CN102071771A - Building waste residue sintering-free embedded pipeline groove brick and using method thereof - Google Patents

Building waste residue sintering-free embedded pipeline groove brick and using method thereof Download PDF

Info

Publication number
CN102071771A
CN102071771A CN2010105903054A CN201010590305A CN102071771A CN 102071771 A CN102071771 A CN 102071771A CN 2010105903054 A CN2010105903054 A CN 2010105903054A CN 201010590305 A CN201010590305 A CN 201010590305A CN 102071771 A CN102071771 A CN 102071771A
Authority
CN
China
Prior art keywords
brick
groove
waste residue
building waste
grooving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010105903054A
Other languages
Chinese (zh)
Other versions
CN102071771B (en
Inventor
周强
廖晓东
谢惠庆
康清泉
吴贵君
杨火安
黄义龙
戴纪文
马驰
汪华双
曾俊卿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu No4 Construction Engineering Co
Original Assignee
Chengdu No4 Construction Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu No4 Construction Engineering Co filed Critical Chengdu No4 Construction Engineering Co
Priority to CN2010105903054A priority Critical patent/CN102071771B/en
Publication of CN102071771A publication Critical patent/CN102071771A/en
Application granted granted Critical
Publication of CN102071771B publication Critical patent/CN102071771B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a building waste residue sintering-free embedded pipeline groove brick and a using method thereof, which belong to the technical field of wall body bricks and installation technology thereof. The pipeline groove brick comprises a brick body, wherein the brick body is provided with a groove; the end part of the groove is provided with a preserved layer; and the thickness of the preserved layer does not surpass 8 millimeters. Moreover, a method for installing a conduit on the brick body by using the groove brick is provided. The pipeline groove brick can be taken as an ordinary wall building brick as well as the building waste residue sintering-free embedded pipeline groove brick which is matched with a pipeline; simultaneously, the pipeline groove brick is convenient to transport, a small number of building wastes is produced, a small amount of flying dust is produced, construction efficiency is high, energy is saved and environment is protected; and the pipeline groove brick is particularly suitable for wall body construction occasions for assembling pipelines.

Description

The unburned knot preheating embedding line of building waste residue groove brick and using method thereof
Technical field
The present invention relates to a kind of brick of building a wall, the especially a kind of unburned knot preheating embedding line of building waste residue groove brick of being convenient to spool installation on the body of wall the invention still further relates to a kind of method of utilizing the unburned knot preheating embedding line of described building waste residue groove brick groove brick that spool is installed on masonry.
Background technology
Secretly joining the conventional job practices of laying PVC conduit and switch enclosure socket box on the brick wall be: adopt cutting machine cutting tube seat and junction box hole after laying bricks, fill floating groove, hole with mortar again after the pipe arrangement peace box.Along with a large amount of hollow brick and 100mm one brick walls of using on the highrise building, make that showing shortcoming day of this construction technology is outstanding: (1) wire casing is scattered in each room of each layer of whole building, line, cutting, slagging-off, overlap joint power supply, carrying utensil etc. expend a large amount of manually, material and the energy; (2) the big pollution of grooving dust is heavy on the brick wall; (3) uniformity of the grooving size depth is difficult to control, and influences architecture quality easily; (4) hollow brick endoporus space is bigger, and it is very difficult to cause civil engineering to be plastered; The junction of smearing cement mortar and brick body (5) is easy to generate the crack influences construction quality etc.
Also had employing to concentrate the brick grooving on construction ground afterwards, the wall body structure quality is improved, but efficiency of construction is still not high, at first needs to calculate according to the amount of spool the quantity of the on-the-spot clip of needs, expends man-hour, and needs the facility of the on-the-spot grooving of configuration.
Summary of the invention
The purpose of this invention is to provide and a kind ofly not only be convenient to dispose spool, but also be convenient to the unburned knot preheating embedding line of the building waste residue groove brick that transports and install.Another object of the present invention is to provide the using method of the unburned knot preheating embedding line of building waste residue groove brick.
Technical scheme of the present invention is: the unburned knot preheating embedding line of a kind of building waste residue groove brick, comprise the brick body, and described brick body is provided with grooving, and the end of described grooving is provided with reserves layer, and the described thickness of reserving layer is no more than 8mm.The unburned knot preheating embedding line of this building waste residue groove brick that is arranged so that of this reservation layer structure has two kinds of functions, both can work as the common brick of building a wall and use, and also can be used for being equipped with pipeline and line box.
The bottom of described grooving is provided with the surface course that flushes with brick body bottom surface.The architectural feature of this surface course is convenient to when building a wall, and is convenient to plaster.
Described reservation layer and grooving junction surface and with the corresponding reservation in this junction surface layer relative groove that is provided with of end face.
Groove adopts V-structure, and the groove groove that is oppositely arranged on described reservation layer point spacing is no more than 4mm.The function of V-type groove structure is to be convenient to the reservation layer is knocked out in pipe laying.
The length of described grooving is no more than half of brick body.Can guarantee the load-carrying properties of brick like this.
Distance between the sidewall of described grooving and the brick body sidewall is not less than 20mm.Can guarantee the load-carrying properties of brick like this.
Described brick body or be solid brick, or be hollow brick.Can select as required.
Described grooving is a U type groove.Be convenient to install spool.
Another technical scheme of the present invention is that the using method of the unburned knot preheating embedding line of building waste residue groove brick comprises following construction sequence:
According to electrical installation drawing spool is installed on masonry;
At the masonry position that does not have spool, directly adopt the unburned knot preheating embedding line of building waste residue groove masonry walls; At the position that has spool to pass through, the reservation layer with the unburned knot preheating embedding line of building waste residue groove brick knocks out earlier, makes it form the grooving brick, makes the grooving cover of groove brick build in spool position formation body of wall then, and spool is interspersed in the groove of U type groove brick;
The U type groove cell body part of U type groove brick is filled and led up, is tamped with masonry mortar.
Technique effect of the present invention is:
(1) one brick is dual-purpose: not only can work as the common brick of building a wall and use, can also work as the unburned knot preheating embedding line of building waste residue groove brick and use with equipped pipeline.
(2) efficiency of construction height, the present invention can directly build a wall when common brick uses; When the unburned knot preheating embedding line of building waste residue groove brick uses, only need knock gently and can knock out, need not special grooving tool and carry out grooving, thereby accelerate the speed of building a wall greatly reserving layer.
(3) energy-conserving and environment-protective: the present invention is convenient to loading and unloading when transportation, can not cause that the brick body damages because of the grooving collision in the transportation; In work progress, the present invention does not have the slag of building and produces when common brick uses, and generation will be reserved a layer minute quantity of removing and build slag when the unburned knot preheating embedding line of building waste residue groove brick uses, and save and build the slag cost of transportation, and the airborne dust of constructing simultaneously is few.
(4) job practices of the present invention is easy, civil engineering is with install all can accelerating construction progress, has reduced operation (reduced conventional constructure scheme at grooving on the masonry or cut the working procedure of " U " shape groove on fragment of brick).
(5) quality and benifit and economic benefit are obvious, on the brick wall pipe arrangement by the past after mechanical slotting on the body of wall changes the mode that adopts groove brick of the present invention into, wire casing has become interior " closed " of body of wall by " open " of body of wall outside on the body of wall, guaranteed the wall body structure quality, eliminated the common quality defect of building structure wall crazing, hollowing and consume material, both increased the body of wall aesthetic property, improved workmanship again, saved cost, reduced because of the dust that the cutting cell body produces, the environment pollution of building slag.
