CN101700517B - Process for automatically cleaning, painting and oiling elevator guide rails - Google Patents

Process for automatically cleaning, painting and oiling elevator guide rails Download PDF

Info

Publication number
CN101700517B
CN101700517B CN2009102111845A CN200910211184A CN101700517B CN 101700517 B CN101700517 B CN 101700517B CN 2009102111845 A CN2009102111845 A CN 2009102111845A CN 200910211184 A CN200910211184 A CN 200910211184A CN 101700517 B CN101700517 B CN 101700517B
Authority
CN
China
Prior art keywords
guide rail
oiling
paint
impeller
room
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009102111845A
Other languages
Chinese (zh)
Other versions
CN101700517A (en
Inventor
郁霞秋
邱其琴
邱江伟
夏家斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changjiang RT Mart (Zhangjiagang) Machinery Co., Ltd.
Original Assignee
CHANGJIANG RUNFA MACHINERY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHANGJIANG RUNFA MACHINERY Co Ltd filed Critical CHANGJIANG RUNFA MACHINERY Co Ltd
Priority to CN2009102111845A priority Critical patent/CN101700517B/en
Publication of CN101700517A publication Critical patent/CN101700517A/en
Application granted granted Critical
Publication of CN101700517B publication Critical patent/CN101700517B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Spray Control Apparatus (AREA)

Abstract

The invention provides a process for automatically cleaning, painting and oiling elevator guide rails, which is characterized in that a moving rack or a lifting rack is used for carrying elevator guide rails to sequentially pass a cleaning machine, a right side painting room, a tipper, a back side painting room, a drying room, a cooling area, an oiling area, another tipper and a discharge rack so as to clean, paint and oil the elevator guide rails by electromechanical automation. Compared with the prior art, the invention enhances the production capacity, reduces the working intensity of workers, enhances the product quality and improves the working environment.

Description

Cage guide cleans automatically, paint, oiling technology
Technical field
The present invention relates to that a kind of cage guide cleans automatically, paint, oiling technology.
Background technology
Guide rail production mainly contains two big indexs: the one, and rigid size; The 2nd, surface quality.Wherein, surface quality mainly is to reach through cleaning, paint, oiling, this technology at first be to prevent that guide rail from getting rusty; Next is embody guide rail attractive in appearance, and the reality latter to a certain extent seems more even more important than the former, because the latter is people's first impression; It is observable, and its good and bad most of people can both judge, and the former needs the professional just can reach a conclusion through professional means; Be that the only a few people can grasp, even need the regular hour section.
In the traditional processing technology; Some producers adopts lacquer spraying technique, and technology although it is so can make that coating layer thickness is even, not only can produce a large amount of coating clouds and causes waste and unnecessary processing cost but spray paint; Coating cloud also can pollute the guide rail machined surface and connecting hole is installed simultaneously, influences the workpiece quality.
For avoiding the problem of above-mentioned lacquer spraying technique, at present most producer all adopts artificial the brushing, and this manual work brushing technique step roughly is: earlier with hanging piece to the artificial sub-material point of driving a vehicle; Carry out sub-material and cleaning through manual work again; Again through artificial blanking, driving hanging piece, artificial sub-material to brushing point; Being coated with impeller front, rollover, manual work through manual work again is coated with the brushing of the impeller back side and accomplishes; Use blower fan to dry up, turn over back original position, oiling and packing at last and accomplish this technology.And manual work brushes not only that workload is very big, and labour cost is higher, and has also that brush is in uneven thickness, surface chromatic aberration is big, and paint sagging, environmental pollution are big, does not clean defectives such as paint film is insecure before the mopping.
Summary of the invention
In order to solve above-mentioned technical problem, the object of the present invention is to provide that a kind of cage guide cleans automatically, paint, oiling processing technology.
The object of the invention is realized through following technical scheme:
A kind of cage guide cleans automatically, paint, oiling technology, can realize that electromechanical automatic ground cleans, paints said cage guide, and the oiling process operation, and it may further comprise the steps:
The first, said guide rail is moved to cleaning machine through first transversely-moving rack, and clean through cleaning machine;
The second, be put on vertical frame cleaning guide rail later, said vertical frame is sent said guide rail into impeller first-surface painting room through electrical equipment control, and said guide rail impeller front is painted;
The 3rd, after accomplishing the positive paint of said guide rail impeller, said guide rail is delivered on the chain, said chain drives said guide rail and steps on second transversely-moving rack, simultaneously the paint on this guide rail of levelling;
The 4th, said second transversely-moving rack is delivered to first tipper with said guide rail, and said first tipper is sent after 180 ° of the said guide rail upsets into impeller reverse side coating room, and paint is implemented at the guide rail impeller back side;
The 5th, said guide rail is sent on vertical lift, and dried by automatic baking room being gone in said guide rail stepping through carrier chain;
The 6th, the said guide rail after the oven dry is sent into the nature cooling zone, after band guide rail temperature is cooled to normal temperature, said guide rail is moved to automatic oiling district by the lifting-transverse shifting car, said guide rail is carried out the oiling operation;
The 7th, the said guide rail after the completion oiling is moved on second tipper, it is clamped 180 ° of back upsets, and said guide rail is delivered to the blanking rack place, thereby accomplish cleaning, paint, the oiling process of whole guide rail workpiece by traversing carriage.
Further, said impeller first-surface painting room and said impeller reverse side coating room adopt manipulator that said guide rail impeller is painted.
Said impeller first-surface painting room and said impeller reverse side coating room use quantitative gear paint feeding pump that guide rail is implemented the paint fuel feeding.
Again further, move to the oiling bogie top in automatic oiling district after said guide rail is suspended in midair by said lifting-transverse shifting car, said guide rail is carried out the oiling operation.
Compared with prior art, the invention has the beneficial effects as follows: improve production capacity, lower labor strength, improved product quality, improved working environment.
Description of drawings
Below in conjunction with accompanying drawing technical scheme of the present invention is described further:
Fig. 1 be according to the present invention cage guide clean automatically, the automatic flow sketch map of paint, oiling technology.
The specific embodiment
Below in conjunction with accompanying drawing and specific embodiment the present invention is done further detailed explanation:
As shown in Figure 1, the guide rail that needs painting moves to cleaning machine 2 through transversely-moving rack 1, and cleans 3 declines of back arrival transversely-moving rack through cleaning machine 2; Workpiece drops on the transversely-moving rack 4; Chain and feeding machine are housed on the transversely-moving rack 4, can at regular time and quantity workpiece be put on vertical frame 5, vertical frame 5 is delivered to 6 pairs of guide rail workpiece impeller front, impeller first-surface painting room with workpiece and is painted under electrical control; Guide rail workpiece behind the paint is delivered on vertical frame 7 automatically; Vertically frame 7 decline guide rails drop on the lateral transfer chain 8, and lateral transfer chain 8 beginning steppings simultaneously also are simultaneously guide rail workpiece paint levelling process during the stepping; After 8 steppings repeatedly of lateral transfer chain the guide rail workpiece is delivered on the transversely-moving rack 9; The guide rail workpiece is delivered to tipper 10 and the guide rail workpiece turned over by transversely-moving rack 9 and deliver to 11 pairs of guide rail workpiece impeller back side, impeller reverse side coating room after the turnback and implement paint, by cradle 12,13 guide rail is sent into vertical crane 15 again, under electrical control, drop on the traversing carrier chain 14 of drying room; Dragging the stepping of guide rail workpiece by the horizontal carrier chain 14 of drying room gets into automatic baking room 16 and dries; In best mode for carrying out the invention, preferred bake out temperature is 0-150 °, can regulate this bake out temperature according to Various Seasonal.Guide rail workpiece oven dry back gets into nature cooling zone 17 makes guide rail workpiece self temperature be cooled to normal temperature; Implement to be coated with antirust oil by lifting-transverse shifting car 18 with guide rail workpiece translational motion to oiling bogie 19 tops and by 19 pairs of guide rail workpiece of oiling bogie machined surface again; When oiling; Being suspended on that this guide rail is T-shaped is aerial, moves down at it through oiling bogie 19 it is carried out oiling.The guide rail workpiece coats behind the oil again by in the lifting-transverse shifting car 18 sliding turnover machines 21; And it is clamped 180 ° of back upsets by tipper 21; At last; Unclamp the guide rail workpiece, it is dropped on the traversing carriage 20, and the guide rail workpiece is delivered to cleaning, paint, the oiling overall process that finishes whole guide rail workpiece in blanking rack 22 places by traversing carriage 20.
What deserves to be mentioned is: above-mentioned when the guide rail workpiece is painted; Described impeller first-surface painting room 6 has all adopted imitative manually-operated manipulator with impeller first-surface painting room 11; Simultaneously, the fuel feeding lacquer has adopted quantitative gear paint feeding pump, and is adjustable so that paint delivery is stablized.Automatically oiling guide rail work status be " ⊥ " and " T " shape, oiling move be that the guide rail workpiece is static, oiling moving of car or oiling mechanism is static, the guide rail workpiece motion s.
Although be the example purpose; Preferred implementation of the present invention is disclosed; But those of ordinary skill in the art will recognize, under the situation that does not break away from disclosed scope of the present invention and spirit by appending claims, various improvement, increase and replacement are possible.

Claims (3)

  1. A cage guide clean automatically, paint, oiling technology, can realize that electromechanical automatic ground cleans, paints said cage guide, and the oiling process operation, it may further comprise the steps:
    The first, said guide rail is moved to cleaning machine through first transversely-moving rack, and clean through cleaning machine;
    The second, be put on vertical frame cleaning guide rail later, said vertical frame is sent said guide rail into impeller first-surface painting room through electrical equipment control, and said guide rail impeller front is painted;
    The 3rd, after accomplishing the positive paint of said guide rail impeller, said guide rail is delivered on the chain, said chain drives said guide rail and steps on second transversely-moving rack, simultaneously the paint on this guide rail of levelling;
    The 4th, said second transversely-moving rack is delivered to first tipper with said guide rail, and said first tipper is sent after 180 ° of the said guide rail upsets into impeller reverse side coating room, and paint is implemented at the guide rail impeller back side;
    The 5th, said guide rail is sent on vertical lift, and dried by automatic baking room being gone in said guide rail stepping through carrier chain;
    The 6th, with the oven dry after said guide rail send into the nature cooling zone, treat that the guide rail temperature is cooled to normal temperature after, said guide rail is moved to automatic oiling district by the lifting-transverse shifting car, said guide rail is carried out the oiling operation;
    The 7th, the said guide rail after the completion oiling is moved on second tipper, it is clamped 180 ° of back upsets, and said guide rail is delivered to the blanking rack place, thereby accomplish cleaning, paint, the oiling process of whole guide rail workpiece by traversing carriage;
    Said impeller first-surface painting room and said impeller reverse side coating room adopt manipulator that said guide rail impeller is painted.
  2. 2. a kind of cage guide according to claim 1 cleans automatically, paint, oiling technology, it is characterized in that: said impeller first-surface painting room and said impeller reverse side coating room use quantitative gear paint feeding pump that guide rail is implemented the paint fuel feeding.
  3. 3. according to claim 1 a kind of by elevator clean automatically, paint, oiling technology, it is characterized in that: said guide rail moves to the oiling bogie top in automatic oiling district after by said lifting-transverse shifting car suspention, and said guide rail is carried out the oiling operation.
CN2009102111845A 2009-11-06 2009-11-06 Process for automatically cleaning, painting and oiling elevator guide rails Expired - Fee Related CN101700517B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009102111845A CN101700517B (en) 2009-11-06 2009-11-06 Process for automatically cleaning, painting and oiling elevator guide rails

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009102111845A CN101700517B (en) 2009-11-06 2009-11-06 Process for automatically cleaning, painting and oiling elevator guide rails

Publications (2)

Publication Number Publication Date
CN101700517A CN101700517A (en) 2010-05-05
CN101700517B true CN101700517B (en) 2012-05-23

Family

ID=42155456

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009102111845A Expired - Fee Related CN101700517B (en) 2009-11-06 2009-11-06 Process for automatically cleaning, painting and oiling elevator guide rails

Country Status (1)

Country Link
CN (1) CN101700517B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102266848B (en) * 2011-07-11 2013-01-23 张家港市优希宏达机电厂 New painting method
CN104437992B (en) * 2013-09-22 2017-02-01 珠海格力电器股份有限公司 Sheet-metal part silkscreen paint spraying apparatus and method
CN103691692B (en) * 2013-12-16 2015-10-28 张家港市张运机械制造有限公司 Automatic elevator guide rail cleaning machine
CN103817494B (en) * 2014-02-26 2016-01-13 长江润发机械股份有限公司 T-shaped guide rail automatic technology
CN104002350B (en) * 2014-05-05 2016-01-20 山西唐人居古典家居文化有限公司 A kind of preparation method of red sandalwood furniture
CN104138814B (en) * 2014-07-01 2017-04-12 南通江中光电有限公司 Paint spraying device
CN104525442B (en) * 2014-09-26 2017-06-13 中航沈飞民用飞机有限责任公司 The paint line of Automatic Control, hand spray
CN107917912B (en) * 2017-11-03 2021-07-09 赣州市畅达电梯销售有限公司 Drying detection mechanism for suspended ceiling of elevator car
CN110449307A (en) * 2019-07-15 2019-11-15 佛山市南海兴圆机械制造有限公司 A kind of door and window special part painting finishing color production line
CN113182109A (en) * 2021-04-13 2021-07-30 盐城市暮君缇商贸有限公司 Tool bit maintenance system of intelligent numerical control milling machine and use method thereof

Also Published As

Publication number Publication date
CN101700517A (en) 2010-05-05

Similar Documents

Publication Publication Date Title
CN101700517B (en) Process for automatically cleaning, painting and oiling elevator guide rails
CN104998786B (en) Large-scale workpiece paint finishing
CN201586614U (en) Automatic elevator guide rail cleaning, painting and oiling system
CN201157809Y (en) Robot paint spraying system
CN107829555A (en) A kind of Intelligent outer wall nacelle construction robot system
CN102218380A (en) Fully-automatic pentagonal spraying machine
CN207343135U (en) A kind of paint line for bogie frame
CN201572727U (en) Automatic spray coating system
CN101474616A (en) Technique for lacquering product
CN203096175U (en) Automatic production line for enamel of water tank inner container of solar water heater
CN201454769U (en) Spraying-gun device of NC painting and drying production line
CN204195962U (en) A kind of ceramic body dust arrester
CN204892214U (en) Large -scale work piece paint finishing
CN106166523A (en) Application reciprocating engine control system and control method
CN207609157U (en) A kind of Intelligent outer wall nacelle construction robot system
CN108273701B (en) Process of automatic production line equipment for processing paint on outer surface of radiator
CN105964468A (en) Spray-coating system for irregular workpieces
CN206184659U (en) Portable powder spraying system
CN205742926U (en) A kind of can the spray equipment of simultaneously spraying various building coatings
CN211756452U (en) Dipping mechanism of annular cantilever impregnator
CN209156192U (en) A kind of conveyer automatic spraying conveying device
CN206935632U (en) A kind of painting gauge
CN206763246U (en) A kind of automatic application product line of chain saw guide plate
CN205761998U (en) A kind of paint spray booth
CN214021549U (en) Panel spraying device with limit function

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20170717

Address after: 215631, Suzhou, Jiangsu province Zhangjiagang city town of morning Feng Feng Road

Patentee after: Changjiang RT Mart (Zhangjiagang) Machinery Co., Ltd.

Address before: 215633 No. 100 West Changjiang Road, Jin Gang Town, Jiangsu, Zhangjiagang

Patentee before: Changjiang Runfa Machinery Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120523

Termination date: 20181106