CN101881028A - 一种筏板基础的施工方法 - Google Patents

一种筏板基础的施工方法 Download PDF

Info

Publication number
CN101881028A
CN101881028A CN 201010225831 CN201010225831A CN101881028A CN 101881028 A CN101881028 A CN 101881028A CN 201010225831 CN201010225831 CN 201010225831 CN 201010225831 A CN201010225831 A CN 201010225831A CN 101881028 A CN101881028 A CN 101881028A
Authority
CN
China
Prior art keywords
electric osmose
mattress layer
time
raft
raft foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010225831
Other languages
English (en)
Other versions
CN101881028B (zh
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Tongji Construction Group Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2010102258310A priority Critical patent/CN101881028B/zh
Publication of CN101881028A publication Critical patent/CN101881028A/zh
Application granted granted Critical
Publication of CN101881028B publication Critical patent/CN101881028B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开一种筏板基础的施工方法,其特征是筏板基础下设置褥垫层,褥垫层采用砂石混合料,厚度为30~40cm,褥垫层下部为刚性桩和地基土,刚性桩与褥垫层之间设置10cm聚苯板,褥垫层外围做围梁,围梁高度与褥垫层相同,宽度为25~30cm,围梁混凝土强度与筏板基础强度相同,褥垫层下面布置电渗井,电渗井深度为9~12m,最边缘电渗井离筏板边缘距离为30cm,边缘4排电渗井间距为2.5~3m,中间电渗井间距为3~4m,筏板四周设置排水沟,排水沟在褥垫层以下15~20cm,宽度为20~25cm。本发明造价低,可以有效地提高结构性能。

Description

一种筏板基础的施工方法
技术领域
本发明涉及建筑领域,特别涉及一种筏板基础的施工方法。
背景技术
由于筏板下应力分布特点是四周大、中间小,而沉降分布刚好相反,沉降分布特点是四周小、中间大。如果考虑到应力特点,优化设计要采用四周多布置桩,中间小布置桩。如果考虑到沉降特点,优化设计要采用四周小布置桩,中间多布置桩。显然两者存在矛盾,故传统基础方案是采用数量较多的桩来解决该矛盾。
发明内容
本发明所要解决的技术问题是提供一种筏板基础的施工方法,解决筏板基础的沉降分布和应力分布不同的问题。
本发明中筏板基础下设置褥垫层,褥垫层采用砂石混合料,厚度为30~40cm,褥垫层下部为刚性桩和地基土,刚性桩与褥垫层之间设置10cm聚苯板,设置聚苯板的目的是为了更好使刚性桩和土共同工作。褥垫层外围做围梁,围梁高度与褥垫层相同,宽度为25~30cm,围梁混凝土强度与筏板基础强度相同,设置围梁目的是为了避免在建筑物建造过程中褥垫层材料挤出造成沉降。褥垫层下面布置电渗井,电渗井深度为9~12m,最边缘电渗井离筏板边缘距离为30cm,边缘4排电渗井间距为2.5~3m,中间电渗井间距为3~4m。筏板四周设置排水沟,排水沟在褥垫层以下15~20cm,宽度为20~25cm。
褥垫层厚度采用30~40cm,传统褥垫层厚度为20~30cm,本实施方案中褥垫层厚度比传统褥垫层厚度大,由于通过电渗降水后土会固结下沉,而褥垫层会补偿下沉部分,促成桩土共同作用,提高了结构性能。
建筑物每砌筑一层结构,实行一次电渗降水。电渗降水后土固结会有一个过程,房子建造中土会出现固结,刚性桩逐渐嵌入褥垫层,既提高电渗效果,又使桩土协调作用效果加强,此外还缩短了工期。
本发明中电渗阳极采用桩钢筋,阴极采用
Figure BSA00000189674300011
的钢筋,电渗阳极有效利用了筏板基础下的桩钢筋,降低了电渗成本。
本发明中电渗降水不仅可以降低含水量,还可以提高桩侧摩阻力。另外,本发明电渗降水的作用在于有效提高了桩土共同作用的效果,这是由于浅部土通过电渗降水,形成硬壳层,硬壳层与刚性桩的刚度比比原来的刚度比有了大幅度的提高,有利于桩土协调变形。
为了防止连续长时间电渗造成电渗效率降低,电渗时间根据不同土质进行调整,对于淤泥质土,电渗时间为2~2.5h;对于粘土,电渗时间为2.5~3h;对于粉土,电渗时间为3~3.5h,对于砂土,电渗时间为3~4h。当电压变化超过10%,必须断电停止电渗,断电间歇时间为3~4h。
本发明造价低,可以减少差异沉降,有效地提高结构性能。
附图说明
图1筏板基础示意图
附图中:1、电渗井,2、褥垫层,3、围梁,4、排水沟,5、筏板。
具体实施方式
下面结合附图详细描述。
某建筑物系九层框架结构,建筑面积为3240m2,采用框架结构,该工程筏板厚度为60cm,桩基采用钻孔灌注桩。
本实施例中筏板基础下设置褥垫层,褥垫层采用砂石混合料,厚度为35cm,褥垫层下部为刚性桩和地基土,刚性桩与褥垫层之间设置10cm聚苯板,褥垫层外围做围梁,围梁高度高度为35cm,宽度为30cm,围梁混凝土强度为C30,褥垫层下面布置电渗井,电渗井深度为10m,最边缘电渗井离筏板边缘距离为30cm,边缘4排电渗井间距为2.5m,中间电渗井间距为3m。筏板四周设置排水沟,排水沟在褥垫层以下20cm,宽度为25cm。
建筑物每砌筑一层结构,实行一次电渗降水。电渗阳极采用钻孔灌注桩钢筋,阴极采用的钢筋。
本实施例的电渗时间为2.5~3h,当电压变化超过10%,必须断电停止电渗,断电间歇时间为3~4h。
该工程采用本发明优化设计后,钻孔灌注桩桩数量减少了36%,基础成本降低了26%,取得了显著的经济效益。工程竣工后差异沉降很小,建筑物未出现结构裂缝等不良现象,结构性能良好。