Description of drawings
The present invention will illustrate by example and with reference to the mode of accompanying drawing, wherein:
Fig. 1 is the structural representation of the embodiment of the invention 1;
Fig. 2 is the sectional view of Fig. 1;
Fig. 3 is Figure 1A place partial enlarged drawing;
Fig. 4 is the structural representation of the embodiment of the invention 2;
Wherein, be labeled as figure: 1 is the brick body, and 2 is grooving, and 3 for reserving layer, and 4 is groove, and 5 is surface course.
The specific embodiment
Embodiment 1
As Fig. 1, Fig. 2, shown in Figure 3, the unburned knot preheating embedding line of a kind of building waste residue groove brick comprises brick body 1, and this brick body adopts the solid brick body, described brick body 1 is provided with grooving 2, described grooving 2 is a U type groove, and in order to guarantee the functional performance of brick body, the length of grooving 2 is no more than half of brick body 1, grooving 2 is positioned at the middle part of brick body width, the end of described grooving 2 is provided with reserves layer 3, and the bottom of described grooving 2 is provided with the surface course 5 that flushes with brick body 1 bottom surface, and surface course 5 is effects of being convenient to plaster.For the load-carrying properties that can guarantee brick body 1 are convenient to again knock out fast, the described thickness of reserving layer 3 is no more than 8mm.The effect of reserving layer has: be convenient to transportation; Keep a reservation layer brick body and can work as the common brick use of building a wall; Knock out a reservation layer brick body and can work as the use of the unburned knot preheating embedding line of building waste residue groove brick.Described reservation layer 3 is provided with V-structure groove 4 with grooving 2 junction surfaces, described junction surface extends to the described position of reserving layer 3 end face and is provided with V-structure groove 4 relatively, and the described groove 4 grooves point spacing b that is oppositely arranged on the layer 3 that reserves is no more than 4mm (as shown in Figure 3).The described V-structure groove 4 of reserving layer 3 is that the brick body is convenient to the reservation layer is removed when the unburned knot preheating embedding line of building waste residue groove brick uses, plays a part to cut in advance.
Utilize the method that spool is installed of the unburned knot preheating embedding line of the described building waste residue of present embodiment groove brick on masonry, comprise following construction sequence:
According to electrical installation drawing spool is installed on masonry;
At the masonry position that does not have spool, directly adopt the unburned knot preheating embedding line of building waste residue groove masonry walls; At the position that has spool to pass through, the reservation layer with the unburned knot preheating embedding line of building waste residue groove brick knocks out earlier, makes it form the grooving brick, makes the grooving cover of groove brick build in spool position formation body of wall then, and spool is interspersed in the groove of U type groove brick;
The U type groove cell body part of U type groove brick is filled and led up, is tamped with masonry mortar.
On the brick wall pipe arrangement by the past after mechanical slotting on the body of wall changes the mode that adopts patent groove brick into, quality and benifit and economic benefit are all very obvious.Wire casing has become interior " closed " of body of wall by " open " of body of wall outside on the body of wall, not only avoid tick slot and filled up the program of groove with compo, and increased the body of wall aesthetic property, more stopped the common quality defect of spool, line box body of wall position vertical cracking hollowing, the overall structure quality improves greatly, through measuring and calculating, is example with work items Chengdu Jin Jiang River City Garden engineering, hookup wire box, spool on the brick wall body, overall economic efficiency saving: 2.34 yuan/m 2
Figure BDA0000038531810000051
Figure BDA0000038531810000071
Embodiment 2
As shown in Figure 4, the unburned knot preheating embedding line of a kind of building waste residue groove brick, comprise brick body 1, this brick body adopts the hollow brick body, and described brick body 1 is provided with grooving 2, in order to guarantee the functional performance of brick body, the length of grooving 2 is no more than half of brick body 1, is not less than 20mm apart from a between the sidewall of grooving 2 and brick body 1 sidewall, and the end of described grooving 2 is provided with reserves layer 3, the bottom of described grooving 2 is provided with the surface course 5 that flushes with brick body 1 bottom surface, and surface course 5 is effects of being convenient to plaster.For the load-carrying properties that can guarantee brick body 1 are convenient to again knock out fast, the described thickness of reserving layer 3 is no more than 8mm.The effect of reserving layer has: be convenient to transportation; Keep a reservation layer brick body and can work as the common brick use of building a wall; Knock out a reservation layer brick body and can work as the use of the unburned knot preheating embedding line of building waste residue groove brick.Described reservation layer 3 is provided with V-structure groove 4 with grooving 2 junction surfaces, described junction surface extends to the described position of reserving layer 3 end face and is provided with V-structure groove 4 relatively, and the described groove 4 grooves point spacing b that is oppositely arranged on the layer 3 that reserves is no more than 4mm (as shown in Figure 3) and is no more than 4mm.The described V-structure groove 4 of reserving layer 3 is that the brick body is convenient to the reservation layer is removed when the unburned knot preheating embedding line of building waste residue groove brick uses, plays a part to cut in advance.Need to prove that the grooving structure of present embodiment is with embodiment 1.
Disclosed all features in this manual, or the step in disclosed all methods or the process except mutually exclusive feature and/or step, all can make up by any way.
Disclosed arbitrary feature in this manual (comprising any accessory claim, summary and accompanying drawing) is unless special narration all can be replaced by other equivalences or the alternative features with similar purpose.That is, unless special narration, each feature is an example in a series of equivalences or the similar characteristics.
The present invention is not limited to the aforesaid specific embodiment.The present invention expands to any new feature or any new combination that discloses in this manual, and the arbitrary new method that discloses or step or any new combination of process.

Claims (9)

1. the unburned knot preheating embedding line of building waste residue groove brick comprises brick body (1), and described brick body (1) is provided with grooving (2), it is characterized in that, the end of described grooving (2) is provided with reserves layer (3), and the described thickness of reserving layer (3) is no more than 8mm.
2. the unburned knot preheating embedding line of building waste residue according to claim 1 groove brick is characterized in that the bottom of described grooving (2) is provided with the surface course (5) that flushes with brick body bottom surface.
3. the unburned knot preheating embedding line of building waste residue according to claim 1 and 2 groove brick is characterized in that, described reservation layer (3) and grooving (2) junction surface and with the corresponding reservation in this junction surface layer relative groove (4) that is provided with of (3) end face.
4. the unburned knot preheating embedding line of building waste residue according to claim 3 groove brick is characterized in that, described groove (4) adopts V-structure, and groove (4) groove that is oppositely arranged on the described reservation layer (3) point spacing is no more than 4mm.
5. the unburned knot preheating embedding line of building waste residue according to claim 4 groove brick is characterized in that the length of described grooving (2) is no more than half of brick body (1).
6. the unburned knot preheating embedding line of building waste residue according to claim 5 groove brick is characterized in that the distance between the sidewall of described grooving (2) and brick body (1) sidewall is not less than 20mm.
7. the unburned knot preheating embedding line of building waste residue according to claim 6 groove brick is characterized in that, described brick body (1) or be solid brick, or be hollow brick.
8. the unburned knot preheating embedding line of building waste residue according to claim 7 groove brick is characterized in that described grooving (2) is a U type groove.
9. a using method of utilizing any unburned knot preheating embedding line of the described building waste residue groove brick of claim 1-8 is characterized in that, comprises following construction sequence:
According to electrical installation drawing spool is installed on masonry;
At the masonry position that does not have spool, directly adopt the unburned knot preheating embedding line of building waste residue groove masonry walls; At the position that has spool to pass through, the reservation layer with the unburned knot preheating embedding line of building waste residue groove brick knocks out earlier, makes it form the grooving brick, makes the grooving cover of groove brick build in spool position formation body of wall then, and spool is interspersed in the groove of U type groove brick;
The U type groove cell body part of U type groove brick is filled and led up, is tamped with masonry mortar.
CN2010105903054A 2010-12-15 2010-12-15 Building waste residue sintering-free embedded pipeline groove brick and using method thereof Active CN102071771B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105903054A CN102071771B (en) 2010-12-15 2010-12-15 Building waste residue sintering-free embedded pipeline groove brick and using method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105903054A CN102071771B (en) 2010-12-15 2010-12-15 Building waste residue sintering-free embedded pipeline groove brick and using method thereof

Publications (2)

Publication Number Publication Date
CN102071771A true CN102071771A (en) 2011-05-25
CN102071771B CN102071771B (en) 2012-10-31

Family

ID=44030511

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105903054A Active CN102071771B (en) 2010-12-15 2010-12-15 Building waste residue sintering-free embedded pipeline groove brick and using method thereof

Country Status (1)

Country Link
CN (1) CN102071771B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103306420A (en) * 2013-07-09 2013-09-18 成都市第四建筑工程公司 Slotted perforated brick
CN104234296A (en) * 2013-06-18 2014-12-24 成都市第四建筑工程公司 Grooved brick and production method and on-site bricklaying method thereof
CN104405130A (en) * 2014-12-15 2015-03-11 陕西省建筑科学研究院 Method for preventing masonry rear embedded wire tube position from cracking
CN112343242A (en) * 2020-12-03 2021-02-09 中建一局集团建设发展有限公司 Pipe wrapping device for wrapping electromechanical wire pipes by using masonry structure and construction method of pipe wrapping device

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS518305A (en) * 1974-07-10 1976-01-23 Sachihiro Matsumoto
CN2455807Y (en) * 2001-01-02 2001-10-24 张志军 Multifunctional hollow cement blocks for construction
CA2481182A1 (en) * 2004-10-07 2006-04-07 Bela Bill Szoke Block building system to resist earthquake damages
KR100581409B1 (en) * 2003-12-29 2006-05-23 (주) 종합건축사사무소 동일건축 groove block for electric wire and pipe laying
CN2923873Y (en) * 2006-06-27 2007-07-18 武汉理工大学 Multi-purpose brick with slot
US20080047219A1 (en) * 2006-07-19 2008-02-28 E.K.B. Designs, Ltd. Molded construction blocks having integrally molded knock-outs for creation of openings for electrical blocks and associated methods
KR100867761B1 (en) * 2007-05-23 2008-11-10 한가람건설 주식회사 Brick
CN201874140U (en) * 2010-12-15 2011-06-22 成都市第四建筑工程公司 Pre-embedded wall chase brick free of sintering building waste residues

