, the opening of the case is higher than the concrete wall surface; a small amount of cement plaster is used to fix the case, and meanwhile the levelness of the case is adjusted; the clearances between the case and the hole are filled with cement plaster, the height of the completion surface of the cement plaster is slightly lower than the concrete surface, and the four edges of the case are formed into an inclined angle beadswith the concrete wall surface; a square frame is formed by using black cement to brush the periphery of the case within the range of 80mm; the inside of the opening of the case is plugged with a plastic cover plate, and fixing bolts are used to fix the cover plate with the case. The invention has the advantages that the repair traces on the surface can be covered, so that the attractiveness and the elegance are achieved; the levelness of the case in the wall is great; the inclined angle beads can better protect the parts of the case, which project from the wall surface; foreign matters such as cement plaster can not enter and pollute the case, so that the future wire threading is facilitated; and the plastic cover plate can be recycled.

Description

The method of splicing of chamber and fulgurite in the concrete walls
Technical field
The present invention relates to the method for splicing of the interior chamber of a kind of concrete walls and fulgurite.
Background technology
When needing to lay all kinds of chamber in the buildings in general, common employing reservation chamber position then chamber is installed and fulgurite is spliced.Chamber and fulgurite lay in the concrete, and to do fado be to lay first fulgurite and foam block watering the stage of smashing, and behind form removal, foam block taken out chamber is put into the hole of vacating, and then fulgurite and chamber is connected and fixed.Technology is first chamber and fulgurite to be fixed at present, and chamber protrudes the metope certain distance, directly the space between chamber and the hole is repaired with cement mortar, and chamber is inner uncovered or use the hardboard shutoff, then waits for next procedure.
And this kind treatment technology may produce following shortcoming:
1, chamber periphery body of wall impression quality is poor, and it is rough and uneven in surface that the cement mortar aberration reaches greatly the surface, and concrete hole limit is irregular;
2, protruding the metope chamber damages easily;
3, chamber is crooked or out-of-level easily within the walls;
4, chamber inside enters cement mortar easily, pollute chamber and cause after threading inconvenient;
5, hardboard can not be reused, and slightly has damage can cause refuse pollution.
Summary of the invention
Technical problem to be solved by this invention provides the method for splicing of the interior chamber of a kind of concrete walls and fulgurite, can remedy the above shortcoming of conventional method.
In order to solve above technical problem, the invention provides the method for splicing of the interior chamber of a kind of concrete walls and fulgurite, may further comprise the steps:
One. chamber is put into the hole of concrete walls, and fix with fulgurite, described chamber oral area is higher than described concrete wall surface;
Two. the chamber that secures the above with a small amount of cement mortar first, adjust simultaneously the levelness of described chamber;
Three. repair space between described chamber and the hole with cement mortar again, the height of described cement mortar finished surface is a little less than concrete surface, and the inclination corner protector is made in described chamber four limits and described concrete walls surface simultaneously.
Preferably, also comprise after the described step 3: four. in described chamber periphery 80mm scope, whitewash into a square frame with black cement.
Further, also comprising after the described step 4: five. described chamber oral area is inboard uses the plastic cover plate shutoff, and with set bolt described cover plate and chamber is fixed.
Preferably, the unnecessary fulgurite that enters in the step 1 in the described chamber will excise, and the fulgurite that enters described chamber is wanted vertically.
Preferably, the described chamber oral area of step 1 is higher than described concrete wall surface 8mm.
Preferably, the described inclination corner protector of step 3 is 45 °.
Preferably, rapid five described plastic cover plate thickness are 2mm, and the size of described plastic cover plate is just put into described chamber.
The present invention has the following advantages:
1, chamber perimeter walls body and function black cement whitewashes, and can hide the skin patching vestige, and is elegant in appearance.
2, the chamber levelness is high within the walls.
3,45 ° of inclination corner protectors can be good at protecting chamber protruding wall face portion.
4, chamber inside is effectively protected, and the foreign material such as cement mortar can not enter the pollution chamber, threading after being convenient to.
5, this plastic cover plate can be recycled repeatedly.
Description of drawings
Below in conjunction with the drawings and specific embodiments the present invention is described in further detail.
Fig. 1 is the schematic diagram of the method for splicing of the interior chamber of concrete walls of the present invention and fulgurite;
Fig. 2 be Fig. 1 along A-A to cutaway view.
Reference numeral among the figure is: 1, concrete; 2, chamber; 3, cement mortar; 4,45 degree inclination corner protectors; 5, bolt fixed head; 6, set bolt; 7, plastic cover plate; 8, black cement frame; 9, concrete walls surface; 10, locking nut; 11, fulgurite.
Embodiment
Such as Fig. 1, shown in 2, wait for that chamber 2 is put into the hole of concrete 1 and fulgurite 11 and fixed after, the chamber oral area will be higher than about concrete wall surface 9 about 8mm.Fix chamber 2 with a small amount of cement mortar 3 first, adjust simultaneously the levelness of chamber 2.The space of repairing between chamber 2 and the hole with cement mortar 3 again after mixing up, mortar finished surface height is a little less than concrete surface, 45 ° of inclination corner protectors 4 are made in chamber 2 four limits and concrete walls surface 9 simultaneously, then in chamber 2 peripheral 80mm scopes, whitewash into a square frame 8 with black cement, 7 shutoff of special plastic cover plate are selected in chamber 2 oral area inboards, be bolted plate 5 usefulness set bolts 6 cover plate 7 and chamber 2 are fixed.Then wait for next procedure.
Embodiment 1
After concrete blinding is removed, the foam block that is embedded in the reinforcing steel bars of wallboards is taken out, the hole periphery is cleaned out.Then with chamber 2 according to fulgurite 11 position perforates (generally be abate empty), chamber 2 is put into the hole, with locking nut 10 fulgurite 11 is fixed with it, notices entering that chamber 2 interior unnecessary fulgurites 11 will excise and the fulgurite of inlet box 2 11 is vertical; The chamber oral area will be given prominence to about concrete wall surface 9 about 8mm simultaneously.Then adjust the levelness of chamber 2, the space of filling between chamber 2 and the hole with a small amount of cement mortar 3 first, all repair with cement mortar 3 after adjust the position for the treatment of chamber 2, mortar finished surface height is a little less than concrete surface again, and 45 ° of corner protectors are made in chamber four limits and concrete walls surface 9.
Embodiment 2
Finish embodiment 1 the institute in steps after, then around chamber 2, whitewash into a square frame (black cement frame 8) with black cement in the 80mm scope, the plastic cover plate 7 about special 2mm is put in chamber oral area inboard, plastic cover plate 7 sizes are advisable just to put into chamber 2, cover plate 7 and chamber 2 are fixed with set bolt 6 by two bolts hole of chamber 2 inside at last.
The present invention has following implementation result:
1, chamber perimeter walls body and function black cement whitewashes, and can hide the skin patching vestige, and is elegant in appearance.
2, the chamber levelness is high within the walls.
3,45 ° of inclination corner protectors can be good at protecting chamber protruding wall face portion.
4, chamber inside is effectively protected, and the foreign material such as cement mortar can not enter the pollution chamber, threading after being convenient to.
5, this plastic cover plate can be recycled repeatedly.

