CN101798919A - Method for monitoring whether drilling mud is invaded by grouting fluid during drilling and grouting parallel operation - Google Patents

Method for monitoring whether drilling mud is invaded by grouting fluid during drilling and grouting parallel operation Download PDF

Info

Publication number
CN101798919A
CN101798919A CN201010145718A CN201010145718A CN101798919A CN 101798919 A CN101798919 A CN 101798919A CN 201010145718 A CN201010145718 A CN 201010145718A CN 201010145718 A CN201010145718 A CN 201010145718A CN 101798919 A CN101798919 A CN 101798919A
Authority
CN
China
Prior art keywords
mud
value
drilling
grouting
injection slurry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201010145718A
Other languages
Chinese (zh)
Other versions
CN101798919B (en
Inventor
孙建荣
张广宇
周兴旺
刘志强
王新
左永江
王正胜
王哓建
李恩涛
李英全
汪船
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing China Coal Mine Engineering Co ltd
Original Assignee
Beijing China Coal Mine Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing China Coal Mine Engineering Co ltd filed Critical Beijing China Coal Mine Engineering Co ltd
Priority to CN2010101457181A priority Critical patent/CN101798919B/en
Publication of CN101798919A publication Critical patent/CN101798919A/en
Application granted granted Critical
Publication of CN101798919B publication Critical patent/CN101798919B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to a method for monitoring whether drilling mud is invaded by grouting fluid during drilling and grouting parallel operation. The specific monitoring processes are that: a pH value online monitoring system is established, the system comprises a sensor, a monitoring instrument and a computer, and the sensor is arranged at a position close to a mud nozzle, wherein the flow rate of mud liquid at the position is 0.6-1.2m/min and the mud liquid at the position contains less sand when being viewed by naked eyes; and the monitoring instrument measures the real-time pH value of mud, the computer compares the real-time pH value with a preset warning value, when the pH value of the mud is higher than the warning value, a corresponding signal is sent out and a grouting pump is paused or shut down according to the signal. By adopting the method of monitoring the pH value of the mud at the drilling mud outlet, whether the drilling mud is invaded by the grouting liquid during the drilling and grouting parallel operation can be intuitively and reliably monitored and thereby effective measures can be taken to ensure the safety of the drilling and grouting parallel operation.

