CN102061727A - Disposable embedded floor drain for drainage in building engineering and construction method thereof - Google Patents

Disposable embedded floor drain for drainage in building engineering and construction method thereof Download PDF

Info

Publication number
CN102061727A
CN102061727A CN2010105899415A CN201010589941A CN102061727A CN 102061727 A CN102061727 A CN 102061727A CN 2010105899415 A CN2010105899415 A CN 2010105899415A CN 201010589941 A CN201010589941 A CN 201010589941A CN 102061727 A CN102061727 A CN 102061727A
Authority
CN
China
Prior art keywords
floor drain
construction work
disposable pre
outer tube
buried floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010105899415A
Other languages
Chinese (zh)
Inventor
周强
廖晓东
谢惠庆
康清泉
吴贵君
杨火安
黄义龙
戴纪文
马驰
汪华双
曾俊卿
魏鑫
田川
刘宏
刘西
郭建
何贤敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu No4 Construction Engineering Co
Original Assignee
Chengdu No4 Construction Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu No4 Construction Engineering Co filed Critical Chengdu No4 Construction Engineering Co
Priority to CN2010105899415A priority Critical patent/CN102061727A/en
Publication of CN102061727A publication Critical patent/CN102061727A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a disposable embedded floor drain for drainage in architectural engineering and a construction method thereof, which belong to the technical field of embedded parts for architectural engineering and a construction technology thereof. The disposable embedded floor drain for drainage in architectural engineering comprises an outer tube, wherein an inner tube is arranged inside the outer tube; the lower end of the inner tube and the lower end of the outer tube are flush with each other and closed to form a circular chamber; the height of the inner tube is less than that of the outer tube; and a connecting support is arranged on the outside of a bottom edge of the outer tube, and provided with a fixing hole. The invention also relates to the construction method for the embedded floor drain. Due to the one-time installation forming of the disposable embedded floor drain for drainage in architectural engineering, the construction process is greatly simplified; the construction efficiency is improved; and the construction cost is reduced. As no construction residue is produced in the construction process, the energy is saved. Moreover, the connection between the embedded floor drain and a bottom die is more reliable, and the connection between the embedded floor drain and in-situ concrete is tighter, consequently the water seepage problem is effectively avoided. The construction method for the embedded floor drain is particularly suitable for the construction of the disposable embedded floor drain for drainage in architectural engineering under the cast-in-situ condition of the architectural engineering.