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS518305A (en) * 1974-07-10 1976-01-23 Sachihiro Matsumoto
CN2455807Y (en) * 2001-01-02 2001-10-24 张志军 Multifunctional hollow cement blocks for construction
KR100581409B1 (en) * 2003-12-29 2006-05-23 (주) 종합건축사사무소 동일건축 groove block for electric wire and pipe laying
CA2481182A1 (en) * 2004-10-07 2006-04-07 Bela Bill Szoke Block building system to resist earthquake damages
CN2923873Y (en) * 2006-06-27 2007-07-18 武汉理工大学 Multi-purpose brick with slot
US20080047219A1 (en) * 2006-07-19 2008-02-28 E.K.B. Designs, Ltd. Molded construction blocks having integrally molded knock-outs for creation of openings for electrical blocks and associated methods
KR100867761B1 (en) * 2007-05-23 2008-11-10 한가람건설 주식회사 Brick
CN201874140U (en) * 2010-12-15 2011-06-22 成都市第四建筑工程公司 Pre-embedded wall chase brick free of sintering building waste residues

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104234296A (en) * 2013-06-18 2014-12-24 成都市第四建筑工程公司 Grooved brick and production method and on-site bricklaying method thereof
CN103306420A (en) * 2013-07-09 2013-09-18 成都市第四建筑工程公司 Slotted perforated brick
CN103306420B (en) * 2013-07-09 2015-06-10 成都市第四建筑工程公司 Slotted perforated brick
CN104405130A (en) * 2014-12-15 2015-03-11 陕西省建筑科学研究院 Method for preventing masonry rear embedded wire tube position from cracking
CN112343242A (en) * 2020-12-03 2021-02-09 中建一局集团建设发展有限公司 Pipe wrapping device for wrapping electromechanical wire pipes by using masonry structure and construction method of pipe wrapping device

Also Published As

Publication number Publication date
CN102071771B (en) 2012-10-31

Similar Documents

Publication Publication Date Title
CN103758272B (en) Autoclaved aerated concrete blocks built-in wall steel pipe buried in advance construction method
CN103321436B (en) Pre-installation construction method for wire box on building bricked body and pre-installation supporting frame thereof
CN102071771B (en) Building waste residue sintering-free embedded pipeline groove brick and using method thereof
CN103061515A (en) Method for perforating and pre-burying polyvinyl chloride (PVC) wiring tubes in concrete hollow block filled walls
CN201474110U (en) Heat insulation system in compound heat insulation keel
CN204001270U (en) A kind of reinforced concrete wall and masonry wall syndeton
CN201713979U (en) Novel light wall body brick with male and female sleeve
CN203947667U (en) Autoclaved aerated concrete slabs
CN203334306U (en) Self-embedding type retaining wall
CN201874140U (en) Pre-embedded wall chase brick free of sintering building waste residues
CN204252367U (en) Air-conditioning duct wears the lightweight precast concrete component of building block exterior wall
CN202152539U (en) Plastic building template
CN202280193U (en) Aerated concrete building block suitable for building construction technology
CN210659110U (en) Assembly type overhead ground installation system of ceramic tile concrete composite board
CN211037664U (en) Stone material ground and ceramic tile ground handing-over department node structure
CN203452335U (en) Water and electricity installation structure for constructional engineering
CN104565557B (en) A kind of dustproof wall bushing
CN204387499U (en) The water power piping network installation device of indoor integrated finishing
CN102352680A (en) Enclosing and insulating integral wall plate
CN202401824U (en) Fence coping structure
RU139253U1 (en) BUILDING BLOCK INSERT (SPECIFICATIONS)
CN105952117A (en) Seam sealing tool for prefabricated concrete external wall heat insulation plate and application method thereof
CN105735547B (en) A kind of walling unit and the wall assembly construction method based on the walling unit
CN205259430U (en) Install special building block
CN208518183U (en) Assembled type pipe prefabricated components

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant