CN102071805A CN 201010613557 CN201010613557A CN102071805A CN 102071805 A CN102071805 A CN 102071805A CN 201010613557 CN201010613557 CN 201010613557 CN 201010613557 A CN201010613557 A CN 201010613557A CN 102071805 A CN102071805 A CN 102071805A
Authority
CN
China
Prior art keywords
exterior wall
reinforcements
outward
chosen
single steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010613557
Other languages
Chinese (zh)
Other versions
CN102071805B (en
Inventor
霍小妹
朱永清
张文杰
卫芷
戴斌
杨军伟
王增强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANXI GUANGYE CONSTRUCTION ENGINEERING Co.,Ltd.
Original Assignee
China Shanxi Sijian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shanxi Sijian Group Co Ltd filed Critical China Shanxi Sijian Group Co Ltd
Priority to CN 201010613557 priority Critical patent/CN102071805B/en
Publication of CN102071805A publication Critical patent/CN102071805A/en
Application granted granted Critical
Publication of CN102071805B publication Critical patent/CN102071805B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention belongs to the building construction technology, in particular a method for positioning and embedding concrete exterior wall overhung member precast reinforcements, which solves the problem of positioning of the concrete exterior wall overhung member reinforcements during construction. The method for positioning and embedding the concrete exterior wall overhung member precast reinforcements comprises the following steps that: 1, positions of embedded reinforcements are marked out on shear wall reinforcements; 2, an exterior wall overhung member is prefabricated and embedded; 3, the exterior wall overhung member is mounted; 4, concrete is poured; and 5, templates are dismantled and the reinforcements are corrected. Thus, the reinforcements are prefabricated in advance, the positions are fixed, then a specific structural design of the embedded exterior wall overhung member is adopted, further fixation is performed, so that a measure for guaranteeing stable positions of the embedded reinforcements can be formed.

Description

Concrete exterior wall is chosen the location built-in process of element precast reinforcing bar outward
 
Technical field
The invention belongs to building construction technology, specifically is the location built-in process that a kind of concrete exterior wall is chosen the member reinforcing bar outward.
Background technology
It always is exactly difficult point engineering in the construction works that concrete exterior wall is chosen the member reinforcing bar pre-buried outward, owing to concretely build and vibrate, the position of embedded bar is easy to be subjected to displacement, so the accuracy of installing always is the difficult problem in the construction.
Summary of the invention
The location built-in process that the present invention provides a kind of concrete exterior wall to choose the member reinforcing bar outward in order to solve concrete exterior wall in the construction and to choose member reinforcing bar location outward.
The present invention is realized by following technical scheme, a kind of concrete exterior wall is chosen the location built-in process of member reinforcing bar outward, step is: one, mark the embedded bar position on shear force wall reinforcing steel bar, two, prefabricated pre-buried exterior wall is chosen member outward, three, exterior wall is installed and is chosen member outward, four, concreting, five, form removal correction reinforcing bar.
Prefabricated pre-buried exterior wall is chosen the member concrete grammar outward, and pre-buried exterior wall is chosen member outward and is made up of some single steel bars, and described outer to choose the member single steel bar be three sections, and two sections of two ends are vertical with the lengths of rebar of centre respectively, and two sections at two ends are spatially vertical.Then the welding of all single steel bars of member is fixed up, it is fixing that method is that the single steel bar with element precast adopts spacer bars to weld, and the upper end of single steel bar is all staggered crooked to the centre, and the pre-buried exterior wall that forms a kind of integral body is chosen member outward.
Fixing by and position prefabricated to shifting to an earlier date of reinforcing bar like this, the structure design that adopts specific pre-buried exterior wall to choose member outward then by further fixing, can form a measure that guarantees the embedded bar position stability again.
Description of drawings
Fig. 1 is the described structural representation of step 1
Fig. 2 is single reinforcing bar perspective view
Fig. 3 chooses the member perspective view outward for pre-buried exterior wall
Fig. 4 is the structural representation that installs
Among the figure: 1-body of wall reinforcing bar, the accurate position of 2-absolute altitude, 3-single steel bar, 4-spacer bars, 5-solder joint, 6-are chosen the transverse reinforcement of member upper end, and 7-chooses the reinforcing bar of the lower end of member outward.
The specific embodiment
The present invention is described in detail below in conjunction with accompanying drawing,
One, on shear force wall reinforcing steel bar, mark the embedded bar position, as schematically shown in Figure 1, after 1 colligation of body of wall reinforcing bar finishes, the accurate position 2 of out choosing the absolute altitude of member reinforcing bar at shear wall vertical reinforcement subscript.
Two, prefabricated pre-buried exterior wall is chosen member outward, and pre-buried exterior wall is chosen member outward and is made up of some single steel bars, and as schematically shown in Figure 2, described outer to choose member single steel bar 3 be three sections, and two sections of two ends are vertical with the lengths of rebar of centre respectively, and two sections at two ends are spatially vertical.Then all single steel bar 3 welding of member are fixed up, method is that the single steel bar 3 with element precast adopts spacer barss 4 to weld fixing, and the upper end of single steel bar is all staggered crooked to the centre, and the pre-buried exterior wall that forms a kind of integral body is as shown in Figure 3 chosen member outward.
Three, exterior wall is installed and is chosen the member reinforcing bar outward, the wall reinforcing bar tie up 1 prick finish after, position according to mark vertically is placed into the prefabricated pre-buried outer reinforcing bar 7 of choosing the lower end of member in the body of wall reinforcing bar, and adopt welding and colligation and body of wall reinforcing bar to fix, must adopt spacer bars 4 and reinforcing bar 1 welding is fixing within the walls, guarantee not to be subjected to displacement, then matched moulds
Four, external member concreting.
Five, as schematically shown in Figure 4, form removal correction reinforcing bar after the concreting form removal, is chosen pre-buried exterior wall outward the transverse reinforcement 6 of member upper end one by one and is pulled directly, carries out the outer member reinforcing bar binding of choosing.Because closeer at bar bending place reinforcing bar, with reinforcing bar pull straight after, can stay groove at metope, when this groove can be easy to external member concreting and metope connect stubble better.

Claims (1)

1. a concrete exterior wall is chosen the location built-in process of member reinforcing bar outward, and it is characterized in that: step is: one, mark the embedded bar position on shear force wall reinforcing steel bar, two, prefabricated pre-buried exterior wall chooses member outward, three, exterior wall is installed and is chosen member outward, four, concreting, five, form removal correction reinforcing bar
Prefabricated pre-buried exterior wall is chosen the member concrete grammar outward, pre-buried exterior wall is chosen member outward and is made up of some single steel bars, choosing the member single steel bar outside described is three sections, two sections of two ends are vertical with the lengths of rebar of centre respectively, two sections at two ends are spatially vertical, then all single steel bar welding of member are fixed up, method is to adopt spacer bars to weld fixing the single steel bar of element precast, and the upper end of single steel bar is all staggered crooked to the centre, and the pre-buried exterior wall that forms a kind of integral body is chosen member outward.
CN 201010613557 2010-12-30 2010-12-30 Method for positioning and embedding concrete exterior wall overhung member precast reinforcements Active CN102071805B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010613557 CN102071805B (en) 2010-12-30 2010-12-30 Method for positioning and embedding concrete exterior wall overhung member precast reinforcements

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010613557 CN102071805B (en) 2010-12-30 2010-12-30 Method for positioning and embedding concrete exterior wall overhung member precast reinforcements

Publications (2)

Publication Number Publication Date
CN102071805A true CN102071805A (en) 2011-05-25
CN102071805B CN102071805B (en) 2012-07-04

Family

ID=44030545

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010613557 Active CN102071805B (en) 2010-12-30 2010-12-30 Method for positioning and embedding concrete exterior wall overhung member precast reinforcements

Country Status (1)

Country Link
CN (1) CN102071805B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103821166A (en) * 2014-02-24 2014-05-28 中天建设集团有限公司 Method for locating steel bars of basement outer wall
CN109736575A (en) * 2018-12-09 2019-05-10 山东泰安建筑工程集团有限公司 A kind of building cast-in-situ layer and preformed layer grouting connection reserved steel bar Exact Location Method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL8801217A (en) * 1988-05-09 1989-12-01 Alfonsus Maria Van Gurp Formation system for two concrete walls - fits fulcrum pieces in recesses round bars before bending straight
CN101538896A (en) * 2009-04-03 2009-09-23 标力建设集团有限公司 Construction method for jettied structure at high attitude of high-rise building
CN201317982Y (en) * 2008-11-25 2009-09-30 天津开发区福林发展有限公司 Single cavity gypse insulation board and connection structure between insulation board and construction main body

