CN102022993A - 一种线路单杆塔基础分坑的方法 - Google Patents

一种线路单杆塔基础分坑的方法 Download PDF

Info

Publication number
CN102022993A
CN102022993A CN2010105280833A CN201010528083A CN102022993A CN 102022993 A CN102022993 A CN 102022993A CN 2010105280833 A CN2010105280833 A CN 2010105280833A CN 201010528083 A CN201010528083 A CN 201010528083A CN 102022993 A CN102022993 A CN 102022993A
Authority
CN
China
Prior art keywords
hole
auxiliary
auxiliary pile
foundation
point
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010105280833A
Other languages
English (en)
Other versions
CN102022993B (zh
Inventor
李岩
刘治稳
郭向阳
霍建伟
姚红亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luoyang Longyu Group Co ltd
Luoyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
Luoyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Luoyang Power Supply Co of State Grid Henan Electric Power Co Ltd filed Critical Luoyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority to CN201010528083.3A priority Critical patent/CN102022993B/zh
Publication of CN102022993A publication Critical patent/CN102022993A/zh
Application granted granted Critical
Publication of CN102022993B publication Critical patent/CN102022993B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • A Measuring Device Byusing Mechanical Method (AREA)

Abstract

本发明涉及输电线路分坑测量的技术领域,公开一种线路单杆塔基础分坑的方法,包括:单坑分坑测量方法一:将仪器安置在杆塔位中心桩o点上,瞄准辅助桩A或B,将水平读盘读数调到0°0′0″位置,然后使望远镜旋45°;单坑分坑测量方法二:a.将仪器安置在杆塔位中心桩o点上,b.然后使望远镜旋45°,c.然后顺时针旋转照准部;利用辅助F、G对基坑开挖的控制和检查,本发明具有操作简单、使用方便,效率高,而且为以后的基础开挖和浇筑等工作的检查和控制奠定了基础,充分体现出上道工序为下道工序服务的思想理念。能够对开挖后的基坑做到很好的控制和检查作用,而且对铁塔基础浇制定位也能起到很好的辅助作用。

Description

一种线路单杆塔基础分坑的方法
 
【技术领域】
本发明涉及输电线路分坑测量的技术领域,尤其是涉及一种线路单杆塔基础分坑的方法。
【背景技术】
目前,送电线路的分坑测量工作,是复测分坑工作的一项重要内容,分坑测量不仅要准确无误的做好坑口放样工作,而且要充分考虑到分坑放样后的开挖、下盘、浇筑等工作的质量控制和检查。单杆塔基础通常有钢筋混凝土电杆基础和铁塔基础,单杆塔基础分坑,按通常的施工方法操作比较繁琐,开挖后中心桩和一些辅助桩无法保存,给以后的基坑开挖等工作的检查和控制造成了困难。通常的施工方法,如图1所示,将仪器安置在杆塔位中心桩o点上,瞄准辅助装A(或B),将水平读盘读数调到0°0′0″位置。然后使望远镜旋45°将皮尺的零刻度对准中心桩标记,在望远镜的视线方向取                                                
Figure 2010105280833100002DEST_PATH_IMAGE001
a的尺寸长度得点1.以后逐次顺时针旋转找准部,在水平度盘读数分别为135°、225°、及315°时,的望远镜视线方向上,同样量取
Figure 661322DEST_PATH_IMAGE001
a尺长,则分别得点、2、3、4,并在这些点上定立木桩,即为单杆主基础坑的四角顶点标志,则分坑完毕。通常施工方法的的缺点:
(1)通常的施工方法需要转动4次仪器、定4次角度才能定出1—4点桩,同时定桩时既要把握方向又要控制尺寸,操作比较繁琐。
(2)因中心桩和1—4点辅助桩开挖后无法保留,给开挖后的检查和控制带来了难度。
 
【发明内容】
鉴于上述存在的不足之处,本发明的目的是提供一种线路单杆塔基础分坑的方法,能够解决通常的分坑方法在实际工作中存在的问题,不仅操作简单而且为以后基坑开挖的检查和控制奠定了基础。
为了实现上述发明目的,本发明采用如下技术方案:
一种线路单杆塔基础分坑的方法,包括:
1、单坑分坑测量方法一:将仪器安置在杆塔位中心桩o点上,瞄准辅助装A(或B),将水平读盘读数调到0°0′0″位置。然后使望远镜旋45°,在望远镜正、倒镜视线合适的位置定上辅助桩F、G并记录尺寸(只作分坑用可以不记录尺寸),此时可以收仪器,将皮尺的零刻度对准中心桩标记,在中心桩O和辅助桩F之间量取a/的尺寸长度得点1,在中心桩O和辅助桩F之间量取a/
Figure 533649DEST_PATH_IMAGE002
的尺寸长度得点3;
在皮尺上取2a长度,使其两点分别固定到1、3点上,拉紧尺长的中点得出2点,用石灰顺着尺子作好标记,同样使尺长中点折向另一侧得中点4,用石灰或其它可作标记的粉状物顺着尺子洒下做好坑口标记,单坑分坑工作即完成,并把辅助桩F、G用水泥保护好;
2、单坑分坑测量新方法2:a.将仪器安置在杆塔位中心桩o点上,瞄准辅助装A(或B),将水平读盘读数调到0°0′0″位置;b.然后使望远镜旋45°,在望远镜视线方向合适的位置定上辅助桩F并记录尺寸;c.然后顺时针旋转照准部,在水平读盘读数为225°时,在望远镜视线方向合适的位置定上辅助桩G并记录尺寸,下面的施工步骤与方法1相同;
3、利用辅助F、 G对基坑开挖的控制和检查,杆塔基础底板在开挖过程中,施工人员一般边开挖边检查,由于尺量方法不准确,在坑深挖到位后会出现坑底边长总尺寸达到要求,而进一步检查会发现一边多、一边少现象,少的一边进行修坑采取掏挖的方法还会引起塌方现象,若是现浇铁塔基础还会引起浇筑材料的浪费;利用辅助桩F、G对基坑开完的控制:在辅助装F和G间上挂上线绳,将皮尺的零刻度对准辅助桩F,另一端放在辅助桩G上,量取尺寸d定出尺量近距1点在线绳上作记号,量取
Figure 959077DEST_PATH_IMAGE002
a+d尺长在尺量远距2点在线绳上做记号,用垂球垂向坑底并定桩或作记号,然后取尺长2d,将两端头分别放在坑底1点、2点,用手钩住尺子中部d处向外拉直角检查坑底两个边长、再折向另一侧检查另外两个边长。若将皮尺零刻度放在辅助桩G上,其操作方法与上所述相同。
由于采用了上述技术方案,本发明具有如下有优越性:
一种线路单杆塔基础分坑的方法,通过对单杆塔基础现有的通常分坑方法在实际工作中存在的问题进行分析、研究产生的,具有操作简单、使用方便而且为以后的基础开挖和浇筑等工作的检查和控制奠定了基础,充分体现出上道工序为下道工序服务的思想理念。本发明与现有通常方法的比较:
(1)通常的方法对单坑基础分坑时需要转4个方向,定4个角度,定桩时还要考虑方向还要兼顾尺寸,操作比较麻烦,效率也较低,改进后的方法只用转一个角度,如果不考虑以后检查和控制,就可以不考录尺寸,若考虑以后的检查尺寸也不是固定尺寸,也可以在分坑后量取尺寸作记录。
(2)通常的施工方法中心桩和1—4点桩在开挖后无法保留,给开挖后的控制和检查增加了难度,改进后的方法可不仅可以对开挖后的基坑能做到很好的控制和检查作用而且对铁塔。基础浇制定位也能起到很好的辅助作用。
【附图说明】
 图1 单杆塔基础分坑示意图;
图2 单杆塔基础分坑示意图;
图3 基础开挖控制和检查示意图。
  【具体实施方式】
如图1、2、3所示,一种线路单杆塔基础分坑的方法,包括:
1、单坑分坑测量新方法一,如图2所示,将仪器安置在杆塔位中心桩o点上,瞄准辅助装A(或B),将水平读盘读数调到0°0′0″位置。然后使望远镜旋45°,在望远镜正、倒镜视线合适的位置定上辅助桩F、G并记录尺寸(只作分坑用可以不记录尺寸),此时可以收仪器,将皮尺的零刻度对准中心桩标记,在中心桩O和辅助桩F之间量取a/
Figure 420145DEST_PATH_IMAGE002
的尺寸长度得点1,在中心桩O和辅助桩F之间量取a/
Figure 36940DEST_PATH_IMAGE002
的尺寸长度得点3。
 (1)在皮尺上取2a长度,使其两点分别固定到1、3点上,拉紧尺长的中点得出2点,用石灰顺着尺子作好标记,同样使尺长中点折向另一侧得中点4,用石灰或其它可作标记的粉状物顺着尺子洒下做好坑口标记,单坑分坑工作即完成,并把辅助桩F、G用水泥保护好。
2、单坑分坑测量新方法二,如图2所示,将仪器安置在杆塔位中心桩o点上,瞄准辅助装A(或B),将水平读盘读数调到0°0′0″位置。然后使望远镜旋45°,在望远镜视线方向合适的位置定上辅助桩F并记录尺寸,然后顺时针旋转照准部,在水平读盘读数为225°时,在望远镜视线方向合适的位置定上辅助桩G并记录尺寸,施工方法和方法1相同。
3、利用辅助F、 G对基坑开挖的控制和检查,杆塔基础底板在开挖过程中,施工人员一般边开挖边检查,由于尺量方法不准确,在坑深挖到位后会出现坑底边长总尺寸达到要求,而进一步检查会发现一边多、一边少现象,少的一边进行修坑采取掏挖的方法还会引起塌方现象,若是现浇铁塔基础还会引起浇筑材料的浪费。以下介绍利用辅助桩F、G对基坑开完的控制。
如图3所示在辅助装F和G间上挂上线绳,将皮尺的零刻度对准辅助桩F,另一端放在辅助桩G上,量取尺寸d定出尺量近距1点在线绳上作记号,量取
Figure 216249DEST_PATH_IMAGE002
a+d尺长在尺量远距2点在线绳上做记号,用垂球垂向坑底并定桩或作记号,然后取尺长2d,将两端头分别放在坑底1点、2点,用手钩住尺子中部d处向外拉直角检查坑底两个边长、再折向另一侧检查另外两个边长。若将皮尺零刻度放在辅助桩G上,其操作方法与上所述相同。

Claims (1)

1.一种线路单杆塔基础分坑的方法,其特征在于:包括:
1)、单坑分坑测量方法一:将仪器安置在杆塔位中心桩o点上,瞄准辅助装A(或B),将水平读盘读数调到0°0′0″位置,然后使望远镜旋45°,在望远镜正、倒镜视线合适的位置定上辅助桩F、G并记录尺寸,只作分坑用可以不记录尺寸,此时可以收仪器,将皮尺的零刻度对准中心桩标记,在中心桩O和辅助桩F之间量取a/                                                
Figure DEST_PATH_IMAGE001
的尺寸长度得点1,在中心桩O和辅助桩F之间量取a/
Figure 104959DEST_PATH_IMAGE001
的尺寸长度得点3;
在皮尺上取2a长度,使其两点分别固定到1、3点上,拉紧尺长的中点得出2点,用石灰顺着尺子作好标记,同样使尺长中点折向另一侧得中点4,用石灰或其它可作标记的粉状物顺着尺子洒下做好坑口标记,单坑分坑工作即完成,并把辅助桩F、G用水泥保护好;
2)、单坑分坑测量新方法二:a.将仪器安置在杆塔位中心桩o点上,瞄准辅助桩A或B,将水平读盘读数调到0°0′0″位置;b.然后使望远镜旋45°,在望远镜视线方向合适的位置定上辅助桩F并记录尺寸;c.然后顺时针旋转照准部,在水平读盘读数为225°时,在望远镜视线方向合适的位置定上辅助桩G并记录尺寸,施工步骤与方法1相同;
3)、利用辅助F、 G对基坑开挖的控制和检查,杆塔基础底板在开挖过程中,施工人员一般边开挖边检查,由于尺量方法不准确,在坑深挖到位后会出现坑底边长总尺寸达到要求,而进一步检查会发现一边多、一边少现象,少的一边进行修坑采取掏挖的方法还会引起塌方现象,若是现浇铁塔基础还会引起浇筑材料的浪费;利用辅助桩F、G对基坑开完的控制:在辅助装F和G间上挂上线绳,将皮尺的零刻度对准辅助桩F,另一端放在辅助桩G上,量取尺寸d定出尺量近距1点在线绳上作记号,量取
Figure 686113DEST_PATH_IMAGE001
a+d尺长在尺量远距2点在线绳上做记号,用垂球垂向坑底并定桩或作记号,然后取尺长2d,将两端头分别放在坑底1点、2点,用手钩住尺子中部d处向外拉直角检查坑底两个边长、再折向另一侧检查另外两个边长。若将皮尺零刻度放在辅助桩G上,其操作方法与上所述相同。
CN201010528083.3A 2010-11-02 2010-11-02 一种线路单杆塔基础分坑的方法 Expired - Fee Related CN102022993B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010528083.3A CN102022993B (zh) 2010-11-02 2010-11-02 一种线路单杆塔基础分坑的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010528083.3A CN102022993B (zh) 2010-11-02 2010-11-02 一种线路单杆塔基础分坑的方法

Publications (2)

Publication Number Publication Date
CN102022993A true CN102022993A (zh) 2011-04-20
CN102022993B CN102022993B (zh) 2015-06-24

Family

ID=43864576

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010528083.3A Expired - Fee Related CN102022993B (zh) 2010-11-02 2010-11-02 一种线路单杆塔基础分坑的方法

Country Status (1)

Country Link
CN (1) CN102022993B (zh)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104266638A (zh) * 2014-08-28 2015-01-07 中国二十冶集团有限公司 一种坑中坑定点放线方法
CN105369838A (zh) * 2015-12-02 2016-03-02 国家电网公司 杆塔基础分坑绳具及其应用和一种杆塔基础分坑方法
CN105421480A (zh) * 2015-11-25 2016-03-23 国家电网公司 输电塔的正方形基础分坑方法
CN105507342A (zh) * 2015-11-25 2016-04-20 国家电网公司 输电塔的长方形基础分坑方法
CN107268662A (zh) * 2017-06-05 2017-10-20 三峡大学 一种输电线路铁塔基础分坑方法
CN109358353A (zh) * 2018-10-31 2019-02-19 中国电建集团山东电力建设第工程有限公司 一种集电线路基础快速分坑放样方法
CN110820727A (zh) * 2019-09-26 2020-02-21 国家电网有限公司 钻孔灌注桩施工的精准定位测量方法
CN111121731A (zh) * 2019-12-11 2020-05-08 荆州市荆力工程设计咨询有限责任公司 一种基础分坑仪及其控制方法
CN113062322A (zh) * 2021-03-31 2021-07-02 任彦东 一种十字分坑方法
CN114526714A (zh) * 2021-12-17 2022-05-24 中国电建集团河南省电力勘测设计院有限公司 一种铁塔基础施工测量工具及其测量方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3855710A (en) * 1973-06-15 1974-12-24 J Lunden Signal control device
JP2006083642A (ja) * 2004-09-17 2006-03-30 Tokyo Electric Power Co Inc:The 鉄塔の基礎構造

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3855710A (en) * 1973-06-15 1974-12-24 J Lunden Signal control device
JP2006083642A (ja) * 2004-09-17 2006-03-30 Tokyo Electric Power Co Inc:The 鉄塔の基礎構造

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王文清: "《电力线路设计安装施工图集 上》", 31 March 2004, 香港:天马图书有限公司 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104266638A (zh) * 2014-08-28 2015-01-07 中国二十冶集团有限公司 一种坑中坑定点放线方法
CN105421480A (zh) * 2015-11-25 2016-03-23 国家电网公司 输电塔的正方形基础分坑方法
CN105507342A (zh) * 2015-11-25 2016-04-20 国家电网公司 输电塔的长方形基础分坑方法
CN105369838A (zh) * 2015-12-02 2016-03-02 国家电网公司 杆塔基础分坑绳具及其应用和一种杆塔基础分坑方法
CN105369838B (zh) * 2015-12-02 2017-07-04 国家电网公司 杆塔基础分坑绳具及其应用和一种杆塔基础分坑方法
CN107268662A (zh) * 2017-06-05 2017-10-20 三峡大学 一种输电线路铁塔基础分坑方法
CN109358353A (zh) * 2018-10-31 2019-02-19 中国电建集团山东电力建设第工程有限公司 一种集电线路基础快速分坑放样方法
WO2020088363A1 (zh) * 2018-10-31 2020-05-07 中国电建集团山东电力建设第一工程有限公司 一种集电线路基础快速分坑放样方法
CN109358353B (zh) * 2018-10-31 2022-12-09 中国电建集团山东电力建设第一工程有限公司 一种集电线路基础快速分坑放样方法
CN110820727A (zh) * 2019-09-26 2020-02-21 国家电网有限公司 钻孔灌注桩施工的精准定位测量方法
CN111121731A (zh) * 2019-12-11 2020-05-08 荆州市荆力工程设计咨询有限责任公司 一种基础分坑仪及其控制方法
CN111121731B (zh) * 2019-12-11 2022-09-09 国网湖北省电力有限公司荆州供电公司 一种基础分坑仪
CN113062322A (zh) * 2021-03-31 2021-07-02 任彦东 一种十字分坑方法
CN114526714A (zh) * 2021-12-17 2022-05-24 中国电建集团河南省电力勘测设计院有限公司 一种铁塔基础施工测量工具及其测量方法

Also Published As

Publication number Publication date
CN102022993B (zh) 2015-06-24

Similar Documents

Publication Publication Date Title
CN102022993B (zh) 一种线路单杆塔基础分坑的方法
US7921573B1 (en) Monitoring verticality of a sinking caisson
CN105043343A (zh) 基于激光位移传感器的自动化测量隧道拱顶沉降的方法
CN101349563A (zh) 一种建筑施工测量放线的方法
CN101158579A (zh) 土地面积多级精度数字自动测定技术
CN105804041A (zh) 大面积超软弱地基沉降监测装置及监测方法
CN204461411U (zh) 一种简易液体地基小沉降测量装置
CN103741726B (zh) 一种沉井沉降量测量方法
CN206772288U (zh) 建筑工程中测量锚杆水平倾角的装置
CN103344214A (zh) 一种1.6次抛物线型特大桥墩测量及墩身线形控制方法
CN203798350U (zh) 一种沉井垂直度测量装置
CN208137932U (zh) 一种方形人工挖孔桩尺寸检具
CN108489455B (zh) 污水沉井内部结构的测量方法
CN205066759U (zh) 地锚板角度测量装置
CN103410135B (zh) 一种基于网格钎探的河床标高测量方法
KR200414287Y1 (ko) 도시기준점 표지
Lewis Greek and Roman surveying and surveying instruments
CN110030985A (zh) 一种地震水准测量标志的迁移方法
CN103572769A (zh) 沉井下沉中倾斜度监控方法
CN104266638A (zh) 一种坑中坑定点放线方法
CN102021917B (zh) 一种送电线路π型杆基础施工的方法
CN205712053U (zh) 大面积超软弱地基沉降监测装置
CN110567448A (zh) 一种全站仪测量标高坐标的方法
CN110926436A (zh) 一种坡面施工测量放线的方法及辅助工具
CN220508053U (zh) 一种隐藏式隧道观测墩

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Li Yan

Inventor after: Zhao Gang

Inventor after: Fan Yuefu

Inventor after: Liu Zhiwen

Inventor after: Guo Xiangyang

Inventor after: Huo Jianwei

Inventor after: Yao Hongliang

Inventor before: Li Yan

Inventor before: Liu Zhiwen

Inventor before: Guo Xiangyang

Inventor before: Huo Jianwei

Inventor before: Yao Hongliang

CB03 Change of inventor or designer information
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 471000 No. 259 Kaiyuan Road, New District, Henan, Luoyang

Patentee after: LUOYANG POWER SUPPLY COMPANY OF STATE GRID HENAN ELECTRIC POWER Co.

Address before: 471000 No. 259 Kaiyuan Road, New District, Henan, Luoyang

Patentee before: Luoyang Power Supply Company of Henan Electric Power Co.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191128

Address after: Xigong District 471000 Henan province Luoyang Kaixuan Road No. 12

Co-patentee after: LUOYANG LONGYU GROUP Co.,Ltd.

Patentee after: LUOYANG POWER SUPPLY COMPANY OF STATE GRID HENAN ELECTRIC POWER Co.

Address before: 471000 No. 259 Kaiyuan Road, New District, Henan, Luoyang

Patentee before: LUOYANG POWER SUPPLY COMPANY OF STATE GRID HENAN ELECTRIC POWER Co.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150624