CN101929882A - Debugging method of dry-quenching automatic meter system - Google Patents

Debugging method of dry-quenching automatic meter system Download PDF

Info

Publication number
CN101929882A
CN101929882A CN2009100534830A CN200910053483A CN101929882A CN 101929882 A CN101929882 A CN 101929882A CN 2009100534830 A CN2009100534830 A CN 2009100534830A CN 200910053483 A CN200910053483 A CN 200910053483A CN 101929882 A CN101929882 A CN 101929882A
Authority
CN
China
Prior art keywords
instrument
debugging
signal
test
value
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2009100534830A
Other languages
Chinese (zh)
Other versions
CN101929882B (en
Inventor
李先林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Wuye Construction Of Zhongye Chenggong Coltd
Original Assignee
Shanghai Wuye Construction Of Zhongye Chenggong Coltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Wuye Construction Of Zhongye Chenggong Coltd filed Critical Shanghai Wuye Construction Of Zhongye Chenggong Coltd
Priority to CN200910053483A priority Critical patent/CN101929882B/en
Publication of CN101929882A publication Critical patent/CN101929882A/en
Application granted granted Critical
Publication of CN101929882B publication Critical patent/CN101929882B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing And Monitoring For Control Systems (AREA)

Abstract

The invention relates to the field of a debugging method of a metallurgy equipment electric system, in particular to a debugging method of a dry-quenching automatic meter system. The debugging method of the dry-quenching automatic meter system comprises the following steps in sequence: a, debugging of a conventional meter; b, debugging of a special meter; c, detection test of an input/output assembly; d, analogue test of a meter system; e, cooperative joint-trial of the meter system; and f, no-load linkage trial run. In the invention, through the strictly-designed standard installation and detection reference, the debugging method is simple, safe and reliable and has high work efficiency.

Description

Debugging method of dry-quenching automatic meter system
Technical field
The present invention relates to the adjustment method field of metallurgical equipment electrical system, be specially a kind of debugging method of dry-quenching automatic meter system.
Background technology
CDQ is that new in the world at present of being born smelts power-saving technology, and its English name is Coke Dry Quenching, is called for short CDQ.Dry coke quenching is to be thermal barrier with circulated inert gas, discharges below by circulating fan cold recyclegas being imported red burnt cooling chamber cooling down high-temperature coke to 250 ℃.Cycling hot conductance behind the absorption coke heat is gone into waste heat boiler and is reclaimed heat, produces steam.After recyclegas cooling, the dedusting, return cooling chamber through blower fan again, so red Jiao of circulation cooling.The steam that coke dry quenching boiler produces or incorporate factory's internal steam pipe net into or send to generating.Dry Quenching Technology is great energy-conservation project, owing to finish the quenching process in closed system, compares with common coke wet quenching, can eliminate the discharging of phenol, HCN, H2S, NH3 substantially, reduces burnt dirt discharging, and saves the quenching water.Dry coke quenching engineering instrument is the important component part in the dry coke quenching equipment, the center of gravity of its debugging work is based on the debugging of " three " system, except that the detection debugging of finishing field instrument self, also should with the electric specialty close fit, satisfy the needs of main process control system and supplement production control system " three " debugging, guarantee to finish whole process system control, finally reach the manufacturing technique requirent of design.Dry coke quenching engineering instrument kind is many, involve a wide range of knowledge, quantity is big, and conventional instrument has thermal resistance, thermopair, temperature switch, thermometer, pressure switch, pressure gauge, flow switch, flowmeter, flow transmitter, fluid level transmitter, Pressure and Difference Pressure Transmitter, electric control valve, electronic stop valve, digital indicator etc.; Special instrument has Moisture Meter, belt conveyer scale, gamma-rays level-sensing device, the high temperature width of cloth to penetrate thermometer, gas analyzer, PH meter, conductivity meter etc.; Also comprise some I/O assemblies and communication module etc. in addition.The debugging of dry coke quenching engineering automatic meter system can be divided into: the debugging of conventional instrument monomer, the debugging of special instrument, I/O component detection, the debugging of instrument secondary, systems modelling, the single examination of system and zero load joint-trial etc.Because Dry Quenching Technology belongs to emerging field, only there is enterprise of the man a few family of very few number in the unit of domestic this method of employing, also is in the stage of fumbling for the installation of dry coke quenching equipment, exists much not science, irrational place, the debug process complexity.
Summary of the invention
In order to overcome the defective of prior art, a kind of safe and reliable electrical equipment adjustment method is provided, the invention discloses a kind of debugging method of dry-quenching automatic meter system.
The present invention reaches goal of the invention by following technical solution:
A kind of debugging method of dry-quenching automatic meter system, carry out successively as follows: a. debugging conventional instrument, b. debug special instrument, c. detects simulation test, the e. instrument system of testing in-out box, d. instrument system and cooperates joint-trial and the zero load interlock test run of f., it is characterized in that:
When a. debugging conventional instrument, conventional instrument carries out monomer in meter specially debugging chamber and debugs in advance, debugged conventional instrument is carried out sensitivity, positive stroke and revesal, fundamental error and return difference adjustment, debugged conventional instrument press 5 in code requirement work with high scale just, the flyback verification
When c. detecting the test in-out box, use standard signal generator, on the system cabinet respective terminal, add standard analog signal, the simulated field detection signal, by active station screen viewing corresponding signal displayed value, do minimum value, intermediate value, 3 input detections of maximal value
D. the simulation test of instrument system comprises systems modelling, the systems modelling of operation control circuit and the systems modelling in interlocking of signals loop that detects the indication loop, when detecting the systems modelling in indication loop, with signal generators such as standard meter or the loop tester on-site signal of analog temperature, pressure, flow instrument at the scene, the analogue value comprises the starting point and the terminal point of range, gets 3~10 points; During the systems modelling in interlocking of signals loop; reach setting value by analogue instrument signal at the scene; check whether regular event and confirming of relevant interlock program, emergency cut-off, defencive function and alarm set point, the course of action of checkout facility, in proper order, delay parameter.
Described debugging method of dry-quenching automatic meter system, it is characterized in that: when c. detects the test in-out box, use standard signal generator, on the system cabinet respective terminal, add standard analog signal, the simulated field detection signal, by active station screen viewing corresponding signal displayed value, doing 10%, 50%, 90% 3 input detects, on active station, send analog output signal, on the respective terminal of control rack, check the output current of assembly simultaneously, do at 10%, 50%, 90% 3 and detect output.
The present invention is by the installation and the detection reference of strict design specifications, and adjustment method is simple, and is safe and reliable, the operating efficiency height.
Description of drawings
Fig. 1 is a process flow diagram of the present invention.
Embodiment
Below further specify the present invention by specific embodiment.
Embodiment 1
A kind of debugging method of dry-quenching automatic meter system, carry out successively as follows after preparation of construction is finished: a. debugging conventional instrument, b. debug special instrument, c. detects simulation test, the e. instrument system of testing in-out box, d. instrument system and cooperates joint-trial and the zero load interlock test run of f.