Description

Bore the monitoring method of whether invading injection slurry in the drilling-grouting parallel operation in the drilling mud
Technical field:
The present invention relates to sinking by boring and slip casting method and construct when carrying out simultaneously, whether invade the monitoring method of injection slurry in the drilling mud.
Background technology:
Boring method " well-digging do not go into the well ", mechanization degree height, safe and reliable, become the well quality good, be in dark thick surface soil, to dig the reliable construction technology of shaft of vertical well, but often need repeatedly to expand the well prefabricated lining that sinks again, speed of application is slow, long in time limit, and when basement rock aquifer, deep slip casting method is constructed, need finish the rock section mortar depositing construction earlier, carry out the alluvium wellbore construction again, cause the pit shaft construction period long.According to present construction technology level, if the shaft of vertical well that 1000m is dark, alluvium 600m is thick, adopts wellbore construction to need more than 2 years, and rock section aquifer, bottom pre grouting from the surface needs 10~12 months; The average speed 64m/ month is built in whole nation shaft of vertical well basement rock pick, and by slip casting-drilling well-sinking shaft sequence construction, the construction period of whole shaft of vertical well approximately needs the time in 4~5 years.If realize the parallel operations of boring method and slip casting method two big working procedures, can save total construction period significantly.
If but in boring the drilling-grouting parallel operation process injection slurry invade sneak into mud in the bored shaft after, the fluid loss of mud is increased, destroy its stability, thereby destroy the performance of drilling mud, influence normally creeping into of sinking by boring, serious meeting damages drilling well well group, causes the hole of collapsing, may cause serious accident, influence the drilling well duration.
So in drilling process, strengthen monitoring to drilling mud, prevent that injection slurry from invading in the drilling mud, be the necessary condition that realizes that brill-drilling-grouting parallel operation carries out smoothly.
Summary of the invention:
Technical problem to be solved by this invention provides sinking by boring and slip casting method is constructed when carrying out simultaneously, whether invades the monitoring method of injection slurry in the drilling mud, thereby provides safety guarantee for boring drilling-grouting parallel operation.
For solving the problems of the technologies described above, technical scheme of the present invention is:
Set up pH value on-line monitoring system, this system comprises sensor, monitoring instrument and computer, wherein sensor is selected sunk pH value sensor for use, and sensor is placed in that slurry flow rate is 0.6~1.2m/min, with the naked eye relatively sand content is less relatively and near the mud nozzle place; The live signal that monitoring instrument is sent by sensor, measure the real-time pH value of mud, and this numerical value is transferred to computer, computer is compared to predefined numerical value and real-time pH value, when mud pH value is higher than the caution value, send alarm signal, suspend slip casting this moment, and the various performance parameters of mud is tested, if other do not change other parameters of mud, continue slip casting,, then stop slip casting if other parameters all change; When mud pH value reaches the warning value, send alarm signal, turn off grouting pump; When the pH value has burst to change, wouldn't give a warning; When burst changes when the short time can't eliminate, send alarm signal.
The setting of described caution, warning value, the pH value comparison back when using drilling mud, injection slurry and mud and injection slurry different blended composition and division in a proportion according to institute's drilling well is determined; Wherein caution value is preferably 8.0, and the warning value is preferably 8.5.
Described monitoring instrument comprises pH value measurement module, and measurement module is measured the pH value of mud according to the live signal of sensor, and the resolution ratio of measurement module is not less than 0.01, the limit of error is not more than ± and 0.002.
The present invention has following beneficial effect: adopt the method in drilling mud exit monitoring mud pH value, what energy was intuitive and reliable monitors whether injection slurry invades in the drilling mud when boring drilling-grouting parallel operation, and then the safety of the assurance brill drilling-grouting parallel operation of adopting an effective measure, this method is simple, quick in addition, is a kind of desirable monitoring method.
The specific embodiment:
Respectively test described ratio in following examples and be mass percent.
Followingly respectively test the pH value to detect used pH meter be the SevenMultis type pH/ electrical conductivity/ion comprehensive tester of Mettler Toledo Inc..
At first each parameter influence of drilling mud is tested, illustrates to select the index of this parameter of mud pH value why as monitoring by following injection slurry:
Took on-the-spot injection slurry on July 14th, 2009, join in the table soil section drilling mud by different proportion, the variation of each parameter of mud sees the following form 1:
Table 1 injection slurry his-and-hers watches soil section drilling mud parameter influence
Figure GSA00000064639200031
September in 2009 enchashment field on the 12nd injection slurry, join in the rock section drilling mud by different proportion, the variation of each parameter of mud sees the following form 2.
Table 2 injection slurry is to rock section drilling mud parameter influence
Prescription/project Apparent viscosity mPas Plastic viscosity mPas Yield value Pa Gel strength Pa Density g/cm 3 The pH value Fluid loss ml/30min
2009.9.12 8:30 injection slurry early ??1.195 ??12
2009.9.12 8:30 drilling mud early ??15.50 ??10.00 ??5.62 ??7.15 ??1.157 ??7 ??22.7
Mud+1% injection slurry ??17.50 ??11.00 ??6.64 ??8.69 ??1.156 ??9 ??25.5
Mud+2% injection slurry ??19.00 ??12.00 ??7.15 ??9.71 ??1.57 ??9.5 ??28.2
Mud+3% injection slurry ??23.00 ??12.00 ??11.24 ??12.78 ??1.57 ??9.8 ??29
Mud+4% injection slurry ??24.00 ??13.00 ??11.24 ??13.80 ??1.58 ??10 ??30
Mud+5% injection slurry ??24.50 ??12.00 ??12.78 ??17.89 ??1.58 ??11 ??33.2
Mud+6% injection slurry ??28.00 ??9.00 ??19.42 ??31.68 ??1.6
From last table 1,2 as can be seen, the ratio that joins in the mud along with injection slurry constantly increases, each parameter all has variation in various degree in the mud, wherein shear force changes maximum, next is pH value and viscosity, so think, after injection slurry joins in the mud, mud changes apparent in view parameter, be that sensitive parameter is the viscosity of mud, shear force and pH value, but apparent in view variation also can take place in the viscosity of mud and shear force usually when boring the chance Different Strata, inartificial when carrying out mud conditioning, the pH value of having only mud is constant substantially, is not subjected to drilling parameter, the influence of factors such as drilling strata, and shear force is the parameter that is difficult for monitoring, generally need just can obtain a result, can not monitor intuitively indoor experimentizing.Generally all about 12, as long as injection slurry invades in the drilling mud, the pH value of mud will change the pH value of injection slurry.So, monitor whether injection slurry is blended in the mud in the actual engineering, mainly can monitor the pH value of mud.
Then by following injection slurry to the influence of drilling mud pH value experiment, determine to invade in the mud Changing Pattern of pH value behind the injection slurry, and further specify the feasibility of selection pH value as monitoring parameter:
What kind of drilling mud pH value had influence rule in order to seek injection slurry, indoorly prepared various different formulations injection slurries respectively, join respectively in the drilling mud in proportion, measure its pH value, experimental result is as follows:
1, single liquid slurry is to the influence of drilling mud pH value
The single liquid slurry of autogamy: water/binder ratio 1: 1, NaCl dosage are 5% of cement, and the triethanolamine dosage is 5 ‰ of a cement dosage, density 1.528kg/m3.
The single liquid slurry of autogamy is joined in the mud by different proportion, and when adding 1%, it is very thick that mud promptly becomes, and is difficult to measure its rheological parameter.Record its pH value with pH meter and see the following form 3:
The single liquid slurry of table 3 is to the influence of drilling mud pH value
Prescription ??pH
September 13 the 10:00 drilling mud ??7.342
The single liquid slurry of mud+0.5% ??9.988
The single liquid slurry of mud+1% ??10.153
The single liquid slurry of mud+2% ??10.776
The single liquid slurry of mud+3% ??11.168
The single liquid slurry of mud+4% ??11.298
Single liquid slurry ??11.492
2, rarer injection slurry is to the influence of drilling mud pH value
The rarer injection slurry of autogamy: magma proportion 1.1kg/m3, cement 150kg, 15 liters of water glass, injection slurry density 1.197kg/m3.
The rarer injection slurry of table 4 is to the influence of drilling mud pH value
Prescription ??pH
September 14 the 8:30 drilling mud ??7.342
Mud+1% injection slurry ??9.019
Prescription ??pH
Mud+2% injection slurry ??9.498
Mud+3% injection slurry ??10.242
Mud+4% injection slurry ??10.566
Mud+5% injection slurry ??10.684
Injection slurry ??11.705
3, injection slurry commonly used is to the influence of drilling mud pH value
Injection slurry is used in autogamy always: magma proportion 1.12kg/m3, cement 150kg, 15 liters of water glass, injection slurry density 1.231kg/m3.
Table 5 injection slurry commonly used is to the influence of drilling mud pH value
Prescription ??pH
September 14 the 8:30 drilling mud ??7.342
Mud+1% injection slurry ??9.738
Mud+2% injection slurry ??10.122
Mud+3% injection slurry ??10.33
Mud+4% injection slurry ??10.637
Mud+5% injection slurry ??10.799
Injection slurry ??11.701
4, thicker injection slurry is to the influence of drilling mud pH value
The thicker injection slurry of autogamy: magma proportion 1.1kg/m3, cement 200kg, 20 liters of water glass, injection slurry density 1.239kg/m3.
The thicker injection slurry of table 6 is to the influence of drilling mud pH value
Prescription ??pH
September 14 the 8:30 drilling mud ??7.342
Prescription ??pH
Mud+1% injection slurry ??10.152
Mud+2% injection slurry ??10.207
Mud+3% injection slurry ??10.596
Mud+4% injection slurry ??10.817
Mud+5% injection slurry ??10.962
Injection slurry ??11.78
5, interpretation
Do not carrying out under the situation of specially treated, the pH value of mud is generally all less than 8.0, and from above experimental result as can be seen, when injection slurry joined in the mud, along with the increase gradually of injection slurry dosage, the pH value of mud all increased gradually, when each prescription injection slurry ratio in the mud of joining is 1%, the Changing Pattern of mud pH value is: the pH value is all greater than 9, and promptly obvious variation has taken place the pH value, than being easier to monitor out the result.
The slurry-outlet quantity of drilling mud is about 1200m 3/ h, the about 14m of grouting amount 3/ h accounts for 1% of mud slurry-outlet quantity.Slip casting is all in the bottom of drilling well, if injection slurry is scurried in the mud, can only scurry into from the bottom of drilling well, and anti-circulation well cleanup mode is adopted in drilling well, the mud at work plane place, drilling well bottom can directly be drawn onto grout outlet, that is to say,, can monitor at the grout outlet place soon if injection slurry is scurried in the mud.
In normal drilling process, there is not any factor can cause the variation of mud pH value, so the pH value of mud is generally constant, front and back can not surpass 0.5 variation.Therefore, in boring the drilling-grouting parallel operation process, whether as long as the pH value of monitoring drilling mud, just can judge has injection slurry to invade in the drilling mud.
We monitor the pH value of drilling mud in boring the drilling-grouting parallel operation process at last, and concrete observation process is as follows:
1, sets up pH value on-line monitoring system, this system comprises sensor, monitoring instrument and computer, sensor is connected by transmission cable with monitoring instrument, transmission cable preferably adopts multicore shielding armouring exploration cable, the life-span of selecting armored cable to help to keep monitoring cable, and in installation process, can utilize cable that sensor etc. is partly carried out lifting operation.The accurate processes sensor signal of monitoring instrument measuring pH value accurately, and transfers to computer with this numerical value through the RS232 interface, also can adopt other forms of interface to link to each other with computer certainly and realize transfer of data; The scope that the measurement category of monitoring instrument should satisfy transducer calibration and set the monitoring, alarming value; Because native system need carry out anticipation and judgement work by record pH Value Data, so monitoring instrument need use resolution ratio to be not less than pH value 0.01, the limit of error is not more than ± 0.002 measurement module; In addition, monitoring instrument should provide the state of measuring transducer to show, sensor is damaged should be able to provide demonstration.Software is finished pH value and other detected recording of information, comparison in the computer, and uses the method for gradual judgement that signal is reported by mistake and judge; Software preferably possesses the function that shows pH value change curve or changing trend diagram simultaneously, watches and analyze monitoring result for the Field Force.
2, the selection of sensor installation position: adopt sunk pH value sensor, the sensor installation site close mud nozzle of should trying one's best, slurry fluidity is better, and flow velocity is moderate and contain the lower place of sand content.The slurry flow rate of measured place should be controlled at 0.6~1.2m/min, and flow velocity is crossed the monitoring promptness will be descended, and wraps up at sensor surface formation mud suitcase easily, thereby reduces certainty of measurement; The grains of sand that the too fast then sensor surface of flow velocity is subjected to suspend in the mud wear and tear, and the rate of wear is accelerated, and reduces its application life.
3, concrete monitor signal processing mode: because of the pH value of different drilling muds is differentiated, so the pH value when needing to detect institute's drilling well drilling mud, injection slurry and drilling mud with the different mixing match of injection slurry before monitoring, those skilled in the art are according to the caution value and the warning value of conventional experience and method and these pH values setting monitoring usefulness; Monitoring shows when mud pH value reaches the caution value, send alarm signal, suspend slip casting this moment, continue to observe mud and change, and do the various performance parameters test of mud, if what variation is other parameters do not have, continue slip casting, if other parameters all change, suspect that then injection slurry has invaded in the drilling mud, should stop slip casting.When mud pH value reaches the warning value, send alarm signal, should turn off grouting pump this moment, stops slip casting.When the pH value has burst to change, as when not meeting pH value gradual change, then should be judged as abnormal signal, and wouldn't give a warning, but should check checkout equipment this moment, and detect the mud parameter situation of change, when burst changes when the short time can't eliminate, then send alarm signal.
Be twice monitoring adopting said method to carry out below, SevenNulti type pH/ electrical conductivity/ion comprehensive tester that monitoring instrument uses Mettler Toledo Inc. to produce, model is " S40K ", pH value electrode model is LE438; Because of the pH value of mud usually below 8.0, so the caution value of this twice monitoring is set at 8.0, the warning value is set at 8.5, concrete monitored data sees Table 7,8:
Table 72,009 13, drilling mud pH on September value monitoring result
??Date ??Time ??Result ??Result?unit ??Temperature ??Temp.Unit
??2009-9-13 ??16:44:00 ??7.395 ??pH ??24.8 ??℃
??2009-9-13 ??16:44:03 ??7.396 ??pH ??24.9 ??℃
??2009-9-13 ??16:44:06 ??7.396 ??pH ??24.9 ??℃
??2009-9-13 ??16:44:09 ??7.397 ??pH ??24.9 ??℃
??2009-9-13 ??16:44:12 ??7.397 ??pH ??24.9 ??℃
??2009-9-13 ??16:44:15 ??7.398 ??pH ??24.9 ??℃
??2009-9-13 ??16:44:18 ??7.397 ??pH ??24.9 ??℃
??2009-9-13 ??16:44:21 ??7.396 ??pH ??24.9 ??℃
??2009-9-13 ??16:44:24 ??7.396 ??pH ??24.9 ??℃
??2009-9-13 ??16:52:38 ??7.395 ??pH ??25 ??℃
??2009-9-13 ??16:52:41 ??7.395 ??pH ??25 ??℃
??Date ??Time ??Result ??Result?unit ??Temperature ??Temp.Unit
??2009-9-13 ??16:52:44 ??7.396 ??pH ??25 ??℃
??2009-9-13 ??16:52:47 ??7.395 ??pH ??25 ??℃
??2009-9-13 ??16:52:50 ??7.396 ??pH ??25 ??℃
??2009-9-13 ??16:52:54 ??7.395 ??pH ??25 ??℃
??2009-9-13 ??16:52:56 ??7.395 ??pH ??25.1 ??℃
??2009-9-13 ??16:53:00 ??7.396 ??pH ??25 ??℃
??2009-9-13 ??16:55:48 ??7.394 ??pH ??25.1 ??℃
??2009-9-13 ??16:55:51 ??7.394 ??pH ??25.1 ??℃
??2009-9-13 ??16:55:54 ??7.394 ??pH ??25.1 ??℃
??2009-9-13 ??16:55:57 ??7.394 ??pH ??25.1 ??℃
??2009-9-13 ??16:56:00 ??7.393 ??pH ??25.1 ??℃
??2009-9-13 ??16:56:03 ??7.394 ??pH ??25.1 ??℃
Table 82,009 15, drilling mud pH on September value monitoring result
??Date ??Time ??Result ??Result?unit ??Temperature ??Temp.Unit
??209-9-15 ??1:25:36 ??7.561 ??pH ??23 ??℃
??2009-9-15 ??11:28:03 ??7.512 ??pH ??22.9 ??℃
??2009-9-15 ??11:28:06 ??7.512 ??pH ??22.9 ??℃
??2009-9-15 ??11:29:06 ??7.511 ??pH ??22.9 ??℃
??2009-9-15 ??11:30:06 ??7.509 ??pH ??22.9 ??℃
??2009-9-15 ??11:31:07 ??7.508 ??pH ??22.9 ??℃
??2009-9-15 ??11:32:07 ??7.507 ??pH ??22.9 ??℃
??Date ??Time ??Result ??Result?unit ??Temperature ??Temp.Unit
??2009-9-15 ??11:33:07 ??7.505 ??pH ??22.8 ??℃
??2009-9-15 ??11:34:08 ??7.503 ??pH ??22.8 ??℃
??2009-9-15 ??11:35:08 ??7.503 ??pH ??22.8 ??℃
??2009-9-15 ??11:36:08 ??7.502 ??pH ??22.8 ??℃
??2009-9-15 ??11:37:09 ??7.5 ??pH ??22.8 ??℃
??2009-9-15 ??11:38:09 ??7.499 ??pH ??22.8 ??℃
??2009-9-15 ??11:39:09 ??7.498 ??pH ??22.8 ??℃
By top two days monitoring result as can be seen, the pH value of this drilling mud on the two is very stable, does not invade injection slurry.

Claims (4)

1. one kind is bored the monitoring method of whether invading injection slurry in the drilling-grouting parallel operation in the drilling mud, concrete observation process is: set up pH value on-line monitoring system, this system comprises sensor, monitoring instrument and computer, wherein sensor is selected sunk pH value sensor for use, and sensor is placed in that slurry flow rate is 0.6~1.2m/min, with the naked eye relatively sand content is less relatively and near the mud nozzle place; Monitoring instrument is measured the real-time pH value of mud by the live signal that sensor sends, and this numerical value is transferred to computer; Preestablish caution value and warning value in the computer, and real-time pH value and predefined caution, warning value compared, when mud pH value is higher than the caution value, send alarm signal, suspend slip casting this moment, and the various performance parameters of mud is tested, if other parameters of mud do not change, continue slip casting,, then stop slip casting if other parameters all change; When mud pH value reaches the warning value, send alarm signal, close grouting pump; When the pH value has burst to change, wouldn't give a warning, when burst changes when the short time can't eliminate, send alarm signal.
2. according to the monitoring method of whether invading injection slurry in the drilling mud in the described brill drilling-grouting parallel operation of claim 1, it is characterized in that: the pH value comparison back when drilling mud, injection slurry and mud and injection slurry different blended composition and division in a proportion are used in the basis of design institute drilling well of described caution, warning value is determined.
3. according to the monitoring method of whether invading injection slurry in the drilling mud in the described brill drilling-grouting parallel operation of claim 1, it is characterized in that: described caution value is 8.0, and the warning value is 8.5.
4. according to the monitoring method of whether invading injection slurry in the drilling mud in the described brill drilling-grouting parallel operation of claim 1, it is characterized in that: the resolution ratio of the measurement module of described monitoring instrument is not less than 0.01, and the limit of error is not more than ± and 0.002.
CN2010101457181A 2010-04-14 2010-04-14 Method for monitoring whether drilling mud is invaded by grouting fluid during drilling and grouting parallel operation Expired - Fee Related CN101798919B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101457181A CN101798919B (en) 2010-04-14 2010-04-14 Method for monitoring whether drilling mud is invaded by grouting fluid during drilling and grouting parallel operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101457181A CN101798919B (en) 2010-04-14 2010-04-14 Method for monitoring whether drilling mud is invaded by grouting fluid during drilling and grouting parallel operation

Publications (2)

Publication Number Publication Date
CN101798919A true CN101798919A (en) 2010-08-11
CN101798919B CN101798919B (en) 2013-04-24

Family

ID=42594745

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101457181A Expired - Fee Related CN101798919B (en) 2010-04-14 2010-04-14 Method for monitoring whether drilling mud is invaded by grouting fluid during drilling and grouting parallel operation

Country Status (1)

Country Link
CN (1) CN101798919B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103291284A (en) * 2013-05-14 2013-09-11 中国海洋石油总公司 Method and device both based on annulus pressure measuring while drilling and for early monitoring gas invasion of wellhole
CN103477746A (en) * 2013-09-29 2014-01-01 江苏名和集团有限公司 Vegetation concrete pore soil alkalinity reconstruction method and device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4904603A (en) * 1987-03-09 1990-02-27 Schlumberger Technology Corporation Monitoring drilling mud
US7140434B2 (en) * 2004-07-08 2006-11-28 Schlumberger Technology Corporation Sensor system
CN1986974A (en) * 2006-12-22 2007-06-27 上海市基础工程公司 Pressure reducing horizontal reinforcing process for soft soil layer
CN101215835A (en) * 2007-12-31 2008-07-09 浙江省一建建设集团有限公司 Hole drilling mudjack pile construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4904603A (en) * 1987-03-09 1990-02-27 Schlumberger Technology Corporation Monitoring drilling mud
US7140434B2 (en) * 2004-07-08 2006-11-28 Schlumberger Technology Corporation Sensor system
CN1986974A (en) * 2006-12-22 2007-06-27 上海市基础工程公司 Pressure reducing horizontal reinforcing process for soft soil layer
CN101215835A (en) * 2007-12-31 2008-07-09 浙江省一建建设集团有限公司 Hole drilling mudjack pile construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
周兴旺: "我国特殊凿井技术的发展与展望", 《煤炭科学技术》 *
王耀林: "国外井巷特殊施工技术", 《中国煤炭》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103291284A (en) * 2013-05-14 2013-09-11 中国海洋石油总公司 Method and device both based on annulus pressure measuring while drilling and for early monitoring gas invasion of wellhole
CN103291284B (en) * 2013-05-14 2015-12-02 中国海洋石油总公司 Based on the pit shaft gas cut early monitoring method measured with brill annular pressure and device
CN103477746A (en) * 2013-09-29 2014-01-01 江苏名和集团有限公司 Vegetation concrete pore soil alkalinity reconstruction method and device

Also Published As

Publication number Publication date
CN101798919B (en) 2013-04-24

Similar Documents

Publication Publication Date Title
AU2013212697B2 (en) Systems, methods and devices for analyzing drilling fluid
US20110220350A1 (en) Identification of lost circulation zones
CN104895595B (en) A kind of method for determining injection slurry range of scatter and rule during bolt grouting
Karasawa et al. Experimental results on the effect of bit wear on torque response
CN108756910B (en) Intelligent early warning type advanced grouting device for earth pressure balance shield and construction method
Liang et al. Field research: measuring water pressure resistance in a fault-induced fracture zone
CN101798919B (en) Method for monitoring whether drilling mud is invaded by grouting fluid during drilling and grouting parallel operation
CN104296804A (en) Monitoring and early warning method for buckling failure precursor information of filling body
CN108086908A (en) The application method of mud in the construction of directional drilling crossing river
CN108571319A (en) A kind of differential gas cut and displaced type gas cut judgment method and device
CN104727815A (en) Real-time well drilling formation correction method and device
CN114622893A (en) Underground leakage measurement-while-drilling device and method and leakage plugging system
CN212743988U (en) Drilling stratum leak source measuring apparatu
CN105545205B (en) High intensity Gas Full-Mechanized Caving Face extraction ground L-type boring method
CN102418513B (en) Method for detecting treatment effect of road goaf
CN114412567B (en) Early warning method for in-situ water-retention coal mining on water with bearing pressure of bottom plate limestone
CN111219183A (en) Water yield and water pressure detection device
TWM586745U (en) Separate sealing hydraulic test and measurement system
CN216588450U (en) Mud dado drilling system of detectable ground water level
CN216642201U (en) Orifice pipe device suitable for intelligent water regime monitored control system of hole of spying in pit
CN109165480B (en) Method and system for predicting pit water inflow based on clay stress path
Huang et al. Variations in Hydraulic Properties of Sendimentary Rocks Induced by Fluid Injection: The Effect of Water Pressure.
JP3744887B2 (en) How to excavate the ground
CN110439614A (en) A kind of unrestrained Fluid Dynamics device of coal mining bottom plate and application method
Ripatti et al. Difference flow and electrical conductivity measurements at the Olkiluoto site in Eurajoki, drillholes OL-KR56, OL-KR57 and OL-KR57B

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130424

Termination date: 20160414