Claims (5)

1.一种筏板基础的施工方法,其特征是筏板基础下设置褥垫层,褥垫层采用砂石混合料,厚度为30~40cm,褥垫层下部为刚性桩和地基土,刚性桩与褥垫层之间设置10cm聚苯板,褥垫层外围做围梁,围梁高度与褥垫层相同,宽度为25~30cm,围梁混凝土强度与筏板基础强度相同,褥垫层下面布置电渗井,电渗井深度为9~12m,最边缘电渗井离筏板边缘距离为30cm,边缘4排电渗井间距为2.5~3m,中间电渗井间距为3~4m,筏板四周设置排水沟,排水沟在褥垫层以下15~20cm,宽度为20~25cm。
2.根据权利要求1所述的筏板基础的施工方法,其特征是建筑物每砌筑一层结构,实行一次电渗降水。
3.根据权利要求1或2所述的筏板基础的施工方法,其特征是电渗阳极采用桩钢筋,阴极采用的钢筋。
4.根据权利要求1或2所述的筏板基础的施工方法,其特征是:电渗时间根据不同土质进行调整,对于淤泥质土,电渗时间为2~2.5h;对于粘土,电渗时间为2.5~3h;对于粉土,电渗时间为3~3.5h,对于砂土,电渗时间为3~4h。当电压变化超过10%,必须断电停止电渗,断电间歇时间为3~4h。
5.根据权利要求3所述的筏板基础的施工方法,其特征是:电渗时间根据不同土质进行调整,对于淤泥质土,电渗时间为2~2.5h;对于粘土,电渗时间为2.5~3h;对于粉土,电渗时间为3~3.5h,对于砂土,电渗时间为3~4h。当电压变化超过10%,必须断电停止电渗,断电间歇时间为3~4h。
CN2010102258310A 2010-07-03 2010-07-03 一种筏板基础的施工方法 Expired - Fee Related CN101881028B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010102258310A CN101881028B (zh) 2010-07-03 2010-07-03 一种筏板基础的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010102258310A CN101881028B (zh) 2010-07-03 2010-07-03 一种筏板基础的施工方法

Publications (2)

Publication Number Publication Date
CN101881028A true CN101881028A (zh) 2010-11-10
CN101881028B CN101881028B (zh) 2011-07-20

Family

ID=43053154

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010102258310A Expired - Fee Related CN101881028B (zh) 2010-07-03 2010-07-03 一种筏板基础的施工方法

Country Status (1)

Country Link
CN (1) CN101881028B (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182174A (zh) * 2011-04-02 2011-09-14 河海大学 一种化学溶液注入电渗法联合碎石桩处理软土地基的施工方法
CN104499497A (zh) * 2014-11-21 2015-04-08 朱奎 混凝土夹砖折板基础
CN104711973A (zh) * 2015-01-07 2015-06-17 朱奎 小直径桩复合地基施工方法
CN104831737A (zh) * 2015-04-29 2015-08-12 孔志坚 地铁车站地下室支护施工方法
CN105220681A (zh) * 2015-10-26 2016-01-06 南京林业大学 一种微生物—电场联合加固可液化地基的方法
CN107700514A (zh) * 2017-03-08 2018-02-16 长江三峡勘测研究院有限公司(武汉) 一种关于软弱地基基础选择结构型式的处理方法
CN108457290A (zh) * 2018-05-25 2018-08-28 电联工程技术股份有限公司 一种预制装配式地基垫层围护结构
CN114809065A (zh) * 2022-04-13 2022-07-29 中国能源建设集团江苏省电力设计院有限公司 一种输电塔基础结构及施工方法

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110295667B (zh) * 2019-06-18 2020-11-27 中国一冶集团有限公司 一种装配式建筑用房施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003147783A (ja) * 2001-11-16 2003-05-21 Aichiken:Kk 建築物の免震基礎とその工法
CN2853905Y (zh) * 2005-07-06 2007-01-03 唐业清 一种抗沉陷地基基础结构
CN1948632A (zh) * 2006-10-19 2007-04-18 杨静明 深层软土地基加固方法
CN101476324A (zh) * 2009-01-20 2009-07-08 叶长青 筏板基础及其施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003147783A (ja) * 2001-11-16 2003-05-21 Aichiken:Kk 建築物の免震基礎とその工法
CN2853905Y (zh) * 2005-07-06 2007-01-03 唐业清 一种抗沉陷地基基础结构
CN1948632A (zh) * 2006-10-19 2007-04-18 杨静明 深层软土地基加固方法
CN101476324A (zh) * 2009-01-20 2009-07-08 叶长青 筏板基础及其施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《广州建筑》 20050228 李觉良,邹鸿洲 某大厦大体积钢筋混凝土筏板基础施工 全文 1-5 , 第2期 2 *
《福建建筑》 20100531 吴国信 某高层建筑考虑砂石垫层处理地基与筏板基础共同作用的工程实践 全文 1-5 , 第5期 2 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182174A (zh) * 2011-04-02 2011-09-14 河海大学 一种化学溶液注入电渗法联合碎石桩处理软土地基的施工方法
CN102182174B (zh) * 2011-04-02 2012-09-26 河海大学 一种化学溶液注入电渗法联合碎石桩复合地基方法
CN104499497A (zh) * 2014-11-21 2015-04-08 朱奎 混凝土夹砖折板基础
CN104711973A (zh) * 2015-01-07 2015-06-17 朱奎 小直径桩复合地基施工方法
CN104831737A (zh) * 2015-04-29 2015-08-12 孔志坚 地铁车站地下室支护施工方法
CN105220681A (zh) * 2015-10-26 2016-01-06 南京林业大学 一种微生物—电场联合加固可液化地基的方法
CN107700514A (zh) * 2017-03-08 2018-02-16 长江三峡勘测研究院有限公司(武汉) 一种关于软弱地基基础选择结构型式的处理方法
CN107700514B (zh) * 2017-03-08 2020-05-05 长江三峡勘测研究院有限公司(武汉) 一种关于软弱地基基础选择结构型式的处理方法
CN108457290A (zh) * 2018-05-25 2018-08-28 电联工程技术股份有限公司 一种预制装配式地基垫层围护结构
CN114809065A (zh) * 2022-04-13 2022-07-29 中国能源建设集团江苏省电力设计院有限公司 一种输电塔基础结构及施工方法

Also Published As

Publication number Publication date
CN101881028B (zh) 2011-07-20

Similar Documents

Publication Publication Date Title
CN101881028B (zh) 一种筏板基础的施工方法
CN202466620U (zh) 钢筋混凝土扶壁挡土墙
CN203174619U (zh) 倒筏板混凝土地坪
CN202117068U (zh) 微型桩板式复合基础
CN104060601B (zh) 利用预制工程桩桩基进行地基处理的施工方法
CN203066104U (zh) H型素砼砌块及其所砌成的小型生态挡土墙
CN109610436A (zh) 一种分块式吹填场地处理方法
CN204080822U (zh) 一种基坑边坡支护结构
CN202830673U (zh) 用地受限区既有路堤增高构造
CN102493427A (zh) 一种使用固化土作为堆载的堆场淤泥快速排水-快速固结施工方法
CN202530465U (zh) 一种基坑排水构造
CN202124863U (zh) 螺旋锚掏挖复合基础
CN207176614U (zh) 新型景观防波堤
CN204199131U (zh) 一种钢筋混凝土凹槽式路基
CN208981043U (zh) 市政道路工程用路基
CN204151767U (zh) Cfg桩与phc管桩组合复合地基
CN203334347U (zh) 箱涵式排水口结构
CN205012318U (zh) 一种软土地基处理装置
CN203066097U (zh) 一种柱墩式桩承台结构的桩筏基础结构
CN103015447A (zh) 一种柱墩式桩承台结构的桩筏基础结构
CN208279958U (zh) 一种饱和高填方路基结构
CN205368919U (zh) 一种公路软土地基处理接桩结构
CN102535464A (zh) 在厚层软土中打入预应力空心桩的施工方法
CN203462476U (zh) 一种风化石边坡的防护绿化结构
CN103912005A (zh) 一种地基基础结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: ANHUI TONGJI CONSTRUCTION GROUP CO., LTD.

Free format text: FORMER OWNER: ZHU KUI

Effective date: 20140327

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 325000 WENZHOU, ZHEJIANG PROVINCE TO: 230000 HEFEI, ANHUI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20140327

Address after: 230000 Anhui Province, Hefei city Yaohai District, Dangtu Road and road junction Jing Tai Building No. 1201

Patentee after: ANHUI TONGJI CONSTRUCTION GROUP Co.,Ltd.

Address before: 325000 Wenzhou City, Ouhai province Jingshan Hill group of the building of the 302 room, room 11, Zhejiang

Patentee before: Zhu Kui

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110720