Finish following preparation of construction before the debugging beginning:
1. technology is prepared
(1) before the debugging, the project leader must carry out safely, confide a technological secret all commissioning staffs, clearly debugs scope and debugging main points, and the debugging requirement is described.
(2) be familiar with instrument construction drawing and correlation technique data, prepare various debugging recording forms.
(3) commissioning staff must hold the electrician and operates card.
2. debugging condition is prepared
Instrument is once debugged the meter specially debugging chamber (the conventional instrument monomer is debugged in advance) of usefulness, should requirement up to specification, and as temperature, power supply and the condition that possessed such as water up and down.
3. the debugging preparation of reference instrument instrument
(1), prepares qualified debugging instrument, instrument and equipment and material according to instrument construction drawing and correlation technique data.
(2) precision of standard meter will be higher than by school instrument secondary.
(3) standard meter will be in the term of validity that is up to the standards.
Can begin debugging after being ready to complete, process flow diagram as shown in Figure 1.
One, the debugging of conventional instrument
The conventional instrument debugging, comprise that visual examination, nameplate affirmation, function and precision checking are (as measurement range, range, zero-bit affirmation, degree of accuracy is confirmed, the adjustment of instrument dead band, return difference, the calibration of error, response time confirms that the instrument insulation characterisitic is confirmed), output signal test, warning function test, auxiliary property test, additional function test etc., and carry out state and debug.
1. conventional instrument is debugged main points
(1) before the installation, conventional instrument should carry out monomer in the meter specially chamber of debugging and debug in advance.Purpose is to check whether instrument meets performance index, does not have in transportation and storing process and damages, and has or not Short Item, defective etc.
(2) instrument monomer debugging should adjust by the requirement of manufacturer specification requirement or country, industry, company standard, debugging standard, verification.
(3) the correct reference instrument instrument of selecting to adjust usefulness provides the test condition that is fit to be transferred instrument verification.
(4) by the school instrumentation when the adjustment, should make a service test by the technical requirement and the technical parameter of operation instruction.
(5) should be carried out sensitivity, positive stroke and revesal, fundamental error and return difference adjustment by the school instrument.Specific requirement: the monomer instrumentation must by code requirement do 5 with high scale just, the flyback verification, linear graduation is got 0%, 25%, 50%, 75%, 100% of range usually, non-linear scale is looked actual conditions and is got representational calibration points.
(6) verification detects the instrument that finishes and should compile the engineering drawing item, packs again, prepares against on-the-spot installation the when having ready conditions.
2. pressure, temperature indicating gauge
(1) carries out the accuracy testing and the stability test of figure, the compliant requirement of counting of test.
(2) the band warning device carries out alarm set point by designing requirement and adjusts, its alarm set point should be provided with accurately, the output contact break-make correctly, reliable in action.
3. flow instrument
(1) flow instrumentation is tackled its manufacturing plant's work certificate and is effectively examined and determine proof and check, carries out parameter and every adjustment according to the data that product description provides.
(2) should check installment state by design before flow instrument puts into operation, satisfy the installation site requirement.Ground connection is complete and good reliable, otherwise influences measuring accuracy.
4. intelligent pressure, differential pressure transmitter
(1) intelligent transducer is carried out the configuration of various parameters with the special-purpose handheld terminal communicator of coordinative composition of equipments.The main contents of configuration comprise figure item, damping parameter, unit, range, transmission of signal-type, data processing mode of transmitter etc.
(2) when transmitter is carried out verification, looking the pressure signal scope adopts the hand held force (forcing) pump of standard piston meter, water force (forcing) pump, supporting special pressure module respectively pressure, differential pressure transmitter to be simulated applied voltage test, and detecting the output signal of transmitter with qualified standard meter, the adjustment transmitter makes it satisfy accuracy requirement.
5. liquid level, flow and pressure switch
(1) confirms model, the specification of liquid level, flow and pressure switch and the actuating range that adapts according to designing requirement.
(2) adjust the related setting of liquid level, flow and pressure switch according to designing requirement.To do adjusting of force value to pressure switch; Should carry out working value to flow switch adjusts; Should carry out the liquid level working value to level switch and adjust, its value should adhere to specification.
6. liquid level instrument
(1) confirm model, the specification of liquid level instrument and the range ability that adapts according to designing requirement, supporting transmitter should conform to the range specification of detection head.
(2) the pressure sensing type fluid level transmitter also needs the physical length of measuring sense line is accurately located to satisfy the measuring accuracy requirement after finishing parameter and being provided with.
(3) output signal of transmitter and additional function are set and confirmed.
(4) use the intelligent communication device that transmitter is carried out distant place communication test.
7. pneumatic and electric control valve
(1) needs to cooperate operating state and the closed condition of confirming valve before the variable valve action with mechanical major.If integral type, must perform the measure that anti-super scope is rotated before the action; Split type movement angle is adjusted topworks separately after determining, connects upper valve body at last again and makes action checking.
(2) earlier manually total travel checks that valve core movement has or not clamping stagnation, normal fully after the actuating length and the linear precision of electricity consumption signal imitation test check valve again, pay special attention to check the conversion accuracy and the stability of electricity/pneumatic valve positioner.
(3), should check the reliable in action of shutoff tightness, total travel action response time, manner of execution and the put limit of stop valve when dissengaged positions to pneumatic cut-off valve.
Should check the positive and negative acting characteristic of variable valve when (4) debugging, should adhere to specification, satisfy and regulate needs.
(5) after precision and designing requirement are satisfied in action, need the backstop of topworks is locked, moment is adjusted, and repetition test, guarantees reliable, effective.
Two, the debugging of special instrument
Special instrument debugging, the requirement of by specification is carried out.
Three, the detection of in-out box test
1. analog input module
According to the fastener kind of system configuration, use standard signal generator, on the system cabinet respective terminal, add standard analog signal, the simulated field detection signal is by active station screen viewing corresponding signal displayed value.Usually require to do minimum value, intermediate value, 3 input detections of maximal value, 10%, 50%, 90% 3 point is made in the requirement that has.
Different analog input module is required that different input signals is arranged, distinguish the analog input module of passive, active, thermopair, thermal resistance, import different signals and carry out verification, guarantee that analog input module satisfies the assurance accuracy requirement of equipment.
2. simulation output precision
On active station, send analog output signal,, on the respective terminal of control rack, check the output current of assembly simultaneously as the aperture instruction of valve.Minimum value, intermediate value, 3 detection outputs of maximal value are done in requirement, and 10%, 50%, 90% 3 point is made in the requirement that has, and guarantees to simulate output precision and satisfies accuracy requirement.
3. digital input module
On terminal cabinet,, check whether the input lamp of assembly is normally lighted, on active station, observe the signal accepting state of respective point position simultaneously and write down the corresponding action state by do the test of open and close signal with shorting stub or voltage signal analog contacts.
4. digital output precision
On active station, set the open and close state and switch, check the break-make of corresponding output end or the action situation of corresponding relay at terminal cabinet.
Four, the simulation test of instrument system
Blind controller system and electric, three complete electric control systems of computing machine composition need to finish whole interface testings before systems modelling.
Debugged at all monomer instrument and equipment and to have finished, when the scene possesses simulation test and requires, site monomer instrument and indoor demonstration control instrument can have been formed single system and carry out static simulation and test.
1. the condition of systems modelling
The in-situs tester table in the simulation test scope and the installation of topworks are finished; Instrument cable all lays and finishes, and Insulation Test is qualified; Relevant speciality has been debugged and has been finished, and finishes with the interface test of PLC/DCS; Adjusting of various technological parameters all confirmed.
2. detect the systems modelling in indication loop
With signal generators such as standard meter or the loop tester on-site signal of instrument such as analog temperature, pressure, flow at the scene, whether the indicated value that is associated in the inspection chamber is entirely true, and systematic error should adhere to specification; The analogue value should comprise the starting point and the terminal point of range, is at least 3 points, at most can be to 10 points, and this example is got 5 points; Signal to on-site signal point should be distinguished active, passive and signal kinds; To the monitoring point of warning interlock requirement is arranged, make analog warning test, check alarm logging and print-on-alarm function.
3. the systems modelling of operation control circuit
On indoor operational control unit, manually export the steering order of analog or digital signal, simultaneously switching characteristic, the aperture situation of on-the-spot electrically operated valve, variable valve, indicator, solenoid valve etc. are checked that the action error value should meet precision and designing requirement.
4. the systems modelling in interlocking of signals loop
In each circuit system, need in system, to report to the police and chain signal, reach setting value by analogue instrument signal at the scene, check whether regular event and confirming of relevant interlock program, emergency cut-off, defencive function and alarm set point.
Reach setting value by certain instrument signal of simulation at the scene or on the operational control unit, after control system is carried out data processing through function calculation, sequential control etc., check the course of action of relevant device, in proper order, whether parameter such as time-delay meet design requirement, and finally satisfy the production-line technique requirement.
Five, instrument system cooperates joint-trial
Finish and detect under the normal situation in the test working of equipment monomer, can carry out instrument system and cooperate joint-trial.
In joint-trial, the instrument specialty should with mechanical, electrical each professional close fit, detect, control by platform equipment and operation automatically according to the order of technological process, the Interlock Status of the running order of equipment, delay time, instrument shows signal, relevant device etc. is confirmed one by one.
Six, zero load interlock test run
Field erected equipment has passed through and has supplied just can enter zero load interlock test run after the debugging of distribution debugging, Electrified Transmission debugging, instrument and meter for automation and automation control system.
The communication in requirement, test run order, check criteria, the test run, record format that test run is confirmed or the like will have a definite purpose before the test run.Also have just in case the counter-measure of the accident that meets accident.
The interlock test run also is the continuation to the equipment component debugging, also is the continuation of checking application software.So must carry out according to plan, satisfy manufacturing technique requirent fully totally.

Claims (2)

1. debugging method of dry-quenching automatic meter system, carry out successively as follows: a. debugging conventional instrument, b. debug special instrument, c. detects simulation test, the e. instrument system of testing in-out box, d. instrument system and cooperates joint-trial and the zero load interlock test run of f., it is characterized in that:
When a. debugging conventional instrument, conventional instrument carries out monomer in meter specially debugging chamber and debugs in advance, debugged conventional instrument is carried out sensitivity, positive stroke and revesal, fundamental error and return difference adjustment, debugged conventional instrument press 5 in code requirement work with high scale just, the flyback verification
When c. detecting the test in-out box, use standard signal generator, on the system cabinet respective terminal, add standard analog signal, the simulated field detection signal, by active station screen viewing corresponding signal displayed value, do minimum value, intermediate value, 3 input detections of maximal value
D. the simulation test of instrument system comprises systems modelling, the systems modelling of operation control circuit and the systems modelling in interlocking of signals loop that detects the indication loop, when detecting the systems modelling in indication loop, with signal generators such as standard meter or the loop tester on-site signal of analog temperature, pressure, flow instrument at the scene, the analogue value comprises the starting point and the terminal point of range, gets 3~10 points; During the systems modelling in interlocking of signals loop; reach setting value by analogue instrument signal at the scene; check whether regular event and confirming of relevant interlock program, emergency cut-off, defencive function and alarm set point, the course of action of checkout facility, in proper order, delay parameter.
2. debugging method of dry-quenching automatic meter system as claimed in claim 1, it is characterized in that: when c. detects the test in-out box, use standard signal generator, on the system cabinet respective terminal, add standard analog signal, the simulated field detection signal, by active station screen viewing corresponding signal displayed value, doing 10%, 50%, 90% 3 input detects, on active station, send analog output signal, on the respective terminal of control rack, check the output current of assembly simultaneously, do at 10%, 50%, 90% 3 and detect output.
CN200910053483A 2009-06-19 2009-06-19 Debugging method of dry-quenching automatic meter system Active CN101929882B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910053483A CN101929882B (en) 2009-06-19 2009-06-19 Debugging method of dry-quenching automatic meter system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910053483A CN101929882B (en) 2009-06-19 2009-06-19 Debugging method of dry-quenching automatic meter system

Publications (2)

Publication Number Publication Date
CN101929882A true CN101929882A (en) 2010-12-29
CN101929882B CN101929882B (en) 2012-09-05

Family

ID=43369188

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910053483A Active CN101929882B (en) 2009-06-19 2009-06-19 Debugging method of dry-quenching automatic meter system

Country Status (1)

Country Link
CN (1) CN101929882B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587910A (en) * 2012-03-01 2012-07-18 山西中新唐山沟煤业有限责任公司 Debugging method of automatic working surface device of thin coal seam drum shearer
CN103033389A (en) * 2012-12-29 2013-04-10 昆明醋酸纤维有限公司 Interlocking testing method for standby boiler of protection device
CN104142161A (en) * 2014-07-31 2014-11-12 天津二十冶建设有限公司 Quick debugging method for thermal meter on construction site
CN107831754A (en) * 2017-11-09 2018-03-23 上海高桥捷派克石化工程建设有限公司 A kind of instrument fault method for removing for ABS composite material process units
CN113759814A (en) * 2021-08-02 2021-12-07 上海二十冶建设有限公司 Step-by-step debugging method for tundish car electrical system of continuous casting machine
CN113790781A (en) * 2021-09-15 2021-12-14 中国航发沈阳黎明航空发动机有限责任公司 Online calibration method for blade water flow testing equipment

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200955955Y (en) * 2006-10-12 2007-10-03 武汉钢铁(集团)公司 Dry quenched coke tank bias detecting device

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587910A (en) * 2012-03-01 2012-07-18 山西中新唐山沟煤业有限责任公司 Debugging method of automatic working surface device of thin coal seam drum shearer
CN103033389A (en) * 2012-12-29 2013-04-10 昆明醋酸纤维有限公司 Interlocking testing method for standby boiler of protection device
CN103033389B (en) * 2012-12-29 2015-12-23 昆明醋酸纤维有限公司 A kind of method of stand-by boiler interlock test of proterctive equipment
CN104142161A (en) * 2014-07-31 2014-11-12 天津二十冶建设有限公司 Quick debugging method for thermal meter on construction site
CN107831754A (en) * 2017-11-09 2018-03-23 上海高桥捷派克石化工程建设有限公司 A kind of instrument fault method for removing for ABS composite material process units
CN113759814A (en) * 2021-08-02 2021-12-07 上海二十冶建设有限公司 Step-by-step debugging method for tundish car electrical system of continuous casting machine
CN113790781A (en) * 2021-09-15 2021-12-14 中国航发沈阳黎明航空发动机有限责任公司 Online calibration method for blade water flow testing equipment
CN113790781B (en) * 2021-09-15 2023-10-27 中国航发沈阳黎明航空发动机有限责任公司 Online calibration method for blade water flow test equipment

Also Published As

Publication number Publication date
CN101929882B (en) 2012-09-05

Similar Documents

Publication Publication Date Title
CN101929882B (en) Debugging method of dry-quenching automatic meter system
CN102087347B (en) Charged test method for current transformer and application thereof
CN105550499B (en) A kind of metering device health degree computational methods
CN101255947B (en) Metered system for automatically capturing fluid flux
CN104898052B (en) The check system and method for switch mechanical characteristic testing device based on IEC61850
CN105548945B (en) A kind of electric energy meter thermodynamic state verification method
CN109188082A (en) A kind of Transformer condition evaluation based on BP neural network
CN105044649B (en) A kind of current transformer error horizontal dynamic detection method and system
CN101539616A (en) Method for detecting accuracy of optical current transformer for measuring
CN105425142A (en) Test method of high-voltage switch motion mechanical property test system
CN102590783A (en) Method for detecting error of indication of electric energy of high voltage energy meter and assessing qualification
CN107907764B (en) Detection method and system suitable for intelligent characteristic verification of intelligent instrument
CN202547815U (en) Main oil temperature change verification apparatus
CN205880191U (en) A isolated plant for being directed at electric energy meter that possesses CT secondary circuit state monitor function carries out global function and detects
CN109613465B (en) Metering supervision method for automatic verification assembly line of low-voltage current transformer
CN103984250B (en) Multi-gear resistance output device and detecting system
DE19501044A1 (en) Detecting leaks in pipes carrying liquid or gases
CN206021071U (en) A kind of diesel engine side monitoring box test system
CN206470331U (en) A kind of transformer operation characteristic evaluating platform based on environmental impact factor
CN112504389B (en) Electric contact water level gauge measuring system and measuring method and diagnosis method thereof
CN104635195B (en) Beam pumping unit applied load electric energy meter error on-spot tester
CN111814302B (en) Transformer insulating oil temperature acquisition transmission loop fault removal system and method
CN105548939A (en) Voltage transformer state detection method
Baen The value of controls and monitoring for electrical heat tracing
CN110864924A (en) Testing device and testing method for converter valve cooling system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant