CN101881003A - Installation method of post tensioned prestressed concrete box girders - Google Patents

Installation method of post tensioned prestressed concrete box girders Download PDF

Info

Publication number
CN101881003A
CN101881003A CN 201010232662 CN201010232662A CN101881003A CN 101881003 A CN101881003 A CN 101881003A CN 201010232662 CN201010232662 CN 201010232662 CN 201010232662 A CN201010232662 A CN 201010232662A CN 101881003 A CN101881003 A CN 101881003A
Authority
CN
China
Prior art keywords
slideway
prestressed concrete
concrete box
box girders
post tensioned
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010232662
Other languages
Chinese (zh)
Other versions
CN101881003B (en
Inventor
赵海莲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN2010102326623A priority Critical patent/CN101881003B/en
Publication of CN101881003A publication Critical patent/CN101881003A/en
Application granted granted Critical
Publication of CN101881003B publication Critical patent/CN101881003B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to an installation method of post tensioned prestressed concrete box girders, which is characterized by comprising the following steps of: (1) installation of a supporting device: laying a first supporting frame and a second supporting frame within a prestressed reinforcing steel tensile section along the installation direction of the post tensioned prestressed concrete box girders, laying a first slideway on the first supporting frame and a second slideway on the second supporting frame; (2) installation of the post tensioned prestressed concrete box girders: firstly, swinging up 5-12 post tensioned prestressed concrete box girders by adopting a gantry crane with the hoisting weight of 100t, and placing the post tensioned prestressed concrete box girders on the first slideway and the second slideway of the supporting device; and secondly, enabling the post tensioned prestressed concrete box girders to run on the first slideway and the second slideway by a hand-drive block so as to assemble two adjacent post tensioned prestressed concrete box girders. The invention has the advantages of simple and convenient construction and low cost.

Description

The mounting method of post tensioned prestressed concrete box girders
Technical field
The invention belongs to precast prestressed concrete case beam installation Technology field, be specifically related to a kind of mounting method of post tensioned prestressed concrete box girders.
Background technology
Each span centre of precast assembly section has 8-12 piece case beam by interim compressive pre-stress extruding the case beam closely to be bolted together with adhering with epoxy resin, stretch-draw steel hinge line then, form continuous span, after tension of prestressed tendon is intact, with its unloading (when bridge is installed be that construction section install with a tension of prestressed tendon section).Carry out next section precast concrete case beam and install, the whole bridge of prefabricated case beam only needs can satisfy the prefabricated case beam installation once striding half bracing frame.Precast concrete case beam adopts hoisting weight to lift for the 100t straddle truck, and the box-shaped sheet beam of lifting is sling with straddle truck, is placed on the support.There is the end face cleaning of shear connector clean the box-shaped plate, then two blocks of adjacent box-shaped plates are tried assembly unit, after corresponding convex-concave two sides matches fully, a box-shaped plate of back lifting is hung about last 1000m, the brushing work of epoxy resin is carried out in preparation, will glue a series of activities such as obedient duct sealing ring because of the duct that will carry out the brushing of epoxy resin, every beam between the every beam, every beam is all wanted just can finish about two hours, and straddle truck can not wait for a long time.
Summary of the invention
The mounting method that the purpose of this invention is to provide a kind of easy construction, post tensioned prestressed concrete box girders that cost is low.
For achieving the above object, the technical solution used in the present invention is: the mounting method of post tensioned prestressed concrete box girders is characterized in that it comprises the steps:
1) installation of bracing or strutting arrangement:
In a tension of prestressed tendon section, lay first bracing frame and second bracing frame along the direction that post tensioned prestressed concrete box girders is installed, first bracing frame is parallel with second bracing frame, on first bracing frame, lay first slideway, on second bracing frame, lay second slideway, first slideway is parallel with second slideway, and the spacing between first slideway and second slideway is less than the width of post tensioned prestressed concrete box girders bottom surface;
2) installation of post tensioned prestressed concrete box girders:
1. adopting hoisting weight is that the 100t straddle truck is placed on the handling of 5-12 piece post tensioned prestressed concrete box girders on first slideway and second slideway of bracing or strutting arrangement, has the end face cleaning of shear connector clean post tensioned prestressed concrete box girders;
2. by bottle gouard moved by hands post tensioned prestressed concrete box girders is walked on first slideway and second slideway, one end of bottle gouard moved by hands ties up on the post tensioned prestressed concrete box girders that has fixed, the other end of bottle gouard moved by hands ties up on the post tensioned prestressed concrete box girders that promptly will move, two adjacent post tensioned prestressed concrete boxes are carried out assembly unit, before corresponding convex-concave two sides matches fully, carry out the brushing work of epoxy resin; So far, finish the installation of post tensioned prestressed concrete box girders.
Method of the present invention makes full use of exactly to be set up dismounting bowl button frame is as support system (i.e. first bracing frame and second bracing frame) flexibly, easily, on the bracing frame of having set up, slideway is installed, adopt hoisting weight to be placed on first slideway and second slideway, by bottle gouard moved by hands post tensioned prestressed concrete box girders is walked on slideway then for the 100t straddle truck carries out handling precast concrete case beam.
The invention has the beneficial effects as follows:
1, easy construction, workable; (can under the narrow situation in place, carry out) applied widely.
2, use this method that post tensioned prestressed concrete box girders is installed, (this method cost is low) can reduce cost, bracing frame is set up dismounting flexibly, conveniently, and has comprehensive technology economic benefit (economic benefit, social benefit and environmental benefit are obvious) preferably.Solved the technical barrier that post tensioned prestressed concrete box girders also can be walked without straddle truck on slideway.
Description of drawings
Fig. 1 is the installation drawing of post tensioned prestressed concrete box girders;
Fig. 2 is the vertical view of Fig. 1;
Fig. 3 is the structural representation of first bracing frame;
Fig. 4 is the structural representation of first slideway;
Among the figure: 1-first bracing frame, 2-first slideway, 3-second bracing frame, 4-second slideway, 5-post tensioned prestressed concrete box girders, 6-sleeper, adjusting screw mandrel under the 7-, 8-bridging, 9-vertical rod, 10-adjusted screw mandrel, the horizontal i iron (14 of 11- #I iron), 12-cross bar, the vertical i iron (20 of 13- #I iron), 14-corrosion resistant plate, 15-polyfluortetraethylene plate, 16-steel plate.
The specific embodiment
As Fig. 1, Fig. 2, Fig. 3, shown in Figure 4, the mounting method of post tensioned prestressed concrete box girders, it comprises the steps:
1) installation of bracing or strutting arrangement:
Bracing or strutting arrangement comprises first bracing frame 1, first slideway 2, second bracing frame 3, second slideway 4;
In a tension of prestressed tendon section, lay first bracing frame 1 and second bracing frame 3 along the direction that post tensioned prestressed concrete box girders (abbreviation prefabricated case beam) is installed, first bracing frame 1 is parallel with second bracing frame 3, on first bracing frame 1, lay first slideway 2, on second bracing frame 3, lay second slideway 4, first slideway 2 is parallel with second slideway 4, and the spacing between first slideway 2 and second slideway 4 (is that post tensioned prestressed concrete box girders 5 can be shelved on first slideway 2 less than the width of post tensioned prestressed concrete box girders 5 bottom surfaces, on second slideway 4);
First bracing frame 1 comprises sleeper 6, following adjusting screw mandrel 7, bridging 8, vertical rod 9, adjusted screw mandrel 10, horizontal i iron 11, cross bar 12; The structure of second bracing frame 3 is identical with the structure of first bracing frame 1;
Concrete steps are:
1. preparation: suspender (snap ring, wire rope etc.) and tensioner are prepared; The examination of cementitious materials is joined with safety technics and is told somebody what one's real intentions are; Ground is handled: surperficial loose ground is removed in the backfill zone, changes the aggregate grading material compacting of filling out 500~800mm, the plain concrete sealing that 50~100mm is thick, and the thick iron plate of 10mm is spread on the surface; Original state ground will be adjusted to graded sand and stone on the same absolute altitude face to surperficial absolute altitude in length and breadth, and concrete thickness depends on the circumstances; Concrete surface is received light and is formed the gradient, must not ponding;
2. the laying of first bracing frame 1 and second bracing frame 3: in a tension of prestressed tendon section, longitudinally lay left sleeper row, the right sleeper row (basis of left sleeper row formation second bracing frame 3, right sleeper row constitutes the basis of first bracing frame 1), left sleeper row is parallel with right sleeper row; Each sleeper row's sleeper 6 and the spacing between the sleeper 6 are 600mm; The length and width of sleeper 6, the thick 2500mm*250mm*250mm that is of a size of;
Along laterally all establishing 7 following adjusting screw mandrels 7, the spacing of the following adjusting screw mandrel 7 on the same sleeper is 300mm on sleepers 6 all on left sleeper row and the right sleeper row;
Vertical rod 9 is installed on adjusting screw mandrel 7 under all, and (the vertical rod horizontal spacing is 300mm, longitudinal pitch is 600mm), by cross bar 12 fixing (the cross bar step pitch is 600mm), the vertical rod that is positioned at same sleeper top is by bridging 8 fixing (vertically the bridging spacing is 6000mm) between vertical rod 9 and the vertical rod 9;
In the upper end of all vertical rods 9 adjusted screw mandrel 10 is set;
On the adjusted screw mandrel 10 that is positioned at above the same sleeper, lay horizontal i iron 11 again; Form first bracing frame 1 and second bracing frame 3;
3. on the horizontal i iron 11 of first bracing frame 1, longitudinally lay vertical i iron 13 of first slideway 2, on the horizontal i iron 11 of second bracing frame 3, longitudinally lay vertical i iron 13 of second slideway 4;
First slideway 2 comprises vertical i iron 13, corrosion resistant plate 14, polyfluortetraethylene plate 15, steel plate 16; The structure of second slideway 4 is identical with the structure of first slideway 2;
At the upper surface spot welding corrosion resistant plate 14 of vertical i iron 13, lay polyfluortetraethylene plate 15 as slide plate at the upper surface of corrosion resistant plate 14, on polyfluortetraethylene plate 15, lay steel plate steel plate 16;
Vertical i iron 13 of first slideway 2 is parallel with vertical i iron 13 of second slideway 4, and the spacing between vertical i iron 13 of the vertical i iron 13 of first slideway 2 and second slideway 4 is less than the width of post tensioned prestressed concrete box girders 5 bottom surfaces; Form bracing or strutting arrangement;
2) installation of post tensioned prestressed concrete box girders:
1. adopting hoisting weight is that the 100t straddle truck is placed on the handling of 5-12 piece post tensioned prestressed concrete box girders on first slideway 2 and second slideway 4 of bracing or strutting arrangement, has the end face cleaning of shear connector clean post tensioned prestressed concrete box girders;
2. by bottle gouard moved by hands post tensioned prestressed concrete box girders 5 is walked on first slideway 2 and second slideway 4, one end of bottle gouard moved by hands ties up on the post tensioned prestressed concrete box girders that has fixed, the other end of bottle gouard moved by hands ties up on the post tensioned prestressed concrete box girders that promptly will move, and two adjacent post tensioned prestressed concrete boxes are carried out assembly unit;
Before matching fully, corresponding convex-concave two sides carries out the brushing work of epoxy resin; Because of the brushing that will carry out epoxy resin between the every beam, when using epoxy resin, from be brushed to be bonded together till, must in official hour, finish (smaller or equal to 2 hours), and concrete surface to keep dry state; Serviceability temperature is 5 ℃-30 ℃, as surpassing 30 ℃, allows to shorten greatly service time, also is difficult to use, so must use as early as possible behind the mix; During brushwork epoxy resin, generally use rubber brush, manually wear Rubber gloves and smear, the thickness of epoxy resin is advisable about with 1mm, and (the brushing amount of epoxy resin is 1.5Kg/m 2); Therefore a mix amount should suitably be controlled according to the brushing progress at scene; Epoxy resin tries not to adhere on the skin during use; If be stained with on the skin, use cloth and wipe or solvent scouring;
So far, finished the installation of post tensioned prestressed concrete box girders.

Claims (3)

1. the mounting method of post tensioned prestressed concrete box girders is characterized in that it comprises the steps:
1) installation of bracing or strutting arrangement:
In a tension of prestressed tendon section, lay first bracing frame (1) and second bracing frame (3) along the direction that post tensioned prestressed concrete box girders is installed, first bracing frame (1) is parallel with second bracing frame (3), go up laying first slideway (2) at first bracing frame (1), go up laying second slideway (4) at second bracing frame (3), first slideway (2) is parallel with second slideway (4), and the spacing between first slideway (2) and second slideway (4) is less than the width of post tensioned prestressed concrete box girders (5) bottom surface;
2) installation of post tensioned prestressed concrete box girders:
1. adopting hoisting weight is that the 100t straddle truck is placed on the handling of 5-12 piece post tensioned prestressed concrete box girders on first slideway (2) and second slideway (4) of bracing or strutting arrangement, has the end face cleaning of shear connector clean post tensioned prestressed concrete box girders;
2. by bottle gouard moved by hands post tensioned prestressed concrete box girders (5) is gone up walking at first slideway (2) and second slideway (4), one end of bottle gouard moved by hands ties up on the post tensioned prestressed concrete box girders that has fixed, the other end of bottle gouard moved by hands ties up on the post tensioned prestressed concrete box girders that promptly will move, two adjacent post tensioned prestressed concrete boxes are carried out assembly unit, before corresponding convex-concave two sides matches fully, carry out the brushing work of epoxy resin; So far, finish the installation of post tensioned prestressed concrete box girders.
2. the mounting method of post tensioned prestressed concrete box girders according to claim 1 is characterized in that: the installation of described bracing or strutting arrangement, and concrete steps are:
1. preparation: surperficial loose ground is removed in the backfill zone, changes the aggregate grading material compacting of filling out 500~800mm, the plain concrete sealing that 50~100mm is thick, and the thick iron plate of 10mm is spread on the surface; Original state ground will be adjusted to graded sand and stone on the same absolute altitude face to surperficial absolute altitude in length and breadth;
2. the laying of first bracing frame (1) and second bracing frame (3): in a tension of prestressed tendon section, longitudinally lay left sleeper row, right sleeper row, left side sleeper row constitutes the basis of second bracing frame (3), right sleeper row constitutes the basis of first bracing frame (1), and left sleeper row is parallel with right sleeper row; Each sleeper row's sleeper (6) and the spacing between the sleeper (6) are 600mm; The length and width of sleeper (6), the thick 2500mm*250mm*250mm that is of a size of;
All sleepers (6) are gone up along laterally all establishing 7 following adjusting screw mandrels (7) on left sleeper row and right sleeper row, and the spacing of the following adjusting screw mandrel (7) on the same sleeper is 300mm;
In all upward installation vertical rods (9) of adjusting screw mandrel (7) down, fixing by cross bar (12) between vertical rod (9) and the vertical rod (9), the vertical rod that is positioned at same sleeper top is fixing by bridging (8);
In the upper end of all vertical rods (9) adjusted screw mandrel (10) is set;
Go up and lay horizontal i iron (11) being positioned at adjusted screw mandrel (10) above the same sleeper again; Form first bracing frame (1) and second bracing frame (3);
3. on the horizontal i iron (11) of first bracing frame (1), longitudinally lay vertical i iron (13) of first slideway (2), on the horizontal i iron (11) of second bracing frame (3), longitudinally lay vertical i iron (13) of second slideway (4);
First slideway (2) comprises vertical i iron (13), corrosion resistant plate (14), polyfluortetraethylene plate (15), steel plate (16); The structure of second slideway (4) is identical with the structure of first slideway (2);
At the upper surface spot welding corrosion resistant plate (14) of vertical i iron (13), lay polyfluortetraethylene plate (15) as slide plate at the upper surface of corrosion resistant plate (14), go up at polyfluortetraethylene plate (15) and lay steel plate steel plate (16);
Vertical i iron (13) of first slideway (2) is parallel with vertical i iron (13) of second slideway (4), and the spacing between vertical i iron (13) of first slideway (2) and the vertical i iron (13) of second slideway (4) is less than the width of post tensioned prestressed concrete box girders (5) bottom surface; Form bracing or strutting arrangement.
3. the mounting method of post tensioned prestressed concrete box girders according to claim 1, it is characterized in that: the brushing amount of epoxy resin is 1.5Kg/m 2
CN2010102326623A 2010-07-21 2010-07-21 Installation method of post tensioned prestressed concrete box girders Expired - Fee Related CN101881003B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010102326623A CN101881003B (en) 2010-07-21 2010-07-21 Installation method of post tensioned prestressed concrete box girders

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010102326623A CN101881003B (en) 2010-07-21 2010-07-21 Installation method of post tensioned prestressed concrete box girders

Publications (2)

Publication Number Publication Date
CN101881003A true CN101881003A (en) 2010-11-10
CN101881003B CN101881003B (en) 2011-11-30

Family

ID=43053130

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010102326623A Expired - Fee Related CN101881003B (en) 2010-07-21 2010-07-21 Installation method of post tensioned prestressed concrete box girders

Country Status (1)

Country Link
CN (1) CN101881003B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103614972A (en) * 2013-11-06 2014-03-05 中铁二十一局集团第二工程有限公司 Steel truss vertical and horizontal position adjusting device
CN104612063A (en) * 2014-12-26 2015-05-13 北京交通大学 Concrete box beam first-aid repair method with prefabricated part on-site assembling combination beam
CN105155422A (en) * 2015-09-15 2015-12-16 中国一冶集团有限公司 Method for controlling pre-camber and pre-offsetting during mounting of post-tensioning precast prestressed concrete box girders
CN110777668A (en) * 2019-11-13 2020-02-11 中铁二院工程集团有限责任公司 Incremental launching construction method for precast concrete bridge deck slab of steel-concrete composite beam
CN112482740A (en) * 2020-10-27 2021-03-12 中国一冶集团有限公司 Large concave curved working face construction operation device and construction operation method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2752430A1 (en) * 1996-08-14 1998-02-20 Cmc Const Metalliques De Chand Movable coffering for concrete bridge
JP2003171008A (en) * 2001-12-03 2003-06-17 Mitsubishi Heavy Ind Ltd Method for erecting long member
RU2233937C1 (en) * 2002-11-20 2004-08-10 Открытое акционерное общество "ПКИ Крангормаш" Bridge building machine
KR100734418B1 (en) * 2006-10-27 2007-07-03 케이블텍 주식회사 The upper girder segment making yard of bridge using launching wall, and the incremental launching method of bridge with typical section and widen section using that
CN101158145A (en) * 2007-11-08 2008-04-09 中国第一冶金建设有限责任公司 Method for mounting trestle bridge segment box girder
CN101555681A (en) * 2009-04-14 2009-10-14 中铁一局集团有限公司 Integral-hole cross sliding construction process of segment assembled simple supported box beam

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2752430A1 (en) * 1996-08-14 1998-02-20 Cmc Const Metalliques De Chand Movable coffering for concrete bridge
JP2003171008A (en) * 2001-12-03 2003-06-17 Mitsubishi Heavy Ind Ltd Method for erecting long member
RU2233937C1 (en) * 2002-11-20 2004-08-10 Открытое акционерное общество "ПКИ Крангормаш" Bridge building machine
KR100734418B1 (en) * 2006-10-27 2007-07-03 케이블텍 주식회사 The upper girder segment making yard of bridge using launching wall, and the incremental launching method of bridge with typical section and widen section using that
CN101158145A (en) * 2007-11-08 2008-04-09 中国第一冶金建设有限责任公司 Method for mounting trestle bridge segment box girder
CN101555681A (en) * 2009-04-14 2009-10-14 中铁一局集团有限公司 Integral-hole cross sliding construction process of segment assembled simple supported box beam

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《大众科技》 20080731 屈明清,瞿翼 30m后张法预应力混凝土箱梁预制安装施工技术 全文 1-3 , 第7期 2 *
《福建建材》 20080131 岳克选 凉水河特大桥无碴轨道后张法预应力混凝土简支箱梁预制施工技术 全文 1-3 , 第1期 2 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103614972A (en) * 2013-11-06 2014-03-05 中铁二十一局集团第二工程有限公司 Steel truss vertical and horizontal position adjusting device
CN103614972B (en) * 2013-11-06 2016-08-17 中铁二十一局集团第二工程有限公司 Steel truss girder adjusting apparatus the most in place
CN104612063A (en) * 2014-12-26 2015-05-13 北京交通大学 Concrete box beam first-aid repair method with prefabricated part on-site assembling combination beam
CN105155422A (en) * 2015-09-15 2015-12-16 中国一冶集团有限公司 Method for controlling pre-camber and pre-offsetting during mounting of post-tensioning precast prestressed concrete box girders
CN110777668A (en) * 2019-11-13 2020-02-11 中铁二院工程集团有限责任公司 Incremental launching construction method for precast concrete bridge deck slab of steel-concrete composite beam
CN112482740A (en) * 2020-10-27 2021-03-12 中国一冶集团有限公司 Large concave curved working face construction operation device and construction operation method thereof

Also Published As

Publication number Publication date
CN101881003B (en) 2011-11-30

Similar Documents

Publication Publication Date Title
CN101881003B (en) Installation method of post tensioned prestressed concrete box girders
CN109747037A (en) A kind of elder generation's post-tensioned prestressing combines the U-shaped beam prefabricated construction technology of large span of construction
CN110409304B (en) Cantilever assembling construction method for segment prefabricated bent cap
CN108004925B (en) Prestress reinforced concrete circular arch tower construction method
CN102817325A (en) Construction method of simply supported-continuous switching system of negative moment beam prestressed precast box beam
RU2481946C2 (en) Method of making decorative reinforced concrete articles
CN101768908A (en) Construction method of steel fiber reinforced concrete floor
ITMI960426A1 (en) METHOD FOR THE REALIZATION OF A COMPOSED BEAM AND BEAM MADE IN THIS
Giussani et al. Durable concrete pavements: The reconstruction of runway head 36R of Milano Linate International Airport
CN104389439A (en) Strengthening method for reinforced concrete column
Hartwell Laboratory testing of Ultra High Performance Concrete deck joints for use in accelerated bridge construction
CN201857576U (en) Supporting device for installing post-tensioned precast prestressed concrete box girder
CN201738245U (en) Slideway for mounting post-tensioning prefabricated prestressed concrete box girder
CN113494055A (en) Double-locking structure for closure section of long-span bridge and construction method
CN113322771A (en) Seamless bridge structure based on ultrahigh-toughness cement-based composite material and construction method
CN111074950B (en) Pre-closed advanced water stop post-cast strip for basement outer wall and construction method
CN103243912B (en) Multilayer is without plate framework construction method
JPH0959929A (en) Repair and reinforcing method of top of reinforced concrete floor slab
CN106368362A (en) Hollow floor for GBF high-infusion alloy thin-walled square boxes and manufacturing method
CN115256615A (en) Intelligent shower maintenance standard construction system for prefabricated box girder of expressway
CN103866684B (en) A kind of Wavelike steel webplate combination girt strip and construction technology thereof
JP4035027B2 (en) Bridge girder structure and bridge girder construction method
CN213571944U (en) Suspension type slip form for one-step forming of large-inclination trash rack
CN105200927B (en) Beam-making construction method on science of bridge building beam
Rempel et al. Extremely light and slender precast-bridge made out of textile-reinforced-concrete

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111130

Termination date: 20200721

CF01 Termination of patent right due to non-payment of annual fee