CN101824878A - 多腔钢管混凝土叠合柱及其制作方法 - Google Patents
多腔钢管混凝土叠合柱及其制作方法 Download PDFInfo
- Publication number
- CN101824878A CN101824878A CN 201010152439 CN201010152439A CN101824878A CN 101824878 A CN101824878 A CN 101824878A CN 201010152439 CN201010152439 CN 201010152439 CN 201010152439 A CN201010152439 A CN 201010152439A CN 101824878 A CN101824878 A CN 101824878A
- Authority
- CN
- China
- Prior art keywords
- steel
- cavity
- steel tube
- concrete
- superposed column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 250
- 239000010959 steel Substances 0.000 title claims abstract description 250
- 239000004567 concrete Substances 0.000 title claims abstract description 85
- 238000002360 preparation method Methods 0.000 title claims abstract description 8
- 238000003466 welding Methods 0.000 claims abstract description 24
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 3
- 230000002787 reinforcement Effects 0.000 claims description 26
- 239000011241 protective layer Substances 0.000 claims description 4
- 239000012530 fluid Substances 0.000 claims description 3
- 238000000034 method Methods 0.000 claims description 3
- 238000000465 moulding Methods 0.000 claims description 3
- 230000000694 effects Effects 0.000 abstract description 6
- 238000010586 diagram Methods 0.000 description 10
- 238000005516 engineering process Methods 0.000 description 2
- 239000000203 mixture Substances 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000002950 deficient Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000035800 maturation Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 230000035939 shock Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Landscapes
- Rod-Shaped Construction Members (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
本发明是一种叠合柱,特别涉及多腔钢管混凝土叠合柱及其制作方法。本发明将预开孔洞的钢板及钢管沿纵向焊接成多腔钢管,并在多腔钢管外壁上焊接铆钉,之后在多腔钢管外绑扎纵向钢筋及箍筋组成钢筋网,最后支模板并浇注混凝土,组合成内部为多腔钢管混凝土柱外部为钢筋混凝土的多腔钢管混凝土叠合柱。本发明的叠合柱不但解决了大尺寸钢管混凝土叠合柱中由于钢管尺寸过大造成的套箍效应降低这一缺点,而且比现有的叠合柱截面形式更加灵活多样,从而在不降低其承载能力的前提下,充分的发挥了建筑物的功能利用并增加了其使用面积。
Description
技术领域
本发明是一种剪力墙叠合柱,特别涉及多腔钢管混凝土叠合柱及其制作方法。
背景技术
随着人民群众生活水平的提高,居民对住宅及办公建筑的要求也越来越高,高层及超高层建筑开始逐渐增多。在这数量众多的钢筋混凝土高层建筑中,钢管混凝土柱的使用已比较广泛,其结构形式不但有效的提高了内部混凝土的承载能力,而且克服了钢管结构的容易发生局部屈曲的缺点。两种材料结合所发挥的作用远远大于两者单纯叠加。然而,随着钢管混凝土技术的成熟,其缺点也日趋显现。钢管混凝土叠合柱的出现为钢管混凝土柱的性能作了补充,不但有效减小了钢管混凝土柱的轴压比,增大了其变形能力而且提高了防火性能。因此,钢管混凝土叠合柱开始在高层建筑的使用中崭露头角。
但是钢管混凝土叠合柱在超高层建筑中的使用尚不广泛,原因之一就是超高层建筑往往要求尺寸巨大的柱以承担巨大荷载,而传统的钢管混凝土叠合柱若要担此重任,务必要增加截面尺寸从而减少了建筑物的使用面积,并且使得空间利用不甚方便。此外,巨大截面尺寸的钢管在承受荷载时减小了传统钢管混凝土柱中的套箍效应,减弱了钢管混凝土内柱的优势发挥,降低了钢管混凝土叠合柱的承载力。
发明内容
本发明的目的在于克服了现有钢管混凝土叠合柱的上述缺陷,提供了一种多腔钢管混凝土叠合柱及其制作方法,本发明能够显著提高钢管混凝土叠合柱的承载力,方便建筑物的空间利用。
为了实现上述目的,本发明采取了如下技术方案。本发明包括多腔钢管混凝土柱和外包钢筋混凝土,所述多腔钢管混凝土柱为由钢管及钢板组合而成的多腔钢管并在钢管内填混凝土构成的钢管混凝土柱,多腔钢管内部各钢板上打孔,以便混凝土浇注,多腔钢管的外壁上焊接有铆钉,钢管与钢管或钢管与钢板通过焊接连接;在多腔钢管外沿管壁绑扎纵向钢筋及箍筋组成钢筋网,在钢筋网外支模板,在模板内与多腔钢管的各个腔内同时浇注混凝土构成多腔钢管混凝土叠合柱。
所述的多腔钢管内各个腔的截面形状为三角形、四边形或圆形。
所述的多腔钢管由三块条形钢板和一个截面为圆形的钢管构成,三块条形钢板焊接成U型槽,U型槽的开口边与圆形钢管的外壁焊接。
所述的多腔钢管由两块条形钢板和两个截面形状为等边直角三角形的尺寸相同的钢管构成,两块条形钢板焊接在两个钢管的两条直角边之间,与两个钢管一起组成外轮廓形状为平行四边形的多腔钢管。
所述的多腔钢管由两块条形钢板和两个截面形状为矩形的尺寸相同的钢管构成,其中一块条形钢板的两边分别与两个钢管的纵向直角边焊接,另一块条形钢板的两边分别与已焊接的两矩形截面钢管纵向直角边的对边焊接,每个矩形截面钢管上的两条已焊接直角边构成的面垂直于两块条形钢板的所在面。
多腔钢管混凝土叠合柱的制作方法,该方法是按以下顺序进行的:
1)配置钢管混凝土叠合柱中的钢管,并在钢管上预留混凝土孔洞;
2)配置条形钢板,并在条形钢板上预留箍筋孔洞和混凝土孔洞;
3)对于需要钢板与钢板焊接的钢管混凝土叠合柱,首先焊接钢板;
4)将钢管与条形钢板或焊接后的钢板焊接,组成多腔钢管;
5)在多腔钢管外壁上焊接铆钉;
6)在焊接后的多腔钢管外配置纵向钢筋,并在纵向钢筋外绑扎箍筋,组成钢筋网。箍筋需要穿过多腔钢板的,将箍筋穿过钢板上预先设置的孔洞;
7)在钢筋网外侧预留保护层厚度,支模板;
8)浇筑多腔钢管混凝土柱内混凝土和钢管外的钢筋混凝土,成型后即为多腔钢管混凝土叠合柱。
本发明多腔钢管混凝土叠合柱将横截面尺寸巨大的钢管沿横向分为多个互相连通的区域,众多缩小的区域有利于钢管混凝土柱发挥套箍效应,从而增加内填混凝土的承载能力,使相同体积的混凝土发挥更大的作用。此外,多腔钢管混凝土叠合柱的出现,使得柱截面能够根据柱的位置及作用做出相应变化,更为有效的承受地震荷载,提高抗震能力,增加结构的稳定性,而且提高了建筑物的空间利用率,使得建筑功能发挥的更加充分合理。
附图说明
图1是本发明多腔钢管混凝土叠合柱中横截面形状为乒乓球拍的结构配钢及配筋示意图;
图2是图1中A-A剖面放大示意图;
图3是图1中B-B剖面放大示意图;
图4是本发明多腔钢管混凝土叠合柱中横截面形状为平行四边形的结构配钢及配筋示意图;
图5是图4中A-A剖面放大示意图;
图6是图4中B-B剖面放大示意图;
图7是本发明多腔钢管混凝土叠合柱中横截面形状为菱形的结构配钢及配筋示意图;
图8是图7中A-A剖面放大示意图;
图9是图7中B-B剖面放大示意图;
图中:1、多腔钢管,2、钢管,3、钢板,4、纵向钢筋,5、圆形箍筋,6、箍筋,7、钢管混凝土内柱,8、钢筋混凝土外柱,9、铆钉。
具体实施方式
下面结合附图1~图9对本发明作进一步说明:
实施例1
多腔钢管混凝土叠合柱中横截面形状为乒乓球拍的结构配钢及配筋示意图如图1~图3所示。本实施例由钢管2、钢板3组合而成的多腔钢管1并内浇混泥土和钢筋混凝土外柱8组合而成,本实施例中的两块条形钢板呈垂直角度于纵边焊接,并与第三块钢板于纵边焊接组成U形槽,将U形槽与圆形截面钢管于纵向焊接,构成钢管混凝土内柱中的多腔钢管1。钢管2和钢板3上预留有方便混凝土浇注的孔洞,钢板3还留有箍筋绑扎的孔洞。多腔钢管1外壁上焊接铆钉9,之后在多腔钢管1外绑扎纵向钢筋4,沿纵向钢筋4均匀的绑扎圆形箍筋5和矩形箍筋6,绑扎圆形箍筋5和矩形箍筋6时,箍筋均应穿过多腔钢管1中预留的孔洞,在纵向钢筋4和箍筋5、6组成的钢筋网外留下保护层厚度距离支模板,在模板内及多腔钢管1内浇注混凝土,构成多腔钢管混凝土叠合柱。
多腔钢管混凝土叠合柱的制作方法,该方法包括以下步骤:
1)配置钢管混凝土叠合柱中的钢管,并在钢管上预留混凝土孔洞;
2)配置条形钢板,并在条形钢板上预留箍筋孔洞和混凝土孔洞;
3)将三块条形钢板沿纵向焊接成U形槽;
4)将U形槽的开口边与钢管的外壁焊接,组成多腔钢管;
5)在多腔钢管外壁上焊接铆钉;
6)在焊接后的多腔钢管外配置纵向钢筋,并在纵向钢筋外绑扎圆形箍筋及矩形箍筋组成钢筋网;圆形箍筋和矩形箍筋需穿过条形钢板上的预留孔洞;
7)在钢筋网外侧预留保护层厚度,支模板;
8)浇筑钢管混凝土柱内混凝土和钢管外的钢筋混凝土,成型后即为多腔钢管混凝土叠合柱。
实施例2
本实施例的结构与实施例1基本相同,不同之处仅在于:多腔钢管的截面形状不同,如图4~图6所示,本实施例中的多腔钢管由两块条形钢板和两个截面形状为等边直角三角形的钢管构成。两块条形钢板的两个长边分别与两等边直角三角形截面钢管的纵向直角边与纵向锐角边焊接,另一块条形钢板的两长边分别与两等边直角三角形截面钢管的纵向锐角边与纵向直角边焊接,两块条形钢板互相平行且垂直于与之焊接的两等边直角三角形截面钢管的钢板,这样就构成了外轮廓形状为平行四边形的多腔钢管。本实施例中不需要U形槽,钢管外箍筋也不需要穿过钢管,即条形钢板上不需要预留箍筋的孔洞。
实施例3
本实施例的结构与实施例1基本相同,不同之处仅在于:多腔钢管的截面形状不同,如图7~图9所示,本实施例中的多腔钢管由两块条形钢板和两个截面形状为矩形的尺寸相同的钢管构成,条形钢板两个长边分别与两个矩形截面钢管的纵向直角边焊接,另一块条形钢板的两长边分别与已焊接的两矩形截面钢管纵向直角边的对边焊接,每个矩形截面钢管上的两条已焊接直角边构成的面垂直于两块条形钢板的所在面,这样就构成了外轮廓形状为菱形的多腔钢管。本实施例中钢管外箍筋不需要穿过钢管,即条形钢板上不需要预留箍筋的孔洞。
Claims (6)
1.多腔钢管混凝土叠合柱,其特征在于:包括多腔钢管混凝土柱和外包钢筋混凝土,所述多腔钢管混凝土柱为由钢管及钢板组合而成的多腔钢管并在钢管内填混凝土构成的钢管混凝土柱,多腔钢管内部各钢板上打孔,以便混凝土浇注,多腔钢管的外壁上焊接有铆钉,钢管与钢管或钢管与钢板通过焊接连接;在多腔钢管外沿管壁绑扎纵向钢筋及箍筋组成钢筋网,在钢筋网外支模板,在模板内与多腔钢管的各个腔内同时浇注混凝土构成多腔钢管混凝土叠合柱。
2.根据权利要求1所述的多腔钢管混凝土叠合柱,其特征在于:所述的多腔钢管内各个腔的截面形状为三角形、四边形或圆形。
3.根据权利要求1所述的多腔钢管混凝土叠合柱,其特征在于:所述的多腔钢管由三块条形钢板和一个截面为圆形的钢管构成,三块条形钢板焊接成U型槽,U型槽的开口边与圆形钢管的外壁焊接。
4.根据权利要求1所述的多腔钢管混凝土叠合柱,其特征在于:所述的多腔钢管由两块条形钢板和两个截面形状为等边直角三角形的尺寸相同的钢管构成,两块条形钢板焊接在两个钢管的两条直角边之间,与两个钢管一起组成外轮廓形状为平行四边形的多腔钢管。
5.根据权利要求1所述的多腔钢管混凝土叠合柱,其特征在于:所述的多腔钢管由两块条形钢板和两个截面形状为矩形的尺寸相同的钢管构成,其中一块条形钢板的两边分别与两个钢管的纵向直角边焊接,另一块条形钢板的两边分别与已焊接的两矩形截面钢管纵向直角边的对边焊接,每个矩形截面钢管上的两条已焊接直角边构成的面垂直于两块条形钢板的所在面。