Description

Disposable pre-buried floor drain of construction work draining and job practices thereof
Technical field
The present invention relates to a kind of joint that connects sewerage system and ground, reach the job practices of this joint in a kind of construction work concrete cast-in-situ floor.
Background technology
Floor drain is the important interface that connects sewerage system and flooring, and as the vitals of drainage system in the dwelling house, its performance quality directly influences the quality of room air, and is extremely important to the control of the peculiar smell between bathroom.The method that floor drain is installed at present remains and reserve the floor drain installing hole in work progress, after drainage pipe installs, floor drain is put into the reservation installing hole, and drainage pipe is inserted end interface under the floor drain, with white cement the slit between floor drain and outer wall and the tube wall is tamped then.This method not only expends man-hour, and causes leakage easily.
The method that generally adopts for the piping erection of cast-in-situ floor is: first service sleeve, remove sleeve pipe again cast-in-place finishing, in the preformed hole of again pipeline being packed into, at last with the slit secondary joint filling between pipeline and the hole wall.Not only the working procedure complexity is various for this method, and the material and the facility that adopt are more, does not meet the developing direction of construction work energy-conserving and environment-protective.
Summary of the invention
One of purpose of the present invention provide a kind of easy construction, cost lower, can effectively prevent the disposable pre-buried floor drain of the construction work draining of leaking.Another purpose of the present invention just provide a kind of in cast-in-situ floor construction the built-in fitting once mounting finish, need not the job practices of the disposable pre-buried floor drain of construction work draining of secondary joint filling.
One of technical scheme of the present invention is: the disposable pre-buried floor drain of a kind of construction work draining, comprise outer tube, be provided with interior pipe in the described outer tube, the pipe lower end flushes with the outer tube lower end and enclosed shape chamber circlewise in described, the pipe height is less than the outer tube height in described, described inner tube wall is provided with at least one and is used for the ring-shaped step that the lower end connects the gutter axial limiting, and the described outer tube bottom margin outside is provided with the connection bearing, connects bearing and is provided with fixing hole.
Described connection bearing has three, and described three connection bearings are symmetrically distributed about the outer axial tube center.The triangle symmetrical distribution structure that connects bearing has improved the reliability that is connected between pre-buried floor drain and the bed die greatly, makes pre-buried floor drain position in concrete cast-in-situ can not be offset; The triangle symmetrical distribution structure that connects bearing has significantly reduced the contact area of bearing and bed die, treat the bed die dismounting after, significantly reduce at the area of bearing soffit finish, therefore, the effect that this structure also has construction in later period to be convenient to plaster.
Described outer tube outer wall is provided with at least one sealing wing ring.The effect of described sealing wing ring has: prevent that 1. ponding is by the gap leakage between outer tube outer wall and the concrete; 2. be equivalent to the effect of the ribs of outer tube, make outer tube intensity increase, not yielding; 3. be connected tightr with the concrete of outer tube periphery.
Described outer tube, sealing wing ring and the external surface that is connected bearing all are made as is convenient to the matsurface that combines with concrete.This rough structure makes that pre-buried floor drain is connected with concrete in cast-in-situ concrete tightr.
The upper end of described outer tube is provided with top cover.The setting of cap structure is to prevent that concrete falls into pre-buried floor drain in cast-in-situ concrete, and perhaps other are built slag foreign material etc. and fall into pre-buried floor drain in the work progress.
The thickness of described connection bearing is no less than 4mm.The bonding strength that this architectural feature makes pre-buried joint connect bearing is guaranteed.
Described fixing hole diameter range is 4-6mm, if the fixing hole aperture is excessive, can form bigger hole on bed die when fixing with wire nail, is unfavorable for the recycling of bed die.According to the practice of construction test, the fixing hole diameter is preferably 5mm.
