CN101709582A - 一种减少预制桩施工挤土的防护方法 - Google Patents
一种减少预制桩施工挤土的防护方法 Download PDFInfo
- Publication number
- CN101709582A CN101709582A CN200910197430A CN200910197430A CN101709582A CN 101709582 A CN101709582 A CN 101709582A CN 200910197430 A CN200910197430 A CN 200910197430A CN 200910197430 A CN200910197430 A CN 200910197430A CN 101709582 A CN101709582 A CN 101709582A
- Authority
- CN
- China
- Prior art keywords
- construction
- engineering
- foundation
- pile
- piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
一种减少预制桩施工挤土的防护方法,在桩基工程施工前,先施工基坑围护工程,用围护结构隔断基坑内外土层连接,然后在进行桩基工程施工;在进行桩基工程施工过程中,先打基坑四周的桩,再打基坑中部的桩。在桩基工程施工中,打桩前在桩位处预钻孔挤土,在桩位之间打释放孔,降低水位,以减少挤土作用。本发明所述的施工方法可以有效的减少沉桩过程对周围环境的影响,由于这种方法对坑外土层没有扰动,所以在基坑工程开挖土方后周边环境影响比传统方法小很多。
Description
技术领域
本发明涉及土木工程技术领域,具体的来说涉及一种桩基的施工过程中减少挤土的防护方法。
背景技术
随着我国经济建设和社会发展日益增长,住房建设、公共建筑、基础设施建设蓬勃发展,在沿海、沿江及我国大部分中部地区建筑基础都采用桩基控制建筑物沉降,在我国大部分地区桩基都采用比较环保、节能及造价经济的预制桩(如PHC管桩、方桩),但是预制桩属于排土桩,即桩打(压)入土层中产生挤土效应,周围土层受到挤压作用后会产生地面隆起或水平位移,对建筑物、构筑物、管线、道路等产生危害,严重时会造成房屋开裂,不均匀沉降(即倾斜);马路破坏开裂、管线断裂等严重后果,为此,桩基工程中预制桩沉桩产生挤土效应危害周边环境一直是困扰建筑工程界的难题。
基坑围护工程主要是为地下工程临时服务的配套工程,在地下室等地下工程开挖土方前先施工,支护基坑周边土体,在完成地下工程结构施工后,围护工程用途结束。围护工程施工常规在预制桩沉桩结束后进行,因为如果在桩基工程前施工,沉桩挤土同样对围护结构产生危害。
发明内容
本发明所要解决的技术问题在于,克服现有技术中存在的问题,提供一种一种减少预制桩施工挤土的防护方法,该方法可以有效的控制沉桩对周边环境的影响。
为了解决上述问题本发明的技术方案是这样的:
一种减少预制桩施工挤土的防护方法,在桩基工程施工前,先施工基坑围护工程,用围护结构形成挡墙隔断基坑内外土层连接,然后再进行桩基工程施工;在进行桩基工程施工过程中,先打基坑四周的桩,再打基坑中部的桩。打桩前在桩位上预钻孔取土,在桩位之间打应力释放孔,打降水孔降低水位,以减少挤土作用。上述措施施工后剩余的少量挤压作用由围护挡墙消散在基础内。
有益效果,本发明所述的施工方法可以有效地减少沉桩过程对周围环境的影响,由于这种方法对坑外土层没有扰动,所以在基坑工程开挖土方后周边环境影响比传统方法小很多。
附图说明
下面结合附图和具体实施方式来详细说明本发明;
图1为本发明的所述的施工方法流程示意图。
具体实施方式
为了使本发明实现的技术手段、创作特征、达成目的与功效易于明白了解,下面结合具体图示,进一步阐述本发明。
一种减少预制桩施工挤土的防护方法,本方法主要是桩基与围护工程逆作法施工,具体为:在桩基工程施工前,先施工基坑围护工程,用围护结构墙隔断坑内外土层连接,在桩基工程施工时,采取桩位预钻孔挤土、打释放孔,降低水位,先打四周的桩再打中间的桩等技术措施,有效减少挤土作用,剩余的挤土作用由围护结构墙消化在基础之内,这样可有效控制沉桩对周边环境的影响。
参看图1
首先在施工的基坑范围内进行基坑围护工程施工,基坑围护工程施工完毕后会形成围护结构墙,围护结构墙将内外土层隔断,以减少对围护结构墙外侧土体的影响。
在基坑围护工程施工完毕后,进行桩基工程施工,首先需要在桩位处钻孔挤土,钻孔大小、深度、数量根据欲打桩的地质情况、桩径、桩长来定,而桩径一般为50-250mm。在桩位之间打应力释放孔,应力释放孔大小、深度、数量也根据欲打桩的地质情况、桩径、桩长来定;打降水孔降低水位,可以有效减少沉桩时的挤土效应。
所述降水孔连接有抽水水泵,水泵可以将基坑内的地下水抽出,以降低水位。
应力释放孔用于释放打桩时土层之间相互挤压的内部应力,使挤压的内部应力在释放孔处趋于消散。
打桩时,先打基坑四周的桩,再打基坑中部的桩;这样可以有效减少挤土作用,剩余的挤土作用由围护结构墙承载,有效的控制了沉桩对周边环境的影响。
以上显示和描述了本发明的基本原理、主要特征和本发明的优点。本行业的技术人员应该了解,本发明不受上述实施例的限制,上述实施例和说明书中描述的只是说明本发明的原理,在不脱离本发明精神和范围的前提下本发明还会有各种变化和改进,这些变化和改进都落入要求保护的本发明范围内。本发明要求保护范围由所附的权利要求书及其等同物界定。
Claims (2)
1.一种减少预制桩施工挤土的防护方法,其特征在于,在桩基工程施工前,先施工基坑围护工程,用围护结构形成挡墙隔断基坑内外土层连接,然后再进行桩基工程施工;在进行桩基工程施工过程中,先打基坑四周的桩,再打基坑中部的桩。
2.根据权利要求1所述的一种减少预制桩施工挤土的防护方法,其特征在于,在桩基工程施工中,打桩前在桩位上预钻孔取土,在桩位之间打应力释放孔,打降水孔,以减少挤土作用。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009101974306A CN101709582B (zh) | 2009-10-20 | 2009-10-20 | 一种减少预制桩施工挤土的防护方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009101974306A CN101709582B (zh) | 2009-10-20 | 2009-10-20 | 一种减少预制桩施工挤土的防护方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101709582A true CN101709582A (zh) | 2010-05-19 |
CN101709582B CN101709582B (zh) | 2011-11-30 |
Family
ID=42402388
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009101974306A Active CN101709582B (zh) | 2009-10-20 | 2009-10-20 | 一种减少预制桩施工挤土的防护方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101709582B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111851516A (zh) * | 2020-06-20 | 2020-10-30 | 中铁上海工程局集团有限公司 | 一种适用于复杂环境下的phc管桩逆序施工方法 |
CN112323873A (zh) * | 2019-08-05 | 2021-02-05 | 张继红 | 一种打桩实时防护方法 |
CN114000726A (zh) * | 2021-07-11 | 2022-02-01 | 广州市地平线岩土工程有限公司 | 一种既有建筑内部增加桩基施工方法 |
CN114482014A (zh) * | 2022-01-12 | 2022-05-13 | 中建八局第二建设有限公司 | 近海超厚淤泥区深基坑内预制桩锤击沉桩施工方法 |
-
2009
- 2009-10-20 CN CN2009101974306A patent/CN101709582B/zh active Active
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112323873A (zh) * | 2019-08-05 | 2021-02-05 | 张继红 | 一种打桩实时防护方法 |
CN111851516A (zh) * | 2020-06-20 | 2020-10-30 | 中铁上海工程局集团有限公司 | 一种适用于复杂环境下的phc管桩逆序施工方法 |
CN114000726A (zh) * | 2021-07-11 | 2022-02-01 | 广州市地平线岩土工程有限公司 | 一种既有建筑内部增加桩基施工方法 |
CN114482014A (zh) * | 2022-01-12 | 2022-05-13 | 中建八局第二建设有限公司 | 近海超厚淤泥区深基坑内预制桩锤击沉桩施工方法 |
CN114482014B (zh) * | 2022-01-12 | 2023-09-08 | 中建八局第二建设有限公司 | 近海超厚淤泥区深基坑内预制桩锤击沉桩施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN101709582B (zh) | 2011-11-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103726495B (zh) | 近海深基坑支护结构及其施工方法 | |
US11840817B2 (en) | Method for constructing steel sheet pile cofferdam on deep sand gravel overburden layer | |
CN204199335U (zh) | 一种减小phc管桩施工挤土效应的泄压井 | |
CN104805854A (zh) | 一种潮汐环境下深水超长钢板桩围堰施工方法 | |
CN102926376A (zh) | 一种围海造地区域软土地基处理方法 | |
CN103924602A (zh) | 深厚软土基坑施工方法 | |
CN101709582B (zh) | 一种减少预制桩施工挤土的防护方法 | |
CN112030956A (zh) | 一种岩溶地层钻孔灌注桩施工方法 | |
WO2024007591A1 (zh) | 一种基于双护筒稳桩平台的嵌岩单桩施工方法 | |
CN101793023A (zh) | 一种基坑施工方法 | |
CN106869138A (zh) | 一种衡重式双排桩支护结构及其基坑开挖方法 | |
CN114033388B (zh) | 富水粉砂层地下隧道顶管用竖井施工方法 | |
CN201896317U (zh) | 复杂土质不排水下沉沉井的施工装置 | |
CN103437712B (zh) | 一种适用于穿透圆砾层土质的三轴搅拌机钻头 | |
CN110259456B (zh) | 一种隧道施工用的溶洞处理方法 | |
CN107780407A (zh) | 二次降水联合动力固结软基处理方法 | |
CN209669900U (zh) | 水底强透水砂性土层中隧道建设围堰结构 | |
CN213625605U (zh) | 一种旋挖桩锚与挂网喷射混凝土的深基坑结构 | |
CN206635766U (zh) | 一种长短间隔交错式水泥土搅拌桩墙施工设备 | |
CN212561534U (zh) | 一种用于临海富水环境的土岩二元基坑围护结构 | |
CN104074234A (zh) | 电厂循环水系统的内河水取水口结构及其施工方法 | |
CN204435321U (zh) | 一种火力发电厂取水明渠 | |
CN106948388A (zh) | 一种磁环式测试基坑开挖引起地基隆起的装置及方法 | |
CN103981858A (zh) | 一种网格状水泥土连续墙防护的抗倾斜管桩及其工法 | |
CN206015695U (zh) | 地下管 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |