CN101899840A - Prefabricated split inspection well - Google Patents
Prefabricated split inspection well Download PDFInfo
- Publication number
- CN101899840A CN101899840A CN2009100273934A CN200910027393A CN101899840A CN 101899840 A CN101899840 A CN 101899840A CN 2009100273934 A CN2009100273934 A CN 2009100273934A CN 200910027393 A CN200910027393 A CN 200910027393A CN 101899840 A CN101899840 A CN 101899840A
- Authority
- CN
- China
- Prior art keywords
- inspection well
- inspection shaft
- prefabricated
- inspection
- prefabricated split
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The invention discloses a prefabricated split inspection well, in particular water supply and drainage pipeline inspection wells and a cable inspection well used in municipal construction. The prefabricated split inspection well consists of an inspection well body, an inspection well cover and a base; an inspection well cover support and the inspection well body are integrated into a whole; and reinforced concrete is cast into special moulds to form various components, and the components are transported to a construction site for assembly. The prefabricated split inspection well can be prevented from settlement or the well body can be prevented from being damaged according to geology and road technical standard configuration technical elements; the inspection well cover support and the inspection well body are integrally cast so as to stop separation; and the prefabricated split inspection well is produced in factories, the construction cost is reduced and the time for occupying the construction site is shortened.
Description
Affiliated technical field:
The present invention relates to a kind of prefabricated split inspection shaft, specifically refer to employed upper and lower waterpipe inspection shaft and cable inspection shaft in the municipal construction.
Background technology:
At present, all there are three big defectives in the numerous inspection shafts on the road of city: the 1st, inspection shaft lid is urib founding, because of the time have that well lid is stolen to stay the life trap to road; The 2nd, all inspection shafts are brick well and embody a construction, and handle the gene basis and brick well body technique standard is difficult to control, and common bulk settling and the breakage of well body influence vehicle ', increase vehicle loss and city noise; 3, no matter be metal or nonmetal well lid, its lid holder all is bonding by cement and well body, the time have lid holder and well body to break away from generation, influence traffic, increase municipal maintenance cost.
Summary of the invention:
To be solved by this inventionly be, a kind of prefabricated split inspection shaft is provided, promptly, behind the independent assembly of reinforced concrete prefabricated one-tenth, be transported to the job site and be assembled into integrated inspection well according to the geology and the road technical standard batch production configuring technical key element in city.
Technical scheme:
The technical solution adopted in the present invention is: prefabricated split inspection shaft is by the inspection shaft body, and inspection shaft covers, and pedestal constitutes, the holder of inspection shaft lid is as a whole with the inspection shaft body, pedestal is provided with positioning table, in the mould of special use, be cast into each assembly by steel concrete after, be transported to the job site and assemble.
The invention has the beneficial effects as follows: can prevent sedimentation or the breakage of well body according to geology and road technical standard configuring technical key element; Holder of inspection shaft lid and the integral cast of inspection shaft body stop to break away from; Batch production is produced, and reduces construction cost and reduces the holding time of job site.
Description of drawings:
The present invention is further described below in conjunction with accompanying drawing.
Fig. 1 is each assembly generalized section before the prefabricated split inspection shaft assembling;
Fig. 2 is a prefabricated split inspection shaft assembling back generalized section.
Among the figure: (1), inspection shaft body, (2), inspection shaft lid, (3), pedestal, (4), pipeline (cable) mouth, (5), positioning table, the holder of (6), inspection shaft lid.
The specific embodiment:
In the embodiment in figure 1, prefabricated split inspection shaft is by inspection shaft body (1), and inspection shaft covers (2), and pedestal (3) constitutes.The bottom of inspection shaft body (1) is reserved with pipeline (cable) mouthful (4), makes things convenient for the attended operation of pipeline; Pedestal (3) diameter greater than inspection shaft body (1) base diameter to ensure enough anti-sedimentation bearing capacity, be provided with positioning table (5) simultaneously, the diameter of positioning table (5) and inspection shaft body (1) bottom internal diameter coincide, except that guaranteeing to install time location accurate, also can prevent to cause inspection shaft body (1) displacement because of the external force effect; Inspection shaft lid holder (6) is same body structure with inspection shaft body (1), has eliminated the hidden danger that the inspection shaft lid asks (6) and inspection shaft body (1) to break away from.
In the embodiment of Fig. 2, prefabricated inspection shaft split assembly is transported to the job site, in ready-made inspection shaft hole, settle pedestal (3) earlier, to allow behind pipeline (cable) mouthful (4) alignment tube line position according to pipeline trend again, positioning table (5) on the pedestal (3) will be inserted in inspection shaft body (1) bottom, at last inspection shaft be covered (2) the inspection shaft lid holder (6) of packing into, promptly finish the assembling of an integrated inspection well, saved a large amount of on-site construction times.
Claims (4)
1. a prefabricated split inspection shaft comprises the inspection shaft body, the inspection shaft lid, and pedestal is characterized in that: be prefabricated into each independent assembly by batch production on the reinforced concrete, be transported to the job site and assemble integrated inspection well.
2. prefabricated split inspection shaft according to claim 1 is characterized in that: described inspection shaft body can be according to different purposes provided pipe road junctions or cable port.
3. prefabricated split inspection shaft according to claim 1 is characterized in that: described inspection shaft body and the holder of inspection shaft lid are as a whole.
4. prefabricated split inspection shaft according to claim 1, it is characterized in that: described pedestal is provided with positioning table, and the diameter of positioning table and inspection shaft body bottom internal diameter coincide.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100273934A CN101899840A (en) | 2009-06-01 | 2009-06-01 | Prefabricated split inspection well |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100273934A CN101899840A (en) | 2009-06-01 | 2009-06-01 | Prefabricated split inspection well |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101899840A true CN101899840A (en) | 2010-12-01 |
Family
ID=43225727
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009100273934A Pending CN101899840A (en) | 2009-06-01 | 2009-06-01 | Prefabricated split inspection well |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101899840A (en) |
-
2009
- 2009-06-01 CN CN2009100273934A patent/CN101899840A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103015719B (en) | Preliminary work for spudding steel concrete wastewater disposal basin monobloc cast technique | |
CN205530344U (en) | Utility tunnel is pour to split type no mould | |
CN201593194U (en) | Prefabricated spilt inspection well | |
CN107059910B (en) | Spigot-and-socket concrete filled steel tube deposits beam pedestal and its construction method | |
CN202131613U (en) | Lined prefabricated reinforced concrete inspection well | |
CN202248241U (en) | Combined type rainwater filter well | |
CN101899840A (en) | Prefabricated split inspection well | |
CN102296633A (en) | Prefabricating pipe shaft | |
CN203188238U (en) | Assembled type prefabricated reinforced concrete combined inspection well | |
CN202440836U (en) | Prefabricated inspection well | |
CN204436457U (en) | The prefabricated evacuation platform of a kind of shield structure running tunnel | |
CN202925483U (en) | Prefabricated assembly type reinforced concrete culvert opening | |
CN203270608U (en) | Prefabricated combined pipe rack | |
CN202577351U (en) | Multi-use combined plastic inspection well | |
CN102943583B (en) | Method for constructing cast-in-situ steel concrete modular sewage treatment facility for town | |
CN102619273B (en) | Conveyable integration sewage collecting and conveying integrated device | |
CN204040061U (en) | Prefabricated pipe gallery | |
CN202416533U (en) | Multi-tube convergence inspection well with butt-jointed pipe top | |
CN202298871U (en) | Straight wall plastic inspection well | |
CN202509609U (en) | Conveyable integrated sewage collecting and conveying integral device | |
CN201883455U (en) | Reinforced concrete prefabricated combined inspection shaft | |
CN202248244U (en) | Integrated sewage delivery device | |
CN217399865U (en) | Assembled precast concrete inspection shaft | |
CN201962781U (en) | Sewage water inspection well | |
CN202440837U (en) | Precast concrete inspection shaft with settlement function |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Open date: 20101201 |