CN201883455U - Reinforced concrete prefabricated combined inspection shaft - Google Patents
Reinforced concrete prefabricated combined inspection shaft Download PDFInfo
- Publication number
- CN201883455U CN201883455U CN2010206520416U CN201020652041U CN201883455U CN 201883455 U CN201883455 U CN 201883455U CN 2010206520416 U CN2010206520416 U CN 2010206520416U CN 201020652041 U CN201020652041 U CN 201020652041U CN 201883455 U CN201883455 U CN 201883455U
- Authority
- CN
- China
- Prior art keywords
- inspection shaft
- reinforced concrete
- concrete prefabricated
- prefabricated combined
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Sewage (AREA)
Abstract
A reinforced concrete prefabricated combined inspection shaft belongs to municipal engineering facilities. Elongated through slots are correspondingly arranged on opposite lateral walls of the bottom position of a shaft body. The inspection shaft is reasonable and simple in structure, simple, convenient and rapid in construction and installation, high in construction efficiency and low in construction cost, and is labor-saving and material-saving.
Description
Technical field
The utility model belongs to municipal facilities, relates generally to the operation part in the plumbing facility.
Background technology
Traditional reinforced concrete prefabricated combined inspection shaft all is to be provided with corresponding manhole on the opposing sidewalls of well body, when water service pipe or gutter construction and installation, must install simultaneously to, gutter and manhole, and make to, gutter inserting and in the manhole of well body, pass.The manhole difficulty of construction of this structure is big, and difficulty is installed, and efficiency of construction is low.
Summary of the invention
The purpose of this utility model is exactly the problem that exists at above-mentioned prior art, and design provides a kind of reinforced concrete prefabricated combined inspection shaft of new construction, reaches the purpose that convenient construction was installed, improved efficiency of construction, reduces construction cost.
Basic design of the present utility model is, reinforced concrete prefabricated combined inspection shaft comprises equipped successively from top to bottom walling crib, well lid and well body, and correspondence is offered long through groove on the opposing sidewalls at position, well body bottom side.
The utility model reasonable in design, simple, construction and installation are simple and efficient, the efficiency of construction height, construction cost is low, labor and material saving.
Description of drawings
Fig. 1 is reinforced concrete prefabricated combined inspection shaft general structure schematic diagram;
Fig. 2 is that the A-A of Fig. 1 is to sectional view.
Piece number explanation among the figure:
1, walling crib, 2, well lid, 3, well body, 4, long through groove.
The specific embodiment
Below in conjunction with accompanying drawing the utility model optimum implementation is described in detail.Reinforced concrete prefabricated combined inspection shaft comprises equipped successively from top to bottom walling crib 1, well lid 2 and well body 3, and correspondence is offered long through groove 4 on the opposing sidewalls at position, well body 3 bottom side.
During installation, can be about to be laid on underground earlier, then this manhole is configured in to, gutter top to, gutter, utilize long through groove 4 to ride to fit on, the gutter, well body 3 is combined with supplying drainage upside outer wall, use the cement paste seal clearance again, promptly finish construction and installation.
Claims (1)
1. a reinforced concrete prefabricated combined inspection shaft comprises equipped successively from top to bottom walling crib (1), well lid (2) and well body (3), it is characterized in that correspondence is offered long through groove (4) on the opposing sidewalls at well body (3) position, bottom side.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010206520416U CN201883455U (en) | 2010-12-10 | 2010-12-10 | Reinforced concrete prefabricated combined inspection shaft |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010206520416U CN201883455U (en) | 2010-12-10 | 2010-12-10 | Reinforced concrete prefabricated combined inspection shaft |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201883455U true CN201883455U (en) | 2011-06-29 |
Family
ID=44180993
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010206520416U Expired - Fee Related CN201883455U (en) | 2010-12-10 | 2010-12-10 | Reinforced concrete prefabricated combined inspection shaft |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201883455U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110528548A (en) * | 2019-07-15 | 2019-12-03 | 中国一冶集团有限公司 | The prefabricated sedimentation well of one kind and the drawing prefabricated sedimentation well construction method of push pipe |
-
2010
- 2010-12-10 CN CN2010206520416U patent/CN201883455U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110528548A (en) * | 2019-07-15 | 2019-12-03 | 中国一冶集团有限公司 | The prefabricated sedimentation well of one kind and the drawing prefabricated sedimentation well construction method of push pipe |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201883454U (en) | Prefabricated reinforced-concrete assembly-type combined inspection well chamber | |
CN205530344U (en) | Utility tunnel is pour to split type no mould | |
CN207268009U (en) | A kind of underground pipe gallery drainage system based on existing blowdown canal | |
CN202227694U (en) | Embedded sleeve for concrete pouring construction of bathroom floor | |
CN201883455U (en) | Reinforced concrete prefabricated combined inspection shaft | |
CN201679008U (en) | Rigid water drainage device for foundation pit | |
CN201817819U (en) | Prefabricated assembled reinforced concrete rectangular inspection well chamber | |
CN204435531U (en) | Plastic inspection well | |
CN201358469Y (en) | Prefabricated armored concrete combined type inspection shaft | |
CN203755435U (en) | Integrated prefabricated pump station with large-rubbish removal function | |
CN202000463U (en) | Prefabricated reinforced concrete drainage inspection well | |
CN2813746Y (en) | Assembling sewage treating tank | |
CN201972231U (en) | Sewage inspection well | |
CN203514353U (en) | Glass fiber reinforced plastics inspection well | |
CN203475578U (en) | Novel inspection well | |
CN202577351U (en) | Multi-use combined plastic inspection well | |
CN202000461U (en) | Novel anti-seepage drainage system | |
CN201981105U (en) | Prefabricated reinforced concrete manure pit | |
CN202745186U (en) | Novel drainage inspection shaft | |
CN204456203U (en) | Manhole | |
CN205116382U (en) | Prefabricated pump station of integration with deodorizing device | |
CN204939229U (en) | Small precast assembled steel reinforced concrete life-stylize manure pit | |
CN204058205U (en) | upper and lower combined plastic septic tank assembly | |
CN203960988U (en) | A kind of mouthful embedded plastic inspection well | |
CN201770588U (en) | Combined type septic tank |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
DD01 | Delivery of document by public notice |
Addressee: Wang Lixin Document name: Notification to Pay the Fees |
|
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |