CN101831913A - Method for jacking steel casting of bored pile by using jacks - Google Patents

Method for jacking steel casting of bored pile by using jacks Download PDF

Info

Publication number
CN101831913A
CN101831913A CN 201010160199 CN201010160199A CN101831913A CN 101831913 A CN101831913 A CN 101831913A CN 201010160199 CN201010160199 CN 201010160199 CN 201010160199 A CN201010160199 A CN 201010160199A CN 101831913 A CN101831913 A CN 101831913A
Authority
CN
China
Prior art keywords
steel
jack
steel casing
steel casting
wire rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010160199
Other languages
Chinese (zh)
Inventor
邵正东
尹传斌
李少辉
吴宗庆
王春兰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
WUHAN FIRST METALLURGICAL COMMUNICATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUHAN FIRST METALLURGICAL COMMUNICATION ENGINEERING Co Ltd filed Critical WUHAN FIRST METALLURGICAL COMMUNICATION ENGINEERING Co Ltd
Priority to CN 201010160199 priority Critical patent/CN101831913A/en
Publication of CN101831913A publication Critical patent/CN101831913A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention relates to a method for jacking a steel casting of a bored pile by using jacks, which comprises the flowing steps of: placing two smooth sleepers horizontally on the ground on two sides of the jacket steel casting, wherein the two sleepers are vertical to the connecting line of two lifting lugs of the steel casting; (b) placing a jacket on each sleeper; arranging a cross beam on the two jackets; arranging a steel wire rope on the cross beam above each lifting lug, wherein the steel wires pass through the lifting lugs of the steel casting and the two free ends of the steel wire ropes are fixedly jointed; and (c) turning the jackets by two persons at the same time to jack the cross beam up so that the steel casting is pulled up by the cross beam through the steel wire ropes. The invention has the advantages of simple structure, convenient and simple operation, high safety and reliability, no limit by places, fast construction and low cost.

Description

Pull bored pile steel casing method with jack
Technical field
The present invention relates to a kind of device of pulling, relate in particular to and a kind ofly pull bored pile steel casing method with jack.
Background technology
Bad at geological condition, the boring in the hole of easily collapsing needs castinplace pile.In general before boring, need to take overlength steel casing to carry out supporting.But because the steel casing is buried underground too dark; very big of static friction force; generally all more than 100 tons; adopt existing equipment; adopt crane or other crane gear as pull steel protective-cylinder; general do not have so big lifting force, work plane also differs and meets the demands surely simultaneously, usually can cause and pull out the casing of not tapping, and sometimes also can cause serious economy loss.
Summary of the invention
The objective of the invention is to address the above problem and provide a kind of simple in structure, simple operation, safe and reliable, not limited by the place, what the fast expense of constructing was low pulls bored pile steel casing method with jack.
The present invention solves the problems of the technologies described above the technical scheme that is adopted:
It comprises the steps: a) with two level and smooth sleepers respectively level be placed on the ground of the steel casing both sides of being pulled the line of two hangers of the steel casing that described two sleepers are vertically pulled; B) place a jack on each sleeper, a crossbeam is set on two jack, be positioned on the crossbeam of each hanger top and be equipped with a wire rope, the hanger of steel wire penetrating steel casing, and affixed wire rope two free ends; C) two people shake jack simultaneously, the jack stand crossbeam, and crossbeam pulls up the steel casing by wire rope.
Above-mentioned wire rope two free ends are provided with steel wire clamp, with steel wire clamp two free ends are connected.
Compared with prior art, the present invention has obtained following technique effect:
1, the top power of jack generation satisfies fully and pulls static friction force all at the overlength steel casing more than 100 tons much larger than the power of hanging of crane gear;
2, jack is pulled does not have place restriction, as then can't the erect-position place at narrow and small crane gear, can well work yet;
3, the jack stroke is slower, control easily, and security performance is very good;
4, the package unit expense is very low, two 200 tons of jack, a crossbeam (can select i iron for use) and two wire rope exactly, and the turnover utilization rate is high.
Description of drawings
Fig. 1 is a front view of the present invention;
Fig. 2 is the vertical view of Fig. 1.
Wherein: 1-crossbeam, 2-steel wire clamp, 3-wire rope, 4-steel casing, 5-hanger, 6-jack, 7-ground, 8-sleeper.
The specific embodiment
Further specify embodiments of the invention below in conjunction with accompanying drawing.
Embodiment 1
Referring to Fig. 1-2, a kind ofly pull bored pile steel casing method with jack, it comprise the steps: a) with two level and smooth sleepers 8 respectively level be placed on the ground 7 of steel casing 4 both sides of being pulled the line of two hangers 5 of the steel casing that described two sleepers are vertically pulled; B) on placement one jack 6, two jack crossbeam 1 (can select i iron for use) is set on each sleeper, the crossbeam of each hanger top is provided with a wire rope 3, the hanger of steel wire penetrating steel casing, and affixed wire rope two free ends; Preferably, can be provided with steel wire clamp 2, two free ends be connected with steel wire clamp at wire rope two free ends; C) two people shake jack simultaneously, the jack stand crossbeam, and crossbeam pulls up the steel casing by wire rope.The steel casing only need be stirred, and static friction force is converted into the dynamic friction resistance after stirring, because the dynamic friction resistance is minimum, can utilize the fishing tackle of rig itself that the steel casing is pulled up again.
Protection scope of the present invention is not limited to the above embodiments, and obviously, those skilled in the art can carry out various changes and distortion and do not depart from the scope of the present invention and spirit the present invention.If these changes and distortion belong in the scope of claim of the present invention and equivalent technologies thereof, then the present invention also is intended to comprise these changes and is out of shape interior.

Claims (2)

1. pull bored pile steel casing method with jack for one kind, it is characterized in that: it comprise the steps: a) with two level and smooth sleepers (8) respectively level be placed on the ground (7) of steel casing (4) both sides of being pulled, described two sleepers are vertically pulled the line of two hangers (5) on the steel casing; B) place a jack (6) on each sleeper, a crossbeam (1) is set on two jack, be positioned on the crossbeam of each hanger top and be equipped with a wire rope (3), the hanger of steel wire penetrating steel casing, and affixed wire rope two free ends; C) two people shake jack simultaneously, the jack stand crossbeam, and crossbeam pulls up the steel casing by wire rope.
2. pull bored pile steel casing method according to claim 1 is described with jack, it is characterized in that: described wire rope two free ends are provided with steel wire clamp (2), with steel wire clamp two free ends are connected.
CN 201010160199 2010-04-23 2010-04-23 Method for jacking steel casting of bored pile by using jacks Pending CN101831913A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010160199 CN101831913A (en) 2010-04-23 2010-04-23 Method for jacking steel casting of bored pile by using jacks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010160199 CN101831913A (en) 2010-04-23 2010-04-23 Method for jacking steel casting of bored pile by using jacks

Publications (1)

Publication Number Publication Date
CN101831913A true CN101831913A (en) 2010-09-15

Family

ID=42716112

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010160199 Pending CN101831913A (en) 2010-04-23 2010-04-23 Method for jacking steel casting of bored pile by using jacks

Country Status (1)

Country Link
CN (1) CN101831913A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102286976A (en) * 2011-06-29 2011-12-21 中铁四局集团第一工程有限公司 Method for making pile foundation construction follow long steel pile casing construction in karst area
CN106013152A (en) * 2016-06-08 2016-10-12 中国十七冶集团有限公司 Cast-in-situ bored pile steel protection pipe recycling device without damage
CN108266144A (en) * 2018-02-08 2018-07-10 浙江绩丰岩土技术股份有限公司 It is a kind of to pull system and its application method for multiaxis drilling rod
CN109252522A (en) * 2018-10-31 2019-01-22 中国冶集团有限公司 Pile pulling device is adjusted in low spatial
CN109518691A (en) * 2018-11-27 2019-03-26 张利均 A kind of pile-drawing machine
CN112554176A (en) * 2020-11-23 2021-03-26 四川路航建设工程有限责任公司 Full-casing twisted pipe follow-up rotary drilling pore-forming construction method
CN113123794A (en) * 2021-03-29 2021-07-16 北京中煤矿山工程有限公司 Horizontal freezing pipe drawing device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU825844A1 (en) * 1979-08-28 1981-04-30 Goj Vladimir L Device for removing casing pipes
JPH09111763A (en) * 1995-10-18 1997-04-28 Nippon Sharyo Seizo Kaisha Ltd Device for pulling-out casing
JP2001234535A (en) * 2000-02-23 2001-08-31 Marugo Foundation Corp Surface casing pulling apparatus
CN201144418Y (en) * 2007-07-18 2008-11-05 乔春明 Special guide sleeve for hydraulic pressure raising and lining

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU825844A1 (en) * 1979-08-28 1981-04-30 Goj Vladimir L Device for removing casing pipes
JPH09111763A (en) * 1995-10-18 1997-04-28 Nippon Sharyo Seizo Kaisha Ltd Device for pulling-out casing
JP2001234535A (en) * 2000-02-23 2001-08-31 Marugo Foundation Corp Surface casing pulling apparatus
CN201144418Y (en) * 2007-07-18 2008-11-05 乔春明 Special guide sleeve for hydraulic pressure raising and lining

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102286976A (en) * 2011-06-29 2011-12-21 中铁四局集团第一工程有限公司 Method for making pile foundation construction follow long steel pile casing construction in karst area
CN106013152A (en) * 2016-06-08 2016-10-12 中国十七冶集团有限公司 Cast-in-situ bored pile steel protection pipe recycling device without damage
CN106013152B (en) * 2016-06-08 2018-02-02 中国十七冶集团有限公司 A kind of cast-in-situ bored pile steel pile casting recycling installment without damage
CN108266144A (en) * 2018-02-08 2018-07-10 浙江绩丰岩土技术股份有限公司 It is a kind of to pull system and its application method for multiaxis drilling rod
CN109252522A (en) * 2018-10-31 2019-01-22 中国冶集团有限公司 Pile pulling device is adjusted in low spatial
CN109518691A (en) * 2018-11-27 2019-03-26 张利均 A kind of pile-drawing machine
CN112554176A (en) * 2020-11-23 2021-03-26 四川路航建设工程有限责任公司 Full-casing twisted pipe follow-up rotary drilling pore-forming construction method
CN113123794A (en) * 2021-03-29 2021-07-16 北京中煤矿山工程有限公司 Horizontal freezing pipe drawing device
CN113123794B (en) * 2021-03-29 2022-08-05 北京中煤矿山工程有限公司 Horizontal freezing pipe drawing device

Similar Documents

Publication Publication Date Title
CN101831913A (en) Method for jacking steel casting of bored pile by using jacks
CN206502579U (en) Power pole hoisting device
CN201757714U (en) Ground anchor type static load testing device
CN202208598U (en) Auxiliary device for lifting prefabricate column
CN103663301B (en) Inclined nacelle device in a kind of
CN202064840U (en) Four-drill column drill derrick
CN201649094U (en) Device for pulling up steel casing of cast-in place pile
CN204532122U (en) Double lifting derrick and base
CN202969379U (en) Hoisting support for rock bolt tensioning jack
CN105317031B (en) A kind of ship lift main equipment room bridge main beam hanging method
CN204551494U (en) Construction equipment is transferred in a kind of steel sheet-pile cofferdam inner support superposition
CN103806850B (en) Separate type workover rig and using method thereof
CN203321336U (en) Device for adopting drilling line to realize lifting of oil rig self-elevating derrick
CN203690809U (en) Wire tensioning pulley
CN205558818U (en) A whole lift -type rig
CN201666123U (en) Drill stem fall-protection rescue device of rotary drilling rig
CN202730764U (en) Immersed tube pile ramming and expanding machine
CN206338037U (en) A kind of well workover self-balancing derrick
CN205916935U (en) Special support fixing device of hoist engine
CN205668869U (en) A kind of boom hoisting for dredge pump maintenance
CN206038199U (en) Static load testing arrangement for winch
CN204590740U (en) With the line bar structural assembly of pull wire arrangement
CN205823161U (en) Multifunctional hole-drilling pole setting machine
CN209083208U (en) Continuous pipe combination drill
CN211169628U (en) Device for lifting drilling machine cable and pipeline along with base

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: CHINA FIRST METALLURGICAL CONSTRUCTION GROUP CORPO

Free format text: FORMER OWNER: WUHAN CFMCGC TRAFFIC ENGINEERING CO., LTD.

Effective date: 20101210

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20101210

Address after: 430081 Wuhan Industrial Zone, Qingshan District, Hubei, No. 3

Applicant after: China First Metallurgical Group Co., Ltd.

Address before: 430081 Wuhan Industrial Zone, Qingshan District, Hubei, No. 3

Applicant before: Wuhan First Metallurgical Communication Engineering Co., Ltd.

C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20100915