6.如权利要求1所述的多腔钢管混凝土叠合柱的制作方法,其特征在于,该方法是按以下顺序进行的:
1)配置钢管混凝土叠合柱中的钢管,并在钢管上预留混凝土孔洞;
2)配置条形钢板,并在条形钢板上预留箍筋孔洞和混凝土孔洞;
3)对于需要钢板与钢板焊接的钢管混凝土叠合柱,首先焊接钢板;
4)将钢管与条形钢板或焊接后的钢板焊接,组成多腔钢管;
5)在多腔钢管外壁上焊接铆钉;
6)在焊接后的多腔钢管外配置纵向钢筋,并在纵向钢筋外绑扎箍筋,组成钢筋网;箍筋需要穿过多腔钢板的,将箍筋穿过钢板上预先设置的孔洞;
7)在钢筋网外侧预留保护层厚度,支模板;
8)浇筑多腔钢管混凝土柱内混凝土和钢管外的钢筋混凝土,成型后即为多腔钢管混凝土叠合柱。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010101524398A CN101824878B (zh) | 2010-04-16 | 2010-04-16 | 多腔钢管混凝土叠合柱及其制作方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010101524398A CN101824878B (zh) | 2010-04-16 | 2010-04-16 | 多腔钢管混凝土叠合柱及其制作方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101824878A true CN101824878A (zh) | 2010-09-08 |
CN101824878B CN101824878B (zh) | 2012-07-04 |
Family
ID=42689024
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010101524398A Expired - Fee Related CN101824878B (zh) | 2010-04-16 | 2010-04-16 | 多腔钢管混凝土叠合柱及其制作方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101824878B (zh) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102251669A (zh) * | 2011-05-26 | 2011-11-23 | 葛洲坝集团第二工程有限公司 | 圆筒式薄壁混凝土墙模板的施工方法 |
CN102409808A (zh) * | 2011-11-28 | 2012-04-11 | 北京工业大学 | 底部带软钢套管外包混凝土的钢管混凝土叠合柱及作法 |
CN102535747A (zh) * | 2011-12-31 | 2012-07-04 | 北京工业大学 | 角部贴焊角钢腔内设置钢筋笼多腔体钢管混凝土柱及作法 |
CN102535749A (zh) * | 2011-12-31 | 2012-07-04 | 北京工业大学 | 底部带软钢套管的双功能多腔体钢管混凝土柱及作法 |
CN103628571A (zh) * | 2013-12-09 | 2014-03-12 | 广州市第一建筑工程有限公司 | 一种逆作法用梁柱节点及施工方法 |
CN103774758A (zh) * | 2014-02-19 | 2014-05-07 | 中国建筑第八工程局有限公司 | 箱型钢管柱与剪力墙端柱之间的连接方法及连接结构 |
CN104863363A (zh) * | 2015-05-08 | 2015-08-26 | 中国建筑第八工程局有限公司 | 一种外包混凝土钢管组合柱的施工方法 |
CN105155778A (zh) * | 2015-09-29 | 2015-12-16 | 江苏沪宁钢机股份有限公司 | 一种组合钢管柱构件及其加工制作方法 |
CN108360838A (zh) * | 2018-03-16 | 2018-08-03 | 湖南科技学院 | 钢混支撑托换架及其施工方法 |
CN113374083A (zh) * | 2021-05-24 | 2021-09-10 | 哈尔滨工业大学 | 钢-再生混凝土组合梁与圆钢管高强混凝土柱的节点构造及其施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10204994A (ja) * | 1997-01-27 | 1998-08-04 | Taisei Corp | 鋼管コンクリート部材 |
CN200989034Y (zh) * | 2006-12-08 | 2007-12-12 | 北京工业大学 | 型钢-钢管混凝土异形柱 |
KR20090010301A (ko) * | 2007-07-23 | 2009-01-30 | (주)에이엠에스 엔지니어링 | 프리컬럼을 사용한 폭렬방지형 고강도 철근콘크리트기둥부재의 제작방법 |
CN201314095Y (zh) * | 2008-11-28 | 2009-09-23 | 沈阳建筑大学 | 一种钢骨—钢管混凝土芯柱 |
CN101555721A (zh) * | 2009-05-06 | 2009-10-14 | 北京航空航天大学 | 多室式钢管混凝土异形柱 |
CN201433512Y (zh) * | 2009-06-11 | 2010-03-31 | 中国京冶工程技术有限公司 | 一种钢板和钢筋联合加劲的异形钢管混凝土柱 |
-
2010
- 2010-04-16 CN CN2010101524398A patent/CN101824878B/zh not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10204994A (ja) * | 1997-01-27 | 1998-08-04 | Taisei Corp | 鋼管コンクリート部材 |
CN200989034Y (zh) * | 2006-12-08 | 2007-12-12 | 北京工业大学 | 型钢-钢管混凝土异形柱 |
KR20090010301A (ko) * | 2007-07-23 | 2009-01-30 | (주)에이엠에스 엔지니어링 | 프리컬럼을 사용한 폭렬방지형 고강도 철근콘크리트기둥부재의 제작방법 |
CN201314095Y (zh) * | 2008-11-28 | 2009-09-23 | 沈阳建筑大学 | 一种钢骨—钢管混凝土芯柱 |
CN101555721A (zh) * | 2009-05-06 | 2009-10-14 | 北京航空航天大学 | 多室式钢管混凝土异形柱 |
CN201433512Y (zh) * | 2009-06-11 | 2010-03-31 | 中国京冶工程技术有限公司 | 一种钢板和钢筋联合加劲的异形钢管混凝土柱 |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102251669A (zh) * | 2011-05-26 | 2011-11-23 | 葛洲坝集团第二工程有限公司 | 圆筒式薄壁混凝土墙模板的施工方法 |
CN102251669B (zh) * | 2011-05-26 | 2012-09-12 | 葛洲坝集团第二工程有限公司 | 圆筒式薄壁混凝土墙模板的施工方法 |
CN102409808A (zh) * | 2011-11-28 | 2012-04-11 | 北京工业大学 | 底部带软钢套管外包混凝土的钢管混凝土叠合柱及作法 |
CN102535747A (zh) * | 2011-12-31 | 2012-07-04 | 北京工业大学 | 角部贴焊角钢腔内设置钢筋笼多腔体钢管混凝土柱及作法 |
CN102535749A (zh) * | 2011-12-31 | 2012-07-04 | 北京工业大学 | 底部带软钢套管的双功能多腔体钢管混凝土柱及作法 |
CN103628571A (zh) * | 2013-12-09 | 2014-03-12 | 广州市第一建筑工程有限公司 | 一种逆作法用梁柱节点及施工方法 |
CN103774758A (zh) * | 2014-02-19 | 2014-05-07 | 中国建筑第八工程局有限公司 | 箱型钢管柱与剪力墙端柱之间的连接方法及连接结构 |
CN103774758B (zh) * | 2014-02-19 | 2016-03-09 | 中国建筑第八工程局有限公司 | 箱型钢管柱与剪力墙端柱之间的连接方法及连接结构 |
CN104863363A (zh) * | 2015-05-08 | 2015-08-26 | 中国建筑第八工程局有限公司 | 一种外包混凝土钢管组合柱的施工方法 |
CN104863363B (zh) * | 2015-05-08 | 2017-03-08 | 中国建筑第八工程局有限公司 | 一种外包混凝土钢管组合柱的施工方法 |
CN105155778A (zh) * | 2015-09-29 | 2015-12-16 | 江苏沪宁钢机股份有限公司 | 一种组合钢管柱构件及其加工制作方法 |
CN105155778B (zh) * | 2015-09-29 | 2017-10-10 | 江苏沪宁钢机股份有限公司 | 一种组合钢管柱构件的加工制作方法 |
CN108360838A (zh) * | 2018-03-16 | 2018-08-03 | 湖南科技学院 | 钢混支撑托换架及其施工方法 |
CN108360838B (zh) * | 2018-03-16 | 2023-07-25 | 湖南科技学院 | 钢混支撑托换架及其施工方法 |
CN113374083A (zh) * | 2021-05-24 | 2021-09-10 | 哈尔滨工业大学 | 钢-再生混凝土组合梁与圆钢管高强混凝土柱的节点构造及其施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN101824878B (zh) | 2012-07-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101824878B (zh) | 多腔钢管混凝土叠合柱及其制作方法 | |
CN102704593B (zh) | “钢管混凝土叠合柱-钢梁-格构钢撑”剪力墙及作法 | |
CN103726594B (zh) | 内藏多腔双钢板及钢管混凝土柱组合剪力墙及作法 | |
CN101260689B (zh) | 一种钢管混凝土斜交网格柱空间相贯节点及其制作方法 | |
CN103122676B (zh) | 角部加强型钢管混凝土叠合柱及作法 | |
CN103615071A (zh) | 内置螺旋箍筋方钢管混凝土柱 | |
CN102444224A (zh) | 混凝土组合剪力墙 | |
CN102704595A (zh) | 钢管混凝土柱间嵌“型钢柱-钢梁-钢撑”剪力墙及作法 | |
CN201433512Y (zh) | 一种钢板和钢筋联合加劲的异形钢管混凝土柱 | |
CN107806006A (zh) | 一种原竹‑混凝土组合桥梁及其制造方法 | |
CN201962844U (zh) | 内置钢管钢板的空心组合板 | |
CN102828559B (zh) | 一种组合梁与45度角布置十字型钢混凝土柱节点 | |
CN203049788U (zh) | 新型钢管混凝土柱双底板刚接柱脚节点 | |
CN202519879U (zh) | 加强核心钢管的高阻尼混凝土叠合柱 | |
CN202644385U (zh) | 铝合金管约束钢筋混凝土桥墩墩柱 | |
CN210369562U (zh) | 一种钢柱插入地下室变截面节点 | |
CN203145193U (zh) | 焊接组合型钢混凝土异形柱-钢梁半刚性节点 | |
CN102704597A (zh) | 钢管混凝土柱间嵌钢板密梁外包混凝土组合剪力墙及作法 | |
CN102094463A (zh) | 一种新型多区格加劲杂交结构 | |
CN109610637B (zh) | 装配式煤矸石陶粒钢管混凝土梁柱节点结构及其施工方法 | |
CN101974958A (zh) | 一种工字型frp型材的钢管混凝土柱 | |
CN106639054A (zh) | 基于预制钢结构的装配式钢板网外包混凝土剪力墙结构 | |
CN203684405U (zh) | 聚丙烯纤维增强异形柱节点 | |
CN204676710U (zh) | 劲性梁柱节点核心区柱钢板箍结构 | |
CN107060076A (zh) | 一种无箍筋的矩形钢管约束混凝土柱节点及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120704 |
|
CF01 | Termination of patent right due to non-payment of annual fee |