CN101767753A - Method for hoisting by lifting belt vertically - Google Patents

Method for hoisting by lifting belt vertically Download PDF

Info

Publication number
CN101767753A
CN101767753A CN200810204883A CN200810204883A CN101767753A CN 101767753 A CN101767753 A CN 101767753A CN 200810204883 A CN200810204883 A CN 200810204883A CN 200810204883 A CN200810204883 A CN 200810204883A CN 101767753 A CN101767753 A CN 101767753A
Authority
CN
China
Prior art keywords
belt
hoisting
lifting
hydraulic lifting
suspender
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200810204883A
Other languages
Chinese (zh)
Other versions
CN101767753B (en
Inventor
宋茂祥
郑小宝
严江华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Construction Co Ltd filed Critical Shanghai Baoye Construction Co Ltd
Priority to CN 200810204883 priority Critical patent/CN101767753B/en
Publication of CN101767753A publication Critical patent/CN101767753A/en
Application granted granted Critical
Publication of CN101767753B publication Critical patent/CN101767753B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)
  • Belt Conveyors (AREA)

Abstract

The invention relates to a conveyor belt vertical-lifting hoisting method, in particular to a method for hoisting by lifting belt vertically. The method involved with a lifting appliance, two sets of jigs and a hydraulic lifting device comprises the following steps: 1. installing the hydraulic lifting device on an uppermost layer platform, debugging to meet standards, placing the jigs on a middle or upper platform; 2. using the jigs to penetrate a belt which is positioned on the ground, connecting the steel strand of the hydraulic lifting device with the lifting appliance; 3. lifting the hydraulic lifting device so as to pull the belt to the top, using the jigs to fix the belt; 4. holding the lifting appliance with a guide chain temporarily, moving the hydraulic lifting device down, connecting the steel strand with the jigs, lifting the hydraulic lifting device continuously; 5. moving the lifting appliance horizontally, penetrating a belt head pulley; and 6. moving the hydraulic lifting device down to completely transfer the gravity of the belt to the belt head pulley and finish the hoisting work. The invention avoids using an ultra-large crane and can successfully finish the high-altitude installation work of the conveyor belt.

Description

A kind of method for hoisting by lifting belt vertically
Technical field
The present invention relates to belt conveyor and install, relate in particular to the conveyor belt vertical-lifting hoisting hanging method.
Background technology
At present, belt conveyor has developed into the whole supply of material of producer, and this belt is used widely in smelter.Because belt conveyor often reaches hundreds of rice, so the belt weight of length is very big.Need to be equipped with vertical belt conveyor in the COREX stove, install in this high-altitude that just the heavy belt conveyor of tens of tons need be risen to about 100 meters.Generally, need will with large-scale loop wheel machine strap clamp hold handling to the high-altitude to finish erection work, the construction cost height; And when belt elevator, the often too small steel wire that causes damaging in the belt of the radius of curvature of belt supporting point; After vertical strap promoted and to put in place, the space was little in the belt, was difficult to changed course, great wheel penetrates and has difficulty in the belt.After great wheel penetrated belt inside, belt was by the stressed stressed difficult point that remains of great wheel that changes into of hoist point.
Summary of the invention
The present invention is intended to solve the problems referred to above of prior art, and a kind of method for hoisting by lifting belt vertically is provided.The present invention avoids adopting the use of ultra-large type loop wheel machine, finishes the high-altitude installation work of belt conveyor smoothly.
The present invention is achieved in that a kind of method for hoisting by lifting belt vertically, and it mainly comprises suspender, two sleeve clamps and hydraulic lifting apparatus and comprises the following steps:
Step 1 is installed in hydraulic lifting apparatus on the superiors' platform, and the operation debugging is qualified, anchor clamps is placed on the platform of middle and upper part;
Step 2 penetrates suspender and is placed in the ground belt, and the steel strand of hydraulic lifting apparatus are connected on the suspender;
Step 3, hydraulic lifting apparatus promotes, and belt traction to the top, is fixed belt with anchor clamps;
Step 4 is lived suspender with leading chain haulage, and hydraulic lifting apparatus descends, and steel strand are connected on the anchor clamps, continues to promote temporarily;
Step 5, the parallel motion suspender penetrates the belt great wheel;
Step 6, hydraulic lifting apparatus descends, and the gravity of belt is all transferred on the belt great wheel can be finished lifting.
Described method for hoisting by lifting belt vertically, described band suspender comprise the cylinder that a cover thongs and rolls up,
A pair of clamping plate, they lay respectively at the cylinder two ends, also are connected with the cylinder end face;
The first half of described a pair of clamping plate body also is respectively equipped with the through hole of a pair of cooresponding lifting usefulness.
Described method for hoisting by lifting belt vertically, a pair of clamping plate body lower part of described suspender is provided with a connecting bore respectively, and the axle of described cylinder two ends is captiveed joint with this connecting bore.
Described method for hoisting by lifting belt vertically, described anchor clamps comprise:
Three clamping bars, their parallel interval are provided with, and the two ends between two adjacent clamping bars connect with one group of Screw arbor with nut at both-ends adjustable ground separately;
A pair of shackle plate is shown on the two ends of the clamping bar in the middle of it is fixed on;
Two secondary limiting stoppers, they are separately positioned on the relative side of two clamping bars of both sides, limiting stopper and left and right limiting stopper in the middle of every secondary limiting stopper comprises, the spacing between them and the sectional dimension of belt conveyor are complementary, and their height is greater than the width of belt conveyor but be less than or equal to distance between the clamping bar.
Described method for hoisting by lifting belt vertically, described clamping bar is made of H shape steel, and comprises three sections of the left, center, right that link together, and wherein the middle linkage section of stage casing H shape steel is and is horizontally disposed with, and the middle interruption of both sides H shape steel is vertically to be provided with.
Described a kind of vertical-lift belt conveyor stone tongs, described anchor clamps have two covers.
Described method for hoisting by lifting belt vertically, described clamping bar have the brace panel parallel with middle linkage section.
The present invention adopts later-model equipment hoisting mode, has avoided the use of ultra-large type loop wheel machine, has designed special-purpose anchor clamps simultaneously, has satisfied vertical strap and has worn the special technical requirement of band, thereby solved the erection work of high-altitude belt smoothly.
Description of drawings
The present invention is described in further detail below in conjunction with drawings and embodiments:
Fig. 1 is a scheme drawing of the present invention;
The described anchor clamps scheme drawing of Fig. 2;
Fig. 3 is described suspender scheme drawing.
The specific embodiment
As shown in Figure 1, a kind of method for hoisting by lifting belt vertically, it mainly comprises suspender 1, two sleeve clamps 2 and hydraulic lifting apparatus 3 and comprises the following steps:
Step 1 is installed in hydraulic lifting apparatus 3 on the superiors' platform, and the operation debugging is qualified, anchor clamps 2 is placed on the platform of middle and upper part;
Step 2 penetrates suspender 1 and is placed in the ground belt 4, and the steel strand 31 of hydraulic lifting apparatus 3 are connected on the suspender 1;
Step 3, hydraulic lifting apparatus 3 promotes, and belt 4 tractions to the top, are fixed belt 4 with anchor clamps 2;
Step 4 is lived suspender with leading chain haulage, and hydraulic lifting apparatus 3 descends, and steel strand 31 are connected on the anchor clamps, continue to promote temporarily;
Step 5, parallel motion suspender 1 penetrates the belt great wheel;
Step 6, hydraulic lifting apparatus 3 descends, and the gravity of belt 4 is all transferred on the belt great wheel can be finished lifting.
As shown in Figure 2, described suspender 1 comprises the cylinder 11 that a cover thongs and rolls up,
A pair of clamping plate 12, they lay respectively at cylinder 11 two ends, also are connected with cylinder 11 end faces;
The first half of described a pair of clamping plate 12 bodies also is respectively equipped with the through hole 13 of a pair of cooresponding lifting usefulness.
The a pair of clamping plate 12 body lower parts of described suspender are provided with a connecting bore respectively, and the axle of described cylinder 11 two ends is captiveed joint with this connecting bore.
As shown in Figure 3, described anchor clamps 2 comprise:
Three clamping bars 21, their parallel interval are provided with, and the two ends between two adjacent clamping bars 21 connect with one group of Screw arbor with nut at both-ends 22 adjustable ground separately;
A pair of shackle plate 23 is shown on the two ends of the clamping bar 21 in the middle of it is fixed on;
Two secondary limiting stoppers 24, they are separately positioned on the relative side of two clamping bars 21 of both sides, limiting stopper and left and right limiting stopper in the middle of every secondary limiting stopper 24 comprises, the spacing between them and the sectional dimension of belt conveyor are complementary, and their height is greater than the width of belt conveyor but be less than or equal to distance between the clamping bar 21.
Described clamping bar 21 is made of H shape steel, and comprises three sections of the left, center, right that link together, and wherein the middle linkage section of stage casing clamping bar 21 is and is horizontally disposed with, and the interlude 211 of both sides clamping bar 21 is vertically to be provided with.Described clamping bar 21 has the brace panel parallel with middle linkage section 25.

Claims (6)

1. a method for hoisting by lifting belt vertically is characterized in that, it mainly comprises suspender, two sleeve clamps and hydraulic lifting apparatus and comprises the following steps:
Step 1 is installed in hydraulic lifting apparatus on the superiors' platform, and the operation debugging is qualified, anchor clamps is placed on the platform of middle and upper part;
Step 2 penetrates suspender and is placed in the ground belt, and the steel strand of hydraulic lifting apparatus are connected on the suspender;
Step 3, hydraulic lifting apparatus promotes, and belt traction to the top, is fixed belt with anchor clamps;
Step 4 is lived suspender with leading chain haulage, and hydraulic lifting apparatus descends, and steel strand are connected on the anchor clamps, continues to promote temporarily;
Step 5, the parallel motion suspender penetrates the belt great wheel;
Step 6, hydraulic lifting apparatus descends, and the gravity of belt is all transferred on the belt great wheel can be finished lifting.
2. method for hoisting by lifting belt vertically according to claim 1 is characterized in that, described band suspender comprises the cylinder that a cover thongs and rolls up,
A pair of clamping plate, they lay respectively at the cylinder two ends, also are connected with the cylinder end face;
The first half of described a pair of clamping plate body also is respectively equipped with the through hole of a pair of cooresponding lifting usefulness.
3. method for hoisting by lifting belt vertically according to claim 1 and 2 is characterized in that, a pair of clamping plate body lower part of described suspender is provided with a connecting bore respectively, and the axle of described cylinder two ends is captiveed joint with this connecting bore.
4. method for hoisting by lifting belt vertically according to claim 1 is characterized in that, described anchor clamps comprise:
Three clamping bars, their parallel interval are provided with, and the two ends between two adjacent clamping bars connect with one group of Screw arbor with nut at both-ends adjustable ground separately;
A pair of shackle plate is shown on the two ends of the clamping bar in the middle of it is fixed on;
Two secondary limiting stoppers, they are separately positioned on the relative side of two clamping bars of both sides, limiting stopper and left and right limiting stopper in the middle of every secondary limiting stopper comprises, the spacing between them and the sectional dimension of belt conveyor are complementary, and their height is greater than the width of belt conveyor but be less than or equal to distance between the clamping bar.
5. according to claim 1 or 4 described method for hoisting by lifting belt vertically, it is characterized in that described clamping bar is made of H shape steel, and comprise three sections of the left, center, right that link together, wherein the middle linkage section of stage casing H shape steel is and is horizontally disposed with, and the middle interruption of both sides H shape steel is vertically to be provided with.
6. method for hoisting by lifting belt vertically according to claim 5 is characterized in that, described clamping bar has the brace panel parallel with middle linkage section.
CN 200810204883 2008-12-30 2008-12-30 Method for hoisting by lifting belt vertically Active CN101767753B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200810204883 CN101767753B (en) 2008-12-30 2008-12-30 Method for hoisting by lifting belt vertically

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200810204883 CN101767753B (en) 2008-12-30 2008-12-30 Method for hoisting by lifting belt vertically

Publications (2)

Publication Number Publication Date
CN101767753A true CN101767753A (en) 2010-07-07
CN101767753B CN101767753B (en) 2013-05-15

Family

ID=42500882

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200810204883 Active CN101767753B (en) 2008-12-30 2008-12-30 Method for hoisting by lifting belt vertically

Country Status (1)

Country Link
CN (1) CN101767753B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102674212A (en) * 2012-05-30 2012-09-19 四川公路桥梁建设集团有限公司 Simple detachable beam lifting and unloading equipment and construction method thereof
CN103332438A (en) * 2013-06-17 2013-10-02 宁波钢铁有限公司 Breakage-proof lifting appliance of high inclination angle skirt adhesive tape
CN113148839A (en) * 2020-11-26 2021-07-23 上海宝冶集团有限公司 Installation method of ultrahigh vertical feeding belt conveyor

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101152949A (en) * 2006-09-27 2008-04-02 十一冶建设有限责任公司 Parallel move method for ultra-high ultra-large large-weight running well frame type hoisting tool and device thereof
CN101195460A (en) * 2007-12-25 2008-06-11 中铁四局集团有限公司 Large box girder bottom-mounting hoisting device and method thereof

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101152949A (en) * 2006-09-27 2008-04-02 十一冶建设有限责任公司 Parallel move method for ultra-high ultra-large large-weight running well frame type hoisting tool and device thereof
CN101195460A (en) * 2007-12-25 2008-06-11 中铁四局集团有限公司 Large box girder bottom-mounting hoisting device and method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102674212A (en) * 2012-05-30 2012-09-19 四川公路桥梁建设集团有限公司 Simple detachable beam lifting and unloading equipment and construction method thereof
CN102674212B (en) * 2012-05-30 2014-09-03 四川公路桥梁建设集团有限公司 Simple detachable beam lifting and unloading equipment and construction method thereof
CN103332438A (en) * 2013-06-17 2013-10-02 宁波钢铁有限公司 Breakage-proof lifting appliance of high inclination angle skirt adhesive tape
CN103332438B (en) * 2013-06-17 2015-09-30 宁波钢铁有限公司 The breakage-proof suspender of a kind of high spud angle shirt rim adhesive tape
CN113148839A (en) * 2020-11-26 2021-07-23 上海宝冶集团有限公司 Installation method of ultrahigh vertical feeding belt conveyor
CN113148839B (en) * 2020-11-26 2023-02-28 上海宝冶集团有限公司 Installation method of ultrahigh vertical feeding belt conveyor

Also Published As

Publication number Publication date
CN101767753B (en) 2013-05-15

Similar Documents

Publication Publication Date Title
CN202090286U (en) Traction system suitable for self-anchored type double cable plane suspension bridge
CN201240810Y (en) Novel manual hoister
CN205294608U (en) Plug borer hoist
CN202181174U (en) Saddle of cable crane
CN211141352U (en) Combined type track dismantling device used in shield construction method
CN101446066A (en) Erection method of stiffening girder of suspension bridge and device thereof
CN106081836A (en) Vertical shaft head rope and tail rope replacing options
CN102963817B (en) Tailing force-free large equipment hoisting vertical tail removal method
CN106758860A (en) A kind of across cable walking cord clip handling erecting device and method
CN101767753B (en) Method for hoisting by lifting belt vertically
CN201436274U (en) Special assembling suspender of long chain for slab rolling mill engineering steel plate conveying device
CN201713229U (en) Steel box girder cable-loaded crane for suspension bridge construction
CN201534742U (en) Mine continuous feeding device for chained ropes
CN210714046U (en) Device for lifting inverted chimney steel inner cylinder by using steel twisted rope hydraulic pressure
CN201354293Y (en) Hanger for vertically hoisting conveyor belt
CN204983693U (en) Hoist device slides in mountain area corridor truss high altitude
CN107706832B (en) Rapid threading device in reinforcement cage and working method
CN107618999B (en) Hoisting tool and hoisting method for narrow space of bridge beam bottom and pier stud
CN215812105U (en) Steel wire rope rigging steering traction dynamic load test device
CN202575637U (en) Lifting device for overhauling annealing furnaces
CN202429868U (en) Novel hoisting and positioning device for prefabricated part
CN102199996B (en) Stand connection method and device thereof
CN203339567U (en) Synchronous hoisting system with ultra-high-voltage rigid hard jumper
CN211228138U (en) Suspension bridge hanging beam system
CN104495644B (en) A kind of crane and crane gooseneck boom thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 200941 Shanghai City, Baoshan District Road, No. four yuan, 168

Patentee after: Shanghai Baoye Group Corp., Ltd.

Address before: 200941 Shanghai City, Baoshan District Road, No. four yuan, 168

Patentee before: Baoye Construction Co., Ltd., Shanghai