CN101858052A - Steel and ultra-high performance concrete combined bridge deck structure - Google Patents

Steel and ultra-high performance concrete combined bridge deck structure Download PDF

Info

Publication number
CN101858052A
CN101858052A CN 201010214651 CN201010214651A CN101858052A CN 101858052 A CN101858052 A CN 101858052A CN 201010214651 CN201010214651 CN 201010214651 CN 201010214651 A CN201010214651 A CN 201010214651A CN 101858052 A CN101858052 A CN 101858052A
Authority
CN
China
Prior art keywords
high performance
ultra
bridge deck
performance concrete
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010214651
Other languages
Chinese (zh)
Inventor
邵旭东
黄政宇
李嘉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University
Original Assignee
Hunan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University filed Critical Hunan University
Priority to CN 201010214651 priority Critical patent/CN101858052A/en
Publication of CN101858052A publication Critical patent/CN101858052A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention relates to a bridge deck structure of a steel bridge, in particular to a steel and ultra-high performance concrete combined bridge deck structure, comprising a steel bridge deck, an ultra-high performance concrete layer is coated above the steel bridge deck, a bridge deck pavement layer is coated above the ultra-high performance concrete layer, and the ultra-high performance concrete layer is internally provided with reinforced bars. The steel and ultra-high performance concrete combined bridge deck structure has the advantages of small construction height, large stiffness, good binding performance between combined layers, good durability, good fatigue resistance, little vehicle impact and the like.

Description

Steel and ultra-high performance concrete combined bridge deck structure
Technical field
The present invention relates to a kind of architectural detail of bridge construction, relate in particular to a kind of bridge deck structure of steel bridge.
Background technology
Orthotropic steel bridge deck adopted in Germany's initiative in 1948, and this light-duty steel bridge face has become the first-selected bridge floor pattern of steel bridge (especially super-huge bridge) over 60 years.Through the engineering constructions of decades practice, the orthotropic steel bridge deck scheme of mating formation mainly develops into following four classes at present, that is: (1) hot mixed asphaltic concrete or modification dense-graded asphalt concrete scheme; (2) high temperature mix cast asphalt concrete scheme; (3) bitumastic concrete scheme; (4) epoxy resin asphalt concrete scheme.Existing conventional steel bridge bridge deck structure form as shown in Figure 1, existing four class steel bridge deck asphalt concrete bridge deck pavements cost an arm and a leg, a shortcoming that self can't overcome is all arranged simultaneously, be that bituminous concrete bridge deck pavement 3 is different with the coefficient of expansion of steel bridge deck 1, the two degree of adhesion is not firm, if bridge location place summer in the winter temperature difference is bigger, under the vehicular load effect, bituminous concrete bridge deck pavement 3 is easy to take place relative slippage with steel bridge deck 1, thereby causes bridge deck pavement 3 diseases such as cracking, rut, heap soil or fertilizer over and around the roots bag to occur.
Because orthotropic steel bridge deck is light-duty bridge floor, panel is thinner, adding that asphalt concrete pavement layer destroys causes pavement roughness, thereby cause the percussion of vehicular load easily, make and drive a vehicle in high density, especially under the vehicular load effect that overloads serious, the problem of fatigue damage of panel and vertical rib weld becomes very outstanding.For the problem of fatigue damage of orthotropic steel bridge deck, existing thinking of dealing with problems is: strengthen plate thickness, adopt large-scale vertical rib, rib is apart from increase, and the spacing of diaphragm (cross rib) also can increase like this, reduces the weld seam of rib and panel in length and breadth; Improve detail structure, and the strict welding manufacturing process of regulation, to reduce the stress concentration phenomenon as far as possible.This thinking is to be conceived to improve the duty of bridge deck by improving physical dimension, though can play certain effect, but can not fundamentally solve the problem of fatigue damage of panel and vertical rib weld, and cost is also than higher, simultaneously, increase bridge deck thickness and can not fundamentally solve the flimsy problem of layer of mating formation.
Summary of the invention
The technical problem to be solved in the present invention is to overcome the deficiencies in the prior art, provides that a kind of building height is little, rigidity is big, good, the good endurance of adhesive property between each combination layer, anti-fatigue performance is good, the vehicular impact effect is little steel and ultra-high performance concrete combined bridge deck structure.
For solving the problems of the technologies described above, the technical scheme that the present invention proposes is a kind of steel and ultra-high performance concrete combined bridge deck structure, described bridge deck structure comprises steel bridge deck, described steel bridge deck top is covered with the ultra-high performance concrete layer, and described ultra-high performance concrete layer top is covered with bridge deck pavement; Is furnished with reinforcing bar in the described ultra-high performance concrete layer.This technical scheme that the present invention proposes is in conjunction with utilization combining structure bridge floor thought and ultra-high performance concrete technology, between existing Orthotropic Steel Bridge Deck and bituminous concrete bridge deck pavement, increase slim ultra-high performance concrete layer, this not only can effectively be avoided steel bridge deck and bridge deck pavement to be in disadvantageous distortion and stress state, and can effectively solve layer cracking of mating formation that steel bridge deck occurs in using easily, slippage, panel and the problems such as fatigue failure of rib in length and breadth.
In the above-mentioned steel and ultra-high performance concrete combined bridge deck structure, described ultra-high performance concrete layer is meant to be built by ultra-high performance concrete and forms.Ultra-high performance concrete in this area is a proprietary name, generally be meant in the present invention and have superhigh intensity, high ductility, high tenacity, high workability, good endurance and can be applicable to the concrete that steel bridge deck is mated formation, it is relative ordinary concrete, the concrete material that the another kind of mechanical property of high performance concrete is excellent more, RPC for example, the very-high performance fibre reinforced concrete, the slip casting fibrous concrete, closely knit arrangement of reinforcement composite material, engineering latex composite material etc., but be preferably RPC, very-high performance fibre reinforced concrete or slip casting fibrous concrete.
In the technique scheme, the bonding surface of steel bridge deck and ultra-high performance concrete layer can be plane or matsurface, but as the further improvement to above-mentioned steel and ultra-high performance concrete combined bridge deck structure, the bonding surface of described steel bridge deck and ultra-high performance concrete layer preferably is arranged to the shearing resistance structure or shear connector is set.Described shearing resistance structure is preferably a coarse bonding surface of a sags and crests configuration or a concavo-convex slot type bonding surface.Described shear connector is preferably peg or PBL shear connector.Even shearing resistance structure and shear connector can be provided with simultaneously.
In the technique scheme, the bonding surface of described ultra-high performance concrete layer and bridge deck pavement can be natural matsurface, but preferably is arranged to the anti-shear ability of concavo-convex slot type bonding surface with further increase interlayer.
In the technique scheme, described bridge deck pavement can be the bridge of all kinds of bituminous concrete bridge deck pavements or the other materials layer of mating formation, in other words, technical scheme of the present invention has compliance widely, can not have influence on the technique effect of technical solution of the present invention because of the materials variances of bridge deck pavement.
Compared with prior art, the present invention is provided with the ultra-high performance concrete layer on steel bridge deck (especially Orthotropic Steel Bridge Deck), on the ultra-high performance concrete layer, lay the bridge deck pavement of bituminous concrete and so on again, existing conventional steel bridge face is transformed into steel-ultra-high performance concrete combined type bridge floor, this has changed the form of structure of steel bridge deck and the duty of deck paving greatly, and this also makes technical scheme of the present invention possess following remarkable advantages:
At first, steel and ultra-high performance concrete combined bridge deck structure of the present invention is stressed jointly, steel bridge deck and the stress of rib under the vehicle wheel load in length and breadth thereof have been reduced, reduced weld fatigue cracking risk between steel bridge deck and vertical rib and dividing plate significantly, and indexs such as the stress of ultra-high performance concrete layer self, distortion can satisfy all and the requirement of steel work collaborative work;
Secondly, steel and ultra-high performance concrete combined bridge deck structure of the present invention has increased the rigidity of bridge deck, has improved the adhesive property of bituminous concrete bridge deck pavement and bridge deck, has improved the cracking resistance and the endurance quality of bridge deck pavement; Especially the shear Design on combined bridge deck structure of the present invention basis, can further reduce the relative slippage between bridge deck pavement and the steel bridge deck, reduced the heap soil or fertilizer over and around the roots bag of bridge deck pavement, reduce the percussion under the vehicular load effect, thereby further improved the endurance quality of bridge deck pavement;
In addition, what the ultra-high performance concrete layer in the technical solution of the present invention was selected is the ultra-high performance concrete that is applicable to steel bridge deck, not only be easy to constructing operation, and can guarantee density, improved the durability of steel bridge deck, and its deck is thinner, the weight of also not obvious on the whole increase bridge floor dead load.
To sum up, advantages such as steel and ultra-high performance concrete combined bridge deck structure of the present invention has that building height is little, rigidity is big, good, the good endurance of adhesive property between each combination layer, anti-fatigue performance is good, the vehicular impact effect is little, have great practical value and good economic benefit, especially build and have broad application prospects in the construction of large-scale, super-huge steel bridge.
Description of drawings
Fig. 1 is the structural representation (cross-sectional drawing) of the orthotropic steel box girder bridge face of existing routine.
Fig. 2 is the structural representation (cross-sectional drawing) of the steel and ultra-high performance concrete combined bridge deck structure of the embodiment of the invention 1.
Fig. 3 is the structural representation (skiagraph) of the steel and ultra-high performance concrete combined bridge deck structure of the embodiment of the invention 2.
Fig. 4 is the structural representation (skiagraph) of the steel and ultra-high performance concrete combined bridge deck structure of the embodiment of the invention 3.
Fig. 5 is the structural representation (cross-sectional drawing) of the steel and ultra-high performance concrete combined bridge deck structure of the embodiment of the invention 3.
Fig. 6 is the structural representation (skiagraph) of the steel and ultra-high performance concrete combined bridge deck structure of the embodiment of the invention 4.
Fig. 7 is the structural representation (skiagraph) of the steel and ultra-high performance concrete combined bridge deck structure of the embodiment of the invention 5.
Marginal data
1, steel bridge deck; 2, ultra-high performance concrete layer; 3, bridge deck pavement; 4, peg; 5, PBL shear connector; 6, concavo-convex slot type bonding surface; 7, reinforcing bar.
The specific embodiment
Embodiment 1
A kind of steel and ultra-high performance concrete combined bridge deck structure of the present invention as shown in Figure 2, this bridge deck structure comprises steel bridge deck 1, steel bridge deck 1 top is covered with ultra-high performance concrete layer 2, ultra-high performance concrete layer 2 top are covered with bridge deck pavement 3, are furnished with reinforcing bar 7 in the ultra-high performance concrete layer 2.Ultra-high performance concrete layer 2 is to be built by ultra-high performance concrete to form, and the ultra-high performance concrete that present embodiment is selected for use is a RPC.Bonding surface place at steel bridge deck 1 and ultra-high performance concrete layer 2 is provided with the peg 4 that shearing resistance is used.Bonding surface between steel bridge deck 1 and the ultra-high performance concrete layer 2 is the plane, and the bonding surface between ultra-high performance concrete layer 2 and the bridge deck pavement 3 is the nature matsurface, and what bridge deck pavement 3 adopted is the plain asphalt concrete material.
The construction sequence of the steel and ultra-high performance concrete combined bridge deck structure of above-mentioned present embodiment is:
(1) the welding production steel bridge deck 1, and the end face of steel bridge deck 1 is the plane, and its end face is done anticorrosive coating, and evenly welds the peg 4 that shearing resistance is used at its end face;
(2) reinforcing bar 7 in the laying ultra-high performance concrete layer is prepared ultra-high performance concrete, and the ultra-high performance concrete for preparing is built on steel bridge deck 1, forms ultra-high performance concrete layer 2, and the end face of ultra-high performance concrete layer 2 is the nature matsurface;
(3) the ultra-high performance concrete layer after building 2 is carried out maintenance;
(4) treat that mechanical index such as ultra-high performance concrete layer intensity reaches designing requirement after, the asphalt concrete material of preparation bridge deck pavement 3 usefulness covers asphalt concrete material then on the good ultra-high performance concrete layer 2 of maintenance;
(5) carry out the maintenance of bridge deck pavement 3 at last, finish the construction of whole steel and ultra-high performance concrete combined bridge deck structure.
Embodiment 2:
A kind of steel and ultra-high performance concrete combined bridge deck structure of the present invention as shown in Figure 3, this bridge deck structure comprises steel bridge deck 1, steel bridge deck 1 top is covered with ultra-high performance concrete layer 2, ultra-high performance concrete layer 2 top are covered with bridge deck pavement 3, are furnished with reinforcing bar 7 in the ultra-high performance concrete layer 2.Ultra-high performance concrete layer 2 is to be built by ultra-high performance concrete to form, and the ultra-high performance concrete that present embodiment is selected for use is a RPC.Steel bridge deck 1 is set to concavo-convex slot type bonding surface 6 with the bonding surface of ultra-high performance concrete layer 2.Bonding surface between ultra-high performance concrete layer 2 and the bridge deck pavement 3 is the nature matsurface, and what bridge deck pavement 3 adopted is the plain asphalt concrete material.
The construction sequence of the steel and ultra-high performance concrete combined bridge deck structure of above-mentioned present embodiment is:
(1) the welding production steel bridge deck 1, and the end face of steel bridge deck 1 is with ribbing of a concavo-convex slot type, and its end face is done anticorrosive coating;
(2) reinforcing bar 7 in the laying ultra-high performance concrete layer is prepared ultra-high performance concrete, and the ultra-high performance concrete for preparing is built on steel bridge deck 1, forms ultra-high performance concrete layer 2, and the end face of ultra-high performance concrete layer 2 is the nature matsurface;
(3) the ultra-high performance concrete layer after building 2 is carried out maintenance;
(4) treat that mechanical index such as ultra-high performance concrete layer intensity reaches designing requirement after, the asphalt concrete material of preparation bridge deck pavement 3 usefulness covers asphalt concrete material then on the good ultra-high performance concrete layer 2 of maintenance;
(5) carry out the maintenance of bridge deck pavement 3 at last, finish the construction of whole steel and ultra-high performance concrete combined bridge deck structure.
Embodiment 3
A kind of as Fig. 4, steel and ultra-high performance concrete combined bridge deck structure of the present invention shown in Figure 5, this bridge deck structure comprises steel bridge deck 1, steel bridge deck 1 top is covered with ultra-high performance concrete layer 2, ultra-high performance concrete layer 2 top are covered with bridge deck pavement 3, are furnished with reinforcing bar 7 in the ultra-high performance concrete layer 2.Ultra-high performance concrete layer 2 is to be built by ultra-high performance concrete to form, and the ultra-high performance concrete that present embodiment is selected for use is a RPC.Bonding surface place at steel bridge deck 1 and ultra-high performance concrete layer 2 is provided with the PBL shear connector 5 that shearing resistance is used.Bonding surface between steel bridge deck 1 and the ultra-high performance concrete layer 2 is the plane, and the bonding surface between ultra-high performance concrete layer 2 and the bridge deck pavement 3 is the nature matsurface, and what bridge deck pavement 3 adopted is the plain asphalt concrete material.
The construction sequence of the steel and ultra-high performance concrete combined bridge deck structure of above-mentioned present embodiment is:
(1) the welding production steel bridge deck 1, and the end face of steel bridge deck 1 is the plane, and its end face is done anticorrosive coating, and evenly welds the PBL shear connector 5 that shearing resistance is used at its end face;
(2) reinforcing bar 7 in the laying ultra-high performance concrete layer is prepared ultra-high performance concrete, and the ultra-high performance concrete for preparing is built on steel bridge deck 1, forms ultra-high performance concrete layer 2, and the end face of ultra-high performance concrete layer 2 is the nature matsurface;
(3) the ultra-high performance concrete layer after building 2 is carried out maintenance;
(4) treat that mechanical index such as ultra-high performance concrete layer intensity reaches designing requirement after, the asphalt concrete material of preparation bridge deck pavement 3 usefulness covers asphalt concrete material then on the good ultra-high performance concrete layer 2 of maintenance;
(5) carry out the maintenance of bridge deck pavement 3 at last, finish the construction of whole steel and ultra-high performance concrete combined bridge deck structure.
Embodiment 4
A kind of steel and ultra-high performance concrete combined bridge deck structure of the present invention as shown in Figure 6, this bridge deck structure comprises steel bridge deck 1, steel bridge deck 1 top is covered with ultra-high performance concrete layer 2, ultra-high performance concrete layer 2 top are covered with bridge deck pavement 3, are furnished with reinforcing bar 7 in the ultra-high performance concrete layer 2.Ultra-high performance concrete layer 2 is to be built by ultra-high performance concrete to form, and the ultra-high performance concrete that present embodiment is selected for use is a RPC.Steel bridge deck 1 is set to concavo-convex slot type bonding surface 6 with the bonding surface of ultra-high performance concrete layer 2, bonding surface between ultra-high performance concrete layer 2 and the bridge deck pavement 3 is set to concavo-convex slot type bonding surface 6 equally, and what bridge deck pavement 3 adopted is the plain asphalt concrete material.
The construction sequence of the steel and ultra-high performance concrete combined bridge deck structure of above-mentioned present embodiment is:
(1) the welding production steel bridge deck 1, and the end face of steel bridge deck 1 is with ribbing of a concavo-convex slot type;
(2) reinforcing bar 7 in the laying ultra-high performance concrete layer, the preparation ultra-high performance concrete, and the ultra-high performance concrete for preparing built on steel bridge deck 1, forming ultra-high performance concrete layer 2, the end face of ultra-high performance concrete layer 2 is set to ribbing of concavo-convex slot type equally;
(3) the ultra-high performance concrete layer after building 2 is carried out maintenance;
(4) treat that mechanical index such as ultra-high performance concrete layer intensity reaches designing requirement after, the asphalt concrete material of preparation bridge deck pavement 3 usefulness covers asphalt concrete material then on the good ultra-high performance concrete layer 2 of maintenance;
(5) carry out the maintenance of bridge deck pavement 3 at last, finish the construction of whole steel and ultra-high performance concrete combined bridge deck structure.
Embodiment 5
A kind of steel and ultra-high performance concrete combined bridge deck structure of the present invention as shown in Figure 7, this bridge deck structure comprises steel bridge deck 1, steel bridge deck 1 top is covered with ultra-high performance concrete layer 2, ultra-high performance concrete layer 2 top are covered with bridge deck pavement 3, are furnished with reinforcing bar 7 in the ultra-high performance concrete layer 2.Ultra-high performance concrete layer 2 is to be built by ultra-high performance concrete to form, and the ultra-high performance concrete that present embodiment is selected for use is a RPC.Steel bridge deck 1 is the plane with the bonding surface of ultra-high performance concrete layer 2, and the bonding surface between ultra-high performance concrete layer 2 and the bridge deck pavement 3 is set to concavo-convex slot type bonding surface 6, and what bridge deck pavement 3 adopted is the plain asphalt concrete material.
The construction sequence of the steel and ultra-high performance concrete combined bridge deck structure of above-mentioned present embodiment is:
(1) the welding production steel bridge deck 1, and the end face of steel bridge deck 1 is the plane, and its end face is done anticorrosive coating;
(2) reinforcing bar 7 in the laying ultra-high performance concrete layer, the preparation ultra-high performance concrete, and the ultra-high performance concrete for preparing built on steel bridge deck 1, forming ultra-high performance concrete layer 2, the end face of ultra-high performance concrete layer 2 is set to ribbing of concavo-convex slot type;
(3) the ultra-high performance concrete layer after building 2 is carried out maintenance;
(4) treat that mechanical index such as ultra-high performance concrete layer intensity reaches designing requirement after, the asphalt concrete material of preparation bridge deck pavement 3 usefulness covers asphalt concrete material then on the good ultra-high performance concrete layer 2 of maintenance;
(5) carry out the maintenance of bridge deck pavement 3 at last, finish the construction of whole steel and ultra-high performance concrete combined bridge deck structure.

Claims (6)

1. steel and ultra-high performance concrete combined bridge deck structure, described bridge deck structure comprises steel bridge deck, it is characterized in that: described steel bridge deck top is covered with the ultra-high performance concrete layer, and described ultra-high performance concrete layer top is covered with bridge deck pavement; Is furnished with reinforcing bar in the described ultra-high performance concrete layer.
2. steel and ultra-high performance concrete combined bridge deck structure according to claim 1, it is characterized in that: described ultra-high performance concrete layer is to be built by ultra-high performance concrete to form, and described ultra-high performance concrete is RPC, very-high performance fibre reinforced concrete, slip casting fibrous concrete, closely knit arrangement of reinforcement composite material or engineering latex composite material.
3. steel and ultra-high performance concrete combined bridge deck structure according to claim 1 and 2 is characterized in that: the bonding surface of described steel bridge deck and ultra-high performance concrete layer is provided with the shearing resistance structure or shear connector is set.
4. steel and ultra-high performance concrete combined bridge deck structure according to claim 3 is characterized in that: described shearing resistance is configured to the coarse bonding surface of a sags and crests configuration or is a concavo-convex slot type bonding surface.
5. steel and ultra-high performance concrete combined bridge deck structure according to claim 3 is characterized in that: described shear connector is peg or PBL shear connector.
6. steel and ultra-high performance concrete combined bridge deck structure according to claim 1 and 2 is characterized in that: the bonding surface of described ultra-high performance concrete layer and bridge deck pavement is the nature matsurface or is set to concavo-convex slot type bonding surface.
CN 201010214651 2010-06-30 2010-06-30 Steel and ultra-high performance concrete combined bridge deck structure Pending CN101858052A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010214651 CN101858052A (en) 2010-06-30 2010-06-30 Steel and ultra-high performance concrete combined bridge deck structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010214651 CN101858052A (en) 2010-06-30 2010-06-30 Steel and ultra-high performance concrete combined bridge deck structure

