The method of elevator through heat engine test
Technical field
The present invention relates to elevator installation quality field tests technology, refer in particular to a kind of method of elevator through heat engine test.
Background technology
As everyone knows, elevator is up and down vertical transport equipment and the vehicle of passenger-carrying or goods in the building, and in modern society, people are accustomed to the elevator as the vertical transportation instrument, and more and more rely on it.As any vehicle, elevator save time to people and muscle power in, also brought inevitably certain risk, for this risk is dropped to bottom line, people are groping elevator safety always for many years, its safety precautions is gradually improved, manages to make elevator to become green channel, emphasize that elevator is more comfortable, be to produce and service for life more safely.
Traditional method, after the elevator installation, examination through Bureau of Technical Supervision, just can deliver to customer to use, but the installation quality of elevator and stability will just embody in client's use procedure, the quality of elevator just can't be guaranteed, and especially elevator installs that the weakest link---the installation quality problem of elevator door and gate can't in time be found.
Summary of the invention
Main purpose of the present invention provides a kind of method of elevator through heat engine test, and the quality problems of door system are finished the elevator through heat engine test automatically in installing with effective solution elevator, and installation quality and the stability of elevator door were found and solved in the very first time.
For realizing above-mentioned goal of the invention, the present invention adopts following technical scheme:
A kind of method of elevator through heat engine test connects a heat engine test input and a heat engine test output terminal at elevator main control board, and the number of run N of default heat engine test in elevator main control board; After the elevator installation, to press this heat engine test input and test, elevator begins to move to successively in order last floor from Stall, and then be reset to Stall and finish the test run process one time, number of run adds 1, and so circulation is until number of run reaches N, and the heat engine test stops; It is in the process of each time operation, automatically open the door and close the door action at every one deck by elevator main control board control elevator door, and detection is opened the door and is closed the door process automatically, if open the door or close the door and break down, then automatically send breakdown signal and indication fault number of floor levels by the heat engine test output terminal, withdraw from the heat engine test mode by the elevator main control board control system simultaneously.
Preferably, the open the door method of fault of described detection is: in the door-opened elevator process, whether the detecting gate lock-switch disconnects, if disconnect, also connects 2 seconds and close door limiting, judges that then this layer can not open the door, and sends breakdown signal.
Preferably, the open the door method of fault of described detection is: in the door-opened elevator process, whether the detecting gate lock-switch disconnects, if disconnect, to close door limiting and also disconnect, detect elevator door and whether reach 1/3 position this moment, if in 5 seconds, 1/3 switch is not connected, and then is judged as the machine stall that opens the door, and sends breakdown signal.
Preferably, the open the door method of fault of described detection is: in the door-opened elevator process, whether the detecting gate lock-switch disconnects, if door switch disconnects, close door limiting and also disconnect, 1/3 switch connection is after 5 seconds, door open limit is not connected, and then is judged as door and does not reach the position, sends breakdown signal.
Preferably, the close the door method of fault of described detection is: in the process of closing the door, when door open limit disconnects, if after 5 seconds, 1/3 switch is not connected, and then is judged as a machine generation stall, sends breakdown signal;
Preferably, the close the door method of fault of described detection is: in the process of closing the door, when door open limit disconnects and 1/3 switch is also connected, in 5 seconds, if door lock is connected, do not connect and close door limiting, then be judged as the door lock short circuit, send breakdown signal.
Preferably, described heat engine test input is the heat engine testing button.
Preferably, described heat engine test output terminal is heat engine test indicator lamp, siren horn or read-out.
After adopting technique scheme, the present invention has obvious advantage and beneficial effect, particularly, as shown from the above technical solution, the present invention is mainly used in testing quality and the stability of elevator car door system, especially after lift-mounting is finished, press the heat engine testing button, elevator can reach each floor automatically, tests every one deck elevator door and installs whether meet standard, and can repeat thousands of times repeatedly test and validation of carrying out, and need not be by manually removing to exhale elevator.When elevator door has problem, the heat engine test stops automatically, the commissioning staff can directly promptly arrive the state that corresponding floor checks elevator door according to indication, to finish quickly and easily debugging and maintenance, and then improved the efficient that elevator installs and the installation quality problem of finding as early as possible elevator door, guaranteed the elevator installation quality.
The specific embodiment
The present invention is described in detail below in conjunction with specific embodiment:
A kind of method of elevator through heat engine test, it connects a heat engine test input and a heat engine test output terminal at elevator main control board, and the number of run N of default heat engine test in elevator main control board.Wherein, this heat engine test input can be heat engine testing button etc., this heat engine test output terminal then can be heat engine test indicator lamp, siren horn or read-out etc., and this number of run N can suitably determine according to parameters such as elevator running model, service lifes for example 2000 times.
After the elevator installation, to press this heat engine test input and test, elevator begins to move to successively in order last floor from Stall, and then be reset to Stall and finish the test run process one time, number of run adds 1, and so circulation is until number of run reaches N, and the heat engine test stops.
It is in the process of each time operation, automatically open the door and close the door action at every one deck by elevator main control board control elevator door, and detection is opened the door and is closed the door process automatically, if open the door or close the door and break down, then automatically send breakdown signal by the heat engine test output terminal, record indication fault number of floor levels, the prompting installation personnel need to be readjusted elevator door in bad order, withdraws from the heat engine test mode by the elevator main control board control system simultaneously.
When the following any elevator door of generation opens the door or close the door fault, the heat engine test will be withdrawed from automatically, and record trouble time and failure code, and the concrete method that detects the fault of opening the door or close the door mainly contains following several:
Method one: in the door-opened elevator process, whether the detecting gate lock-switch disconnects, if disconnect, also connects 2 seconds and close door limiting, judges that then this layer can not open the door, and sends breakdown signal.
Method two: in the door-opened elevator process, whether the detecting gate lock-switch disconnects, if disconnect, close door limiting and also disconnect, detect elevator door and whether reach 1/3 position this moment, if in 5 seconds, 1/3 switch is not connected, and then is judged as the machine stall that opens the door, and sends breakdown signal.
Method three: in the door-opened elevator process, whether the detecting gate lock-switch disconnects, if door switch disconnects, closes door limiting and also disconnects, and 1/3 switch connection, after 5 seconds, door open limit is not connected, and then is judged as door and does not reach the position, sends breakdown signal.
Method four: in elevator was closed the door process, when door open limit disconnects, if after 5 seconds, 1/3 switch was not connected, and then decision gate machine generation stall sends breakdown signal;
Method five: in elevator is closed the door process, when door open limit disconnects and 1/3 switch is also connected, in 5 seconds, if door lock is connected, do not connect and close door limiting, then be judged as the door lock short circuit, send breakdown signal.
In sum, the present invention is mainly used in testing quality and the stability of elevator car door system, especially after lift-mounting is finished, press the heat engine testing button, elevator can reach each floor automatically, test every one deck elevator door and install whether meet standard, and can repeat thousands of times repeatedly test and validation of carrying out, and need not be by manually removing to exhale elevator.When elevator door has problem, the heat engine test stops automatically, the commissioning staff can directly promptly arrive the state that corresponding floor checks elevator door according to indication, to finish quickly and easily debugging and maintenance, and then improved the efficient that elevator installs and the installation quality problem of finding as early as possible elevator door, guaranteed the elevator installation quality.
The above, it only is preferred embodiment of the present invention, be not that technical scope of the present invention is imposed any restrictions, therefore every foundation technical spirit of the present invention all still belongs in the scope of technical solution of the present invention any trickle modification, equivalent variations and modification that above embodiment does.