CN101666099A - Layer-by-layer foundation consolidating method based on barrel-type foundation negative pressure technology - Google Patents

Layer-by-layer foundation consolidating method based on barrel-type foundation negative pressure technology Download PDF

Info

Publication number
CN101666099A
CN101666099A CN200910307872A CN200910307872A CN101666099A CN 101666099 A CN101666099 A CN 101666099A CN 200910307872 A CN200910307872 A CN 200910307872A CN 200910307872 A CN200910307872 A CN 200910307872A CN 101666099 A CN101666099 A CN 101666099A
Authority
CN
China
Prior art keywords
foundation
negative pressure
barrel
layer
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910307872A
Other languages
Chinese (zh)
Other versions
CN101666099B (en
Inventor
丁红岩
张浦阳
练继建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Daoda Offshore Wind Power Engineering Technology Co., Ltd.
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN2009103078721A priority Critical patent/CN101666099B/en
Publication of CN101666099A publication Critical patent/CN101666099A/en
Application granted granted Critical
Publication of CN101666099B publication Critical patent/CN101666099B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a layer-by-layer foundation consolidating method based on a barrel-type foundation negative pressure technology, comprising the following steps: (1) a reserved negative pressure hole is arranged on a cover plate of the barrel top of the barrel-type foundation, a plurality of steel tubes with sieving holes at the side walls are fixedly connected below the cover plate of thebarrel top of the barrel-type foundation, the length of the plurality of steel tubes is lengthened gradually according to the set depth of layered consolidated foundation soil layer in the direction starting from the negative pressure hole to the barrel wall of the barrel-type foundation, each steel tube is parallel to the central line of the barrel-type foundation, and geotextile is laid below the cover plate of the barrel top of the barrel-type foundation; (2) according to set injection negative pressure value, the barrel-type foundation is sunk and positioned by negative pressure; and (3) negative pressure equipment is used for pumping water and/or air by the reserved negative pressure hole and carrying out negative pressure foundation consolidation treatment according to set prepressing value of the foundation soil till the foundation soil is overconsolidated. The layer-by-layer foundation consolidating method realizes layer-by-layer foundation consolidation, and effectively increases the depth and width of the foundation consolidation, thus improving the bearing capability and stability of the barrel-type foundation.

Description

Foundation reinforcement method successively based on bucket foundation negative pressure technology
Technical field
The present invention relates to a kind of foundation reinforcement method, particularly a kind of foundation reinforcement method successively based on bucket foundation negative pressure technology.
Background technology
At present, in harbour, ocean, water conservancy and bridge engineering, especially on mucky soil matter, be the main puzzlement that bucket foundation is used as the settlement issues of the bucket foundation of shallow foundation.In the disadvantageous zone of this geological conditions, bucket foundation is difficult to satisfy the requirement of bearing capacity and stability, has problem safe in utilization.
Summary of the invention
The present invention provides a kind of foundation reinforcement method successively based on bucket foundation negative pressure technology for solving the technical problem that exists in the known technology, this method has solved in the unfavorable zone of geological conditions the bucket foundation settlement issues as shallow foundation, can improve the bearing capacity and the stability of bucket foundation, strengthen the safety in the bucket foundation use.
The technical scheme that the present invention takes for the technical problem that exists in the solution known technology is: a kind of foundation reinforcement method successively based on bucket foundation negative pressure technology, may further comprise the steps: (one) offers the reservation negative pressure hole on the tube lamina tecti of described bucket foundation, below the tube lamina tecti of described bucket foundation, be connected with the steel pipe that many sidewalls have sieve aperture, barrel direction towards described bucket foundation progressively extends by setting layering consolidated subsoil soil depth the length of described many steel pipes from described negative pressure hole, described every steel pipe is parallel with the center line of described bucket foundation, lays geotextiles below the tube lamina tecti of described bucket foundation; (2) according to the injection negative pressure value of setting, with described sinking and positioning bucket foundation; (3) draw water and/or gas by reserving negative pressure hole with negative pressure equipment, carry out the negative pressure ground stabilization according to the foundation soil precompressed value of setting and handle, until the foundation soil overconsolidation.
Described foundation soil precompressed value is (0 ,-0.6) Mpa, and the described negative pressure ground stabilization processing time is: at least 7 days
Advantage and good effect that the present invention has are: by the suction utilization basis itself that negative pressure equipment applies foundation soil is carried out the overconsolidation processing, carry out ground stabilization; Permeable/gas material efficient balance the ground such as geotextiles that are laid on below the tube lamina tecti between tube top and the foundation soil reinforce the shallow foundation ground, the steel pipe of the different length of the band sieve aperture that welds below by the tube lamina tecti transmits negative pressure fast to different soil depths, realize ground stabilization successively, increase the degree of depth and the range of ground stabilization effectively, thereby improve the bearing capacity and the stability of bucket foundation, ground stabilization is remarkably productive, use equipment is simple, easy construction, duration weak point, economic benefit is obvious, and the integration engineering cost is low.
Description of drawings
Fig. 1 is a structural representation of the present invention;
Fig. 2 is the upward view that is connected with the bucket foundation of steel pipe among the present invention;
Fig. 3 is the structural representation that is fixed in the steel pipe in the bucket foundation among the present invention.
Among the figure: 1, bucket foundation, 2, geotextiles, 3, reserve negative pressure hole, 4, water and/or gas, 5, steel pipe, 6, sieve aperture.
The specific embodiment
For further understanding summary of the invention of the present invention, characteristics and effect, exemplify following examples now, and conjunction with figs. is described in detail as follows:
See also Fig. 1~Fig. 3, a kind of foundation reinforcement method based on bucket foundation negative pressure technology of the present invention may further comprise the steps:
(1) on the tube lamina tecti of bucket foundation 1, offers reservation negative pressure hole 3, permeable/gas materials such as the steel pipe 5 of the different length of many bands of welding sieve apertures 6 and laying geotextiles 2 below the tube lamina tecti of bucket foundation 1; (2) according to the injection negative pressure value of setting, with sinking and positioning bucket foundation; (3) water and/or the gas of extracting out in the bucket foundations 1 by reservation negative pressure hole 3 with negative pressure equipment 4 carries out the negative pressure ground stabilization according to the foundation soil precompressed value of setting and handles, the overconsolidation of realization foundation soil.Foundation soil precompressed value, promptly the tube external and internal pressure difference of bucket foundation is (0 ,-0.6) Mpa, and the parameter that adopts under different depth conditions has been shown in the following table:
The environment for use situation Tube external pressure value (Mpa) The suction value that negative pressure equipment applies (Mpa) Cylinder pressure value (Mpa) Foundation soil precompressed value (the tube external and internal pressure difference of bucket foundation) (Mpa) Squeeze time
The sea, beach 0 (0,0.1) ??(0,-0.1) ??(0,-0.1) At least 7 days
The 30m depth of water 0.3 (0,0.3) ??(0.3,0) ??(0,-0.3) At least 7 days
The 60m depth of water 0.6 (0,0.6) ??(0.6,0) ??(0,-0.6) At least 7 days
The steel pipe of many parallel with the bucket foundation center line and different lengths sidewall band sieve aperture of welding below the tube lamina tecti of bucket foundation, the length of steel pipe is corresponding with the layering consolidated subsoil soil depth of setting respectively, progressively extend by setting the consolidated subsoil soil depth from reserving the barrel direction of negative pressure hole towards bucket foundation, guaranteed effective processing of foundation soil overconsolidation on the degree of depth of foundation soil and range, above-mentioned steel pipe adopts round steel pipe usually; Below the tube lamina tecti of bucket foundation, lay permeable/gas materials such as geotextiles, on the range of foundation soil, guaranteed the balanced effectively processing of foundation soil overconsolidation.
The present invention adopts submersible pump, negative pressure equipment such as drainage pump and vacuum pump draws water and/or gas work by the negative pressure preformed hole on the bucket foundation tube lamina tecti, permeable/gas materials such as the round steel pipe of the different length by wearing sieve aperture under the tube lamina tecti and geotextiles, hierarchically carry out the precompressed of foundation soil equably, foundation soil precompressed value, the tube external and internal pressure difference that is bucket foundation is (0,-0.6) Mpa, it is precompressed at least 7 days that the negative pressure ground stabilization is handled, be generally 7~15 days or longer, after realizing the overconsolidation of foundation soil, its intensity and stability improve, thereby guarantee that bucket foundation is safe in utilization.
The present invention at first carries out sinking and positioning bucket foundation work, continues to carry out the negative pressure ground stabilization by bucket foundation top cover preformed hole then and handles.The bucket foundation cap base is laid permeable/gas materials such as geotextiles, guarantees the balanced effectively processing of foundation soil overconsolidation.The precompressed value of foundation soil adopts 0.5~0.8 times of bucket foundation injection negative pressure value, and the time is 7~15 days or longer.The present invention itself carries out ground stabilization by the suction utilization basis that negative pressure equipment applies, only need simple device and corresponding electric power systems such as negative pressure equipment, equipment is simple, easy construction, the integrated construction expense is low, can guarantee the stability and the safety of bucket foundation effectively.
The present invention is applicable to the ground stabilization processing in harbour, ocean, water conservancy and the bridge engineering.Adopt the present invention that foundation soil is carried out overconsolidation and handle, can reinforce the shallow foundation ground in efficient balance ground, improve the bearing capacity and the stability of bucket foundation, construction is simple, the duration is short, and economic benefit is obvious.
Although in conjunction with the accompanying drawings the preferred embodiments of the present invention are described above; but the present invention is not limited to the above-mentioned specific embodiment; the above-mentioned specific embodiment only is schematic; be not restrictive; those of ordinary skill in the art is under enlightenment of the present invention; not breaking away under the scope situation that aim of the present invention and claim protect, can also make a lot of forms, these all belong within protection scope of the present invention.

Claims (2)

1. the foundation reinforcement method successively based on bucket foundation negative pressure technology is characterized in that, may further comprise the steps:
(1) on the tube lamina tecti of described bucket foundation, offers the reservation negative pressure hole, below the tube lamina tecti of described bucket foundation, be connected with the steel pipe that many sidewalls have sieve aperture, barrel direction towards described bucket foundation progressively extends by setting layering consolidated subsoil soil depth the length of described many steel pipes from described negative pressure hole, described every steel pipe is parallel with the center line of described bucket foundation, lays geotextiles below the tube lamina tecti of described bucket foundation;
(2) according to the injection negative pressure value of setting, with described sinking and positioning bucket foundation;
(3) draw water and/or gas by reserving negative pressure hole with negative pressure equipment, carry out the negative pressure ground stabilization according to the foundation soil precompressed value of setting and handle, until the foundation soil overconsolidation.
2. the foundation reinforcement method successively based on bucket foundation negative pressure technology according to claim 1 is characterized in that, described foundation soil precompressed value is (0 ,-0.6) Mpa, and the described negative pressure ground stabilization processing time is: at least 7 days.
CN2009103078721A 2009-09-28 2009-09-28 Layer-by-layer foundation consolidating method based on barrel-type foundation negative pressure technology Active CN101666099B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009103078721A CN101666099B (en) 2009-09-28 2009-09-28 Layer-by-layer foundation consolidating method based on barrel-type foundation negative pressure technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009103078721A CN101666099B (en) 2009-09-28 2009-09-28 Layer-by-layer foundation consolidating method based on barrel-type foundation negative pressure technology

Publications (2)

Publication Number Publication Date
CN101666099A true CN101666099A (en) 2010-03-10
CN101666099B CN101666099B (en) 2011-02-16

Family

ID=41802866

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009103078721A Active CN101666099B (en) 2009-09-28 2009-09-28 Layer-by-layer foundation consolidating method based on barrel-type foundation negative pressure technology

Country Status (1)

Country Link
CN (1) CN101666099B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101812838A (en) * 2010-04-27 2010-08-25 天津大学 Foundation reinforcement method based on curing agent and bucket foundation suction technique
CN101824819A (en) * 2010-04-27 2010-09-08 天津大学 Method for stabilizing foundation based on electro-osmosis technique and bucket foundation negative pressure technique
CN102108711A (en) * 2010-11-29 2011-06-29 天津大学 Large-size head cover loaded type shallow foundation component and self-strengthening method thereof
CN102162254A (en) * 2010-07-30 2011-08-24 江苏道达海上风电工程科技有限公司 Device and method for reinforcing foundation by using curing agent in barrel-shaped base
CN102162240A (en) * 2010-07-30 2011-08-24 道达(上海)风电投资有限公司 System and method for realizing self-release of curing agent in cylinder foundation
CN102877484A (en) * 2012-09-11 2013-01-16 天津大学 Steel-concrete composite cylinder-type foundation structure and construction method thereof

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL8802177A (en) * 1988-09-02 1990-04-02 Darya Paye Jetty Co Ltd Hollow column installation method in water course bed - generates vacuum below floor before injecting hardening material
CN100343454C (en) * 2005-09-07 2007-10-17 天津大学 Maritime air float hauling and positioning sinking mounting method for soft-foundation box-cylinder type infrastructure
CN100560873C (en) * 2007-12-21 2009-11-18 天津大学 The self-mounting type bucket base that has oil storage chamber

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101812838A (en) * 2010-04-27 2010-08-25 天津大学 Foundation reinforcement method based on curing agent and bucket foundation suction technique
CN101824819A (en) * 2010-04-27 2010-09-08 天津大学 Method for stabilizing foundation based on electro-osmosis technique and bucket foundation negative pressure technique
CN101812838B (en) * 2010-04-27 2011-08-10 天津大学 Foundation reinforcement method based on curing agent and bucket foundation suction technique
CN102162254A (en) * 2010-07-30 2011-08-24 江苏道达海上风电工程科技有限公司 Device and method for reinforcing foundation by using curing agent in barrel-shaped base
CN102162240A (en) * 2010-07-30 2011-08-24 道达(上海)风电投资有限公司 System and method for realizing self-release of curing agent in cylinder foundation
CN102162240B (en) * 2010-07-30 2015-02-25 江苏道达海上风电工程科技有限公司 System and method for realizing self-release of curing agent in cylinder foundation
CN102162254B (en) * 2010-07-30 2015-09-16 江苏道达海上风电工程科技有限公司 Curing agent foundation reinforced device in bucket foundation and its reinforcement means
CN102108711A (en) * 2010-11-29 2011-06-29 天津大学 Large-size head cover loaded type shallow foundation component and self-strengthening method thereof
CN102877484A (en) * 2012-09-11 2013-01-16 天津大学 Steel-concrete composite cylinder-type foundation structure and construction method thereof
CN102877484B (en) * 2012-09-11 2015-04-22 天津大学 Steel-concrete composite cylinder-type foundation structure and construction method thereof

Also Published As

Publication number Publication date
CN101666099B (en) 2011-02-16

Similar Documents

Publication Publication Date Title
CN101666099B (en) Layer-by-layer foundation consolidating method based on barrel-type foundation negative pressure technology
CN101824819A (en) Method for stabilizing foundation based on electro-osmosis technique and bucket foundation negative pressure technique
CN102330424B (en) Vacuum preloading consolidation method for duplex vacuum tube well of blowing filling soft soil
CN102011391A (en) Reinforcement processing method of soft foundation
CN102127908A (en) Method for quickly reinforcing ultra-soft soil foundation by using bagged sand cushion
CN104652413B (en) A kind of new mudflat sludge Roadbed Treatment
CN101736734A (en) Quick strengthening method of extremely soft sludge
CN101748721A (en) Large-area soft soil foundation duplex negative pressure consolidation processing method
CN102220757A (en) Immediate processing method for drainage solidifying of super soft soil shallow surface space
CN101591918B (en) Foundation reinforcement method based on bucket foundation negative pressure technology
CN203741899U (en) Mixing and sucking type air suction dredge
CN106677158B (en) A kind of blowing-filling sludge superficial layer Quick uniform processing method and structure recently
CN102767174A (en) Dynamic and static water-discharging vibration method
CN104652409A (en) Continuous forced drainage and compaction combined soft foundation treatment technical method
CN106930304A (en) Drift sand base pit dewatering construction method
CN202595725U (en) Water discharge structure for vacuum preloading soft soil foundation treatment
CN106436680B (en) Blowing-filling sludge positive/negative-pressure quick consolidation method based on strength control
CN101812838B (en) Foundation reinforcement method based on curing agent and bucket foundation suction technique
CN105970909B (en) Well point plastic strip vacuum preloading seepage consolidation joint precipitating, pre-pressing dynamic consolidation method
CN105926577B (en) Vacuum preloading seepage consolidation method
CN106013046B (en) Varying stress path well point plastic strip vacuum preloading seepage consolidation hierarchical loading method
CN104831688A (en) Method for cofferdam construction
CN105970910B (en) Well point plastic strip overlay film vacuum pre-pressed joint precipitating, pre-pressing dynamic consolidation method
CN104762951A (en) Construction method of new hydraulic fill muck reclamation by twice straight-line vacuum prepressing treatment
CN205314117U (en) Foundation structure that draw water is carried out with centrifugal pump

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: DAODA (SHANGHAI) WIND POWER INVESTMENT CO., LTD.

Free format text: FORMER OWNER: TIANJIN UNIVERSITY

Effective date: 20110125

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 300072 NO. 72, WEIJIN ROAD, NANKAI DISTRICT, TIANJIN CITY TO: 200129 ROOM 210, NO. 212, LINGHE ROAD, PUDONG NEW DISTRICT, SHANGHAI

TA01 Transfer of patent application right

Effective date of registration: 20110125

Address after: 200129 Shanghai city Pudong New Area Linghe Road No. 212 room 210

Applicant after: Daoda (Shanghai) Wind Power Investment Co., Ltd.

Address before: 300072 Tianjin City, Nankai District Wei Jin Road No. 72

Applicant before: Tianjin University

EE01 Entry into force of recordation of patent licensing contract

Assignee: Jiangsu Daoda Offshore Wind Power Engineering Technology Co., Ltd.

Assignor: Daoda (Shanghai) Wind Power Investment Co., Ltd.

Contract record no.: 2011320000097

Denomination of invention: Layer-by-layer foundation consolidating method based on barrel-type foundation negative pressure technology

Granted publication date: 20110216

License type: Exclusive License

Open date: 20100310

Record date: 20110225

ASS Succession or assignment of patent right

Owner name: JIANGSU DAODA MARINE WIND POWER ENGINEERING TECHNO

Free format text: FORMER OWNER: DAODA (SHANGHAI) WIND POWER INVESTMENT CO., LTD.

Effective date: 20110407

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 200129 ROOM 210, NO. 212, LINGHE ROAD, PUDONG NEW DISTRICT, SHANGHAI TO: 226259 KAIXUAN ROAD, ECONOMIC AND TECHNOLOGICAL DEVELOPMENT ZONE, QIDONG CITY, JIANGSU PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20110407

Address after: 226259 triumph Road, Qidong economic and Technological Development Zone, Jiangsu

Patentee after: Jiangsu Daoda Offshore Wind Power Engineering Technology Co., Ltd.

Address before: 200129 Shanghai city Pudong New Area Linghe Road No. 212 room 210

Patentee before: Daoda (Shanghai) Wind Power Investment Co., Ltd.

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160309

Address after: 226333 No. 8, the Yellow River Road, Binhai Park, Jiangsu, Nantong

Patentee after: Jiangsu Daoda Offshore Wind Power Engineering Technology Co., Ltd.

Address before: 226259 triumph Road, Qidong economic and Technological Development Zone, Jiangsu

Patentee before: Jiangsu Daoda Offshore Wind Power Engineering Technology Co., Ltd.

TR01 Transfer of patent right

Effective date of registration: 20181105

Address after: 226000 Jianghai Road 159, Nantong economic and Technological Development Zone, Jiangsu

Patentee after: Jiangsu Daoda Offshore Wind Power Engineering Technology Co., Ltd.

Address before: 226333 8 the Yellow River Road, Binhai Park, Nantong, Jiangsu

Patentee before: Jiangsu Dolda Wind Power Equipment Technology Co., Ltd

TR01 Transfer of patent right
PP01 Preservation of patent right

Effective date of registration: 20190716

Granted publication date: 20110216

PP01 Preservation of patent right
PD01 Discharge of preservation of patent

Date of cancellation: 20201028

Granted publication date: 20110216

PD01 Discharge of preservation of patent