CN101895102B - 继电保护整定计算集中式一体化的应用方法 - Google Patents
继电保护整定计算集中式一体化的应用方法 Download PDFInfo
- Publication number
- CN101895102B CN101895102B CN 201010250026 CN201010250026A CN101895102B CN 101895102 B CN101895102 B CN 101895102B CN 201010250026 CN201010250026 CN 201010250026 CN 201010250026 A CN201010250026 A CN 201010250026A CN 101895102 B CN101895102 B CN 101895102B
- Authority
- CN
- China
- Prior art keywords
- company
- system operation
- operation modes
- calculating
- operational mode
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Emergency Protection Circuit Devices (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
公开了一种易于实现各公司运行方式的有效交互的继电保护整定计算集中式一体化的应用方法,将运行方式分为系统运行方式和公司运行方式两个等级,公司运行方式由公司根据本公司实际运行情况进行设置,系统运行方式由各公司运行方式组合而成;各公司在计算各保护定值时,根据组合结果形成的各种系统运行方式进行整定计算,在系统运行方式的基础上对本公司中计算保护的相邻支路和各公司边界母线上所连支路进行组合轮检,获得整定参数的极值,在此基础上进行整定计算,其中整定参数包括电流最值、分支系数。
Description
技术领域
本发明涉及电力技术领域,尤其涉及一种继电保护整定计算集中式一体化的应用方法。
背景技术
在电力系统信息化建设中,早期各级电网继电保护整定计算工作均独立开展,各公司之间的相互影响通过发送等值数据的方式进行,各公司之间一般一年发布一次对其他公司的等值数据。获取等值数据后,各公司将其他公司对本公司的影响手工录入到本公司的整定计算模型中。由于等值发布间隔长,在等值发布的间隔期中,各公司电网均发生了不同情况的变化,这些变化对其他公司的保护装置动作情况均有一定的影响。这种工作模式下,无法准确反映电网电网互联互通的特点,造成继电保护整定计算结果的不准确,从而影响整个电网的安全稳定运行。
针对传统继电保护整定计算模式的缺陷,提出了一种全新的符合当前电网特点的新的应用思想,即继电保护整定计算集中式一体化应用方案,多级电网共用一张电网模型进行联合整定计算。在这种新的模式下,由于各级电网在同一模型下应用,具备了各公司能实时响应整个电网变化的前提条件。
但是由于运行方式的特殊性,每个公司的用户仅了解本公司的运行方式,也只能设置本公司设备的运行方式。多级电网共用一张电网模型进行联合整定计算要解决的主要技术难题就是各公司之间的运行方式交互问题。
发明内容
为克服现有技术的缺陷,本发明要解决的技术问题是提供了一种易于实现各公司运行方式的有效交互的继电保护整定计算集中式一体化的应用方法。
本发明的技术方案是:这种继电保护整定计算集中式一体化的应用方法,将运行方式分为系统运行方式和公司运行方式两个等级,公司运行方式由公司根据本公司实际运行情况进行设置,系统运行方式由各公司运行方式组合而成;各公司在计算各保护定值时,根据组合结果形成的各种系统运行方式进行整定计算,在系统运行方式的基础上对本公司中计算保护的相邻支路和各公司边界母线上所连支路进行组合轮检,获得整定参数的极值,在此基础上进行整定计算,其中整定参数包括电流最值、分支系数。
通过系统方式的引入,每个公司整定计算的过程中可以将系统中各公司的运行方式的变化反应到本公司的整定计算结果中,体现多级电网共用一张电网模型联合整定计算数据交互及时、准确的优点。
附图说明
图1为采用本发明的方法的流程图。
具体实施方式
下面通过附图和实施例,对本发明的技术方案做进一步的详细描述。
这种继电保护整定计算集中式一体化的应用方法,将运行方式分为系统运行方式和公司运行方式两个等级,公司运行方式由公司根据本公司实际运行情况进行设置,系统运行方式由各公司运行方式组合而成;各公司在计算各保护定值时,根据组合结果形成的各种系统运行方式进行整定计算,在系统运行方式的基础上对本公司中计算保护的相邻支路和各公司边界母线上所连支路进行组合轮检,获得整定参数的极值,在此基础上进行整定计算,其中整定参数包括电流最值、分支系数。
如图1所示,该方法包括以下步骤:
(1)各公司建立本公司运行方式,公司运行方式由公司内设备的投退、变压器接地刀闸的开合共同确定。
(2)系统根据各公司运行方式自动组合为系统运行方式。如多级电网中共有A、B、C三个公司,每个公司有两种运行方式,A公司有A1、A2两种运行方式,B公司有B1、B2两种运行方式,C公司有C1、C2两种运行方式。A公司在整定计算过程中系统运行方式共包括考虑8种系统方式,分别由各种公司运行方式组合而成,组合后的系统运行方式包括F1(A1,B1,C1组合),F2(A1,B2,C1组合),F3(A1,B1,C2组合),F4(A1,B2,C2组合),F5(A2,B1,C1组合),F6(A2,B2,C1组合),F7(A2,B1,C2组合),F8(A2,B2,C2组合)。各公司用户将系统运行方式作为整定计算的基础方式,包括(F1,F2,F3,F4,F5,F6,F7,F8)。
(3)各公司计算本公司保护时,在各个系统方式的基础上,对计算保护的相邻支路和各公司之间边界母线上支路进行组合轮检,根据轮检后的方式计算出对应的整定参数。
根据DL/T 584-2007《3~110KV电网继电保护装置运行整定规程》,DL/T 559-2007《220~750kV电网继电保护装置运行整定规程》的规定,整定计算过程中需要考虑N-1轮检,对应到多级电网同一网络模型的联合整定计算,需要考虑多公司的不检修和仅检修一条支路进行组合。
考虑到影响最大的情况,需要考虑本支路的相邻支路和公司间边界母线所连支路的检修组合。边界母线所连支路支路主要考虑线路,边界母线上所连的变压器的方式设置通过各公司设置的公司方式确定,不考虑轮检。
如计算A公司支路AL1上的保护,AL1的相邻支路有AL2,A公司和B公司的边界母线ABBUS1上的支路有ALine1,ALine2,A公司和C公司的边界母线ACBUS1上的支路有ALine3,ALine4,则轮检包括如下情况:不检修、检修AL2,检修ALine1,检修ALine2,检修ALine3,检修ALine4,检修(AL2,ALine1),检修(AL2,ALine2),检修(AL2,ALine3),检修(AL2,ALine4),检修(AL2,ALine1,ALine3),检修(AL2,ALine1,ALine4),检修(AL2,ALine2,ALine3),检修(AL2,ALine2,ALine4)。
(4)根据整定参数的计算结果完成整定计算,得到整定计算结果。
以上所述,仅是本发明的较佳实施例,并非对本发明作任何形式上的限制,凡是依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化与修饰,均仍属本发明技术方案的保护范围。
Claims (2)
1.一种继电保护整定计算集中式一体化的应用方法,其特征在于,将运行方式分为系统运行方式和公司运行方式两个等级,公司运行方式由公司内设备的投退、变压器接地刀闸进行设置,系统运行方式由各公司运行方式组合而成;各公司在计算各保护定值时,根据组合结果形成的各种系统运行方式进行整定计算,在系统运行方式的基础上对本公司中计算保护的相邻支路和各公司边界母线上所连支路进行组合轮检,获得整定参数的极值,在此基础上进行整定计算,其中整定参数包括电流最值和分支系数。
2.根据权利要求1所述的继电保护整定计算集中式一体化的应用方法,其特征在于,该方法包括以下步骤:
(1)各公司建立本公司运行方式,公司运行方式由公司内设备的投退、变压器接地刀闸的开合共同确定;
(2)系统根据各公司运行方式自动组合为系统运行方式;
(3)各公司计算本公司保护时,在各个系统运行方式的基础上,对计算保护的相邻支路和各公司之间边界母线上支路进行组合轮检,根据轮检后的方式计算出对应的整定参数;
(4)根据整定参数的计算结果完成整定计算,得到整定计算结果。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010250026 CN101895102B (zh) | 2010-08-04 | 2010-08-04 | 继电保护整定计算集中式一体化的应用方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010250026 CN101895102B (zh) | 2010-08-04 | 2010-08-04 | 继电保护整定计算集中式一体化的应用方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101895102A CN101895102A (zh) | 2010-11-24 |
CN101895102B true CN101895102B (zh) | 2013-01-02 |
Family
ID=43104215
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201010250026 Expired - Fee Related CN101895102B (zh) | 2010-08-04 | 2010-08-04 | 继电保护整定计算集中式一体化的应用方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101895102B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102521305B (zh) * | 2011-12-01 | 2013-04-17 | 华中科技大学 | 继电保护整定计算的数据整合方法 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101242093A (zh) * | 2007-11-16 | 2008-08-13 | 燕山大学 | 基于多通道暂态极性方向比较算法的集成继电保护系统 |
CN101425682A (zh) * | 2008-12-11 | 2009-05-06 | 宜宾电业局 | 电网继电保护定值在线校核一体化数据处理方法 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11113157A (ja) * | 1997-10-06 | 1999-04-23 | Toshiba Corp | ディジタル保護リレー装置 |
-
2010
- 2010-08-04 CN CN 201010250026 patent/CN101895102B/zh not_active Expired - Fee Related
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101242093A (zh) * | 2007-11-16 | 2008-08-13 | 燕山大学 | 基于多通道暂态极性方向比较算法的集成继电保护系统 |
CN101425682A (zh) * | 2008-12-11 | 2009-05-06 | 宜宾电业局 | 电网继电保护定值在线校核一体化数据处理方法 |
Non-Patent Citations (2)
Title |
---|
JP平11-113157A 1999.04.23 |
仇向东,等.面向中调的整定计算软件的设计和开发.《电力信息化》.2007,39-41. * |
Also Published As
Publication number | Publication date |
---|---|
CN101895102A (zh) | 2010-11-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Sakar et al. | Integration of large-scale PV plants in non-sinusoidal environments: Considerations on hosting capacity and harmonic distortion limits | |
CN103746368B (zh) | 一种电力系统静态安全稳定运行极限优化方法 | |
CN103384068B (zh) | 电力系统暂态安全稳定紧急控制在线策略优化计算方法 | |
CN109063408B (zh) | 一种基于直算法的电磁机电暂态仿真方法 | |
CN101609989B (zh) | 一种城市电网供电充裕度计算系统 | |
CN109523303A (zh) | 一种基于节点边际电价的低压有源配电网阻塞管理方法 | |
CN103390893B (zh) | 一种水电站avc控制方法 | |
CN103986171A (zh) | 抑制次同步振荡的ssdc和sedc协调控制优化方法 | |
CN102801165A (zh) | 一种考虑静态安全性的自动电压控制方法 | |
CN105117560A (zh) | 一种中压配电线路理论线损计算方法 | |
CN106295952A (zh) | 一种高阻抗变压器限制短路电流效果的模糊综合评价方法 | |
Dartawan et al. | Case study: Applying IEEE Std. 519-2014 for harmonic distortion analysis of a 180 MW solar farm | |
CN103401249B (zh) | 一种基于无功设备可用资源的无功自动安排方法 | |
CN116247726A (zh) | 一种配网系统可接入容量计算及承载力评估方法、系统 | |
CN105474498A (zh) | 用于将电功率馈送到供电网中的方法 | |
CN101895102B (zh) | 继电保护整定计算集中式一体化的应用方法 | |
CN104767207A (zh) | 基于发电机无功储备灵敏度的电压稳定预防控制方法 | |
CN107451685A (zh) | 一种基于配电自动化的配电网规划lcc模型 | |
CN104362652A (zh) | 发电机励磁调差系数的控制方法和装置 | |
CN109829178B (zh) | 一种基于模型分割法的变电站实时仿真方法 | |
CN105354645A (zh) | 一种220kV变电站负荷转带方法 | |
CN104410071A (zh) | 一种35千伏高压配电网合解环电流估算方法 | |
CN115528670A (zh) | 基于多主体博弈的分布式电源及配套电网投资决策建模方法 | |
CN104201697A (zh) | 一种110kV及35kV电网无功优化补偿方法 | |
CN110661260B (zh) | 基于四绕组感应滤波变压器等效模型的电网潮流计算方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130102 Termination date: 20210804 |
|
CF01 | Termination of patent right due to non-payment of annual fee |