Claims (5)

1. the method for splicing of chamber and fulgurite in the concrete walls is characterized in that, may further comprise the steps:
One. chamber is put into the hole of concrete walls, and fix with fulgurite, described chamber oral area is higher than the metope of described concrete walls;
Two. the chamber that secures the above with a small amount of cement mortar first, adjust simultaneously the levelness of described chamber;
Three. repair space between described chamber and the hole with cement mortar again, the height of described cement mortar finished surface is a little less than concrete surface, and the surface of wall of described chamber four limits and described concrete walls is made the inclination corner protector simultaneously;
Four. in described chamber periphery 80mm scope, whitewash into a square frame with black cement;
Five. described chamber oral area is inboard uses the plastic cover plate shutoff, and with set bolt described cover plate and chamber is fixed.
2. the method for splicing of chamber and fulgurite in the concrete walls as claimed in claim 1 is characterized in that the unnecessary fulgurite that enters in the step 1 in the described chamber will excise, and the fulgurite that enters described chamber wants vertical.
3. the method for splicing of chamber and fulgurite in the concrete walls as claimed in claim 1 is characterized in that the described chamber oral area of step 1 is higher than the metope 8mm of described concrete walls.
4. the method for splicing of chamber and fulgurite in a kind of concrete walls as claimed in claim 1 is characterized in that the described inclination corner protector of step 3 is 45 °.
5. the method for splicing of chamber and fulgurite in the concrete walls as claimed in claim 1 is characterized in that the described plastic cover plate thickness of step 5 is 2mm, and the size of described plastic cover plate is just put into described chamber.
CN 201010571106 2010-12-02 2010-12-02 Method for inserting electric tubes into case in concrete wall Expired - Fee Related CN102074921B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010571106 CN102074921B (en) 2010-12-02 2010-12-02 Method for inserting electric tubes into case in concrete wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010571106 CN102074921B (en) 2010-12-02 2010-12-02 Method for inserting electric tubes into case in concrete wall

Publications (2)

Publication Number Publication Date
CN102074921A CN102074921A (en) 2011-05-25
CN102074921B true CN102074921B (en) 2013-01-30

Family

ID=44033321

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010571106 Expired - Fee Related CN102074921B (en) 2010-12-02 2010-12-02 Method for inserting electric tubes into case in concrete wall

Country Status (1)

Country Link
CN (1) CN102074921B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110086112A (en) * 2019-04-01 2019-08-02 上海聚通装饰集团有限公司 A kind of wet zone power supply comb leakage preventing structure and its mounting process

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6648277B2 (en) * 2000-05-23 2003-11-18 Douglas F. De Leu Electrical conduit box mounting strap
CN201084864Y (en) * 2006-09-26 2008-07-09 徐金旺 A terminal box for wall pre-embedded pipes

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6648277B2 (en) * 2000-05-23 2003-11-18 Douglas F. De Leu Electrical conduit box mounting strap
CN201084864Y (en) * 2006-09-26 2008-07-09 徐金旺 A terminal box for wall pre-embedded pipes

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
住宅楼混凝土柱中线盒固定法;张士国等;《建筑工人》;20050228(第2期);31 *
张士国等.住宅楼混凝土柱中线盒固定法.《建筑工人》.2005,(第2期),31.
才家刚.接线盒的安装.《家庭小电工》.1999,63-65. *

Also Published As

Publication number Publication date
CN102074921A (en) 2011-05-25

Similar Documents

Publication Publication Date Title
CN208056637U (en) A kind of concrete shear force wall sealing hole device
US9255413B2 (en) Method for plastering construction in architectural decoration
CN101368444B (en) Novel profiled bar and wood combination type door, window shaping template and its installation method
CN204001662U (en) A kind of fastening devices external member of Cantilever Beams
US7311867B1 (en) Method of rapid mold development for swimming pools, spas and ponds
CN213683198U (en) Pay-off hole mold sealing device capable of being circulated
CN102074921B (en) Method for inserting electric tubes into case in concrete wall
CN107237492A (en) The installation method of sizing cylindrical form
CN204112860U (en) Detachable enclosure wall
CN205370110U (en) Constructon site fence
CN110630021A (en) One-step forming construction process for embedded distribution box
CN206737184U (en) A kind of rammed earth feature wall
CN207314830U (en) A kind of shear wall negative and positive angle construction mould
CN205857565U (en) The column mounting seat on stair provisional protection hurdle and mounting structure thereof
CN106381999A (en) Fair-faced concrete wall intaglio character die plate construction method
CN205243157U (en) Enclose fender from counter weight door plant formula
CN205743005U (en) Inflatable adjustable concrete structural slab hole to be provided construction mould
CN207829461U (en) The die device of component hole to be provided
CN113431369A (en) Ancient building wall repairing method
CN110924691A (en) Environment-friendly building construction method
CN111042414A (en) Electromechanical embedded box installation method for building floor construction supported by all-aluminum mold
CN201184026Y (en) Wall body internal wall corner protecting structure
CN113216653B (en) Construction device and construction method for sunken toilet
CN204960190U (en) Stair bone for building shape angle bead
CN212706234U (en) A sand blasting unit for imitating production of pc brick

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130130

CF01 Termination of patent right due to non-payment of annual fee