Another technical scheme of the present invention is: the job practices of the disposable pre-buried floor drain of construction work draining comprises following construction sequence:
The bed die of cast-in-situ floor is installed, and described bed die adopts composite bamboo rubber plate or wooden bed die, on the bed die that installs by the designing requirement unwrapping wire, to the installation site fixed point of the disposable pre-buried floor drain of construction work draining;
According to designing requirement the disposable pre-buried floor drain of construction work draining is installed on described bed die, the disposable pre-buried floor drain bottom margin of the described construction work draining outside is provided with the connection bearing, connects bearing and is provided with fixing hole;
The fixing hole that adopts wire nail to pass on the connection bearing of the disposable pre-buried floor drain of described construction work draining during installation is fixed on the disposable pre-buried floor drain of construction work draining on the described bed die;
The employing top cover covers in the top of the disposable pre-buried floor drain of described construction work draining, in case concrete is fallen in the disposable pre-buried floor drain of construction work draining;
Cast-in-situ concrete on described bed die, concrete vibrating is closely knit, and the outer wall of the disposable pre-buried floor drain of described construction work draining all adopts rough structure, and combining between the disposable pre-buried floor drain of construction work draining and the concrete is tightr;
The cast-in-place floor that finishes is carried out maintenance;
When treating that cast-in-situ floor reaches the performance requirement of design, with the floor bottom mould demoulding.
After the floor bottom mould demoulding of the present invention, the wire nail that stretches out the concrete cast-in-situ soffit is milled to soffit flushes, the wire nail after polishing is carried out antirust processing, again the concrete cast-in-situ soffit is plastered.
The length of the wire nail of disposable pre-buried floor drain of described fixed building engineering drainage and bed die is not less than thickness and the bed die thickness sum that is connected bearing.Be that the length of wire nail will make it satisfy it to follow closely at least and wear bed die.
Technique effect of the present invention is: use this pre-buried floor drain, construction technology has been simplified in the once mounting moulding greatly, has improved efficiency of construction, has reduced construction cost, does not build slag simultaneously in the work progress and produces, and has saved the energy; And being connected between this pre-buried floor drain and the bed die is more reliable, and being connected between pre-buried floor drain and the cast-in-situ concrete is tightr, has effectively prevented the ponding leakage problems.
Description of drawings
The present invention will illustrate by example and with reference to the mode of accompanying drawing, wherein:
Fig. 1 is the structural representation that the disposable pre-buried floor drain of construction work draining of the present invention has partial cutaway;
Fig. 2 is the vertical view that removes top cover among Fig. 1;
Fig. 3 is the upward view of Fig. 1;
Fig. 4 is disposable pre-buried floor drain of construction work draining of the present invention and bed die mounting structure schematic diagram;
Wherein, be labeled as figure: 1 for outer tube, and 2 be interior pipe, and 3 be annular chamber, and 4 is ring-shaped step, and 5 is the connection bearing, and 6 is top cover, and 7 is fixing hole, hydrofoil ring till 8, and 9 is bed die.
The specific embodiment
Preferred implementation
As shown in Figure 1 to Figure 3, the disposable pre-buried floor drain of a kind of construction work draining, comprise outer tube 1, pipe 2 in being provided with in the described outer tube 1, described interior pipe 2 lower ends flush with outer tube 1 lower end, pipe 2 lower ends and outer tube 1 lower end closed form annular chamber 3 in described, pipe 2 height are less than outer tube 1 height in described, and in general, interior pipe 2 highly is half of outer tube 1 height, pipe 2 inwalls are provided with at least one ring-shaped step 4 in described, and this ring-shaped step 4 is used for pre-buried floor drain lower end connection gutter is carried out axial limiting.The described outer tube 1 bottom margin outside is provided with and connects bearing 5, connects bearing 5 and is provided with fixing hole 7, and described connection bearing 5 has three, and described three connection bearings 5 are symmetrically distributed about 1 center of outer tube.The triangle symmetrical distribution structure that connects bearing 5 has improved the reliability that is connected of pre-buried floor drain and bed die greatly, makes pre-buried floor drain position in concrete cast-in-situ can not be offset.Described outer tube 1 outer wall is provided with at least one sealing wing ring 8.Described outer tube 1, sealing wing ring 8 and the external surface that is connected bearing 5 all are made as is convenient to the matsurface that combines with concrete, and this rough structure makes that pre-buried floor drain is connected with concrete in cast-in-situ concrete tightr.The upper end of described outer tube 1 is provided with top cover 6, and the setting of cap structure is to prevent that concrete falls into pre-buried floor drain in cast-in-situ concrete, and perhaps other is built slag foreign material etc. and falls into pre-buried floor drain and cause obstruction in the work progress.The thickness of described connection bearing 5 is no less than 4mm.The purpose of this architectural feature is to strengthen pre-buried floor drain and the bonding strength that is connected bearing.The described fixing hole diameter range of present embodiment is 4-6mm.If the fixing hole aperture is excessive, can on bed die, form bigger hole when fixing with wire nail, be unfavorable for the recycling of bed die, according to the practice of construction test, the fixing hole diameter is preferably 5mm.
As shown in Figure 4, the job practices of the disposable pre-buried floor drain of the described construction work draining of present embodiment comprises following construction sequence:
The bed die 9 of cast-in-situ floor is installed, and described bed die 9 adopts composite bamboo rubber plate or wooden bed dies, on the bed die that installs by the designing requirement unwrapping wire, to the installation site fixed point of the disposable pre-buried floor drain of construction work draining;
According to designing requirement the disposable pre-buried floor drain of construction work draining is installed on described bed die, the disposable pre-buried floor drain bottom margin of the described construction work draining outside is provided with the connection bearing, connects bearing and is provided with fixing hole;
The fixing hole that adopts wire nail to pass on the connection bearing of the disposable pre-buried floor drain of described construction work draining during installation is fixed on the disposable pre-buried floor drain of construction work draining on the described bed die;
The employing top cover covers in the top of the disposable pre-buried floor drain of described construction work draining, in case concrete is fallen in the disposable pre-buried floor drain of construction work draining;
Cast-in-situ concrete on described bed die, concrete vibrating is closely knit, and the outer wall of the disposable pre-buried floor drain of described construction work draining all adopts rough structure, and combining between the disposable pre-buried floor drain of construction work draining and the concrete is tightr;
The cast-in-place floor that finishes is carried out maintenance;
When treating that cast-in-situ floor reaches the performance requirement of design, with the floor bottom mould demoulding.
After the floor bottom mould demoulding of the present invention, the wire nail that stretches out the concrete cast-in-situ soffit is milled to soffit flushes, the wire nail after polishing is carried out antirust processing, again the concrete cast-in-situ soffit is plastered.
The length of the wire nail of disposable pre-buried floor drain of described fixed building engineering drainage and bed die is not less than thickness and the bed die thickness sum that is connected bearing.Be that the length of wire nail will make it satisfy it to follow closely at least and wear bed die.
Adopt the job practices of present embodiment, can improve efficiency of construction greatly, save construction material, reduce construction equipment, energy-saving and environmental protection.
Disclosed all features in this manual, or the step in disclosed all methods or the process except mutually exclusive feature and/or step, all can make up by any way.
Disclosed arbitrary feature in this manual (comprising any accessory claim, summary and accompanying drawing) is unless special narration all can be replaced by other equivalences or the alternative features with similar purpose.That is, unless special narration, each feature is an example in a series of equivalences or the similar characteristics.
The present invention is not limited to the aforesaid specific embodiment.The present invention expands to any new feature or any new combination that discloses in this manual, and the arbitrary new method that discloses or step or any new combination of process.

Claims (11)

1. disposable pre-buried floor drain of construction work draining, comprise outer tube (1), it is characterized in that, be provided with interior pipe (2) in the described outer tube (1), pipe (2) lower end flushes with outer tube (1) lower end and enclosed shape chamber (3) circlewise in described, pipe (2) height less than outer tube (1) highly in described, pipe (2) inwall is provided with the ring-shaped step (4) that at least one is used for lower end connection gutter axial limiting in described, described outer tube (1) the bottom margin outside is provided with and connects bearing (5), connects bearing (5) and is provided with fixing hole (7).
2. the disposable pre-buried floor drain of construction work draining according to claim 1 is characterized in that described connection bearing (5) has three, and described three connection bearings (5) are symmetrically distributed about outer tube (1) axle center.
3. the disposable pre-buried floor drain of construction work draining according to claim 2 is characterized in that, described outer tube (1) outer wall is provided with at least one sealing wing ring (8).
4. the disposable pre-buried floor drain of construction work draining according to claim 3 is characterized in that, described outer tube (1), sealing wing ring (8) and the external surface that is connected bearing (5) all are made as is convenient to the matsurface that combines with concrete.
5. according to any disposable pre-buried floor drain of described construction work draining in the claim 4, it is characterized in that the upper end of described outer tube (1) is provided with top cover (6).
6. according to any disposable pre-buried floor drain of described construction work draining in the claim 5, it is characterized in that the thickness of described connection bearing (5) is no less than 4mm.
7. according to any disposable pre-buried floor drain of described construction work draining in the claim 6, it is characterized in that fixing hole (7) diameter range on the described connection bearing is 4-6mm.
8. according to any disposable pre-buried floor drain of described construction work draining in the claim 7, it is characterized in that described fixing hole (7) diameter is 5mm.
9. the job practices according to any disposable pre-buried floor drain of described construction work draining of claim 1-8 is characterized in that, comprises following construction sequence:
The bed die of cast-in-situ floor is installed, and described bed die adopts composite bamboo rubber plate or wooden bed die, on the bed die that installs by the designing requirement unwrapping wire, to the installation site fixed point of the disposable pre-buried floor drain of construction work draining;
According to designing requirement the disposable pre-buried floor drain of construction work draining is installed on described bed die, the disposable pre-buried floor drain bottom margin of the described construction work draining outside is provided with the connection bearing, connects bearing and is provided with fixing hole;
The fixing hole that adopts wire nail to pass on the connection bearing of the disposable pre-buried floor drain of described construction work draining during installation is fixed on the disposable pre-buried floor drain of construction work draining on the described bed die;
The employing top cover covers in the top of the disposable pre-buried floor drain of described construction work draining, in case concrete is fallen in the disposable pre-buried floor drain of construction work draining;
Cast-in-situ concrete on described bed die, concrete vibrating is closely knit, and the outer wall of the disposable pre-buried floor drain of described construction work draining all adopts rough structure, and combining between the disposable pre-buried floor drain of construction work draining and the concrete is tightr;
The cast-in-place floor that finishes is carried out maintenance;
When treating that cast-in-situ floor reaches the performance requirement of design, with the floor bottom mould demoulding.
10. the job practices of the disposable pre-buried floor drain of construction work draining according to claim 9, it is characterized in that, after the described floor bottom mould demoulding, the wire nail that stretches out the concrete cast-in-situ soffit is milled to soffit flushes, wire nail after polishing is carried out antirust processing, again the concrete cast-in-situ soffit is plastered.
11. the job practices of the disposable pre-buried floor drain of construction work draining according to claim 10 is characterized in that, the length of the wire nail of disposable pre-buried floor drain of described fixed building engineering drainage and bed die is not less than thickness and the bed die thickness sum that is connected bearing.
CN2010105899415A 2010-12-15 2010-12-15 Disposable embedded floor drain for drainage in building engineering and construction method thereof Pending CN102061727A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105899415A CN102061727A (en) 2010-12-15 2010-12-15 Disposable embedded floor drain for drainage in building engineering and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105899415A CN102061727A (en) 2010-12-15 2010-12-15 Disposable embedded floor drain for drainage in building engineering and construction method thereof

Publications (1)

Publication Number Publication Date
CN102061727A true CN102061727A (en) 2011-05-18

Family

ID=43997208

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105899415A Pending CN102061727A (en) 2010-12-15 2010-12-15 Disposable embedded floor drain for drainage in building engineering and construction method thereof

Country Status (1)

Country Link
CN (1) CN102061727A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110259122A (en) * 2019-07-16 2019-09-20 江苏省苏中建设集团股份有限公司 A kind of construction method of roofing floor drain prior involvement installation
CN111691531A (en) * 2019-03-14 2020-09-22 河南五建建设集团有限公司 Disposable embedded floor drain for drainage of constructional engineering and construction method thereof
CN112962750A (en) * 2021-02-05 2021-06-15 康泰塑胶科技集团有限公司 Local sinking construction method for floor slab
CN113404142A (en) * 2021-05-24 2021-09-17 江苏捷顺机电设备有限公司 Disposable embedded floor drain for drainage of constructional engineering and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201195867Y (en) * 2008-02-27 2009-02-18 陈志文 Anti-water leakage floor drain
CN101871228A (en) * 2010-06-30 2010-10-27 刘宪武 Drainage pipeline system in building wall
CN101906810A (en) * 2010-07-29 2010-12-08 江苏万邦建设集团有限公司 Pre-embedded type anti-seepage floor drain
CN201901934U (en) * 2010-11-18 2011-07-20 成都川行科技塑业有限公司 Water stop deodorized floor drain
CN201943178U (en) * 2010-12-15 2011-08-24 成都市第四建筑工程公司 Disposable embedded floor drain for constructional engineering drain

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201195867Y (en) * 2008-02-27 2009-02-18 陈志文 Anti-water leakage floor drain
CN101871228A (en) * 2010-06-30 2010-10-27 刘宪武 Drainage pipeline system in building wall
CN101906810A (en) * 2010-07-29 2010-12-08 江苏万邦建设集团有限公司 Pre-embedded type anti-seepage floor drain
CN201901934U (en) * 2010-11-18 2011-07-20 成都川行科技塑业有限公司 Water stop deodorized floor drain
CN201943178U (en) * 2010-12-15 2011-08-24 成都市第四建筑工程公司 Disposable embedded floor drain for constructional engineering drain

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《建筑结构施工》 20050228 杨南方 《建筑结构施工》 , 1 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111691531A (en) * 2019-03-14 2020-09-22 河南五建建设集团有限公司 Disposable embedded floor drain for drainage of constructional engineering and construction method thereof
CN110259122A (en) * 2019-07-16 2019-09-20 江苏省苏中建设集团股份有限公司 A kind of construction method of roofing floor drain prior involvement installation
CN112962750A (en) * 2021-02-05 2021-06-15 康泰塑胶科技集团有限公司 Local sinking construction method for floor slab
CN113404142A (en) * 2021-05-24 2021-09-17 江苏捷顺机电设备有限公司 Disposable embedded floor drain for drainage of constructional engineering and construction method thereof

Similar Documents

Publication Publication Date Title
CN102095033B (en) One-time embedded water-stop section for construction engineering drainage and construction method thereof
CN106836516B (en) A kind of integrated water-proof chassis of toilet pipeline
CN202730881U (en) Integral embedded part with functions of lateral drainage, water stop and seepage prevention
CN104358305B (en) A kind of cyclone, water drainage riser connecting piece of caisson type washroom
CN102061727A (en) Disposable embedded floor drain for drainage in building engineering and construction method thereof
CN105650357B (en) A kind of disposable embedded water stop joint of constructional engineering drain and its construction method
CN204875972U (en) Pre -buried seat of drain pipe between kitchen guarding
CN103410318B (en) Washroom pipe well water-leakage construction method
CN102071733B (en) Disposable embedded fecal connector for constructional engineering drainage and construction method thereof
CN202227694U (en) Embedded sleeve for concrete pouring construction of bathroom floor
CN201943178U (en) Disposable embedded floor drain for constructional engineering drain
CN207092237U (en) Pre-buried deodorization washing machine floor drain
JP3160407U (en) Drain trap repair parts
CN114045880A (en) Basement post-cast strip treatment process
CN201943172U (en) Disposable embedded excrement connector for constructional engineering drainage
CN206290845U (en) Toilet antiseep built-in fitting
CN202865928U (en) Multifunctional integrated embedded part for drainage system of buildings
CN206554180U (en) A kind of integrated water-proof chassis of toilet pipeline
CN207092238U (en) The overboard standpipe floor drain of integral type
KR101173406B1 (en) Pipe sleeve
KR200480115Y1 (en) Assembly of Flange, Socket and Drainpipe for Piping Above Slab of Toilet Bow
CN104746592A (en) Water supply and drainage integration module and water supply and drainage system for buildings
CN215635439U (en) Drain pipe pre-embedding device with telescopic and waterproof functions
CN203297768U (en) Leakage preventing connecting tube penetrating through floor slab and connecting structure thereof
CN109779319A (en) A kind of co-layer draining blank precast block toilet of outer wall provided pipe line groove hole

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20110518