Publications (1)

Publication Number Publication Date
CN101858052A true CN101858052A (en) 2010-10-13

Family

ID=42944191

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010214651 Pending CN101858052A (en) 2010-06-30 2010-06-30 Steel and ultra-high performance concrete combined bridge deck structure

Country Status (1)

Country Link
CN (1) CN101858052A (en)

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383374A (en) * 2011-11-28 2012-03-21 湖南大学 Fabricated fibrous concrete combined deck structure and construction method thereof
CN102392413A (en) * 2011-09-30 2012-03-28 宁波天意钢桥面铺装技术有限公司 Pavement structure of combined steel bridge deck and pavement method thereof
CN102704394A (en) * 2012-06-15 2012-10-03 湖南大学 Steel-fiber concrete combined bridge deck structure with reinforced joints and construction method of steel-fiber concrete combined bridge deck structure
CN103015317A (en) * 2012-12-27 2013-04-03 南京工业大学 Factory-made orthotropic steel plate and composite combined deck structure
CN103114527A (en) * 2013-03-19 2013-05-22 南京工业大学 Orthotropic steel plate-composite material hollow slab combined bridge floor structure
CN103696366A (en) * 2013-12-20 2014-04-02 浙江省交通工程建设集团有限公司第二分公司 Pavement structure and pavement method of combined steel bridge deck
CN104005337A (en) * 2014-06-19 2014-08-27 湖南大学 Separately-poured connector of steel and fiber concrete combination board and construction method
CN104131652A (en) * 2014-07-17 2014-11-05 湖南大学 Fabricated RPC-steel-concrete hybrid beam structure
CN104631318A (en) * 2015-02-16 2015-05-20 清华大学 Bridge deck slab transverse unequal-strength steel-concrete combined bridge deck system and construction method thereof
CN104631319A (en) * 2015-02-16 2015-05-20 清华大学 Connector-free steel and ultrahigh-performance concrete combined bridge deck structure and construction method thereof
CN104846740A (en) * 2015-03-19 2015-08-19 南通大学 Large-span steel box beam bridge deck pavement layer material gradient structure pavement construction method
CN105113405A (en) * 2015-08-21 2015-12-02 同济大学 Composite bridge deck based on steel and UHPC (Ultra High Performance Concrete)
CN105604319A (en) * 2015-11-22 2016-05-25 云南德政建筑新材料科技有限公司 Steel column and steel girder decoration construction process
CN105821762A (en) * 2016-05-30 2016-08-03 上海市政工程设计研究总院(集团)有限公司 Rigid combined steel bridge deck pavement structure
CN103556565B (en) * 2013-11-25 2016-08-17 湖南大学 A kind of connecting structure of different performance beams of concrete
CN106801376A (en) * 2017-03-14 2017-06-06 中铁第四勘察设计院集团有限公司 A kind of longitudinal rib overhead steel reinforced concrete composite entity box beam
CN107237256A (en) * 2017-08-09 2017-10-10 上海市市政规划设计研究院 Long-acting endurance bridge deck pavement structure
CN107815965A (en) * 2017-10-25 2018-03-20 南京林业大学 A kind of bridge deck pavement structure with reinforced structure
CN108589518A (en) * 2018-04-27 2018-09-28 上海市市政规划设计研究院有限公司 Ultra-high performance concrete bridge deck pavement structure and its construction method
CN109024268A (en) * 2018-09-19 2018-12-18 华北水利水电大学 A kind of COCS combined bridge deck structure
CN109208474A (en) * 2018-11-06 2019-01-15 长沙理工大学 A kind of steel-UHPC the combined bridge deck structure and construction method of non-arrangement of reinforcement
CN110205937A (en) * 2019-05-23 2019-09-06 长沙理工大学 Orthotropic plate-ultra-high performance concrete combined bridge deck structure and construction method
CN110552289A (en) * 2019-09-30 2019-12-10 中交第三公路工程局有限公司工程总承包分公司 Ultra-high performance concrete combined bridge deck pavement layer structure and construction method thereof
CN112538820A (en) * 2020-07-27 2021-03-23 同济大学 Steel-ultrahigh-performance concrete combined bridge deck contraction weak-constraint connection structure and construction method
CN112627029A (en) * 2021-01-15 2021-04-09 太原理工大学 Orthotropic combined bridge deck with replaceable damage elements and construction method thereof
CN113215983A (en) * 2021-05-31 2021-08-06 中交第三公路工程局有限公司 High-performance concrete bridge deck and paving process thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1624243A (en) * 2004-12-21 2005-06-08 武汉理工大学 Paving method of sleel bridge surface composite layer
CN201704626U (en) * 2010-06-30 2011-01-12 湖南大学 Steel and ultra-high-property-concrete integrated bridge deck structure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1624243A (en) * 2004-12-21 2005-06-08 武汉理工大学 Paving method of sleel bridge surface composite layer
CN201704626U (en) * 2010-06-30 2011-01-12 湖南大学 Steel and ultra-high-property-concrete integrated bridge deck structure

Cited By (35)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392413B (en) * 2011-09-30 2015-03-25 宁波天意钢桥面铺装技术有限公司 Pavement structure of combined steel bridge deck and pavement method thereof
CN102392413A (en) * 2011-09-30 2012-03-28 宁波天意钢桥面铺装技术有限公司 Pavement structure of combined steel bridge deck and pavement method thereof
CN102383374A (en) * 2011-11-28 2012-03-21 湖南大学 Fabricated fibrous concrete combined deck structure and construction method thereof
CN102704394A (en) * 2012-06-15 2012-10-03 湖南大学 Steel-fiber concrete combined bridge deck structure with reinforced joints and construction method of steel-fiber concrete combined bridge deck structure
CN102704394B (en) * 2012-06-15 2014-09-10 湖南大学 Steel-fiber concrete combined bridge deck structure with reinforced joints and construction method of steel-fiber concrete combined bridge deck structure
CN103015317A (en) * 2012-12-27 2013-04-03 南京工业大学 Factory-made orthotropic steel plate and composite combined deck structure
CN103114527A (en) * 2013-03-19 2013-05-22 南京工业大学 Orthotropic steel plate-composite material hollow slab combined bridge floor structure
CN103556565B (en) * 2013-11-25 2016-08-17 湖南大学 A kind of connecting structure of different performance beams of concrete
CN103696366B (en) * 2013-12-20 2015-07-22 浙江省交通工程建设集团有限公司第二分公司 Pavement structure and pavement method of combined steel bridge deck
CN103696366A (en) * 2013-12-20 2014-04-02 浙江省交通工程建设集团有限公司第二分公司 Pavement structure and pavement method of combined steel bridge deck
CN104005337A (en) * 2014-06-19 2014-08-27 湖南大学 Separately-poured connector of steel and fiber concrete combination board and construction method
CN104005337B (en) * 2014-06-19 2016-02-24 湖南大学 The construction method of jointing is built in a kind of steel-fibrous concrete compoboard gradation
CN104131652A (en) * 2014-07-17 2014-11-05 湖南大学 Fabricated RPC-steel-concrete hybrid beam structure
CN104631318A (en) * 2015-02-16 2015-05-20 清华大学 Bridge deck slab transverse unequal-strength steel-concrete combined bridge deck system and construction method thereof
CN104631319A (en) * 2015-02-16 2015-05-20 清华大学 Connector-free steel and ultrahigh-performance concrete combined bridge deck structure and construction method thereof
CN104846740A (en) * 2015-03-19 2015-08-19 南通大学 Large-span steel box beam bridge deck pavement layer material gradient structure pavement construction method
CN105113405A (en) * 2015-08-21 2015-12-02 同济大学 Composite bridge deck based on steel and UHPC (Ultra High Performance Concrete)
CN105604319A (en) * 2015-11-22 2016-05-25 云南德政建筑新材料科技有限公司 Steel column and steel girder decoration construction process
CN105604319B (en) * 2015-11-22 2018-01-16 云南德政建筑新材料科技有限公司 Steel column and girder steel decoration construction technique
CN105821762A (en) * 2016-05-30 2016-08-03 上海市政工程设计研究总院(集团)有限公司 Rigid combined steel bridge deck pavement structure
CN106801376A (en) * 2017-03-14 2017-06-06 中铁第四勘察设计院集团有限公司 A kind of longitudinal rib overhead steel reinforced concrete composite entity box beam
CN107237256A (en) * 2017-08-09 2017-10-10 上海市市政规划设计研究院 Long-acting endurance bridge deck pavement structure
CN107815965A (en) * 2017-10-25 2018-03-20 南京林业大学 A kind of bridge deck pavement structure with reinforced structure
CN108589518A (en) * 2018-04-27 2018-09-28 上海市市政规划设计研究院有限公司 Ultra-high performance concrete bridge deck pavement structure and its construction method
CN108589518B (en) * 2018-04-27 2024-03-12 上海市市政规划设计研究院有限公司 Super-high-performance concrete steel bridge deck pavement structure and construction method thereof
CN109024268B (en) * 2018-09-19 2024-01-16 华北水利水电大学 COCS combined bridge deck structure
CN109024268A (en) * 2018-09-19 2018-12-18 华北水利水电大学 A kind of COCS combined bridge deck structure
CN109208474A (en) * 2018-11-06 2019-01-15 长沙理工大学 A kind of steel-UHPC the combined bridge deck structure and construction method of non-arrangement of reinforcement
CN110205937A (en) * 2019-05-23 2019-09-06 长沙理工大学 Orthotropic plate-ultra-high performance concrete combined bridge deck structure and construction method
CN110552289A (en) * 2019-09-30 2019-12-10 中交第三公路工程局有限公司工程总承包分公司 Ultra-high performance concrete combined bridge deck pavement layer structure and construction method thereof
CN112538820A (en) * 2020-07-27 2021-03-23 同济大学 Steel-ultrahigh-performance concrete combined bridge deck contraction weak-constraint connection structure and construction method
CN112538820B (en) * 2020-07-27 2024-05-14 同济大学 Shrinkage weak constraint connection structure of steel-ultra-high performance concrete combined bridge deck and construction method
CN112627029A (en) * 2021-01-15 2021-04-09 太原理工大学 Orthotropic combined bridge deck with replaceable damage elements and construction method thereof
CN113215983A (en) * 2021-05-31 2021-08-06 中交第三公路工程局有限公司 High-performance concrete bridge deck and paving process thereof
CN113215983B (en) * 2021-05-31 2022-08-16 中交第三公路工程局有限公司 Paving process of high-performance concrete bridge deck

Similar Documents

Publication Publication Date Title
CN101858052A (en) Steel and ultra-high performance concrete combined bridge deck structure
CN201704626U (en) Steel and ultra-high-property-concrete integrated bridge deck structure
CN201172796Y (en) Steel box girder bridge deck structure with upper longitudinal ribs
CN106245511B (en) A kind of two-fold shape combined beam structure and its construction method
CN102383374B (en) Fabricated fibrous concrete combined deck structure and construction method thereof
CN102979037A (en) Steel deck composite pavement structure laying grid type shear connectors
CN104831617A (en) Steel-super high performance concrete composite beam based on ribbed plate type bridge deck and construction method
CN103556565B (en) A kind of connecting structure of different performance beams of concrete
CN104988823A (en) Cement concrete pavement structure provided with continuous steel bars
CN104831627A (en) Bridge deck slab longitudinal unequal strength steel-concrete composite structure bridge and construction method thereof
CN110847007A (en) Section steel-concrete composite beam hogging moment area structure based on high-performance material
WO2011160562A1 (en) Double-direction interlocking brick, pavement and paving method using the same
CN103114524A (en) Light type wave-shaped steel and high-strength activity powder concrete composite bridge panel
CN108589528B (en) Prefabricated pavement layer structure of super-tough durability of assembled steel bridge
CN209428931U (en) Lightweight steel-coarse aggregate Reactive Powder Concrete combined beam structure
CN109024216A (en) Composite Steel-Concrete Bridges structure and combined bridge deck
CN203593939U (en) Connecting structure of concrete beams differing in performance
CN211848904U (en) Compound pouring type pavement structure
CN104631318A (en) Bridge deck slab transverse unequal-strength steel-concrete combined bridge deck system and construction method thereof
CN202766969U (en) Steel and wood combination bridge deck pavement structure with shear keys
CN206256363U (en) A kind of two-fold shape combined beam structure
CN203007833U (en) Steel bridge deck compound paving structure based on PBL (Perfobond Leiste) connecting pieces
CN204185768U (en) Based on the steel-ultra-high performance concrete combined bridge deck plated construction of connector of steel tube
CN212656113U (en) Steel box girder bridge deck pavement structure and suspension bridge
CN109338885A (en) There are the bridge deck pavement structure and its construction method of transition of stress layer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20101013