CN101886391A - Waterproof guide pipe for underwater concrete filling pile - Google Patents

Waterproof guide pipe for underwater concrete filling pile Download PDF

Info

Publication number
CN101886391A
CN101886391A CN 201010217625 CN201010217625A CN101886391A CN 101886391 A CN101886391 A CN 101886391A CN 201010217625 CN201010217625 CN 201010217625 CN 201010217625 A CN201010217625 A CN 201010217625A CN 101886391 A CN101886391 A CN 101886391A
Authority
CN
China
Prior art keywords
guide pipe
pipe
conduit
concrete
filling pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010217625
Other languages
Chinese (zh)
Inventor
黎明中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
WUHAN FIRST METALLURGICAL COMMUNICATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUHAN FIRST METALLURGICAL COMMUNICATION ENGINEERING Co Ltd filed Critical WUHAN FIRST METALLURGICAL COMMUNICATION ENGINEERING Co Ltd
Priority to CN 201010217625 priority Critical patent/CN101886391A/en
Publication of CN101886391A publication Critical patent/CN101886391A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to a guide pipe for a filling material for a borehole filling pile or an underwater concrete filling pile of an underground continuous wall and the like. The guide pipe consists of a bottom guide pipe (1), a middle guide pipe (2) on the upper part of the bottom guide pipe (1), an upper guide pipe (3) at the upper end of the middle guide pipe (2), and a hopper (4); a flexible inner pipe (5) is arranged in the bottom guide pipe (1), one end of the flexible inner pipe (5) is fixedly connected with the upper end of the bottom guide pipe (1), and the other end of the flexible inner pipe (5) is locked by using an elastic locker (6); and the pipe wall of the bottom guide pipe (1) is provided with a through hole (7). The guide pipe can effectively prevent underground water from entering the guide pipe at the bottom of the filling material to keep the filling guide pipe in a water-free state during construction so as to ensure the construction quality of the concrete filling pile; and the guide pipe can adapt to the filling of the underwater concrete filling pile under various environments, can be continuously constructed by reinserting a concrete mixture in midway, and has a simple structure and easy implementation.

Description

A kind of waterproof guide pipe of underwater concrete filling pile
Technical field
The present invention relates to the perfusion material conduit of underwater concrete filling pile, specifically belong to the conduit of the perfusion material of underwater concrete filling piles such as bored pile or diaphragm wall.
Background technology
At present, when underwater concretes such as bored pile, diaphragm wall poured into, often adopting bottom formula and side valve type also was two kinds of catheterized reperfusion technologies of water proof bolt.The bottom formula is to install bottom in the bottom of the used conduit of concrete perfusion, again conduit is slowly sunk at the bottom of the hole, back penetration concrete in anhydrous conduit, when progressively mentioning conduit, bottom comes off and stays in the concrete, after again according to process specification requirements perfusion concrete.
Side valve type is under the opened state of conduit bottom, conduit is slowly sunk at the bottom of the hole 0.3~0.5 meter depths; Before concrete perfusion, guiding valve is put on the water surface in the conduit; Then first batch of concrete mix is filled up, after cut off the iron wire that hangs guiding valve, guiding valve and concrete mix descend along pipe, the water in the pipe is extruded, guiding valve just comes off and stays in the base concrete of hole, after pour into concrete according to technological requirement again.Its advantage: can pour into a large amount of concrete rapidly to depth of water place, without draining, implement and utensil are simple.Its deficiency: the conduit of bottom formula is bigger to buoyancy when water is dark, and must add the counterweight of offsetting buoyancy this moment, as for 10 meters with headwater depth, then the conduit very difficulty that just falls because bottom is blocked bottom the conduit, utilizes the clear hole of conduit to become also very difficult in addition.And the conduit construction requirement strictness of side valve type, otherwise easily produce water injection through pipe and make the quality problems of concrete disintegration; If conduit stops up the tremie concrete that can not placing of concrete then must adopt the bottom formula again, waste time and energy, construction quality also is difficult for guaranteeing.In addition, stick to the concrete that condenses on the pipe inner wall, in time clear Xian otherwise knock and easily cause deformation of guide tube to influence construction quality, especially very unfavorable to the quality of castinplace pile, have a strong impact on the quality of the building of on this castinplace pile, building, even can cause very big harm.
The perfusion material conduit of present employed cast-in-place concrete pile, because there is certain irrationality in structure, when concrete perfusion, there are vegetables suddenly descend muddy water then can enter in the conduit slightly, the perfusion material of underground muddy water and castinplace pile is mixed, thereby will be extremely harmful to the quality of castinplace pile pile body, have a strong impact on construction quality, this is that institute is unallowed.In case this problem occurs, then can cause doing over again, perfusion is time-consuming, take material again, influences programming, causes the increasing of construction cost.
Summary of the invention
The objective of the invention is to overcome above-mentioned deficiency, provide a kind of and can prevent effectively that underground muddy water from entering the conduit of perfusion, guarantee the waterproof guide pipe of the underwater concrete filling pile of cast-in-place concrete pile construction quality.
Realize the technical measures of above-mentioned purpose:
A kind of waterproof guide pipe of underwater concrete filling pile, upper end conduit, the hopper of its intermediate conductor by bottom conduit, conduit top, bottom, intermediate conductor upper end are formed.It is: pipe in the flexibility is installed in the conduit of bottom, and an end of flexible interior pipe is fixedlyed connected with the upper end of bottom conduit, and the other end of flexible interior pipe blocks with the elasticity locker; On the tube wall of bottom conduit, be provided with through hole.
It is: the elasticity locker is a clamping hoop type or annular.
It is: the material of pipe is percolation-proof and wear-resisting rubber, engineering plastics material in flexible.
The present invention compared with prior art, it can prevent effectively that underground water from entering the conduit of perfusion material bottom, make in the inherent work progress of perfusion cannula and remain anhydrous state, thereby guarantee the construction quality of cast-in-place concrete pile, for solid basis has been established in next step building operations, and can be adapted to the perfusion of underwater concrete filling pile under the various ambient conditionss, also can continue construction because of certain reason can repeat to insert concrete mix midway, and simple in structure, very easily implement.
Description of drawings
Fig. 1 is the structural representation of the bottom conduit of cast-in-place concrete pile
Fig. 2 is the contour structures schematic diagram of bottom conduit among Fig. 1
Fig. 3 is the structural representation of clip shape elasticity locker among Fig. 1
Fig. 4 is the structural representation of cyclic spring locker among Fig. 1
Fig. 5 is the structural representation of flexible interior pipe among Fig. 1
The specific embodiment
Be further described below in conjunction with accompanying drawing
A kind of waterproof guide pipe of underwater concrete filling pile, its intermediate conductor 2 by bottom conduit 1, bottom conduit 1 top, the upper end conduit 3 of intermediate conductor 2 upper ends, hopper 4 are formed.It processes equally distributed through hole 7 on the tube wall of bottom conduit 1; Again in bottom conduit 1 installation can prevent to seep water and wear-resisting rubber material or engineering plastics flexible in manage 5, its can prevent to seep water and wear-resisting rubber material or engineering plastics flexible in the upper end of an end and bottom conduit 1 of pipe 5 by bolt or clip or peg graft fast and fixedly connected, can prevent to seep water and wear-resisting rubber material or engineering plastics flexible in the other end of pipe 5 tight with clamping hoop type or cyclic spring locker 6 envelopes, and be the state that freely hangs.
Principle
Before concrete spouting, can prevent to seep water and wear-resisting rubber material or engineering plastics flexible in pipe 5 owing to blocked by clamping hoop type or cyclic spring locker 6, underground muddy water is entered less than in the pipe 5 in this flexibility, and, owing to the through hole 7 on bottom conduit 1 tube wall has entering of underground water and mud to make the interior pipe 5 of this flexibility and the inwall of bottom conduit 1 is to separate shape, and should manage 5 owing to the pressure that is subjected to outside muddy water is close in the flexibility, thereby guaranteed and to be in dry state by the interior pipe 5 of flexibility; When the concrete spouting material passes through catheter perfusion, because the concrete spouting material has an impact force to pipe 5 in this flexibility, make muddy water between the inwall of pipe 5 and bottom conduit 1 in this flexibility under pressurized by through hole 7 and the discharge of conduit 1 end opening, increase along with pipe 5 concrete spouting material in this flexibility, pipe 5 and the inwall of bottom conduit 1 are for pasting state mutually in this flexibility, the concrete spouting material struts clamping hoop type or cyclic spring locker 6, makes the concrete spouting materials flow go out in this flexibility pipe 5 and pours into into cast-in-place concrete pile.When pipe 5 in this flexibility is damaged by the concrete spouting material or clamping hoop type or cyclic spring locker 6 can not then should in time be changed in should flexibility during pipe 5 lockings.Plugging appears in running into the extraordinary circumstances construction, insert in the concrete of having poured into a mould more under water after then conduit can being extracted cleaning, this process makes that the concrete pouring quality is unaffected proceeds that because of above-mentioned principle has kept anhydrous in the pipe this point is that traditional handicraft method institute is unvanquishable.

Claims (3)

1. the waterproof guide pipe of a underwater concrete filling pile, upper end conduit (3), the hopper (4) of its intermediate conductor (2) by bottom conduit (1), bottom conduit (1) top, intermediate conductor (2) upper end are formed, it is characterized in that: pipe (5) in the flexibility is installed in bottom conduit (1), an end of pipe (5) is fixedlyed connected with the upper end of bottom conduit (1) in flexible, and the other end of flexible interior pipe (5) blocks with elasticity locker (6); On the tube wall of bottom conduit (1), be provided with through hole (7).
2. the waterproof guide pipe of a kind of underwater concrete filling pile as claimed in claim 1 is characterized in that: elasticity locker (5) is for clamping hoop type or annular.
3. the waterproof guide pipe of a kind of underwater concrete filling pile as claimed in claim 1 is characterized in that: the material of pipe (5) is percolation-proof and wear-resisting rubber, engineering plastics in flexible.
CN 201010217625 2010-06-25 2010-06-25 Waterproof guide pipe for underwater concrete filling pile Pending CN101886391A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010217625 CN101886391A (en) 2010-06-25 2010-06-25 Waterproof guide pipe for underwater concrete filling pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010217625 CN101886391A (en) 2010-06-25 2010-06-25 Waterproof guide pipe for underwater concrete filling pile

Publications (1)

Publication Number Publication Date
CN101886391A true CN101886391A (en) 2010-11-17

Family

ID=43072468

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010217625 Pending CN101886391A (en) 2010-06-25 2010-06-25 Waterproof guide pipe for underwater concrete filling pile

Country Status (1)

Country Link
CN (1) CN101886391A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102995642A (en) * 2012-12-26 2013-03-27 广西建工集团第三建筑工程有限责任公司 Underwater concrete spouting laitance prevention water-proof device
CN106400808A (en) * 2016-12-06 2017-02-15 新疆新工勘岩土工程勘察设计院有限公司 Waterproof-bolt-proof underwater pouring construction device and application method thereof
CN110331725A (en) * 2019-04-25 2019-10-15 黄宗海 A kind of construction method of water proof pouring underwater concrete

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4129008A (en) * 1975-05-28 1978-12-12 Kajima Kensetsu Kabushiki Kaisha Tremie tube
US4199279A (en) * 1977-03-25 1980-04-22 The Shimizu Construction Co., Ltd. Method and apparatus for placing concrete under water
CN1337499A (en) * 2000-08-04 2002-02-27 泰昇机械租赁有限公司 Method for pouring concrete into guide pipe in non-driven pile

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4129008A (en) * 1975-05-28 1978-12-12 Kajima Kensetsu Kabushiki Kaisha Tremie tube
US4199279A (en) * 1977-03-25 1980-04-22 The Shimizu Construction Co., Ltd. Method and apparatus for placing concrete under water
CN1337499A (en) * 2000-08-04 2002-02-27 泰昇机械租赁有限公司 Method for pouring concrete into guide pipe in non-driven pile

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102995642A (en) * 2012-12-26 2013-03-27 广西建工集团第三建筑工程有限责任公司 Underwater concrete spouting laitance prevention water-proof device
CN106400808A (en) * 2016-12-06 2017-02-15 新疆新工勘岩土工程勘察设计院有限公司 Waterproof-bolt-proof underwater pouring construction device and application method thereof
CN106400808B (en) * 2016-12-06 2018-10-16 新疆新工勘岩土工程勘察设计院有限公司 A kind of no water proof bolt underwater grouting constructing device and its application method
CN110331725A (en) * 2019-04-25 2019-10-15 黄宗海 A kind of construction method of water proof pouring underwater concrete

Similar Documents

Publication Publication Date Title
CN102168420B (en) Method for processing soft soil base by geotextile light active material piles
CN111074899A (en) Grouting method for karst caves with different filling types
CN102134852A (en) Concrete pouring device and method
CN101886391A (en) Waterproof guide pipe for underwater concrete filling pile
CN104975612B (en) Open caisson construction new technology waterborne
CN106381869A (en) Double-protective barrel impact pile-forming method at silt rock soil layer
CN107587502A (en) A kind of spiral-digging pore pressure pour water soil occlusion curtain pile construction method
CN211973505U (en) A slip casting system for different filling type karsts
CN101586341B (en) Water sealing method for civil engineering groundwork
CN201738323U (en) Underwater concrete filling pile conduit capable of preventing underground water from entering to concrete
US10626574B2 (en) Device for building an underwater construction, filter apparatus for a corresponding device and method for building an underwater construction
CN206529769U (en) Cast-in-situ bored pile underwater concrete pouring steel conduit
CN204238221U (en) Continuous wall grab special (purpose) rubber pipe
CN104060622A (en) Method for discharging water in pint through steel bucket in pit
CN1337499A (en) Method for pouring concrete into guide pipe in non-driven pile
CN104790380B (en) Underground diaphragm wall framework
CN206581271U (en) Water proof plug
CN210086320U (en) Anti-floating water drainage well structure
CN104912057B (en) Construction method of underground continuous wall
CN212641364U (en) Underwater leakage blocking structure system for concrete faced rockfill dam
CN210087318U (en) Underwater vertical shaft lining device
CN207362833U (en) A kind of karst cave treatment structure of diaphram wall
CN113445470A (en) Water seepage blocking structure for settlement joint of flood wall and construction process
CN206667239U (en) One kind expansion uplift pile
CN202969371U (en) Novel pipe pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: CHINA FIRST METALLURGICAL GROUP CO., LTD.

Free format text: FORMER OWNER: WUHAN YIYE TRAFFIC ENGINEERING CO., LTD.

Effective date: 20101216

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 430080 YIYE TECHNOLOGY BUILDING, NO. 3, GONGYE AVENUE, QINGSHAN DISTRICT, WUHAN CITY, HUBEI PROVINCE TO: 430081 NO. 3, GONGYE AVENUE, QINGSHAN DISTRICT, WUHAN CITY, HUBEI PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20101216

Address after: 430081 Wuhan Industrial Zone, Qingshan District, Hubei, No. 3

Applicant after: China First Metallurgical Group Co., Ltd.

Address before: The rule of science and Technology Building No. 3 430080 Hubei Province, Wuhan City Qingshan District Industrial Avenue

Applicant before: Wuhan First Metallurgical Communication Engineering Co., Ltd.

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20101117