CN101718096B - 一种导流和负压技术相结合的大壁厚基础下沉方法 - Google Patents

一种导流和负压技术相结合的大壁厚基础下沉方法 Download PDF

Info

Publication number
CN101718096B
CN101718096B CN 200910228122 CN200910228122A CN101718096B CN 101718096 B CN101718096 B CN 101718096B CN 200910228122 CN200910228122 CN 200910228122 CN 200910228122 A CN200910228122 A CN 200910228122A CN 101718096 B CN101718096 B CN 101718096B
Authority
CN
China
Prior art keywords
negative pressure
foundation
diversion
wall thickness
top cover
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 200910228122
Other languages
English (en)
Other versions
CN101718096A (zh
Inventor
练继建
丁红岩
张浦阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Daoda Offshore Wind Power Engineering Technology Co., Ltd.
Original Assignee
JIANGSU DAODA OFFSHORE WIND POWER ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU DAODA OFFSHORE WIND POWER ENGINEERING TECHNOLOGY Co Ltd filed Critical JIANGSU DAODA OFFSHORE WIND POWER ENGINEERING TECHNOLOGY Co Ltd
Priority to CN 200910228122 priority Critical patent/CN101718096B/zh
Publication of CN101718096A publication Critical patent/CN101718096A/zh
Application granted granted Critical
Publication of CN101718096B publication Critical patent/CN101718096B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

一种导流和负压技术相结合的大壁厚基础下沉方法,由基础壁的导流系统和基础顶盖的负压系统构成,基础壁的导流系统包括沿筒壁周长等间距设置的竖向孔洞,竖向孔洞中设置吸泥管,吸泥管中间设置导流管,吸泥管底部设置喇叭状锥形腔体和松土空腔,松土空腔通过竖向孔洞底部设置的隔板分隔;基础顶盖的负压系统为在基础密封顶盖上预留抽负压孔,吸泥管和导流管均从密封顶盖穿出。本发明的优点是:通过导流和负压技术相结合的基础下沉系统,利用导流海水和施加负压,使大壁厚筒型基础以较经济的费用沉入到各种类型的地基土体中,下沉过程更加简单,安装速度大大提高,能避免环境条件的干扰,可实现下沉过程的全自动监控作业、保证施工质量和安全。

Description

一种导流和负压技术相结合的大壁厚基础下沉方法
所属技术领域
本发明涉及于港口、海洋、水利和桥梁工程中的大壁厚基础施工技术,特别是一种导流和负压技术相结合的大壁厚基础下沉方法。
背景技术
目前在港口、海洋、水利和桥梁工程中,大型混凝土圆筒结构和大壁厚筒型基础的使用越来越广泛,目前将大型圆筒型式结构沉入到地基土体中,可实施的方法主要有费用较高的基坑开挖法,适用范围有限的压载法、对设备要求较高的振动法以及高压喷气和空气吸排等下沉方法。大型圆筒结构下沉时,阻力主要来自筒壁内外侧土的摩擦和粘聚阻力和筒壁底端土阻力。尤其对于大壁厚结构型式,阻力会更大,传统的下沉方式将不能满足结构的有效下沉到位。本发明就是针对解决这些问题,提高大型圆筒结构型式的下沉质量和效率。
发明内容
本发明的目的在于针对上述存在问题,提供一种结构简单、施工简便、效率高、成本低且安全可靠的导流和负压技术相结合的大壁厚基础下沉方法。
本发明的技术方案:
一种导流和负压技术相结合的大壁厚基础下沉方法,由基础壁的导流系统和基础顶盖的负压系统构成,基础壁的导流系统包括沿筒壁周长等间距设置的竖向孔洞,竖向孔洞中设置吸泥管,吸泥管中间设置用于导流的供气管和/或供水管,吸泥管底部设置喇叭状锥形腔体和松土空腔,松土空腔通过竖向孔洞底部设置的隔板分隔;基础顶盖的负压系统为在基础密封顶盖上预留抽负压孔,吸泥管和用于导流的供气管和/或供水管均从密封顶盖穿出。
本发明的工作原理:大壁厚基础靠自重下沉时,启用基础壁的导流系统不断排出基础壁度底部的泥土,实现基础的初步下沉;当基础下沉阻力超过导流设备提供的下沉力时,启用负压设备通过基础顶部的预留负压孔向基础内抽真空,增大基础下沉力,使其继续下沉。
本发明的有益效果是:通过导流和负压技术相结合的基础下沉系统,利用导流海水和施加负压,使大壁厚筒型基础以较经济的费用沉入到各种类型的地基土体中至预定的深度,下沉过程更加简单,安装速度大大提高,很大程度上能避免环境条件的干扰,可实现下沉过程的全自动监控作业、保证下沉的施工质量和安全。
附图说明
图1是应用本发明的基础结构壁导流系统布置示意图。
图2是应用本发明的基础结构俯视图。
图3是应用本发明的基础结构侧面图。
图4是应用本发明的基础结构仰视图。
图5是应用本发明的基础结构下沉示意图。
图中:1、基础密封顶盖 2、预留负压孔 3、吸泥管4、用于导流的供气管和/或供水管 5、基础壁 6、锥体空腔 7、松土空腔8、隔板 9、吸泥管排出的松散土块 10,负压孔抽出的水和/或气
具体实施方式
为能进一步了解本发明的发明内容、特点及功效,兹例举以下实施例,并配合附图详细说明如下:
本发明的一个实施例如下:一个直径35m,高15m的混凝土筒型基础,基础壁5厚0.5m,在基础壁5上沿周长等间隔设置12个直径0.3m的竖向孔洞,即吸泥管3,吸泥管3中间放置直径5cm的用于导流的供气管和/或供水管4(亦称导流管),吸泥管3孔洞到基础壁5底部呈锥形扩大成高度为0.5m的锥体空腔6,基础壁筒底下面连接有隔板8形成的高度为0.5m的松土空腔7。
筒型基础首先靠自重下沉,然后通过导流系统的供气管和/或供水管4向筒壁底部供高压水和高压气,高压水会将筒壁底部松土空腔7中的小块土体冲松散,高压气会在吸泥管3内形成负压从而将松土空腔7中的水和松散土块9从吸泥管3中带出,当松土空腔7中的土体被排出后,筒壁底端的土阻力减小,在自重作用下筒型基础就会继续下沉,当筒型基础所受的下沉阻力大于导流系统提供的下沉力时,通过负压设备,从基础密封顶盖1上的预留负压孔2向筒内抽真空并抽出水和/或气10,真空的范围,即基础的内外压力差值为(0,-0.6)Mpa,利用真空压力和筒顶水头压力来增大筒型基础的下沉力,使筒型基础继续下沉,筒壁底部土受到挤压,又会有土体进入到松土空腔7中,如此循环,就可将大壁厚混凝土圆筒结构沉入到海底地基土中。在筒型基础下沉的过程中,实时监测下沉过程,通过导流系统和负压系统的相互配合有效快速的进行工作。
该基础下沉方法适用于各种土质条件,能避免环境条件的干扰,安装速度快,成本低,基础下沉效率高,安全性强,并可实现下沉过程的全自动监控作业。

Claims (1)

1.一种导流和负压技术相结合的大壁厚基础下沉方法,其特征在于:由基础壁的导流系统和基础顶盖的负压系统构成,基础壁的导流系统包括沿筒壁周长等间距设置的竖向孔洞,竖向孔洞中设置吸泥管,吸泥管中间设置用于导流的供气管和/或供水管,吸泥管底部设置喇叭状锥形腔体和松土空腔,松土空腔通过竖向孔洞底部设置的隔板分隔;基础顶盖的负压系统为在基础密封顶盖上预留抽负压孔,吸泥管和用于导流的供气管和/或供水管均从密封顶盖穿出。
CN 200910228122 2009-11-10 2009-11-10 一种导流和负压技术相结合的大壁厚基础下沉方法 Active CN101718096B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200910228122 CN101718096B (zh) 2009-11-10 2009-11-10 一种导流和负压技术相结合的大壁厚基础下沉方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910228122 CN101718096B (zh) 2009-11-10 2009-11-10 一种导流和负压技术相结合的大壁厚基础下沉方法

Publications (2)

Publication Number Publication Date
CN101718096A CN101718096A (zh) 2010-06-02
CN101718096B true CN101718096B (zh) 2013-10-30

Family

ID=42432729

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910228122 Active CN101718096B (zh) 2009-11-10 2009-11-10 一种导流和负压技术相结合的大壁厚基础下沉方法

Country Status (1)

Country Link
CN (1) CN101718096B (zh)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102425183A (zh) * 2011-12-12 2012-04-25 中交二航局第四工程有限公司 一种加快钢围堰组件下沉速度的吸泥方法
CN105926661B (zh) * 2016-05-11 2018-03-13 中国海洋大学 能消除土塞的海上风电的负压筒基
CN105926666B (zh) * 2016-05-11 2018-03-13 中国海洋大学 能自动消除土塞的吸力锚
CN105926627B (zh) * 2016-05-11 2018-04-03 中国海洋大学 能下贯至海底面以下的吸力锚及其安装方法
CN105951873B (zh) * 2016-05-11 2018-03-27 中国海洋大学 海底双筒吸力锚
CN105926664B (zh) * 2016-05-11 2018-04-03 中国海洋大学 适用于海洋风电能下贯至海底面以下的负压筒及安装方法
CN106759419A (zh) * 2017-03-16 2017-05-31 天津大学前沿技术研究院有限公司 一种环形分区水力破土开槽装置
CN108104148A (zh) * 2017-12-12 2018-06-01 河海大学 一种带加强管的薄壁钢制吸力桶基础及其安装方法
CN109625217A (zh) * 2018-12-20 2019-04-16 中国船舶重工集团公司七五0试验场 一种便于回收的海床吸附式基座及其吸附、回收方法
CN110055991A (zh) * 2019-05-30 2019-07-26 安徽省交通控股集团有限公司 一种双壁中空沉井基础及其下沉施工方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1016199B (zh) * 1989-06-03 1992-04-08 渤海石油公司工程设计公司 海底施工用基础导流下沉工艺及其专用基础装置
CN2687178Y (zh) * 2003-11-21 2005-03-23 中国石油天然气集团公司 滩涂软土筑路用负压沉箱
CN1730842A (zh) * 2005-09-07 2006-02-08 天津大学 软基箱筒型基础结构海上气浮拖运和定位下沉安装方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1016199B (zh) * 1989-06-03 1992-04-08 渤海石油公司工程设计公司 海底施工用基础导流下沉工艺及其专用基础装置
CN2687178Y (zh) * 2003-11-21 2005-03-23 中国石油天然气集团公司 滩涂软土筑路用负压沉箱
CN1730842A (zh) * 2005-09-07 2006-02-08 天津大学 软基箱筒型基础结构海上气浮拖运和定位下沉安装方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JP特开平9-177088A 1997.07.08

Also Published As

Publication number Publication date
CN101718096A (zh) 2010-06-02

Similar Documents

Publication Publication Date Title
CN101718096B (zh) 一种导流和负压技术相结合的大壁厚基础下沉方法
CN100591859C (zh) 一种用拔桩机进行拔桩的施工方法
CN102312442A (zh) 栈桥钢管桩基础的施工方法
WO2022126801A1 (zh) 一种海域天然气水合物筒式开采装置及其方法
CN102383431A (zh) 中掘预应力离心管桩(方桩)沉桩装置及其新型沉桩法
CN1963044A (zh) 拔出废桩的施工方法
CN101748731A (zh) 一种厚壁筒型基础注气破土下沉方法
CN101748732B (zh) 一种带承力环结构筒型基础的下沉方法
CN102322074A (zh) 一种导管架基础结构及施工方法
CN203296047U (zh) 水下锚桩打入扶正器
CN103572770B (zh) 一种桩箱水工结构物及其建造方法
CN1206421C (zh) 钻孔灌注桩减阻拔除方法
CN203756036U (zh) 一种防真空效应的旋挖钻机钻头
CN103243717A (zh) 一种辅助拔桩机构及其使用方法
CN203498848U (zh) 一种轻型井点降水管成孔装置
CN203768927U (zh) 一种柔性地下防渗帷幕结构
CN201232184Y (zh) 钢管护壁干取土灌注桩成桩装置
CN211849570U (zh) 一种吸力锚
CN101748743B (zh) 一种气置换水的筒型基础地基加固方法
CN210621738U (zh) 一种适用于软弱深厚沉积层的海上风电单桩基础
CN110205996A (zh) 在已建水库、湖泊中修建取水口的方法
CN111424663A (zh) 一种环保、高效的桩头破除方法
CN202659139U (zh) 风动搅拌钻渣装置
CN201391231Y (zh) 一种钻孔定位器
CN207003511U (zh) 一种清理深水塑性黏土的施工装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: DAODA (SHANGHAI) WIND POWER INVESTMENT CO., LTD.

Free format text: FORMER OWNER: TIANJIN UNIVERSITY

Effective date: 20100916

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 300072 NO.92, WEIJIN ROAD, NANKAI DISTRICT, TIANJIN CITY TO: 200129 ROOM 210, NO.212, LINGHE ROAD, PUDONG NEW DISTRICT, SHANGHAI

TA01 Transfer of patent application right

Effective date of registration: 20100916

Address after: 200129 Shanghai city Pudong New Area Linghe Road No. 212 room 210

Applicant after: Daoda (Shanghai) Wind Power Investment Co., Ltd.

Address before: 300072 Tianjin City, Nankai District Wei Jin Road No. 92

Applicant before: Tianjin University

EE01 Entry into force of recordation of patent licensing contract

Assignee: Jiangsu Daoda Offshore Wind Power Engineering Technology Co., Ltd.

Assignor: Daoda (Shanghai) Wind Power Investment Co., Ltd.

Contract record no.: 2011320000097

Denomination of invention: Large wall thickness foundation sinking method by combining diversion and negative pressure technology

License type: Exclusive License

Open date: 20100602

Record date: 20110225

ASS Succession or assignment of patent right

Owner name: JIANGSU DAODA MARINE WIND POWER ENGINEERING TECHNO

Free format text: FORMER OWNER: DAODA (SHANGHAI) WIND POWER INVESTMENT CO., LTD.

Effective date: 20110331

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 200129 ROOM 210, NO. 212, LINGHE ROAD, PUDONG NEW DISTRICT, SHANGHAI TO: 226259 KAIXUAN ROAD, ECONOMIC AND TECHNOLOGICAL DEVELOPMENT ZONE, QIDONG CITY, JIANGSU PROVINCE, CHINA

TA01 Transfer of patent application right

Effective date of registration: 20110331

Address after: 226259 triumph Road, Qidong economic and Technological Development Zone, Jiangsu, China

Applicant after: Jiangsu Daoda Offshore Wind Power Engineering Technology Co., Ltd.

Address before: 200129 Shanghai city Pudong New Area Linghe Road No. 212 room 210

Applicant before: Daoda (Shanghai) Wind Power Investment Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160301

Address after: 226333 No. 8, the Yellow River Road, Binhai Park, Jiangsu, Nantong

Patentee after: Jiangsu Daoda Offshore Wind Power Engineering Technology Co., Ltd.

Address before: Triumph Road, Qidong economic and Technological Development Zone, Jiangsu, China

Patentee before: Jiangsu Daoda Offshore Wind Power Engineering Technology Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20181106

Address after: 226000 Jianghai Road 159, Nantong economic and Technological Development Zone, Jiangsu

Patentee after: Jiangsu Daoda Offshore Wind Power Engineering Technology Co., Ltd.

Address before: 226333 8 the Yellow River Road, Binhai Park, Nantong, Jiangsu

Patentee before: Jiangsu Dolda Wind Power Equipment Technology Co., Ltd

PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20190716

Granted publication date: 20131030

PD01 Discharge of preservation of patent
PD01 Discharge of preservation of patent

Date of cancellation: 20201028

Granted publication date: 20131030