CN101710702B - Method for realizing dynamic energy-saving distribution of electrical power system - Google Patents

Method for realizing dynamic energy-saving distribution of electrical power system Download PDF

Info

Publication number
CN101710702B
CN101710702B CN2009101917055A CN200910191705A CN101710702B CN 101710702 B CN101710702 B CN 101710702B CN 2009101917055 A CN2009101917055 A CN 2009101917055A CN 200910191705 A CN200910191705 A CN 200910191705A CN 101710702 B CN101710702 B CN 101710702B
Authority
CN
China
Prior art keywords
generator
load
period
electrical network
sigma
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009101917055A
Other languages
Chinese (zh)
Other versions
CN101710702A (en
Inventor
熊小伏
孙斌
林成
陈星田
赵维兴
秦志龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUIZHOU ELECTRIC POWER SCHEDULING COMMUNICATIONS OFFICE
Chongqing University
Original Assignee
GUIZHOU ELECTRIC POWER SCHEDULING COMMUNICATIONS OFFICE
Chongqing University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUIZHOU ELECTRIC POWER SCHEDULING COMMUNICATIONS OFFICE, Chongqing University filed Critical GUIZHOU ELECTRIC POWER SCHEDULING COMMUNICATIONS OFFICE
Priority to CN2009101917055A priority Critical patent/CN101710702B/en
Publication of CN101710702A publication Critical patent/CN101710702A/en
Application granted granted Critical
Publication of CN101710702B publication Critical patent/CN101710702B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a method for realizing dynamic energy-saving distribution of an electrical power system, which is implemented by collecting data from the EMS systems of each node of a generator in certain element power grid; substituting the data into an objective function of multi-period dynamic energy-saving distribution; equaling the connecting lines for connecting other element power grids with the element power grid to obtain a new generation scheme; and finally feeding the new generation scheme back to the EMS systems of each node of the generator in the certain element power grid. The method can convert grid loss into standard coal consumption, and formulates a generation scheme with minimum multi-period generation coal consumption according to the change of the load of the electrical power system while satisfying the generator set security constraint and grid power transmission security constraint, namely, comprehensive coal consumption totaling the generation coal consumption and the equivalent coal consumption of grid loss is secured.

Description

Realize the method for dynamic energy-saving distribution of electrical power system
Technical field
The invention belongs to the dispatching automation of electric power systems technical field, relate in particular to a kind of method that realizes dynamic energy-saving distribution of electrical power system.
Background technology
Energy-saving and emission-reduction are important measures of alleviating energy supply contradiction and environmental constraints contradiction, are the important channels with benefit of improving the quality of economic growth, and are national fundamental state policies, are directly connected to the national sustainable development implementation.Implementing energy-saving distribution in the power-management centre is the effective means of implementing national energy-saving and emission-reduction policy.
The energy-saving distribution target is after the via net loss conversion is standard coal consumption, realizes satisfying the minimum optimization generation schedule of the whole network total consumption of coal of security constraint, ensures that promptly the comprehensive total consumption of coal of the equivalent coal consumption sum of gross coal consumption rate and via net loss is minimum.Because load changes in time, generation schedule also should change according to load variations.
In the prior art, the optimized calculation method in the energy-saving distribution only considers that generally the generating set coal consumption is minimum in a certain calculation interval, can't consider the demand of multi-period optimization; Or in multi-period calculating, can not take into account constraint of generating set security constraint, power grid security and via net loss simultaneously.
Summary of the invention
Above-mentioned deficiency to the prior art existence; The purpose of this invention is to provide a kind of when satisfying generating set security constraint, network transmission of electricity security constraint; Press the variation of power system load, formulate the method for realization dynamic energy-saving distribution of electrical power system of the generation schedule of multi-period minimum gross coal consumption rate.
The method of realization dynamic energy-saving distribution of electrical power system provided by the invention comprises the steps:
1) the burden with power P of acquisition node in the EMS system of each generator node from certain unit electrical network D, branch road ij constraints P Ijmax, the last one actual P that exerts oneself of generator bus i constantly Gi 0, this moment generator bus i the actual P that exerts oneself Gi, generator bus i the minimum P that exerts oneself Gimin, generator bus i EIAJ P Gimax, branch road quantity NT and generator quantity NG;
2) data of gathering are brought into the target function of multi-period dynamic energy-saving distribution, the calculating generator adjustment amount of exerting oneself:
minF(t)=h 1F 1(t)+h 2F 2(t)
Constraints: Σ i ∈ NG P Gi ( t ) = Σ k ∈ ND P Dk ( t ) + P L ( t )
P Gi(t)-P Gi(t-1)≤ΔP GRCimax i∈NG
P Gi(t-1)-P Gi(t)≤ΔP GRCimax i∈NG
|P ij(t)|≤P ijmax ij∈NT
Wherein, h 1: the weight factor of energy consumption in the very first time section target function
h 2: the weight factor of generator output adjustment in the second time period target function
F 1(t) be the target function of minimum comprehensive coal consumption of first period:
min F 1 = Σ i = 1 NG F i ( P Gi ) + γ P L
F 2(t) be the minimum target function of the second period generator output adjustment amount:
min F 2 = Σ i = 1 NG ( P Gi - P Gi 0 ) 2
Constraints comprises meritorious balance, generator output restriction and the constraint of circuit trend:
Σ i ∈ NG P Gi = Σ k ∈ ND P Dk + P L
P Gimin≤P Gi≤P Gimax i∈NG
|P ij|≤P ijmax ij∈NT
Wherein, P D: the burden with power of node
Figure G2009101917055D00025
system's total load
P Ij: the trend on the branch road ij, carry out trend through Niu Lafa and calculate
P Ijmax: the constraints of branch road ij, the heap(ed) capacity of circuit and transformer
P GI 0: last one actual the exerting oneself of generator bus i constantly
P Gi: actual the exerting oneself of this moment generator bus i
P Gimin: the minimum of generator bus i is exerted oneself
P Gimax: the EIAJ of generator bus i
The total consumption of coal of all generating sets of system
P L: via net loss
F i: the fuel consumption of generator unit i
NT: branch road quantity
NG: generator quantity
γ: active loss is converted to the conversion coefficient of coal consumption
3) application load distribution factor method is assigned to system's total load the load bus of each power plant;
4) with other unit electrical network through carrying out equivalence, the generation schedule that must make new advances with the joining interconnection of this unit electrical network;
5) new generation schedule is fed back in the EMS system of each generator node in this unit electrical network, as next step implementation plan.
Further, said h 1Value be 1, h 2Value be 1.25;
Further, in said step 3), the generator output adjustment amount that calculates goes out the sharing of load factor through being connected with the SCADA database to check with corrected Calculation;
Further, in said step 4), said equivalence is to be duty value or equivalent power supplys such as this unit electrical network is borderline with the Power Exchange between unit electrical network and other unit electrical network is equivalent.
Beneficial effect of the present invention: the present invention is through the data of the EMS system of each generator node in the collecting unit electrical network; And the target function that data are brought multi-period dynamic energy-saving distribution into calculated and through the equivalent generation schedule that must make new advances; New generation schedule is fed back in the EMS system of each generator node in this unit electrical network, implement target as next step.This method can be standard coal consumption with the via net loss conversion; When satisfying generating set security constraint, network transmission of electricity security constraint; Press the variation of power system load; Formulate the generation schedule of multi-period minimum gross coal consumption rate, ensure that promptly the comprehensive total consumption of coal of the equivalent coal consumption sum of gross coal consumption rate and via net loss is minimum.
Description of drawings
Fig. 1 is an overview flow chart of the present invention;
Fig. 2 is the topological structure sketch map of power system network;
Fig. 3 is the external system isopleth map of electrical network;
Fig. 4 is the whole network load chart;
Fig. 5 is the total system total consumption of coal comparison diagram before and after optimizing.
Embodiment
Below in conjunction with accompanying drawing and embodiment the present invention is done to describe in further detail.
Fig. 1 is an overview flow chart of the present invention, and Fig. 2 is the topological structure sketch map of power system network, and Fig. 3 is the external system isopleth map of electrical network, and is as shown in the figure.The concrete steps of the method for realization dynamic energy-saving distribution of electrical power system are following:
1), the burden with power P of acquisition node in the EMS system of each generator node from certain unit electrical network D, branch road ij constraints P Ijmax, the last one actual P that exerts oneself of generator bus i constantly Gi 0, this moment generator bus i the actual P that exerts oneself Gi, generator bus i the minimum P that exerts oneself Gimin, generator bus i EIAJ P Gimax, branch road quantity NT and generator quantity NG.In the present embodiment, certain unit electrical network refers to certain provincial power network, and other unit electrical network refers to other provinces electrical network.
2) in the present embodiment, be divided into 96 operating points (per 15 minutes operating points) with one day, one-time calculation goes out the generation schedule optimized distribution plan of 96 operating points.
Different with static energy-saving distribution, when formulating multi-period generation schedule and dynamic electricity generation plan, the meritorious adjusting constraint Δ P of generator GRCimaxShould take in.The product of adjusting time and governing speed (speed of promptly climbing) is depended in the meritorious adjusting constraint of generator, that is:
ΔP GRCimax=ΔP GRi×Δt i∈NG (1)
Wherein,
Δ P GRCimax: take into account the meritorious adjusting constraint of the generator i of generator climbing speed
Δ P GRi: the climbing speed of generator i
Δ t: running time
The meritorious adjusting constraint expression formula of considering the generator i of generator climbing speed does
Generator rises to gain merit and regulates the constraint expression formula
P Gi ( t ) - P Gi ( t - 1 ) ≤ Δ P GRCi max up i∈NG (2)
Like some moment t:
The generator node number P Gi(t) P Gi(t-1) ΔP GRCimax up
85 45 0 45
86 90 45 45
87 135 90 45
Generator descends to gaining merit and regulates the constraint expression formula
P Gi ( t - 1 ) - P Gi ( t ) ≤ Δ P GRCi max down i∈NG (3)
Like some moment t:
The generator node number P Gi(t) P Gi(t-1) ΔP GRCimax up
85 0 45 45
86 45 90 45
87 90 135 45
Wherein,
Δ P GRCimax Up: take into account the meritorious adjusting constraint of the generator i of generator climbing speed (rising)
Δ P GRCimax Down: take into account the meritorious adjusting constraint of the generator i of generator climbing speed (decline)
T: running time section
P Gi(t): generator i is in the meritorious output of section running time (t)
P Gi(t-1): generator i is in the meritorious output of section running time (t-1)
Ordinary circumstance can consider that the generator rate of climb and decrease speed are the same, so the meritorious adjusting constraint that generator rises and descends is equal, promptly
Δ P GRCi max up = Δ P GRCi max down = Δ P GRCi max i∈NG (4)
So adjacent period generator rising meritorious adjusting constraint expression formula and the meritorious adjusting of generator decline constraint expression formula can be expressed as:
P Gi(t)-P Gi(t-1)≤ΔP GRCimax i∈NG (5)
P Gi(t-1)-P Gi(t)≤ΔP GRCimax i∈NG (6)
The target function of minimum comprehensive coal consumption of first period:
min F 1 = Σ i = 1 NG F i ( P Gi ) + γ P L - - - ( 7 )
The mathematical expression of generator consumption characteristic is:
F i(P Gi)=a iP Gi 2+b iP Gi+c i
Wherein,
a i: the characteristic quadratic term of generator consumption
b i: the characteristic once item of generator consumption
c i: the characteristic constant term of generator consumption
Like some moment t:
The generator node number a b c
85 0.00065 0.01390 41.84502
86 0.00065 0.01390 41.84502
87 0.00065 0.01390 41.84502
The second period generation schedule will be with changing load, and the adjusting target that the present invention proposes is to make the generator output adjustment amount minimum, to improve the stability of unit.Target function is:
min F 2 = Σ i = 1 NG ( P Gi - P Gi 0 ) 2 - - - ( 8 )
As being directed against a certain generating set:
Period P Gi 0 P Gi
0:00 100 100
0:15 110 108
0:30 110 108
Constraints comprises meritorious balance, generator output restriction and the constraint of circuit trend (being network transmission of electricity security constraint), that is:
Σ i ∈ NG P Gi = Σ k ∈ ND P Dk + P L - - - ( 9 )
Like some moment t:
Figure G2009101917055D00072
P Gimin≤P Gi≤P Gimax i∈NG (10)
Like some moment t:
The generator node number P Gimin P Gi P Gimax
85 150 170 300
86 150 200 300
87 150 250 300
|P ij|≤P ijmax ij∈NT (11)
As:
Branch road top node number Branch road end segment period P ij P ijmax
1 20 3600 4091.85
98 1 1600 2045.90
38 2 -240 400
Wherein:
P D: the burden with power of node
Figure G2009101917055D00073
system's total load
P Ij: the trend on the branch road ij, carry out trend through Niu Lafa and calculate
P Ijmax: the constraints of branch road ij, the heap(ed) capacity of branch road (circuit and transformer)
P Gi 0: last one actual the exerting oneself of generator bus i constantly
P Gi: actual the exerting oneself of this moment generator bus i
P Gimin: the minimum of generator bus i is exerted oneself
P GimaxThe EIAJ of generator bus i
The total consumption of coal of
Figure G2009101917055D00081
all generating sets of system
F i: the fuel consumption of generator unit i
NT: branch road quantity
NG: generator quantity
γ: active loss is converted to the conversion coefficient of coal consumption
Therefore, the Mathematical Modeling of multi-period dynamic energy-saving distribution can continuous iterative computation be accomplished on the basis that following two period generation schedules are optimized:
minF(t)=h 1F 1(t)+h 2F 2(t) (12)
Constraints:
Σ i ∈ NG P Gi ( t ) = Σ k ∈ ND P Dk ( t ) + P L ( t ) - - - ( 13 )
P Gi(t)-P Gi(t-1)≤ΔP GRCimax i∈NG (14)
P Gi(t-1)-P Gi(t)≤ΔP GRCimax i∈NG (15)
|P ij(t)|≤P ijmax ij∈NT (16)
Wherein:
H1: the weight factor of energy consumption in the very first time section target function
H2: the weight factor of generator output adjustment in the second time period target function
Usually the value of h2 is greater than the value of h1, the h of present embodiment 1Value be 1, h 2Value be 1.25.
3) the sharing of load factorization method in the dynamic energy-saving distribution
No matter it is that system safety is checked that energy-saving distribution calculates, still one day 96 economic dispatch is calculated, and all needs the load data of each load bus of using system.The load of predicting each node accurately is to calculate one of key.
The present invention is assigned to the system prediction total load method of each concrete load bus:
Prognoses system total load PD at first; Carry out match according to each concrete load bus in the historical load data of each period then; But recursion obtains the load value of each concrete load bus in each period; With its sharing of load factor, combine system's total load of prediction to carry out the load calculating of each concrete load bus again as this load bus.
If system's total load that the t period is predicted is PD (t), the sharing of load factor of load point k is PDFk (t), and so, load point k can go out through computes at the load value of period t
P Dk ( t ) = P DFk ( t ) Σ k = 1 ND P DFk ( t ) × P D ( t ) i∈ND
(17)
During actual the use through be connected the sharing of load factor that can check to go out with the EMS system database with corrected Calculation; That is: with the same day in the real time data each concrete load point at the load value of each period as the sharing of load factor, the load that combines system's total load of prediction to carry out each concrete load point again calculates.
If system's total load that the t period is predicted is PD (t), the load of the load point k that obtains through real time data is PRTDk (t), and so, load point k can go out through computes at the load value of period t during energy-saving distribution calculated
P Dk ( t ) = P RTDk ( t ) Σ k = 1 ND P RTDk ( t ) × P D ( t ) i∈ND
(18)
4) external system in the dynamic energy-saving distribution is equivalent
Provincial power network is the important component part of large regional grid company, and each is economized, and electrical network is coupled to each other between net, support each other, but is being again relatively independent aspect energy scheduling management, the benefit accounting.Provincial power network saving energy and decreasing loss, energy source optimization dispatching management serve as main carrying out with himself electrical network.Provincial power network is referred to as built-in system, is referred to as external system with the joining other provinces of this electrical network electrical network.Since in the net each to economize between net electrical network be to be coupled to each other, need to carry out equivalence to external system.
Concrete grammar is each province Netcom to be crossed with the joining interconnection of this provincial power network carry out equivalence; According to Power Exchange between this certain provincial power network and other provinces electrical network and power supply agreement; With other provinces network equivalence is borderline duty value or the equivalent power supply of waiting of certain provincial power network; As shown in Figure 3, P is an active power among the figure, and Q is a reactive power.
Equivalent through external province electrical network, can under the prerequisite that keeps certain provincial power network total system topology and characteristic, simplify network configuration, reduce amount of calculation.
Example:
Required system's basic model and the relevant parameter of dynamic energy-saving distribution is following:
1, system's basic parameter
A. branch road parameter
IFROM,ITO,R,X,B,TAP,SMAX,SMAXC,TAPMAX,TAPMIN
Wherein:
IFROM-branch road top node number,
ITO-branch road end segment period
R-branch road resistance
X-branch road reactance
B-line charging power (1/2)
TAP-transformer branch road no-load voltage ratio
SMAX-branch road maximum power output constraint
SMAXC-branch trouble maximum power output constraint
The maximum no-load voltage ratio of TAPMAX-transformer branch road
The minimum no-load voltage ratio of TAPMIN-transformer branch road
The real system instance is economized by China:
As:
IFROM,ITO,R,X,B,TAP,SMAX,SMAXC,TAPMAX,TAPMIN
1 20 0.00002 0.00053 0.1020 0.000 4091.85 4091.85 0.00 0.00
98 1 0.00060 0.00830 0.4688 0.000 2045.90 2045.90 0.00 0.00
38 2 0.00000 0.00010 0.0000 0.000 400.00 400.00 0.00 0.00
40 38 0.00050 0.00640 0.3408 0.000 2119.58 2119.58 0.00 0.00
39 37 0.00049 0.00646 1.4766 0.000 4239.16 4239.16 0.00 0.00
36 38 0.00021 0.00355 0.7878 0.000 4239.16 4239.16 0.00 0.00
B. node parameter:
BUSTYP,IBUS,PGEN,QGEN,PLOAD,QLOAD,PMAX1,PMIN1,QMAX1,QMIN1,VOLT,ANGLE,Vnup,Vnlo,Vcup,Vclo,Qgcup,Qgclo,Ownregn
Explain:
BUSTYP-node type
IBUS-node number
PGEN-generator is meritorious exerts oneself
QGEN-generator reactive is exerted oneself
PLOAD-node burden with power
QLOAD-node load or burden without work
PMAX-generator EIAJ of gaining merit
The meritorious minimum of PMIN-generator is exerted oneself
QMAX-generator reactive EIAJ
QMIN-generator reactive minimum is exerted oneself
VOLT-node initial voltage
ANGLE-node initial voltage phase angle
Vnup-node voltage the upper limit
Vnlo-node voltage lower limit:
Vcup-node failure upper voltage limit
Vclo-node failure lower voltage limit
The idle EIAJ of Qgcup-generator failure
The idle minimum of Qgclo-generator failure is exerted oneself
Ownregn-node location
The real system instance is economized by China:
Illustrate:
BUSTYP,IBUS,PGEN,QGEN,PLOAD,QLOAD,PMAX1,PMIN1,QMAX1,QMIN1,VOLT,ANGLE,Vnup,Vnlo,Vcup,Vclo,Qgcup,Qgclo,Ownregn
1 1 0.00 0.00 1800.60 45.00 0.00 0.00 0.00 0.00 1.050 0.00
1.100 0.900 1.100 0.900 0.00 0.00 1
1 2 0.00 0.00 1800.60 111.00 0.00 0.00 0.00 0.00 1.050
0.00 1.100 0.900 1.100 0.900 0.00 0.00 1
2 3 400.00 0.00 42.00 21.00 600.00 0.00 290.00 -90.00
1.000 0.00 1.100 0.900 1.100 0.900 290.00 -90.00 1
2 4 400.00 0.00 42.00 21.00 600.00 0.00 290.00 -90.00
1.000 0.00 1.100 0.900 1.100 0.900 290.00 -90.00 1
2 5 400.00 0.00 42.00 21.00 600.00 0.00 290.00 -90.00
1.000 0.00 1.100 0.900 1.100 0.900 290.00 -90.00 1
2 6 420.00 0.00 42.00 21.00 600.00 0.00 290.00 -90.00
1.000 0.00 1.100 0.900 1.100 0.900 290.00 -90.00 1
C. system network architecture parameter:
TIME,IFROMB,ITOB,R,X,B,TAP,SMAX,SMAXC,TAPMAX,TAPMIN,BRSTAT
Explain:
System network architecture parameter and the difference of front a. branch road parameter: front a. branch road parameter is the basic model parameter of every day, is static; The parameter here is dynamic, promptly only imports the parameter of localized variation.
There are following four kinds of situation to embody the network topology circuit and change (transformer that has four kinds of situation to embody localized network equally changes):
(1), the network parameter of certain time point and the same day basic model just the same, do not import any circuit-switched data this moment;
(2), the network parameter of certain time point with the same day basic model compare, have the parameter of several branch roads to change;
(3), the network parameter of certain time point with the same day basic model compare, have branch road to stop transport;
(4), the network parameter of certain time point with the same day basic model compare, have new branch road to put into operation;
First kind of situation, this time point is not imported any circuit-switched data;
For reaching (2)-(4) purpose, one line state (BRSTAT) of circuit-switched data end input
BRSTAT=0 representes that this branch road cut-offs (corresponding situation (3)) at this time point
BRSTAT=1 representes that this branch road is in this time point parameter update (corresponding situation (2))
BRSTAT=2 representes that this branch road increases newly at this time point, does not originally have (corresponding situation (4)) in the basic model
Wherein:
TIME-time period
IFROMB-branch road top node number
ITOB-branch road end segment period
R-branch road resistance
X-branch road reactance
B-line charging power (1/2)
TAP-transformer branch road no-load voltage ratio
SMAX-branch road maximum power output constraint
SMAXC-branch trouble maximum power output constraint
The maximum no-load voltage ratio of TAPMAX-transformer branch road
The minimum no-load voltage ratio of TAPMIN-transformer branch road
BRSTAT-Zhi line state
The real system instance is economized by China:
Illustrate:
TIME,IFROMB,ITOB,R,X,B,TAP,SMAX,SMAXC,TAPMAX,TAPMIN,BRSTAT
1 154 184 0.00860 0.04040 0.0659 0.000 406.33 406.33
0.00 0.00 0
2 154 184 0.00860 0.04040 0.0659 0.000 406.33 406.33
0.00 0.00 0
3 154 184 0.00860 0.04040 0.0659 0.000 406.33 406.33
0.00 0.00 0
4 154 184 0.00860 0.04040 0.0659 0.000 406.33 406.33
0.00 0.00 0
5 154 184 0.00860 0.04040 0.0659 0.000 406.33 406.33
0.00 0.00 0
6 154 184 0.00860 0.04040 0.0659 0.000 406.33 406.33
0.00 0.00 0
2, economic dispatch parameter
PGNO,ALPHA,BETA,GAMMA,PGMIN,PGMAX,AGCSTATUS,PGCTG,PGGRC
Explain:
PGNO-generator node number
ALPHA-generator (factory) coal consumption curve constant term
BETA-generator (factory) coal consumption curve is item once
GAMMA-generator (factory) coal consumption curve quadratic term
The meritorious minimum of PGMI N-generator is exerted oneself
The PGMAX-generator EIAJ of gaining merit
AGCSTATUS-generator AGC state:
AGCSTATUS=1, expression AGC state, promptly adjustable unit
AGCSTATUS=0 representes non-AGC state, promptly non-adjustable unit
The PGCTG-generator is stopped transport or the trouble hunting state:
PGCTG=1, the expression generator puts into operation
PGCTG=0, the expression generator is stopped transport or trouble hunting
PGGRC-generator climbing speed
The real system instance is economized by China:
Illustrate:
PGNO,ALPHA,BETA,GAMMA,PGMI N,PGMAX,AGCSTATUS,PGCTG,PGGRC
85 41.84502 0.01390 0.00065 150.000 300.000 1 1 45.0
86 41.84502 0.01390 0.00065 150.000 300.000 1 1 45.0
87 41.84502 0.01390 0.00065 150.000 300.000 1 1 45.0
88 41.84502 0.01390 0.00065 0.000 200.000 1 1 60.0
90 39.81035 0.01322 0.00062 0.000 200.000 1 1 60.0
91 39.81035 0.01322 0.00062 0.000 200.000 1 1 60.0
3, system's total load and generator parameter:
A. the given initial generation schedule parameter of generator (factory):
TIME,PGNO,PG,AGCST,UNCTGST,V0
Explain:
The TIME-time period
PGNO-generator node number
The given generation schedule of PG-
AGCST-this time period generator AGC state
AGCST=1, expression AGC state, promptly adjustable unit
AGCST=0 representes non-AGC state, promptly non-adjustable unit
UNCTGST-this time period generator is stopped transport or the trouble hunting state
UNCTGST=1, the expression generator puts into operation
UNCTGST=0, the expression generator is stopped transport or trouble hunting
V0-this time period generator voltage
The real system instance is economized by China:
Illustrate:
TIME,PGNO,PG,AGCST,UNCTGST,V0
1 3 0.000 0 1 1.000
1 4 375.000 0 0 1.000
1 5 375.000 0 0 1.000
1 6 0.000 0 1 1.000
1 7 0.000 0 1 0.970
1 8 400.000 0 0 1.015
B. system's total load parameter
TIME,TotalLoad
Explain:
The TIME-time period
TotalLoad-this time period system total load
The real system instance is economized by China:
Illustrate:
TIME,TotalLoad
1 10352.000
2 10325.000
3 10264.000
4 10052.000
5 10044.000
6 9782.000
Practical power systems is economized by China be optimized, comprising 520 load buses, 679 branch roads, 104 generator nodes (with reference to accompanying drawing 2,4 load buses that only draw among the figure, 6 branch road ij, 2 generator nodes, all the other do not draw).
min
Figure S2006800150290D9997
min F 2 = Σ i = 1 NG ( P Gi - P Gi 0 ) 2
min F ( t ) = h 1 F 1 ( t ) + h 2 F 2 ( t ) = h 1 ( Σ i = 1 NG F i ( P Gi ) + γ P L ) + h 2 ( Σ i = 1 NG ( P Gi - P Gi 0 ) 2 )
Get h in the present embodiment 1=1, h 2=1.25.
γ: coal consumption conversion factor (being the coal tonnage that per 1000 kilowatt hours consume) value 0.53
F i(P Gi)=a iP Gi 2+b iP Gi+c i
Wherein:
a i: the characteristic quadratic term of generator consumption
b i: the characteristic once item of generator consumption
c i: the characteristic constant term of generator consumption
The generator node number a b c
85 0.00065 0.01390 41.84502
86 0.00065 0.01390 41.84502
87 0.00065 0.01390 41.84502
Got a bit in per 15 minutes, whole day 24 hours was exactly 96 points so.
To a certain generating set:
Period P Gi 0 P Gi
0:00 100 100
0:15 110 108
0:30 110 108
After the optimization before optimizing
System's saving ratio of economizing on coal after system optimizes before the network optimizationization of the net electrical network of the total negative electricity net of the whole network
The total consumption of lotus (MW) damage (MW) damage (MW) system coal is always united, and the consumption coal always consumes coal
Period (ton) (ton) (ton)
0:00 10092 185.975 184.376 881.403 857.2365 24.16654 2.74%
0:15 10065 185.975 184.376 881.298 857.1367 24.16133 2.74%
0:30 10004 185.975 184.376 880.899 856.92 23.97905 2.72%
0:45 9792 185.975 184.376 880.388 856.4532 23.93475 2.72%
1:00 9784 185.218 183.626 877.687 854.3294 23.35761 2.66%
1:15 9522 173.328 171.751 840.666 821.775 18.89098 2.25%
1:30 9522 169.903 168.326 831.59 813.1909 18.3991 2.21%
1:45 9377 169.153 167.576 828.549 810.7939 17.75513 2.14%
2:00 9320 169.153 167.576 828.338 810.5963 17.7417 2.14%
2:15 9095 167.902 166.326 823.684 806.8153 16.8687 2.05%
2:30 8992 165.905 164.326 816.67 801.6251 15.0449 1.84%
2:45 8852 157.73 156.151 793.979 781.9872 11.99175 1.51%
3:00 8652 151.08 149.501 777.224 766.706 10.51803 1.35%
3:15 8619 151.08 149.501 777.11 766.5971 10.5129 1.35%
3:30 8618 151.08 149.501 777.107 766.5941 10.51292 1.35%
3:45 8649 151.08 149.501 777.213 766.6959 10.51711 1.35%
4:00 8600 151.08 149.501 777.047 766.5366 10.51038 1.35%
4:15 8584 151.08 149.501 776.994 766.4862 10.50778 1.35%
4:30 8634 151.08 149.501 777.161 766.6465 10.5145 1.35%
4:45 8613 151.08 149.501 777.09 766.578 10.51205 1.35%
5:00 8614 151.08 149.501 777.094 766.581 10.51302 1.35%
5:15 8606 153.08 151.501 783.448 770.8821 12.56589 1.60%
5:30 8584 153.08 151.501 783.38 770.8176 12.5624 1.60%
5:45 8619 153.83 152.251 786.228 772.5655 13.66253 1.74%
6:00 8786 155.827 154.251 793.239 777.5067 15.73231 1.98%
6:15 8820 155.827 154.251 793.358 777.6186 15.73942 1.98%
6:30 8855 156.052 154.451 793.824 778.181 15.64296 1.97%
6:45 9056 156.177 154.576 794.82 779.2152 15.60475 1.96%
7:00 9290 165.172 163.5757 819.931 800.7794 19.15161 2.34%
7:15 9628 175.297 173.7007 851.853 827.4984 24.35455 2.86%
7:30 10106 175.302 173.7007 853.874 829.1133 24.76074 2.90%
7:45 10649 175.302 173.7007 855.671 830.8632 24.80785 2.90%
8:00 11068 180.547 178.9495 872.018 845.6273 26.39067 3.03%
8:15 11760.9 196.6 195.0218 918.723 893.2584 25.46465 2.77%
8:30 12402.9 208.09 206.497 952.68 932.1823 20.49773 2.15%
8:45 12940.9 215.491 213.897 978.681 959.7067 18.97428 1.94%
9:00 13336.9 216.626 215.022 983.797 964.9564 18.84062 1.92%
9:15 13502.9 216.626 215.022 984.849 965.9886 18.86042 1.92%
9:30 13646.9 216.626 215.022 985.186 966.3081 18.87789 1.92%
9:45 13814.9 216.626 215.022 986.426 967.5278 18.89821 1.92%
10:00 13848.9 216.851 215.247 987.467 968.563 18.90399 1.91%
10:15 13848.9 216.851 215.247 987.467 968.563 18.90399 1.91%
10:30 13882.9 216.851 215.247 987.741 968.8332 18.90785 1.91%
10:45 13882.9 216.851 215.247 987.741 968.8332 18.90785 1.91%
11:00 13916.9 217.626 216.022 990.675 971.7644 18.91058 1.91%
11:15 13885.9 216.851 215.247 989.278 968.8573 20.42066 2.06%
11:30 13680.9 216.626 215.022 987.285 966.8857 20.3993 2.07%
11:45 13380.9 216.626 215.0223 985.36 964.9382 20.42176 2.07%
12:00 13118.9 216.626 215.022 983.874 963.4182 20.45582 2.08%
12:15 12980.9 216.626 215.0217 982.979 962.4807 20.49826 2.09%
12:30 12875.9 216.626 215.0217 982.285 961.763 20.52196 2.09%
12:45 12763.9 216.626 215.022 981.576 961.0252 20.55082 2.09%
13:00 12702.9 216.626 215.0215 981.15 960.5635 20.58648 2.10%
13:15 12868.9 216.626 215.022 981.851 961.2873 20.56374 2.09%
13:30 13000.9 216.626 215.022 982.044 961.4637 20.58034 2.10%
13:45 13000.9 216.626 215.022 982.044 961.4637 20.58034 2.10%
14:00 13000.9 216.626 215.022 982.044 961.4637 20.58034 2.10%
14:15 13046.9 216.626 215.022 982.28 961.6955 20.5845 2.10%
14:30 13076.9 216.626 215.022 982.44 961.8507 20.58926 2.10%
14:45 13074.9 216.626 215.022 982.429 961.8407 20.58834 2.10%
15:00 13074.9 216.626 215.022 982.429 961.8407 20.58834 2.10%
15:15 13000.9 216.626 215.0215 981.923 961.3004 20.62263 2.10%
15:30 12966.9 216.626 215.0215 981.748 961.129 20.61899 2.10%
15:45 12864.9 216.626 215.0217 981.146 960.5 20.64598 2.10%
16:00 12694.9 216.626 215.0225 980.196 959.484 20.71205 2.11%
16:15 12838.9 216.626 215.0225 980.621 959.8902 20.73082 2.11%
16:30 13079.9 216.626 215.0217 981.966 961.2923 20.6737 2.11%
16:45 13203.9 216.626 215.0215 982.726 962.0775 20.64846 2.10%
17:00 13340.9 216.626 215.022 983.373 962.766 20.607 2.10%
17:15 13476.9 216.626 215.022 984.224 963.6047 20.61934 2.10%
17:30 13544.9 216.626 215.0217 984.768 964.1822 20.58576 2.09%
17:45 13578.9 216.626 215.0217 984.246 963.6631 20.58288 2.09%
18:00 13612.9 216.626 215.0217 984.083 963.5008 20.58217 2.09%
18:15 13646.9 216.626 215.0217 984.293 963.7075 20.58553 2.09%
18:30 13716.9 216.626 215.1215 984.842 964.6248 20.21725 2.05%
18:45 13782.9 216.626 215.0217 985.286 964.7235 20.56246 2.09%
19:00 13918.9 216.626 215.0217 986.411 965.9352 20.47585 2.08%
19:15 14168.9 217.001 215.397 989.862 969.3755 20.48654 2.07%
19:30 14186.9 217.451 215.847 991.524 971.0639 20.46014 2.06%
19:45 14069.9 216.876 215.272 989.784 968.1951 21.58891 2.18%
20:00 13885.9 216.626 215.022 988.391 966.2426 22.14841 2.24%
20:15 13602.9 216.626 215.0228 986.915 964.7276 22.18743 2.25%
20:30 13505.9 216.626 215.0228 987.74 965.5703 22.16974 2.24%
20:45 13281.9 216.626 215.0228 986.082 963.8899 22.19208 2.25%
21:00 13082.9 216.626 215.0235 984.729 962.4626 22.26641 2.26%
21:15 12880.9 216.626 215.023 983.476 961.1834 22.29256 2.27%
21:30 12722.9 216.626 215.0233 982.576 960.2591 22.3169 2.27%
21:45 12644.9 216.626 215.0233 982.393 960.0706 22.32239 2.27%
22:00 12371.9 216.626 215.0235 981.115 958.7814 22.33362 2.28%
22:15 12038.9 216.626 215.023 980 957.6625 22.3375 2.28%
22:30 11714 211.248 209.6505 967.142 938.3361 28.80589 2.98%
22:45 11400 199.325 197.7255 925.482 898.5413 26.94072 2.91%
23:00 11008 194.077 192.4755 910.983 882.122 28.86103 3.17%
23:15 10572 194.077 192.4755 910.353 881.6099 28.7431 3.16%
23:30 10068 187.102 185.5005 883.294 860.1607 23.13333 2.62%
23:45 9528 172.227 170.6005 838.78 818.6855 20.0945 2.40%
Whole day amounts to 18,897 18743.79 88386.091 86499.59 1886.496 2.13%
Fig. 4 is the whole network load chart (transverse axis is the time among the figure, and the longitudinal axis is electric weight MW); (transverse axis is the time to Fig. 5 among the figure, and the longitudinal axis is the coal consumption amount ton for the total system total consumption of coal comparison diagram before and after optimizing; 1 line always consumes coal for the system before optimizing, and 2 lines are that the system after optimizing always consumes coal), as shown in the figure: the system after the optimization always consumes coal and always consumes the coal reduction obviously than the system before optimizing.System always consumes 88386.091 tons in coal before optimizing, and optimization back system always consumes 86499.59 tons in coal, optimizes the back and practices thrift 1886.496 tons of coals, and the coal consumption reduction is about 2.134%.
Explanation is at last; Above embodiment is only unrestricted in order to technical scheme of the present invention to be described; Although with reference to preferred embodiment the present invention is specified, those of ordinary skill in the art should be appreciated that and can make amendment or be equal to replacement technical scheme of the present invention; And not breaking away from the aim and the scope of technical scheme of the present invention, it all should be encompassed in the middle of the claim scope of the present invention.

Claims (3)

1. a method that realizes dynamic energy-saving distribution of electrical power system is characterized in that, comprises the steps:
1) the burden with power P of acquisition node in the EMS system of each generator node from certain unit electrical network D, branch road ij constraints P Ijmax, last one actual the exerting oneself of generator bus i constantly
Figure FSB00000701757600011
The actual P that exerts oneself of this moment generator bus i Gi, generator bus i the minimum P that exerts oneself Gimin, generator bus i EIAJ P Gimax, branch road quantity NT and generator quantity NG;
2) data of gathering are brought into the target function of multi-period dynamic energy-saving distribution, the calculating generator adjustment amount of exerting oneself:
min F(t)=h 1F 1(t)+h 2F 2(t)
Constraints: Σ i ∈ NG P Gi ( t ) = Σ k ∈ ND P Dk ( t ) + P L ( t )
P Gi(t)-P Gi(t-1)≤ΔP GRCimax i∈NG
P Gi(t-1)-P Gi(t)≤ΔP GRCimax
|P ij(t)|≤P ijmax ij∈NT
Wherein, h 1: the weight factor of energy consumption in the very first time section target function
h 2: the weight factor of generator output adjustment in the second time period target function
P Dk(t): load point k is at the load value of period t;
T: running time section;
P Gi(t): generator i is in the meritorious output of section t running time;
P Gi(t-1): generator i is in the meritorious output of section t-1 running time;
Δ P GRCimax: take into account the meritorious adjusting constraint of the generator i of generator climbing speed;
F 1(t) be the target function of minimum comprehensive coal consumption of first period:
min F 1 = Σ i = 1 NG F i ( P Gi ) + γP L
F 2(t) be the minimum target function of the second period generator output adjustment amount:
min F 2 = Σ i = 1 NG ( P Gi - P Gi 0 ) 2
The target function of minimum comprehensive coal consumption of first period and the minimum bound for objective function of the second period generator output adjustment amount comprise meritorious balance, generator output restriction and the constraint of circuit trend:
Σ i ∈ NG P Gi = Σ k ∈ ND P Dk + P L
P Gimin≤P Gi≤P Gimax
|P ij|≤P ijmax
Wherein, system's total load
P Ij: the trend on the branch road ij, carry out trend through Niu Lafa and calculate
P Ijmax: the heap(ed) capacity of circuit and transformer
The total consumption of coal of
Figure FSB00000701757600024
all generating sets of system
P L: via net loss
F i: the fuel consumption of generator unit i
γ: active loss is converted to the conversion coefficient of coal consumption
3) application load distribution factor method is assigned to system's total load the load bus of each power plant; The said sharing of load factor is to be obtained through being connected to check with corrected Calculation with the SCADA database by the generator output adjustment amount that calculates; The method of said check and correction be with the same day in the real time data each concrete load point at the load value of each period as the sharing of load factor, the load that combines system's total load of prediction to carry out each concrete load point again calculates;
4) with other unit electrical network through carrying out equivalence, the generation schedule that must make new advances with the joining interconnection of this unit electrical network;
5) new generation schedule is fed back in the EMS system of each generator node in this unit electrical network, as next step implementation plan.
2. the method for realization dynamic energy-saving distribution of electrical power system according to claim 1 is characterized in that: said h 1Value be 1, h 2Value be 1.25.
3. the method for realization dynamic energy-saving distribution of electrical power system according to claim 1; It is characterized in that: in said step 4), said equivalence is to be duty value or equivalent power supplys such as this unit electrical network is borderline with the Power Exchange between this unit electrical network and other unit electrical network is equivalent.
CN2009101917055A 2009-12-03 2009-12-03 Method for realizing dynamic energy-saving distribution of electrical power system Expired - Fee Related CN101710702B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009101917055A CN101710702B (en) 2009-12-03 2009-12-03 Method for realizing dynamic energy-saving distribution of electrical power system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009101917055A CN101710702B (en) 2009-12-03 2009-12-03 Method for realizing dynamic energy-saving distribution of electrical power system

Publications (2)

Publication Number Publication Date
CN101710702A CN101710702A (en) 2010-05-19
CN101710702B true CN101710702B (en) 2012-04-11

Family

ID=42403469

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009101917055A Expired - Fee Related CN101710702B (en) 2009-12-03 2009-12-03 Method for realizing dynamic energy-saving distribution of electrical power system

Country Status (1)

Country Link
CN (1) CN101710702B (en)

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101938141B (en) * 2010-08-02 2013-03-27 中国南方电网有限责任公司 Method for evaluating and optimizing auto generation control effect of large power network grid-connected power plant
CN102195362A (en) * 2011-05-26 2011-09-21 中国电力科学研究院 Dynamic probability dispatching method for calculating system operation reliability
US20130030587A1 (en) * 2011-07-29 2013-01-31 General Electric Company System and method for power curtailment in a power network
CN103051001B (en) * 2013-01-07 2015-02-18 中国电力科学研究院 Minor-cycle real-time generation schedule
CN103078319B (en) * 2013-01-11 2015-12-23 华中电网有限公司 The real-time achieve an equilibrium ikn planning merit rating method and system of electrical network
CN103746394B (en) * 2013-12-27 2015-12-30 国家电网公司 Low and medium voltage distribution network power-saving method
CN104239961B (en) * 2014-07-16 2016-05-18 广东工业大学 A kind of based on the Economic Dispatch optimization method of crossover algorithm in length and breadth
CN104682392B (en) * 2014-12-04 2017-02-01 重庆大学 Circuit security constraint-considering provincial grid AGC (automatic generation control) unit dynamic optimization scheduling method
KR101717360B1 (en) 2015-07-30 2017-03-16 엘에스산전 주식회사 Apparatus and method for managing of data base in energy management system
CN109977444B (en) * 2017-12-28 2020-09-25 广东电网有限责任公司电力调度控制中心 Bus load prediction data correction method for power generation plan optimization
CN108879796B (en) * 2018-08-10 2021-07-23 广东电网有限责任公司 Electric power day-ahead market clearing calculation method, system, device and readable storage medium
CN111489009B (en) * 2019-06-06 2023-07-25 国网辽宁省电力有限公司 Optimization calculation method and device for operation mode of electric vehicle charging station
CN112510704B (en) * 2020-11-26 2022-10-11 贵州电网有限责任公司 Online coal consumption curve real-time generation method and system
CN114849890B (en) * 2022-04-28 2023-07-07 安徽立卓智能电网科技有限公司 Method for reducing station power consumption based on optimized coal mill station start

Also Published As

Publication number Publication date
CN101710702A (en) 2010-05-19

Similar Documents

Publication Publication Date Title
CN101710702B (en) Method for realizing dynamic energy-saving distribution of electrical power system
CN106169108B (en) Active power distribution network short-term active power optimization method containing battery energy storage system
CN109492861B (en) Method for decomposing medium-term electricity quantity trading plan of cascade hydropower station group
CN110365013B (en) Capacity optimization method of photo-thermal-photovoltaic-wind power combined power generation system
CN103942613B (en) Method for grid and province two-stage real-time generation schedule coordinative optimization under generalized tie line mode
CN109948849B (en) Power distribution network frame planning method considering energy storage access
CN108123492A (en) A kind of generation schedule optimization method a few days ago for considering thermoelectricity electricity accumulation of heat combined adjusting peak
CN103986153B (en) Within the scope of interconnection of bulk power grids, coordinate to carry out the optimization method of balance of electric power and ener
CN104299072A (en) Security constraint generation schedule planning method based on water and fire coordination
CN111428970B (en) Large-scale hydropower station group cross-province capacity analysis model and solving method
CN109687534B (en) Power system generator set active power control method based on step water quantity matching
CN110661301A (en) Capacity allocation optimization method for water-light-storage multi-energy complementary power generation system
CN107798430A (en) Meter and the optimization method of bidding of the transregional consumption of regenerative resource
CN116231765B (en) Virtual power plant output control method
CN113128844A (en) Distributed power supply planning method based on power supply equipment capacity limitation
CN104253439B (en) Battery energy storage power station reactive power is distributed and control method
CN110826778A (en) Load characteristic optimization calculation method actively adapting to new energy development
CN108764758B (en) Power and natural gas interconnection system cooperation method considering demand side management
CN101719668A (en) Energy-saving power generation dispatching method considering security constraint and network loss modification
CN103761680B (en) Grid and provincial dispatching method and system for AC/DC interconnected large power grid with wind farm
CN116362400A (en) Large-industry user electricity fee optimization method based on light storage system configuration
CN110571868A (en) Optimal configuration method of microgrid
CN113240546B (en) Monthly scheduling method for units in dense hydropower region
CN113991714A (en) Elastic resource aggregation method and system based on power swapping station
HUII et al. Cross-regional Joint Scheduling Method of Renewable Energy Based on Multi-period Coordination

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120411