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL8801217A (en) * 1988-05-09 1989-12-01 Alfonsus Maria Van Gurp Formation system for two concrete walls - fits fulcrum pieces in recesses round bars before bending straight
CN201317982Y (en) * 2008-11-25 2009-09-30 天津开发区福林发展有限公司 Single cavity gypse insulation board and connection structure between insulation board and construction main body
CN101538896A (en) * 2009-04-03 2009-09-23 标力建设集团有限公司 Construction method for jettied structure at high attitude of high-rise building

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《石家庄铁路职业技术学院学报(增刊)》 20070630 杨志良 混凝土悬挑结构中钢筋移位的预防与处理 25-27 1 第6卷, 2 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103821166A (en) * 2014-02-24 2014-05-28 中天建设集团有限公司 Method for locating steel bars of basement outer wall
CN109736575A (en) * 2018-12-09 2019-05-10 山东泰安建筑工程集团有限公司 A kind of building cast-in-situ layer and preformed layer grouting connection reserved steel bar Exact Location Method

Also Published As

Publication number Publication date
CN102071805B (en) 2012-07-04

Similar Documents

Publication Publication Date Title
CN106121094B (en) The precast concrete shell structure of concrete shear force wall based on 3D printing
CN106906955B (en) Shear wall integral prefabricated reinforcement mesh structure and construction method thereof
CN105155683A (en) Prefabricated beam-column connection in prefabricated concrete buildings and construction method thereof
KR101228593B1 (en) Composite girder using inner molding member and bridge construction method therwith
CN104775553A (en) Novel L-shaped edge member for superimposed slab shear walls and connecting method for novel L-shaped edge member
KR101478131B1 (en) Construction Method of Precast Pier
CN111379219A (en) Assembly type bridge pier column and bearing platform connecting structure and construction method thereof
KR20140012805A (en) The bi-prestressed concrete u-type girder and its construction method
KR101186053B1 (en) Method of Constructing Insitu Concrete Beam Using Preinstalled Precast Concrete Slab
CN102071805B (en) Method for positioning and embedding concrete exterior wall overhung member precast reinforcements
CN104727552A (en) Construction method for reserving water feed pipe grooves in prefabricated shear wall
KR101196874B1 (en) Girder making methos for precast end seggement using end mold and girder therewith
CN109208823B (en) Quick-assembly built-in steel box type concrete filled steel tube column and production process thereof
CN103711065B (en) Cantilever construction Composite Steel-Concrete Bridges and construction method thereof
KR20140110490A (en) Half precast concrete column manufacturing method using prefabricated PC panels and constructing method using the same
KR200393006Y1 (en) Connection structure of precast concrete using fiber reinforced plastics construction
CN204385921U (en) Clear-water concrete wall column joint bar fastening devices
CN111042442A (en) Precast concrete hollow component and preparation method thereof
KR100735681B1 (en) Thick wall using truss decks as permanent concrete form
CN104947853A (en) Built-in stand type cast-in-place reinforced concrete pillar and construction method
CN102092096B (en) Method for fixing pre-stressed hose of precast beam
KR20120091934A (en) Method for connecting between precast concrete columns in construction layer using headed reinforcement
CN204551824U (en) A kind of Novel L-shaped overlaid plate type shear wall edge member
CN103352568A (en) Method for building constructional column on foundation pad
KR100665246B1 (en) Precast concrete connection structure using Fiber Reinforced Plastics construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Zhang Wenjie

Inventor after: Zhu Yongqing

Inventor after: Huo Xiaomei

Inventor after: Wei Zhi

Inventor after: Dai Bin

Inventor after: Yang Junwei

Inventor after: Wang Zengqiang

Inventor before: Huo Xiaomei

Inventor before: Zhu Yongqing

Inventor before: Zhang Wenjie

Inventor before: Wei Zhi

Inventor before: Dai Bin

Inventor before: Yang Junwei

Inventor before: Wang Zengqiang

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: HUO XIAOMEI ZHU YONGQING ZHANG WENJIE WEI ZHI DAI BIN YANG JUNWEI WANG ZENGQIANG TO: ZHANG WENJIE ZHU YONGQING HUO XIAOMEI WEI ZHI DAI BIN YANG JUNWEI WANG ZENGQIANG

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200511

Address after: 030006 Shanxi Province, Taiyuan city district and State Road two West Lane No. 8

Patentee after: SHANXI GUANGYE CONSTRUCTION ENGINEERING Co.,Ltd.

Address before: 030012 No. 7 sports North Street, Shanxi, Taiyuan

Patentee before: CHINA SHANXI SIJIAN GROUP Co.,Ltd.