CN102051888B - Method for constructing built-in foundation bolt regulating hole of equipment foundation - Google Patents
Method for constructing built-in foundation bolt regulating hole of equipment foundation Download PDFInfo
- Publication number
- CN102051888B CN102051888B CN2009102280580A CN200910228058A CN102051888B CN 102051888 B CN102051888 B CN 102051888B CN 2009102280580 A CN2009102280580 A CN 2009102280580A CN 200910228058 A CN200910228058 A CN 200910228058A CN 102051888 B CN102051888 B CN 102051888B
- Authority
- CN
- China
- Prior art keywords
- polystyrene foam
- burried
- direct
- stone bolt
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The invention relates to a method for constructing a built-in foundation bolt regulating hole of an equipment foundation, which comprises the step of: firstly, embedding a built-in foundation bolt of the equipment foundation to a preset position where concrete is poured, and also comprises the steps of: 1, wrapping two semicircle polystyrene foam tubes on the outer wall of the built-in foundation bolt of the equipment foundation, wherein the top elevation of the polystyrene foam tubes is equal to the top elevation of poured concrete, and the bottom elevation of the polystyrene foam tubes is 300-400mm lower than the top elevation of the poured concrete; 2, binding the outer parts of the polystyrene foam tubes with iron wires for fixing before the concrete is poured, pouring the concrete; and 3, after the concrete poured at the outer parts of the two semicircle polystyrene foam tubes in the step 2 is strengthened, melting the polystyrene foam tubes with gasoline and forming the built-in foundation bolt regulating hole. The method has the advantages of being simple and easy to operate, effectively improving the construction quality, shortening the construction time, improving the construction efficiency, and being high in operation safety and accuracy.
Description
Technical field
The invention belongs to the realm of building construction, the job practices in especially a kind of Equipment Foundations direct-burried stone bolt adjustment hole.
Background technology
Along with expanding economy; The construction of the infrastructure of steel industry is increasing, and in the construction of the infrastructure of steel industry, its civil works part is main with Equipment Foundations mainly; The most of direct-burried stone bolt that adopts of Equipment Foundations in design; The installation accuracy of direct-burried stone bolt directly has influence on next process unit and installs, and therefore, the installation accuracy of stone bolt is particularly important in the construction.The Equipment Foundations direct-burried stone bolt center displacement allowable variation that national regulation requires to have constructed is ± 2mm; Because the installation accuracy of Equipment Foundations direct-burried stone bolt is high; Difficulty of construction is big; The Equipment Foundations direct-burried stone bolt of having constructed does not often reach the national regulation requirement; Need Equipment Foundations direct-burried stone bolt is carried out the secondary adjustment, promptly constructed in Equipment Foundations direct-burried stone bolt adjustment hole, traditional job practices has two kinds at present: 1, direct-burried stone bolt adjustment hole, artificial cutter concrete forming device basis; 2, adopt the prefabricated direct-buried stone bolt adjustment of cement perlite hole; There is following problem in the construction that above-mentioned two kinds of methods are carried out Equipment Foundations direct-burried stone bolt adjustment hole: (1), artificial cutter concrete are wasted time and energy, and have prolonged the engineering time, have reduced efficiency of construction; (2), cement perlite intensity is low, cracky, complex process, concrete pours and is difficult to take out.
Summary of the invention
The objective of the invention is to overcome the deficiency of prior art; The job practices in a kind of Equipment Foundations direct-burried stone bolt adjustment hole is provided, and this method construction precision is high, operation is simple, effectively improve construction quality, shorten the engineering time, improve efficiency of construction, processing safety is high.
The present invention solves its technical problem and realizes through following technical scheme:
A kind of Equipment Foundations direct-burried stone bolt is adjusted the job practices in hole, at first Equipment Foundations direct-burried stone bolt is buried underground the precalculated position of pour concrete, and it also comprises the steps:
(1) the polystyrene foam pipe of two semicircles is wrapped in the outer wall of Equipment Foundations direct-burried stone bolt, polystyrene foam pipe top absolute altitude is identical with pour concrete top absolute altitude, and polystyrene foam pipe bottom absolute altitude is than the low 300~400mm of pour concrete top absolute altitude;
(2) the polystyrene foam pipe outside of two semicircles is fixed pour concrete after fixing the completion with the iron wire colligation before pour concrete;
(3) treat on the outside pour concrete of polystyrene foam pipe of two semicircles in the step (2) with gasoline the polystyrene foam pipe to be dissolved after the intensity, form direct-burried stone bolt adjustment hole.
And the polystyrene foam bore of described two semicircles equals the external diameter of Equipment Foundations direct-burried stone bolt.
And the polystyrene foam pipe of described two semicircles adopts the iron wire colligation to fix.
Advantage of the present invention and beneficial effect are:
1, the job practices in these Equipment Foundations direct-burried stone bolt adjustment hole adopts the mould of the polystyrene foam pipe of two semicircles as the adjustment hole; After casting and constructing is accomplished, only need the polystyrene foam pipe be dissolved with gasoline, easy for installation; Need not dismounting work; Save the engineering time, improved efficiency of construction, and construction quality.
2, the polystyrene foam pipe adopts the iron wire colligation to fix in the job practices in these Equipment Foundations direct-burried stone bolt adjustment hole, and after the polystyrene foam pipe dissolved, the iron wire of colligation can reuse, economical with materials.
3, operation is simple, effectively improve construction quality, shorten the engineering time, improve efficiency of construction, processing safety is high in the present invention, is the job practices in the high Equipment Foundations direct-burried stone bolt adjustment hole of a kind of precision.
Description of drawings
Fig. 1 carries out the structural representation after concrete is poured into a mould for the present invention;
Fig. 2 is the structural representation after the polystyrene foam pipe of two semicircles of the present invention dissolves.
The specific embodiment
Through specific embodiment the present invention is made further detailed description below, following examples are descriptive, are not determinate, can not limit protection scope of the present invention with this.
The job practices in a kind of Equipment Foundations direct-burried stone bolt adjustment hole is at first carried out the concrete construction of Equipment Foundations, in the process of construction, Equipment Foundations direct-burried stone bolt 3 is buried underground on the precalculated position of pour concrete 1, wherein also comprises the steps:
(1) the polystyrene foam pipe 2 of two semicircles is wrapped in the outside of Equipment Foundations direct-burried stone bolt; The polystyrene foam bore of two semicircles equals the external diameter of Equipment Foundations direct-burried stone bolt; Polystyrene foam pipe top absolute altitude is identical with pour concrete top absolute altitude; Polystyrene foam pipe bottom absolute altitude is than the low 300~400mm of pour concrete top absolute altitude, and the polystyrene foam pipe of present embodiment bottom absolute altitude is than the low 400mm of pour concrete top absolute altitude;
(2) the polystyrene foam pipe outside of two semicircles is fixed with iron wire 4 colligations before pour concrete after; Also can adopt bonding mode that the polystyrene foam pipe of two semicircles is fixed; Adopt iron wire colligation mode shown in the present embodiment accompanying drawing, pour concrete after fixing the completion;
(3) treat on the outside pour concrete of polystyrene foam pipe of two semicircles in the step (2) with gasoline the polystyrene foam pipe to be dissolved after the intensity, form direct-burried stone bolt adjustment hole 5, the iron wire that colligation is used can directly take out from the adjustment hole, recycles.
The present invention utilizes the polystyrene foam pipe can be dissolved in the characteristics in the gasoline in work progress, and constructing operation is simple, has effectively ensured the accuracy at Equipment Foundations direct-burried stone bolt center, the adjustment of foot bolt easily.
Claims (2)
1. the job practices in Equipment Foundations direct-burried stone bolt adjustment hole is at first buried Equipment Foundations direct-burried stone bolt underground the precalculated position of pour concrete, it is characterized in that: also comprise the steps:
(1) the polystyrene foam pipe of two semicircles is wrapped in the outer wall of Equipment Foundations direct-burried stone bolt, polystyrene foam pipe top absolute altitude is identical with pour concrete top absolute altitude, and polystyrene foam pipe bottom absolute altitude is than the low 300~400mm of pour concrete top absolute altitude;
(2) the polystyrene foam pipe outside of two semicircles is fixed pour concrete after fixing the completion with the iron wire colligation before pour concrete;
(3) treat on the outside pour concrete of polystyrene foam pipe of two semicircles in the step (2) with gasoline the polystyrene foam pipe to be dissolved after the intensity, form direct-burried stone bolt adjustment hole.
2. the job practices in Equipment Foundations direct-burried stone bolt adjustment according to claim 1 hole, it is characterized in that: the polystyrene foam bore of described two semicircles equals the external diameter of Equipment Foundations direct-burried stone bolt.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009102280580A CN102051888B (en) | 2009-11-06 | 2009-11-06 | Method for constructing built-in foundation bolt regulating hole of equipment foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009102280580A CN102051888B (en) | 2009-11-06 | 2009-11-06 | Method for constructing built-in foundation bolt regulating hole of equipment foundation |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102051888A CN102051888A (en) | 2011-05-11 |
CN102051888B true CN102051888B (en) | 2012-07-18 |
Family
ID=43956662
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009102280580A Active CN102051888B (en) | 2009-11-06 | 2009-11-06 | Method for constructing built-in foundation bolt regulating hole of equipment foundation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102051888B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102493643B (en) * | 2011-12-15 | 2013-12-11 | 中国一冶集团有限公司 | Method for constructing circular hole of anchor bolt reserved by equipment foundation |
CN108385711B (en) * | 2018-04-18 | 2024-03-22 | 浙江星达能源科技有限公司 | Anchor cage ring type foundation and installation method thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1727144A (en) * | 2005-07-27 | 2006-02-01 | 上海人造板机器厂有限公司 | Structure of bottom girder of continuous press and installation |
KR100808560B1 (en) * | 2007-11-22 | 2008-02-29 | 영성산업 주식회사 | Self level adjustment method of constructing a water tank using the foundation pad |
KR100874033B1 (en) * | 2007-11-15 | 2008-12-17 | 주식회사 젠트로 | Waterproof structure and constructing method of the same |
CN101450578A (en) * | 2007-11-30 | 2009-06-10 | 天津市世纪东方建筑景观雕塑技术开发中心 | Method of using polystyrol compression-board as relief die |
-
2009
- 2009-11-06 CN CN2009102280580A patent/CN102051888B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1727144A (en) * | 2005-07-27 | 2006-02-01 | 上海人造板机器厂有限公司 | Structure of bottom girder of continuous press and installation |
KR100874033B1 (en) * | 2007-11-15 | 2008-12-17 | 주식회사 젠트로 | Waterproof structure and constructing method of the same |
KR100808560B1 (en) * | 2007-11-22 | 2008-02-29 | 영성산업 주식회사 | Self level adjustment method of constructing a water tank using the foundation pad |
CN101450578A (en) * | 2007-11-30 | 2009-06-10 | 天津市世纪东方建筑景观雕塑技术开发中心 | Method of using polystyrol compression-board as relief die |
Also Published As
Publication number | Publication date |
---|---|
CN102051888A (en) | 2011-05-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103422674B (en) | Prefabricated concrete structure Cast-in-Situ Segment concrete construction method | |
CN206267422U (en) | A kind of assembly concrete superposed column | |
CN103485370B (en) | A kind of concrete construction control method preventing wallboard harmful cracks | |
CN203270599U (en) | Foundation bolt pre-buried die | |
CN207297034U (en) | Tunnel double-lining concrete vault backfills grouting device | |
CN102051888B (en) | Method for constructing built-in foundation bolt regulating hole of equipment foundation | |
CN209837042U (en) | Reinforced concrete temporary component capable of being rapidly and statically crushed | |
CN104727339B (en) | Power equipment basis two-step construction method | |
CN204626453U (en) | The supporting device of pipeline in Urban Underground pipe gallery | |
CN206408951U (en) | A kind of architectural industrialization project conversion layer position level ladder muscle | |
CN102041806A (en) | Construction method for inserting steel column in bored pile | |
CN211113740U (en) | Prestressed steel cylinder concrete pipe with base | |
CN204780928U (en) | Major diameter bored concrete pile concrete first set groundwater increment controlling means | |
CN203730920U (en) | Sill anchor used in tunnel and used for fixing petroleum and natural gas pipelines | |
CN104908150B (en) | A kind of piping shaft making template and the method based on factorial praluction piping shaft | |
CN205343431U (en) | Prefabricated wall body grout sleeve strip solid matter exposes accurate positioning die of reinforcing bar | |
CN205476528U (en) | Precast pile device of taking one's place fast | |
CN207193782U (en) | A kind of pole type box culvert supporting embedded part of primary concreting Underground Culvert | |
CN107762053A (en) | Prefabricated basement pipeline module and preparation method thereof | |
CN211229633U (en) | Anti-punching pre-buried structure for large-aperture static crushing of reinforced concrete member | |
CN204715350U (en) | A kind of for stake top mark height in the pile extension device of design elevation | |
CN102248602A (en) | Die for manufacturing steel frame for prestressed concrete pipe | |
CN202273345U (en) | Positioning and anti-floating device for BDF thin-walled cement hollow pipes | |
CN204326495U (en) | A kind of structure of tool-type anchored end of Overhanging Outside Scaffold section steel beam | |
CN206376878U (en) | Railway tunnel self-propelled hydraulic inverted arch arc formwork adjusting means |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |