CN101871210B - 高含水率淤泥区域大面积深基坑施工中电渗排水方法 - Google Patents
高含水率淤泥区域大面积深基坑施工中电渗排水方法 Download PDFInfo
- Publication number
- CN101871210B CN101871210B CN2009100498497A CN200910049849A CN101871210B CN 101871210 B CN101871210 B CN 101871210B CN 2009100498497 A CN2009100498497 A CN 2009100498497A CN 200910049849 A CN200910049849 A CN 200910049849A CN 101871210 B CN101871210 B CN 101871210B
- Authority
- CN
- China
- Prior art keywords
- foundation pit
- drainage
- electro
- drain
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
本发明涉及深基坑施工中电渗排水方法,尤其涉及一种淤泥区域大面积深基坑施工中电渗排水方法。一种高含水率淤泥区域大面积深基坑施工中电渗排水方法,在所述基坑外围设置电渗井点,稳定基坑边坡及控制基坑外部地下水向基坑内渗入;同时在基坑内根据基坑面积设置排水板,同时在排水板上设置电极以提高排水板的排水功效;在设置排水板的同时,按照排水板的平面布置走向设置方格网状盲沟,排水板顶端设置在盲沟内,盲沟同基坑的排水系统相连;排水板上捆绑圆钢作为负电极,距排水板0.85-1.2m处设置正电极;通电,利用电泳特性将基坑内地下水快速疏干。本发明适应大面积基坑排水,成本低,效果好。
Description
技术领域
本发明涉及深基坑施工中电渗排水方法,尤其涉及一种淤泥区域大面积深基坑施工中电渗排水方法。
背景技术
我国目前建设的大型钢铁基地基本上都在临海或水域发达地区,如上海、天津、宁波等地,而临海地区多为吹填地基,该地基多为淤泥或淤泥质粉土,含水率40~70%,饱和度100%,而渗透系数K值偏小一般为10-6~10-8cm/s,在这种地基上建造各类建筑物时基坑开挖难度非常大,而淤泥质土层厚度与埋深从0~-20m各有所不同,如何快速有效地将淤泥中的滞水疏干,提高该土质的工程性能,以免在基坑开挖过程中发生因基坑边坡滑坡导致推桩及对机械或人身造成伤害等事故一直是施工难以解决的问题。
根据在的轧线基坑施工经验,冷热轧工程的基坑群基底标高差异比较大,坑中带坑,交错复杂,土方开挖量也非常大,多数都在100万m3以上,在这些区域的基坑施工中,常用的方法是轻型井点封闭基坑护坡及拦截地下水,基坑中部设置真空深井或过渡轻型井点,但此措施只适用于渗透系数大于10-5cm/s的土质中,而如前所述,吹填地基含水率高,渗透系数要低一到三个数量级,采用常规的降排水方法不能满足高含水率淤泥质土层深基坑的施工,并且冶金建设项目基坑开挖面积非常大,采用预压或强夯有一定的局限性,即预压或强夯在开挖面积较小的基坑比较适用,但在大面积、深基坑施工中使用则需要大量的人力、物力和时间。
发明内容
本发明旨在解决吹填基地排水困难,现有技术浪费大的缺陷,提供一种高含水率淤泥区域大面积深基坑施工中电渗排水方法。本发明适应大面积基坑排水,成本低,效果好。
本发明是这样实现的:一种高含水率淤泥区域大面积深基坑施工中电渗排水方法,它包括:
在所述基坑外围设置电渗井点,稳定基坑边坡及控制基坑外部地下水向基坑内渗入;
同时在基坑内根据基坑面积设置排水板,同时在排水板上设置电极以提高排水板的排水功效;
在设置排水板的同时,按照排水板的平面布置走向设置方格网状盲沟,排水板顶端设置在盲沟内,盲沟同基坑的排水系统相连;
排水板上捆绑圆钢作为负电极,距排水板0.85-1.2m处设置正电极;
通电,利用电泳特性将基坑内地下水快速疏干。
所述的高含水率淤泥区域大面积深基坑施工中电渗排水方法,所述盲沟设置成500×500mm的方格网状。
所述的高含水率淤泥区域大面积深基坑施工中电渗排水方法,所述正点极设置在距排水板1米处。
所述任一高含水率淤泥区域大面积深基坑施工中电渗排水方法,该方法适用于渗水速率为10-6至10-8cm/s的基坑。
本发明电渗施工技术与电渗排水板结合施工应用于大面积深基坑降水施工;将电渗原理应用到排水板施工中,提高了排水的降排水功效。施工场地按排水板布置走向设置方格网状盲沟,同场地满铺黄砂相比,降低了施工成本,形成了完整排水网络。本发明操作简单、便捷,普通工人可以很快掌握;有效的缩短基坑围护的施工周期,同其他软土基坑处理方法相比,费用也比较低。所用机具、材料可以全部回收,多次使用.
附图说明
下面,结合附图,进一步说明本发明:
图1为发明电极设置示意图;
具体实施方式
下面,结合具体实施例对本发明作进一步详细说明:一种高含水率淤泥区域大面积深基坑施工中电渗排水方法,它包括:
1、大面积基坑1外围开挖井点沟,施工电渗井点5。
2、开挖场地开挖盲沟,按电渗排水板4走向开挖,盲沟宽度为500mm,深度为500mm,间距为1000mm。
3、排水板4捆绑直径16mm圆钢,然后沿盲沟打入地下,排水板间距2000mm。
4、在相邻排水板盲沟内设置电渗正电极3,正电极3为直径16mm圆钢,长度同排水板4相同,沉设时采用高压水冲抢成孔,成孔直径为80~100mm,成孔后直接将正电极3圆钢放入孔内,正电极3圆钢的数量,间距同排水板4相同。
5、排水板4为负电极,同正电极3沿基坑1宽度方向布置,布置规律为排水板4-正电极3-排水板4-正电极3依次排布。
6、排水板正负电极圆钢外露部分刷沥青漆绝缘,用直径20mm圆钢2分别同正负电极焊接,焊接后刷沥青漆绝缘。
7、按电渗井点计算公式配备直流电焊机或直流变压器,按套数分别同电渗排水板正负极相连。
计算公式:变压器功率P=UJF/100
其中:
U为工作电压
J为电流密度(A/m2)土中取0.5-1A/m2
F为电极列平面上降水的面积。
8、设置盲沟集中排水点,将盲沟导出地下水排除。
9、电渗排水板通电试运转,调整。
10、电渗排水板通电运转,初期每天通电20小时,然后按基坑内排水情况逐步缩短通电时间。
11、基坑开挖时,按基坑开挖顺序逐步拆除回收电渗排水板正负电极,并加以维修周转使用。
Claims (3)
1.一种高含水率淤泥区域大面积深基坑施工中电渗排水方法,其特征在于,该方法适用于渗水速率为10-6至10-8cm/s的基坑;它包括:
在所述基坑外围设置电渗井点,稳定基坑边坡及控制基坑外部地下水向基坑内渗入;
同时在基坑内根据基坑面积设置排水板,同时在排水板上设置电极以提高排水板的排水功效;
在设置排水板的同时,按照排水板的平面布置走向设置方格网状盲沟,排水板顶端设置在盲沟内,盲沟同基坑的排水系统相连;
排水板上捆绑圆钢作为负电极,距排水板0.85-1.2m处设置正电极;
通电,利用电泳特性将基坑内地下水快速疏干。
2.根据权利要求1所述的高含水率淤泥区域大面积深基坑施工中电渗排水方法,其特征在于,所述盲沟设置成500×500mm的方格网状。
3.根据权利要求1所述的高含水率淤泥区域大面积深基坑施工中电渗排水方法,其特征在于,所述正电极设置在距排水板1米处。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100498497A CN101871210B (zh) | 2009-04-23 | 2009-04-23 | 高含水率淤泥区域大面积深基坑施工中电渗排水方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100498497A CN101871210B (zh) | 2009-04-23 | 2009-04-23 | 高含水率淤泥区域大面积深基坑施工中电渗排水方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101871210A CN101871210A (zh) | 2010-10-27 |
CN101871210B true CN101871210B (zh) | 2012-01-25 |
Family
ID=42996281
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009100498497A Active CN101871210B (zh) | 2009-04-23 | 2009-04-23 | 高含水率淤泥区域大面积深基坑施工中电渗排水方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101871210B (zh) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104775448A (zh) * | 2015-03-30 | 2015-07-15 | 朱奎 | 软土地区地下室施工方法 |
CN109209493B (zh) * | 2018-10-29 | 2019-10-11 | 六盘水师范学院 | 一种黄泥灌浆采空区下煤层开采的探放水方法 |
CN112570437A (zh) * | 2020-11-26 | 2021-03-30 | 北京建工环境修复股份有限公司 | 一种原位热传导耦合电渗井点降水修复有机污染场地的系统和方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1884707A (zh) * | 2006-07-11 | 2006-12-27 | 叶吉 | 真空电渗降水及低能量强夯综合加固软土地基的方法 |
CN101016739A (zh) * | 2007-02-15 | 2007-08-15 | 张志铁 | 真空电渗降水及低能量强夯的深层加固方法 |
CN101139833A (zh) * | 2007-07-20 | 2008-03-12 | 朱怡 | 复合真空预压软基综合加固方法 |
CN101349056A (zh) * | 2008-08-29 | 2009-01-21 | 陈江涛 | 复合电渗和交流电击排水方法及其用途 |
-
2009
- 2009-04-23 CN CN2009100498497A patent/CN101871210B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1884707A (zh) * | 2006-07-11 | 2006-12-27 | 叶吉 | 真空电渗降水及低能量强夯综合加固软土地基的方法 |
CN101016739A (zh) * | 2007-02-15 | 2007-08-15 | 张志铁 | 真空电渗降水及低能量强夯的深层加固方法 |
CN101139833A (zh) * | 2007-07-20 | 2008-03-12 | 朱怡 | 复合真空预压软基综合加固方法 |
CN101349056A (zh) * | 2008-08-29 | 2009-01-21 | 陈江涛 | 复合电渗和交流电击排水方法及其用途 |
Non-Patent Citations (1)
Title |
---|
JP特开平9-119128A 1997.05.06 |
Also Published As
Publication number | Publication date |
---|---|
CN101871210A (zh) | 2010-10-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101768976B (zh) | 一种基坑降水节水装置及其施工方法 | |
CN102418347B (zh) | 一种深基坑内盲沟和集水井排水施工方法 | |
CN103953008B (zh) | 一种适用于尾矿库的改进型混合坝 | |
CN203174616U (zh) | 一种粘土地基降水节水系统 | |
CN103967028A (zh) | 一种沉管降水结构及其采用此结构处理突发性基坑水涌、喷泉的方法 | |
CN105256788A (zh) | 吹填软土地基加固处理系统及网格式真空预压联用电渗法的处理方法 | |
CN102926378A (zh) | 导电复合真空软土加固预压方法 | |
CN103911996B (zh) | 临近既有建筑物钢板桩拔除施工方法 | |
LU500273B1 (en) | New comprehensive dewatering and drainage method and drainage device for mudstone subway station | |
CN102433886A (zh) | 一种集水井内增加降水井施工方法 | |
CN104846711A (zh) | 用于土质边坡加固的电渗方法 | |
CN103334452B (zh) | 一种地下工程混合施工法 | |
CN107152035A (zh) | 地下管廊穿越河流的施工方法 | |
CN107630500A (zh) | 一种给排水施工方法 | |
CN105714762A (zh) | 换填夯实改进软黏土电渗加固方法 | |
CN112281885B (zh) | 防渗膜接头自粘接装置及其自粘接式截水帷幕构筑方法 | |
CN105179011A (zh) | 一种隧洞封堵设施及其封堵方法 | |
CN100572688C (zh) | 预排水动力固结加固软土地基的方法 | |
CN101871210B (zh) | 高含水率淤泥区域大面积深基坑施工中电渗排水方法 | |
CN109083100B (zh) | 一种吹泥成陆后的河道开挖施工工艺 | |
CN113026719A (zh) | 一种大面积软土地基电渗分离井点降水系统及其加固方法 | |
CN203383316U (zh) | 一种城市生活垃圾卫生填埋场渗滤液渗漏监测结构 | |
CN216552030U (zh) | 一种地下室外墙肥槽降排水结构 | |
CN215290068U (zh) | 一种大面积软土地基电渗分离井点降水系统 | |
CN203022015U (zh) | 基础筏板底局部深基坑降水装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |