CN101929579B - 干熄焦仪表管线敷设方法 - Google Patents

干熄焦仪表管线敷设方法 Download PDF

Info

Publication number
CN101929579B
CN101929579B CN200910053485XA CN200910053485A CN101929579B CN 101929579 B CN101929579 B CN 101929579B CN 200910053485X A CN200910053485X A CN 200910053485XA CN 200910053485 A CN200910053485 A CN 200910053485A CN 101929579 B CN101929579 B CN 101929579B
Authority
CN
China
Prior art keywords
pipeline
cable
laying
wire
instrument
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN200910053485XA
Other languages
English (en)
Other versions
CN101929579A (zh
Inventor
宋德翔
刘作安
胡斌
朱忠荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN200910053485XA priority Critical patent/CN101929579B/zh
Publication of CN101929579A publication Critical patent/CN101929579A/zh
Application granted granted Critical
Publication of CN101929579B publication Critical patent/CN101929579B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)
  • Rigid Pipes And Flexible Pipes (AREA)

Abstract

本发明涉及冶金设备仪表装置安装领域,具体为一种干熄焦仪表管线敷设方法。一种干熄焦仪表管线敷设方法,包括仪表管路施工和电缆电线敷设,仪表管路施工按如下步骤依次进行:作业准备、洞孔准备、敷设管路、固定管路、管路严密性试验、检验管路、吹扫管路、管路上涂刷保温油漆和验收,电缆电线敷设按如下步骤依次进行:作业准备、敷设预埋管、敷设电缆桥架、敷设电缆电线管路、敷设电源电缆、敷设信号控制电缆、连接电缆电线、伴热管线保温和验收。本发明的有益效果是:步骤合理,安装可靠,安全系数高,质量高。

Description

干熄焦仪表管线敷设方法
技术领域
本涉及冶金设备仪表装置安装领域,具体为一种干熄焦仪表管线敷设方法。
背景技术
干法熄焦是目前世界上新诞生的一项冶炼节能技术,其英文名称为Coke Dry Quenching,简称CDQ。干熄焦是用循环惰性气体为热载体,由循环风机将冷的循环气体输入红焦冷却室冷却高温焦炭至250℃以下排出。吸收焦炭热量后的循环热气导入废热锅炉回收热量,产生蒸汽。循环气体冷却、除尘后,再经风机返回冷却室,如此循环冷却红焦。干熄焦锅炉产生的蒸汽或并入厂内蒸汽管网或送去发电。干熄焦技术是重大节能项目,由于在密闭系统内完成熄焦过程,与通常湿熄焦相比,可基本消除酚、HCN、H2S、NH3的排放,减少焦尘排放,且节省熄焦用水。干熄焦的仪表管线敷设作业是通过各种管道、电缆电线的敷设安装,把现场分散的仪表和操作室、控制室连接起来,构成完整的控制系统,达到干熄焦装置能安全生产的目的。安装工程所涉及的仪表种类有:仪表柜、箱、温度仪表、压力仪表、流量仪表、各种传感器、物位仪表、气体分析仪表、秤量仪表等,涉及的安装地点有:干熄焦本体、锅炉、除氧给水泵站、干熄焦除尘、发电系统、循环水泵房、操作室、控制室等。干熄焦的仪表管线敷设作业是干熄焦能否正常开工安全生产的重要保证,但由于干熄焦技术属新兴领域,国内采用此法的单位仅有寥寥数家几家企业,对于干熄焦设备的安装还处在摸索阶段,存在着很多不科学、不合理的地方,安装过程复杂。
发明内容
为了克服现有技术的缺陷,提供一种安全可靠的仪表管线敷设方法,本发明公开了一种干熄焦仪表管线敷设方法。
本发明通过如下技术方案达到发明目的:
一种干熄焦仪表管线敷设方法,包括仪表管路施工和电缆电线敷设,仪表管路施工按如下步骤依次进行:作业准备、洞孔准备、敷设管路、固定管路、管路严密性试验、检验管路、吹扫管路、管路上涂刷保温油漆和验收,电缆电线敷设按如下步骤依次进行:作业准备、敷设预埋管、敷设电缆桥架、敷设电缆电线管路、敷设电源电缆、敷设信号控制电缆、连接电缆电线、伴热管线保温和验收,其特征是:仪表管路施工时,作业准备时,用无缝管作为仪表管道,管材选用铜或不锈钢,同时准备角钢支架、“U”型螺栓和“Ω”型管卡;敷设管路时,根据施工设计选用不同材质、不同大小的管材。根据安装长度需要对管材进行切割或连接。仪表管道的连接方法采用焊接、压接、丝接或法兰连接,仪表管道的弯制采用机械冷弯,弯曲半径应符合施工规范的要求。固定管路时,仪表管道边敷设边固定,不同的管道采用不同的固定方式。当仪表管道沿水平方向敷设时,应根据不同的介质及测量要求,设有1∶10~1∶100的坡度,其倾斜方向用以排除气体或冷凝液,管路严密性试验时,当试验压力小于1.6×106帕且管路内介质为气体时,采用气压试压,其试验压力为管路设计压力的1.15倍,当达到试验压力后,保持压力5分钟,压力下降值不大于试验压力的1%即为合格,其他试验压力工质时管路严密性试验采用液压进行,其试验压力为管路设计压力的1.25倍,当达到试验压力后,继续保持压力5分钟,无泄漏即为合格;管路上涂刷保温油漆时,根据不同测量介质,选用不同色标的油漆,与被测介质工艺管路或设备的色标相同;
电缆电线敷设时,作业准备时,准备电源电缆、控制电缆、信号电缆、普通导线、伴热导线、补偿导线、电缆桥架、黑铁管、镀锌管,并且连接清理管道、安装电缆的仪表设备;敷设电缆桥架时,桥架安装时应与建筑物、构筑物具有相同的坡度,行进方向变化时角度变化在15°~45°之间,敷设电缆电线管路时,管路中挠性连接处采用以塑料被覆的金属软管,采用螺纹连接的管子,在螺纹连接处做接地跨接线,管路的固定采用“U”型螺栓或“Ω”型管卡,暴露在室外的电缆管在电缆穿入之后,其管口采用防水胶泥封堵严密,伴热管线保温采用电伴热时,在敷设电热线前检查其外观和绝缘,绝缘电阻值不小于1兆欧。
本发明的有益效果是:步骤合理,安装可靠,安全系数高,质量高。
附图说明
图1是本发明中仪表管路施工的流程图;
图2是本发明中电缆电线敷设的流程图;
图3是本发明中伴热管线保温结构的轴测图;
图4是图3的I-I剖视图。
具体实施方式
现需在干熄焦设备内敷设仪表管线,敷设过程包括仪表管路施工和电缆电线敷设,仪表管路施工流程图如图1所示,按如下步骤依次进行:作业准备、洞孔准备、敷设管路、固定管路、管路严密性试验、检验管路、吹扫管路、管路上涂刷保温油漆和验收。
作业准备时,仪表管道管材用无缝管,管材料选用铜或不锈钢管敷设管路时,根据施工设计选用不同材质、不同大小的管材。根据安装长度需要对管材进行切割或连接。仪表管道的连接方法采用焊接、压接、丝接或法兰连接,仪表管道的弯制采用机械冷弯,弯曲半径应符合施工规范的要求。固定管路时,仪表管道边敷设边固定,不同的管道采用不同的固定方式。当仪表管道沿水平方向敷设时,应根据不同的介质及测量要求设有坡度,其倾斜方向用以排除气体或冷凝液,管路严密性试验时,当管路内介质为气体时采用气压试压,其他试验压力工质时管路严密性试验采用液压进行,管路上涂刷保温油漆时,根据不同测量介质,选用不同色标的油漆,与被测介质工艺管路或设备的色标相同。
电缆电线敷设流程图如图2所示,按如下步骤依次进行:作业准备、敷设预埋管、敷设电缆桥架、敷设电缆电线管路、敷设电源电缆、敷设信号控制电缆、连接电缆电线、伴热管线保温和验收。作业准备时,准备电源电缆、控制电缆、信号电缆、普通导线、伴热导线、补偿导线、电缆桥架、黑铁管、镀锌管,并且连接清理管道、安装电缆的仪表设备;敷设电缆桥架时,桥架安装时应与建筑物、构筑物具有相同的坡度,敷设电缆电线管路时,管路中挠性连接处采用以塑料被覆的金属软管,采用螺纹连接的管子,在螺纹连接处做接地跨接线,管路的固定采用“U”型螺栓或“Ω”型管卡,暴露在室外的电缆管在电缆穿入之后,其管口采用防水胶泥封堵严密,伴热管线保温采用电伴热时,在敷设电热线前检查其外观和绝缘,绝缘电阻值不小于1兆欧。
电缆电线敷设时,拌热管线保温采用电伴热的结构如图3和图4所示,导压管1和伴热铜管2之间衬有石棉带3,伴热铜管2选用φ8mm×1mm的紫铜管,石棉带3厚度3mm,导压管1、伴热铜管2和石棉带3都穿在岩棉管壳4的内部,岩棉管壳4外用厚度为0.3mm镀锌铁皮5裹紧,镀锌铁皮5外用φ0.9mm镀锌铁丝6捆扎。

Claims (1)

1.一种干熄焦仪表管线敷设方法,包括仪表管路施工和电缆电线敷设,仪表管路施工按如下步骤依次进行:作业准备、洞孔准备、敷设管路、固定管路、管路严密性试验、检验管路、吹扫管路、管路上涂刷保温油漆和验收,电缆电线敷设按如下步骤依次进行:作业准备、敷设预埋管、敷设电缆桥架、敷设电缆电线管路、敷设电源电缆、敷设信号控制电缆、连接电缆电线、伴热管线保温和验收,其特征是:仪表管路施工时,作业准备时,用无缝管作为仪表管道,管材选用铜或不锈钢,同时准备角钢支架、“U”型螺栓和“Ω”型管卡;敷设管路时,仪表管道的连接方法采用焊接、压接、丝接或法兰连接,仪表管道的弯制采用机械冷弯,固定管路时,仪表管道边敷设边固定,当仪表管道沿水平方向敷设时设有坡度,管路严密性试验时,管路内介质为气体时采用气压试压,其他试验压力工质时管路严密性试验采用液压进行;
电缆电线敷设时,作业准备时,准备电源电缆、控制电缆、信号电缆、普通导线、伴热导线、补偿导线、电缆桥架、黑铁管、镀锌管,并且连接清理管道、安装电缆的仪表设备;敷设电缆桥架时,桥架安装时与建筑物、构筑物具有相同的坡度,敷设电缆电线管路时,管路中挠性连接处采用以塑料被覆的金属软管,采用螺纹连接的管子,在螺纹连接处做接地跨接线,管路用卡子固定,暴露在室外的电缆管在电缆穿入之后,其管口采用防水胶泥封堵严密。
CN200910053485XA 2009-06-19 2009-06-19 干熄焦仪表管线敷设方法 Active CN101929579B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910053485XA CN101929579B (zh) 2009-06-19 2009-06-19 干熄焦仪表管线敷设方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910053485XA CN101929579B (zh) 2009-06-19 2009-06-19 干熄焦仪表管线敷设方法

Publications (2)

Publication Number Publication Date
CN101929579A CN101929579A (zh) 2010-12-29
CN101929579B true CN101929579B (zh) 2012-07-04

Family

ID=43368916

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910053485XA Active CN101929579B (zh) 2009-06-19 2009-06-19 干熄焦仪表管线敷设方法

Country Status (1)

Country Link
CN (1) CN101929579B (zh)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104242191B (zh) * 2013-06-20 2016-08-10 五冶集团上海有限公司 苯加氢工程仪表管线敷设方法
CN104676195A (zh) * 2015-03-06 2015-06-03 华能无锡电热器材有限公司 仪表用保温管
CN108414134A (zh) * 2018-03-19 2018-08-17 浙江省水利河口研究院 一种闸泵建筑物底板渗压计的埋设装置及其安装方法
CN108488543A (zh) * 2018-04-04 2018-09-04 山西省工业设备安装集团有限公司 一种分布式瓦斯发电安装方法
CN113187953B (zh) * 2021-04-27 2022-05-31 成都建工工业设备安装有限公司 一种机电管线穿越沉降缝部位定位辅助施工方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1884888A (zh) * 2005-06-20 2006-12-27 吕迎智 热电厂蒸汽管道铺设方法
CN101319738A (zh) * 2008-06-25 2008-12-10 江苏江都建设工程有限公司 地辐热管道的一种敷设施工方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1884888A (zh) * 2005-06-20 2006-12-27 吕迎智 热电厂蒸汽管道铺设方法
CN101319738A (zh) * 2008-06-25 2008-12-10 江苏江都建设工程有限公司 地辐热管道的一种敷设施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
JP特开2004-80953A 2004.03.11
JP特开平9-312924A 1997.12.02

Also Published As

Publication number Publication date
CN101929579A (zh) 2010-12-29

Similar Documents

Publication Publication Date Title
CN101929579B (zh) 干熄焦仪表管线敷设方法
CN108980504B (zh) 长输管线电伴热系统以及其铺设方法
CN107449730B (zh) 一种流动腐蚀介质中90°弯头金属腐蚀电化学测试装置
CN104242191B (zh) 苯加氢工程仪表管线敷设方法
CN201622133U (zh) 磁力表面温度传感器
CN104655549A (zh) 电站锅炉烟气低温酸露点腐蚀实验装置
CN101928579B (zh) 干熄焦火灾自动报警系统安装方法
CN208938670U (zh) 一种柔软耐高温传输信号电缆
CN101760206B (zh) 干熄焦电气配管及管内穿线安装方法
CN206929972U (zh) 电磁加热装置
CN206515282U (zh) 用于锅炉化学清洗系统的在线测量装置
CN106769814A (zh) 一种低温腐蚀检测系统及其检测方法
CN206302103U (zh) 内置测温探头的汽轮机推力瓦及轴瓦防漏油结构
CN203811519U (zh) Adss光缆试验装置
CN101256026A (zh) 原油长输管道电热膜安全加热系统及其施工方法
CN206742835U (zh) 一种电缆接地箱
CN108844688A (zh) 一种用于低温换热器泄漏监测的系统及方法
JPH0972489A (ja) 漏洩センサ付き蒸気供給用断熱管
CN209910182U (zh) 一种石墨烯发热管及石墨烯热水设备
CN104880283B (zh) 一种烟道换能器故障检测装置及方法
CN106532573A (zh) 825型合金矿物绝缘发热电缆伴热的施工方法
CN208313524U (zh) 一种用于低温换热器泄漏监测的系统
CN111550606A (zh) 一种热力管道施工方法
CN113075509A (zh) 水内冷发电机线棒水电接头绝缘在线监测装置及监测方法
CN111519192A (zh) 一种开放式阴极保护电流量和电位分布的测定方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant