CN106677158B - A kind of blowing-filling sludge superficial layer Quick uniform processing method and structure recently - Google Patents

A kind of blowing-filling sludge superficial layer Quick uniform processing method and structure recently Download PDF

Info

Publication number
CN106677158B
CN106677158B CN201710117197.0A CN201710117197A CN106677158B CN 106677158 B CN106677158 B CN 106677158B CN 201710117197 A CN201710117197 A CN 201710117197A CN 106677158 B CN106677158 B CN 106677158B
Authority
CN
China
Prior art keywords
drain bar
blowing
vacuum pump
vacuum
days
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710117197.0A
Other languages
Chinese (zh)
Other versions
CN106677158A (en
Inventor
吴价城
周琳
吴安琪
陈杰德
廖雄辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Yidong Engineering Technology Co.,Ltd.
Original Assignee
Hangzhou Yidong Geotechnical Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Yidong Geotechnical Engineering Co Ltd filed Critical Hangzhou Yidong Geotechnical Engineering Co Ltd
Priority to CN201710117197.0A priority Critical patent/CN106677158B/en
Publication of CN106677158A publication Critical patent/CN106677158A/en
Application granted granted Critical
Publication of CN106677158B publication Critical patent/CN106677158B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0053Production methods using suction or vacuum techniques

Abstract

The invention discloses a kind of blowing-filling sludge superficial layer Quick uniform processing method and structures recently, blowing-filling sludge to be processed is located on the base of original place, the following steps are included: blowing-filling sludge upper surface to be processed is successively equipped with lower geotextile layer, upper geotextile layer and two layers of vacuum sealing film, manually it is inserted with vertical long and short drain bar downwards from lower geotextile layer, the vertical long and short drain bar is connected with different vacuum pumps, that is vacuum pump one and vacuum pump two are connected between the upper surface of the vertical short drain bar with horizontal draining board;Start vacuum pump one and vacuum pump two simultaneously first, and stablizes 15 days~20 days reaching 80kpa or more;It is then shut off vacuum pump two, vacuum pump one is closed after vacuum pump one is continued to run 15 days~20 days;Finally starting vacuum pump two stops vacuumizing after running 7 days~10 days, reaches design requirement.The invention avoids the generation of " earth pillar ", be conducive to the ground secondary treatment for avoiding the later period, to reduce time cost and fund input cost again.

Description

A kind of blowing-filling sludge superficial layer Quick uniform processing method and structure recently
Technical field
The present invention relates to the foundation treatment technology fields of the fixed buildings such as port engineering, architectural engineering, highway engineering, especially It is related to a kind of blowing-filling sludge superficial layer Quick uniform processing method and structure recently.
Background technique
In recent years, as coastal strand Park district economy construction investment paces are accelerated, it is becoming tight land resource day, to guarantee warp Help the connecting built, and large area becomes one of the effective way that coastal area solves land resource scarcity, due to China coast The shortage of sand resource, reclaiming fields from the sea generally to be increased using blowing-filling sludge is handled, and due to saturated dredger soft soil high-moisture, is suppressed Contracting, low-permeability, ultralow bearing capacity bad engineering characteristic, not can guarantee subsequent soft base construction big machinery and personnel into ?.
In order to which to saturated dredger soft soil, especially blowing-filling sludge carries out the reinforcing of superficial layer recently, and the country is being invented simultaneously nearly ten years Superficial layer technique of soft soil foundation treatment, vacuum preloading (the directly discharging type vacuum prepressing skill of the flat sand bedding course of free direct-drain water therein are promoted Art) it is even more to be widely used in recent years.But in Guangdong, Fujian, Wenzhou, Ningbo, Qingdao, Lianyun Harbour, Tianjin, Dalian etc. It is found in the practice on ground, with occurring so-called " earth pillar (native stake) " after the technical treatment recently blowing-filling sludge, i.e., approximation is to drain Plate is center axis, the from top to bottom irregular column of diameter not etc., and being reflected in earth's surface is exactly " column (stake) head ".It opens at many scenes Dig experiments have shown that, the height of " earth pillar (native stake) " is generally in 1.5m~1.6m, and in the up big and down small form of falling elliptic cone, upper end is straight Diameter 0.5m~0.6m, such as to drain plate spacing as 0.8m, " earth pillar (native stake) " upper end spacing is 0.2m~0.3m, when weak soil depth For 1.0m, then earth pillar (native stake) depth is 0.4m~0.6m, and when weak soil depth is 1.5m~1.6m, then earth pillar (native stake) depth is 0.8m, soil body range between " earth pillar (native stake) " is that treated weak band, weakness shows as strong, weak alternate with place Inhomogeneities.In 1.5m~1.6m or less drain bar generally without clay attachment phenomenon, weak soil discharging consolidation is substantially uniform, and deep Intensity is higher than superficial part.For blowing-filling sludge place, the purpose of superficial processing is to be formed the working face further constructed, and one As the influence depth of construction equipment be 2m~3m, reach due to this place surface layer caused by " earth pillar (native stake) " phenomenon is inhomogenous Less than processing intent, therefore eliminates directly discharging type vacuum prepressing and form " earth pillar (native stake) " phenomenon with very direct engineering meaning Justice.
For forming " earth pillar (native stake) " above by traditional directly discharging type vacuum prepressing, using the gradual of classification The method of vacuum preloading pressurization or encryption draining plate spacing is eliminated, but there is processing again after using these suggestion and measures The problem of time long (being increased to 90 days~100 days by 45 days~50 days) and processing cost increase.It is therefore desirable to existing The method and structure that silt soft soil superficial layer is handled make improvements.
Summary of the invention
Aiming at the shortcomings in the prior art, the present invention provides a kind of blowing-filling sludge superficial layer Quick uniform processing sides recently Method and structure eliminate the place non-uniform phenomenon that depth is generated by directly discharging type vacuum prepressing within 2m, avoid " earth pillar The generation of (native stake) ", is conducive to the secondary treatment for avoiding the later period, to reduce time cost and fund input cost again.
To achieve the goals above, the technical solution used in the present invention is:
Recently blowing-filling sludge superficial layer Quick uniform processing method, blowing-filling sludge to be processed are located on the base of original place one kind, Include the following steps:
Step 1, blowing-filling sludge upper surface to be processed are equipped with lower geotextile layer, manually plug downwards from lower geotextile layer There are vertically long drain bar and vertical short drain bar, vertically long drain bar and vertical short drain bar are in matrix equidistantly distributed, institute It states in the original place base under the insertion depth to blowing-filling sludge to be processed of vertically long drain bar, the adjacent vertically long drain bar is logical It crosses long slab directly discharging type vacuum pipe to be connected, each long slab directly discharging type vacuum pipe is connected with vacuum pump one, and adjacent is described vertical Straight short drain bar is connected by short slab directly discharging type vacuum pipe, and each short slab directly discharging type vacuum pipe is connected with vacuum pump two, It is connected between the upper surface of the vertical short drain bar with the horizontal draining board of high water-permeability plastics, the horizontal draining board water Tiling is located at the upper surface of vertical short drain bar, is equipped with geotextile layer above the horizontal draining board, in upper geotextile layer Side is equipped with two layers of vacuum sealing film, i.e. upper layer vacuum sealing film and lower layer's vacuum sealing film, buries under lower layer's vacuum sealing film There is vacuum meter, two layers of vacuum sealing film surrounding is excavated with press mold ditch, and press mold ditch is backfilled with silt clay, wherein vertically Long drain bar connects different vacuum pumps with vertical short drain bar, to realize to vertically long drain bar and vertical short drain bar Control is vacuumized, so that the different upper layer weak soil and lower layer's weak soil of moisture content and inserting vertically long drain bar, vertical short drain bar model The weak soil enclosed can be controlled with the vacuum pump different time, preferably to facilitate the operation for carrying out people;
Step 2: starting vacuum pump one and the progress vacuum preloading of vacuum pump two simultaneously, by burying under above-mentioned vacuum sealing film If vacuum meter reach 80kpa or more and stablize 15 days~20 days;
Step 3: closing vacuum pump two, vacuum pump one is continued to run 15 days~20 days, vacuum pump one is then shut off;
Step 4: starting vacuum pump two, the vacuum pump two stops reaching design requirement after running 7 days~10 days, overall The vacuum preloading time is 45 days~50 days, to realize to the equal of blowing-filling sludge upper layer High water cut weak soil (1.5m~2.0m) to be processed Even reinforcing is reinforced.
Vertically long drain bar and vertical short drain bar use the plastic draining board of SPB-B type in the step 1.
Spacing in the step 1 between the long drain bar of neighboring vertical presses 0.8m~0.9m, the long drain bar of neighboring vertical Between spacing be by the spacing between the long drain bar of neighboring vertical by blowing-filling sludge surface layer ultra-soft soil's water content to be processed depending on, When blowing-filling sludge surface layer ultra-soft soil's water content to be processed is greater than 110%, the spacing between the long drain bar of neighboring vertical is 0.8m, when blowing-filling sludge surface layer ultra-soft soil's water content to be processed is lower than 110%, between the long drain bar of neighboring vertical between Away from for 0.9m, the spacing between the long drain bar of neighboring vertical is determined by the concrete condition of moisture content so as to more preferably realize The speed and efficiency of draining, are better able to satisfy the use demand.
Vertical short drain bar is inserted into 1.5m~2.0m in blowing-filling sludge to be processed in the step 1, vertical short drain bar Insertion depth is by blowing-filling sludge surface layer ultra-soft soil's water content, sand content and infiltration coefficient to be processed etc. factor according to specific feelings Depending on condition, specifically when blowing-filling sludge surface layer ultra-soft soil's water content to be processed is greater than 110%, (moisture content is greater than 110% Weak soil to be treated), take 2.0m when sand content is less than 5%, sand content takes 1.5m when being greater than 15%, silt content 5%~ Any number in 1.5m~2.0m is taken when 15%.
High water-permeability plastics c-type drain bar or use can be used in the horizontal draining board of high water-permeability plastics in the step 1 Permeable, gas permeability circular wave chimney filter replacement, the upper surface of vertical short drain bar is laid on by horizontal draining board level, is made Horizontal drainage channel is formed at the blowing-filling sludge surface layer ultra-soft soil top to be processed of vertical short drain bar control, to quickly be discharged soft The Free water on native surface layer, the horizontal draining board can also be used horizontal drain pipe and mutually replace, mode multiplicity, available leeway compared with Greatly.
Recently blowing-filling sludge superficial layer Quick uniform processing structure, blowing-filling sludge to be processed are located on the base of original place one kind, The blowing-filling sludge upper surface to be processed is equipped with lower geotextile layer, is manually inserted with vertically long draining downwards from lower geotextile layer Plate and vertical short drain bar, vertically long drain bar and vertical short drain bar are in matrix equidistantly distributed, and the neighboring vertical is long Spacing between drain bar is 0.8m~0.9m, between the long drain bar of neighboring vertical spacing be by the long drain bar of neighboring vertical it Between spacing by depending on blowing-filling sludge surface layer ultra-soft soil's water content to be processed, when in blowing-filling sludge surface layer to be processed ultra-soft soil When moisture content is greater than 110%, the spacing between the long drain bar of neighboring vertical is 0.8m, when in blowing-filling sludge surface layer to be processed ultra-soft When soil's water content is lower than 110%, the spacing between the long drain bar of neighboring vertical is 0.9m, the insertion of the vertically long drain bar In original place base under depth to blowing-filling sludge to be processed, the vertical short drain bar be inserted into 1.5m in blowing-filling sludge to be processed~ 2.0m, the insertion depth of vertical short drain bar is by blowing-filling sludge surface layer ultra-soft soil's water content to be processed, sand content and infiltration system Number etc. factors as the case may be depending on, specifically blowing-filling sludge surface layer ultra-soft soil's water content to be processed be greater than 110% When (moisture content be greater than 110% be only weak soil to be treated), 2.0m is taken when sand content is less than 5%, when sand content is greater than 15% 1.5m is taken, silt content takes any number in 1.5m~2.0m at 5%~15%, and the adjacent vertically long drain bar passes through length Plate directly discharging type vacuum pipe is connected, and each long slab directly discharging type vacuum pipe is connected with vacuum pump one, and adjacent is described vertical short Drain bar is connected by short slab directly discharging type vacuum pipe, and each short slab directly discharging type vacuum pipe is connected with vacuum pump two, described It is connected between the upper surface of vertical short drain bar with the horizontal draining board of high water-permeability plastics, the horizontal draining board level paving It is located at the upper surface of vertical short drain bar, geotextile layer, paving above upper geotextile layer are equipped with above the horizontal draining board Equipped with two layers of vacuum sealing film, i.e. upper layer vacuum sealing film and lower layer's vacuum sealing film, it is embedded under lower layer's vacuum sealing film true Empty table, two layers of vacuum sealing film surrounding are excavated with press mold ditch, and press mold ditch is backfilled with silt clay.
Vertically long drain bar in the present invention and vertical short drain bar be in matrix equidistantly distributed, particularly every row A square is constituted between vertically long drain bar, then square center position is inserted with vertical short drain bar, thus Constitute one it is quincunx so that the vertically long drain bar on center position vertically short drain bar to periphery is equidistant, have in this way Conducive to blowing-filling sludge superficial layer non-uniform phenomenon is reduced, be conducive to the secondary treatment for avoiding the later period, to reduce time cost With fund input cost again.
Inventive principle
Saturated dredger soft soil is usually to flow mud~mud scum, and surface layer is almost slime water, has particle carefully uneven, High water cut The features such as rate, high-ductility, high-compressibility and extremely low intensity.A large amount of sampling test tables of the blast-filled ground after 1 month~3 months Bright, moisture content highest in 0.5m~2.0m gradually decreases down up to 110%~150%;Vane shear strength (Cu value) It is 0 in 0.5m~2.0m, is gradually increased to 2kpa~5kpa down.This is because blowing-filling sludge early stage falls produced by silt process The phenomenon that.When being handled using directly discharging type vacuum prepressing, since the suction of negative pressure of vacuum produces in the High water cut soil body Raw penetration makes clay migrate and be gradually attached on drain bar outer membrane to drain bar, thickeies over time and constantly It unites and forms " earth pillar " around drain bar, and the Free water except " earth pillar " is prevented to suck in vertical drain bar, make drain bar Between the soil body cannot further discharging consolidation and to eventually lead to basement process uneven.
Many digging in-situs experiments have shown that, the length of " earth pillar " is generally in 1.5m~1.6m, in the up big and down small ellipse that falls Cone shape, upper end diameter 0.5m~0.6m, such as to drain plate spacing as 0.8m, " earth pillar " upper end spacing is 0.2m~0.3m, is blown Filling out earth pillar depth when mud depth is 1.0m is 0.4m~0.6m, and earth pillar is 0.8m when blowing-filling sludge depth is 1.5m~1.6m, Soil body range between " earth pillar " is that treated weak band, place shows as strong, weak alternate inhomogeneities.1.5m~ For 1.6m or less drain bar generally without clay attachment phenomenon, weak soil discharging consolidation is substantially uniform, and deep intensity is higher than superficial part.For For blowing-filling sludge place, the purpose of superficial processing is to form the working face further constructed, the influence of general construction equipment Depth is 2m~3m, this because caused by " earth pillar " phenomenon place surface layer it is inhomogenous, so that processing intent be not achieved.Therefore disappear " earth pillar " phenomenon is formed except directly discharging type vacuum prepressing with very direct engineering significance.In order to eliminate within 2m depth because straight Row's formula vacuum preloading and the place non-uniform phenomenon generated, prevent the generation of " earth pillar ", and the present invention is from lower geotextile layer to servant Work is inserted with vertically long drain bar and vertical short drain bar, according to the combination of vertically long drain bar and vertical short drain bar, strengthens The consolidation of mud and control clay are formed " native on drain bar (vertically long drain bar and vertical short drain bar) top in the 2m of surface layer The Quick uniform of column " is handled.The present invention is using vertically long drain bar and vertical short drain bar, vertically long drain bar and vertically short row The corresponding vacuum pump one of water plate and vacuum pump two control vertically long draining by different vacuum pump one and vacuum pump two The evacuated time of plate and vertical short drain bar, to realize outside the barged-in fill discharging consolidation of different designs depth, emphasis improves table The intensity of mud within layer 2m;Open vacuum pump precompressed → stop vertical short drain bar simultaneously with first vacuum pump one and vacuum pump two Vacuum pump two, the vacuum pump one for only starting vertically long drain bar carry out the vacuum pump one of the vertically long drain bar of vacuum preloading → stop, Only open two vacuum preloading of vacuum pump of vertical short drain bar.Clay can be promoted in the initial rank of vacuum preloading by such step Segment sync drains compression concretion between vertically long drain bar and vertical short drain bar, prevents from generating " earth pillar " on surface layer and makes 2m The soil body in depth is strengthened processing because moisture content is high, intensity is low.Since vertical short drain bar upper surface is permeable with height Property plastics horizontal draining board carry out horizontal connection, the surface layer High water cut mud between vertically long drain bar can be made quickly to be discharged from By water, surface layer clay is reduced or prevented to migrate to vertical displacement hull and be attached to vertically long drain bar and vertical short drain bar outer layer It on filter membrane, prevents " earth pillar " to be formed, improves the uniformity for the treatment of, be conducive to the secondary treatment for avoiding the later period, to reduce Time cost and fund input cost again.
Beneficial effects of the present invention:
1) present invention blowing-filling sludge upper surface to be processed is equipped with lower geotextile layer, manually plugs downwards from lower geotextile layer There are vertically long drain bar and vertical short drain bar, vertically long drain bar and vertical short drain bar are in matrix equidistantly distributed, institute It states in the original place base under the insertion depth to blowing-filling sludge to be processed of vertically long drain bar, the adjacent vertically long drain bar is logical It crosses long slab directly discharging type vacuum pipe to be connected, each long slab directly discharging type vacuum pipe is connected with vacuum pump one, and adjacent is described vertical Straight short drain bar is connected by short slab directly discharging type vacuum pipe, and each short slab directly discharging type vacuum pipe is connected with vacuum pump two, It is connected between the upper surface of the vertical short drain bar with the horizontal draining board of high water-permeability plastics, the horizontal draining board water Tiling is located at the upper surface of vertical short drain bar, is equipped with geotextile layer above the horizontal draining board, in upper geotextile layer Side is equipped with two layers of vacuum sealing film, i.e. upper layer vacuum sealing film and lower layer's vacuum sealing film, buries under lower layer's vacuum sealing film There is vacuum meter, two layers of vacuum sealing film surrounding is excavated with press mold ditch, and press mold ditch is backfilled with silt clay, on the one hand ties Structure is simple, convenient to carry out, on the other hand eliminates the field that depth is generated by directly discharging type vacuum prepressing within 2m so as to realize Ground non-uniform phenomenon avoids the generation of " earth pillar (native stake) ";
2) present invention passes through while starting vacuum pump one and vacuum pump two carries out vacuum preloading, passes through above-mentioned vacuum sealing film Under inbuilt vacuum meter reach 80kpa or more and stablize 15 days~20 days;Vacuum pump two is closed, vacuum pump one is continued to run 15 It~20 days, it is then shut off vacuum pump one;Finally start vacuum pump two, stops after the vacuum pump two is run 7 days~10 days Reach design requirement, the reinforcing of blowing-filling sludge recently can be rapidly completed in 45 days~50 days using the present invention, to reduce Time cost and fund input cost again, are also prevented from surface layer and generate " earth pillar (native stake) " phenomenon, be also beneficial to make high-moisture percentage Mud obtains uniform treatment, is also beneficial to avoid the secondary treatment in later period.
Detailed description of the invention
Fig. 1 is a kind of flow diagram of blowing-filling sludge superficial layer Quick uniform processing method recently of the present invention;
Fig. 2 is a kind of diagrammatic cross-section of blowing-filling sludge superficial layer Quick uniform processing structure recently of the present invention;
Fig. 3 is a kind of top view of blowing-filling sludge superficial layer Quick uniform processing structure recently of the present invention.
Specific embodiment
As shown in Figure 1, a kind of blowing-filling sludge superficial layer Quick uniform processing method recently, blowing-filling sludge to be processed are located at original On ground, include the following steps:
Step 1, blowing-filling sludge upper surface to be processed are equipped with lower geotextile layer, manually plug downwards from lower geotextile layer There are vertically long drain bar and vertical short drain bar, vertically long drain bar and vertical short drain bar are in matrix equidistantly distributed, institute It states vertically long drain bar and vertical short drain bar uses the plastic draining board of SPB-B type, between the long drain bar of neighboring vertical Spacing be 0.8m~0.9m, between the long drain bar of neighboring vertical spacing be by the spacing between the long drain bar of neighboring vertical by Depending on blowing-filling sludge surface layer ultra-soft soil's water content to be processed, it is greater than when in blowing-filling sludge surface layer ultra-soft soil's water content to be processed When 110%, the spacing between the long drain bar of neighboring vertical is 0.8m, when in blowing-filling sludge surface layer ultra-soft soil's water content to be processed When lower than 110%, the spacing between the long drain bar of neighboring vertical is 0.9m, and adjacent hang down is determined by the concrete condition of moisture content Spacing between straight long drain bar is better able to satisfy the use demand, institute so as to more preferably realize the speed and efficiency of draining It states in the original place base under the insertion depth to blowing-filling sludge to be processed of vertically long drain bar, the vertical short drain bar is inserted into wait locate 1.5m~2.0m in blowing-filling sludge is managed, the insertion depth of vertical short drain bar is by the aqueous of blowing-filling sludge surface layer to be processed ultra-soft soil Rate, sand content and infiltration coefficient etc. factor as the case may be depending on, specifically blowing-filling sludge surface layer to be processed ultra-soft soil Moisture content when being greater than 110% (moisture content be greater than 110% be only weak soil to be treated), take 2.0m when sand content is less than 5%, Sand content takes 1.5m when being greater than 15%, silt content takes any number in 1.5m~2.0m at 5%~15%, and adjacent is described vertical Straight long drain bar is connected by long slab directly discharging type vacuum pipe, and each long slab directly discharging type vacuum pipe is connected with vacuum pump one, The adjacent vertical short drain bar is connected by short slab directly discharging type vacuum pipe, each short slab directly discharging type vacuum pipe connection There is vacuum pump two, is connected between the upper surface of the vertical short drain bar with the horizontal draining board of high water-permeability plastics, it is high saturating The horizontal draining board of water-based plastic can be used high water-permeability plastics c-type drain bar or be filtered using permeable, gas permeability circular wave Pipe replacement, the upper surface of vertical short drain bar is laid on by horizontal draining board level, make vertical short drain bar control wait locate It manages blowing-filling sludge surface layer ultra-soft soil top and forms horizontal drainage channel, so that the Free water on weak soil surface layer, the water quickly be discharged Flat drain bar can also be used horizontal drain pipe and mutually replace, and mode multiplicity, available leeway is larger, and the horizontal draining board is horizontal It is laid on the upper surface of vertical short drain bar, geotextile layer, upper geotextile layer top are equipped with above the horizontal draining board It is equipped with two layers of vacuum sealing film, i.e. upper layer vacuum sealing film and lower layer's vacuum sealing film, is embedded under lower layer's vacuum sealing film Vacuum meter, two layers of vacuum sealing film surrounding are excavated with press mold ditch, and press mold ditch is backfilled with silt clay, wherein vertically long Drain bar connects different vacuum pumps with vertical short drain bar, to realize the pumping to vertically long drain bar and vertical short drain bar Vacuum control, so that the different upper layer weak soil and lower layer's weak soil of moisture content and inserting vertically long drain bar, vertical short drain bar range Weak soil can be controlled with the vacuum pump different time, so as to preferably facilitate carry out people operation;
Step 2: starting vacuum pump one and the progress vacuum preloading of vacuum pump two simultaneously, by burying under above-mentioned vacuum sealing film If vacuum meter reach 80kpa or more and stablize 15 days~20 days;
Step 3: closing vacuum pump two, vacuum pump one is continued to run 15 days~20 days, vacuum pump one is then shut off;
Step 4: starting vacuum pump two, the vacuum pump two stops reaching design requirement after running 7 days~10 days, thus Realize that the uniform reinforcing to blowing-filling sludge upper layer High water cut weak soil (1.5m~2.0m) to be processed is reinforced.
As shown in Figures 2 and 3, a kind of blowing-filling sludge superficial layer Quick uniform processing structure recently, blowing-filling sludge 1 to be processed Between original place base 2,1 upper surface of blowing-filling sludge to be processed is equipped with lower geotextile layer 11, from lower geotextile layer 11 to It is manually inserted with vertically long drain bar 12 and vertical short drain bar 13 down, vertically long drain bar 12 and vertical short drain bar 13 are in Matrix equidistantly distributed, the spacing between the long drain bar 12 of neighboring vertical is by 1 surface layer ultra-soft soil of blowing-filling sludge to be processed Depending on moisture content, the spacing between the specific long drain bar 12 of neighboring vertical is 0.8m~0.9m, when in blowing-filling sludge table to be processed It is 0.8m that layer ultra-soft soil's water content, which is greater than spacing when 110% between adjacent vertically long drain bar, is become silted up when in hydraulic reclamation to be processed It is 0.9m that mud surface layer ultra-soft soil's water content, which is lower than spacing when 110% between adjacent vertically long drain bar, passes through moisture content Concrete condition is come the speed and efficiency that determine the spacing between the long drain bar of neighboring vertical so as to more preferably realize draining, more It can satisfy use demand, in the original place base 2 under the insertion depth to blowing-filling sludge 1 to be processed of the vertically long drain bar 12, The vertical short drain bar 13 is inserted into 1.5m~2.0m in blowing-filling sludge 1 to be processed, and the insertion depth of vertical short drain bar 13 is pressed 1 surface layer ultra-soft soil's water content of blowing-filling sludge, sand content and infiltration coefficient to be processed etc. factor as the case may be depending on, tool Body when 1 surface layer ultra-soft soil's water content of blowing-filling sludge to be processed is greater than 110%, (moisture content is greater than 110% and is only and needs to locate The weak soil of reason), 2.0m is taken when sand content is less than 5%, sand content takes 1.5m when being greater than 15%, and silt content takes at 5%~15% Any number in 1.5m~2.0m, the adjacent vertically long drain bar 12 are connected by long slab directly discharging type vacuum pipe 121, often A long slab directly discharging type vacuum pipe 121 is connected with vacuum pump 1, and the adjacent vertical short drain bar 13 is straight by short slab Row's formula vacuum tube 131 is connected, and each short slab directly discharging type vacuum pipe 131 is connected with vacuum pump 2 132, the vertical short row It is connected between the upper surface of water plate 13 with the horizontal draining board 14 of high water-permeability plastics, the horizontal draining board 14 is horizontal to be laid with In the upper surface of vertical short drain bar 13, geotextile layer 16, upper geotextile layer 16 are equipped with above the horizontal draining board 14 Top is equipped with two layers of vacuum sealing film 17, i.e. upper layer vacuum sealing film and lower layer's vacuum sealing film, under lower layer's vacuum sealing film It is embedded with vacuum meter, two layers of vacuum sealing film, 17 surrounding is excavated with press mold ditch 18, and press mold ditch 18 is returned with silt clay It fills out.
Vertically long drain bar 12 and vertical short drain bar 13 in the present invention are in matrix equidistantly distributed, particularly often A square is constituted between the vertically long drain bar 12 of row, then square center position is inserted with vertical short drain bar 13, thus constitute one it is quincunx so that center position vertically short drain bar 13 to periphery vertically long drain bar 12 away from From equal, blowing-filling sludge superficial layer non-uniform phenomenon is advantageously reduced in this way, is conducive to the processing herein for avoiding the later period, to subtract Time cost and fund input cost again are lacked.
Inventive principle
Saturated dredger soft soil is usually to flow mud~mud scum, and surface layer is almost slime water, has particle carefully uneven, High water cut Rate, high-ductility, high-compressibility and extremely low intensity.A large amount of sampling tests of the blast-filled ground after 1 month~3 months show that it contains Water rate highest in 0.5m~2.0m gradually decreases down up to 110%~150%;Vane shear strength (Cu value) 0.5m~ It is 0 in 2.0m, is gradually increased to 2kpa~5kpa down.This is because blowing-filling sludge early stage falls phenomenon caused by silt process. When being handled using directly discharging type vacuum prepressing, the infiltration that is generated in the High water cut soil body due to the suction of negative pressure of vacuum Power makes clay migrate and be gradually attached on drain bar outer membrane to drain bar, thickeies unite in row over time and constantly " earth pillar " is formed around water plate, and the Free water except " earth pillar " is prevented to suck in vertical drain bar, makes the soil between drain bar Body cannot further discharging consolidation and to eventually lead to basement process uneven.
Many digging in-situs experiments have shown that, the length of " earth pillar " is generally in 1.5m~1.6m, in the up big and down small ellipse that falls Cone shape, upper end diameter 0.5m~0.6m, such as to drain plate spacing as 0.8m, " earth pillar " upper end spacing is 0.2m~0.3m, is blown Filling out earth pillar depth when mud depth is 1.0m is 0.4m~0.6m, and earth pillar is 0.8m when blowing-filling sludge depth is 1.5m~1.6m, Soil body range between " earth pillar " is that treated weak band, place shows as strong, weak alternate inhomogeneities.1.5m~ For 1.6m or less drain bar generally without clay attachment phenomenon, weak soil discharging consolidation is substantially uniform, and deep intensity is higher than superficial part.For For blowing-filling sludge place, the purpose of superficial processing is to form the working face further constructed, the influence of general construction equipment Depth is 2m~3m, and processing intent is not achieved due to this place surface layer caused by " earth pillar " phenomenon is inhomogenous.Therefore it eliminates Directly discharging type vacuum prepressing and form " earth pillar " phenomenon with very direct engineering significance.In order to eliminate within 2m depth because in line Formula vacuum preloading and the place non-uniform phenomenon generated, prevent the generation of " earth pillar ", the present invention is artificial downwards from lower geotextile layer It is inserted with vertically long drain bar and vertical short drain bar, according to the combination of vertically long drain bar and vertical short drain bar, strengthens table The consolidation of mud and control clay are in drain bar (vertically long drain bar and vertical short drain bar) top formation " earth pillar " in layer 2m Quick uniform processing.The present invention uses vertically long drain bar and vertical short drain bar, vertically long drain bar and vertical short draining The corresponding vacuum pump one of plate and vacuum pump two control vertically long drain bar by different vacuum pump one and vacuum pump two With the evacuated time of vertical short drain bar, to realize outside the barged-in fill discharging consolidation of different designs depth, emphasis improves surface layer The intensity of mud within 2m;Open vacuum pump precompressed → stop the true of vertical short drain bar simultaneously with first vacuum pump one and vacuum pump two Sky pump two, the vacuum pump one for only starting vertically long drain bar carry out the vacuum pump one of the vertically long drain bar of vacuum preloading → stop, only Open two vacuum preloading of vacuum pump of vertical short drain bar.Clay can be promoted in the vacuum preloading initial stage by such step It is synchronous to drain compression concretion between vertically long drain bar and vertical short drain bar, it prevents from generating " earth pillar " on surface layer and keeps 2m deep The soil body in degree is strengthened processing because moisture content is high, intensity is low.Due to inciting somebody to action vertical short drain bar upper surface with high water-permeability The horizontal draining board (pipe) of plastics carries out horizontal connection, and the surface layer High water cut mud between vertically long drain bar can be made quickly to be discharged Free water reduces or prevents surface layer clay to migrate and be attached to outside vertically long drain bar and vertical short drain bar to vertical displacement hull On layer filter membrane, prevents " earth pillar " from being formed, improve the uniformity for the treatment of, be conducive to the secondary treatment for avoiding the later period, to subtract Time cost and fund input cost again are lacked.
Beneficial effects of the present invention:
1) present invention blowing-filling sludge upper surface to be processed is equipped with lower geotextile layer, manually plugs downwards from lower geotextile layer There are vertically long drain bar and vertical short drain bar, vertically long drain bar and vertical short drain bar are in matrix equidistantly distributed, institute It states in the original place base under the insertion depth to blowing-filling sludge to be processed of vertically long drain bar, the adjacent vertically long drain bar is logical It crosses long slab directly discharging type vacuum pipe to be connected, each long slab directly discharging type vacuum pipe is connected with vacuum pump one, and adjacent is described vertical Straight short drain bar is connected by short slab directly discharging type vacuum pipe, and each short slab directly discharging type vacuum pipe is connected with vacuum pump two, It is connected between the upper surface of the vertical short drain bar with the horizontal draining board of high water-permeability plastics, the horizontal draining board water Tiling is located at the upper surface of vertical short drain bar, is equipped with geotextile layer above the horizontal draining board, in upper geotextile layer Side is equipped with two layers of vacuum sealing film, i.e. upper layer vacuum sealing film and lower layer's vacuum sealing film, buries under lower layer's vacuum sealing film There is vacuum meter, two layers of vacuum sealing film surrounding is excavated with press mold ditch, and press mold ditch is backfilled with silt clay, on the one hand ties Structure is simple, convenient to carry out, on the other hand eliminates the field that depth is generated by directly discharging type vacuum prepressing within 2m so as to realize Ground non-uniform phenomenon avoids the generation of " earth pillar (native stake) ";
2) present invention passes through while starting vacuum pump one and vacuum pump two carries out vacuum preloading, passes through above-mentioned vacuum sealing film Under inbuilt vacuum meter reach 80kpa or more and stablize 15 days~20 days;Vacuum pump two is closed, vacuum pump one is continued to run 15 It~20 days, it is then shut off vacuum pump one;Finally start vacuum pump two, stops after the vacuum pump two is run 7 days~10 days Reach design requirement, the reinforcing of blowing-filling sludge recently can be rapidly completed in 45 days~50 days using the present invention, to reduce Time cost and fund input cost again, are also prevented from surface layer and generate " earth pillar (native stake) " phenomenon, be also beneficial to make high-moisture percentage Mud obtains uniform treatment, is also beneficial to avoid the secondary treatment in later period.

Claims (5)

1. a kind of blowing-filling sludge superficial layer Quick uniform processing method, blowing-filling sludge to be processed recently are located on the base of original place, It is characterized in that including the following steps:
Step 1, blowing-filling sludge upper surface to be processed are equipped with lower geotextile layer, are manually inserted with downwards from lower geotextile layer vertical Straight long drain bar and vertical short drain bar, vertically long drain bar and vertical short drain bar are in matrix equidistantly distributed, described to hang down In original place base under the insertion depth to blowing-filling sludge to be processed of straight long drain bar, the adjacent vertically long drain bar passes through length Plate directly discharging type vacuum pipe is connected, and each long slab directly discharging type vacuum pipe is connected with vacuum pump one, and adjacent is described vertical short Drain bar is connected by short slab directly discharging type vacuum pipe, and each short slab directly discharging type vacuum pipe is connected with vacuum pump two, described It is connected between the upper surface of vertical short drain bar with the horizontal draining board of high water-permeability plastics, the horizontal draining board level paving It is located at the upper surface of vertical short drain bar, geotextile layer, paving above upper geotextile layer are equipped with above the horizontal draining board Equipped with two layers of vacuum sealing film, i.e. upper layer vacuum sealing film and lower layer's vacuum sealing film, it is embedded under lower layer's vacuum sealing film true Empty table, two layers of vacuum sealing film surrounding are excavated with press mold ditch, and press mold ditch is backfilled with silt clay;
Step 2: starting vacuum pump one and the progress vacuum preloading of vacuum pump two simultaneously, by inbuilt under above-mentioned vacuum sealing film Vacuum meter reaches 80kpa or more and stablizes 15 days~20 days;
Step 3: closing vacuum pump two, vacuum pump one is continued to run 15 days~20 days, vacuum pump one is then shut off;
Step 4: starting vacuum pump two, the vacuum pump two stop vacuumizing after running 7 days~10 days, reach design requirement.
2. a kind of blowing-filling sludge superficial layer Quick uniform processing method recently as described in claim 1, which is characterized in that the step Vertically long drain bar and vertical short drain bar use the plastic draining board of SPB-B type in rapid one.
3. a kind of blowing-filling sludge superficial layer Quick uniform processing method recently as described in claim 1, which is characterized in that the step Spacing in rapid one between the long drain bar of neighboring vertical presses 0.8m~0.9m.
4. a kind of blowing-filling sludge superficial layer Quick uniform processing method recently as described in claim 1, which is characterized in that the step Vertical short drain bar is inserted into 1.5m~2.0m in blowing-filling sludge to be processed in rapid one.
5. a kind of blowing-filling sludge superficial layer Quick uniform processing method recently as described in claim 1, which is characterized in that the step High water-permeability plastics c-type drain bar can be used or using permeable, gas permeability in the horizontal draining board of high water-permeability plastics in rapid one The replacement of circular wave chimney filter.
CN201710117197.0A 2017-03-01 2017-03-01 A kind of blowing-filling sludge superficial layer Quick uniform processing method and structure recently Active CN106677158B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710117197.0A CN106677158B (en) 2017-03-01 2017-03-01 A kind of blowing-filling sludge superficial layer Quick uniform processing method and structure recently

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710117197.0A CN106677158B (en) 2017-03-01 2017-03-01 A kind of blowing-filling sludge superficial layer Quick uniform processing method and structure recently

Publications (2)

Publication Number Publication Date
CN106677158A CN106677158A (en) 2017-05-17
CN106677158B true CN106677158B (en) 2019-02-22

Family

ID=58861385

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710117197.0A Active CN106677158B (en) 2017-03-01 2017-03-01 A kind of blowing-filling sludge superficial layer Quick uniform processing method and structure recently

Country Status (1)

Country Link
CN (1) CN106677158B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107663857A (en) * 2017-10-26 2018-02-06 三峡大学 The device and method of mud moisture content is reduced using wick principle
CN109295969A (en) * 2018-08-24 2019-02-01 温州大学 The construction technology of different length drain bar series turbocharging vacuum pre-pressed soft soil foundation
CN113605359B (en) * 2021-08-13 2022-06-21 中冶集团武汉勘察研究院有限公司 Multilayer complex soft soil foundation rapid dewatering consolidation construction structure and construction method
CN114960608B (en) * 2022-03-22 2023-08-22 温州大学 Alternating bidirectional vacuum preloading consolidation method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101906772A (en) * 2010-07-26 2010-12-08 李燕青 Fast consolidation method of blow-filled soft soil for land reclamation
CN203452064U (en) * 2013-07-26 2014-02-26 南京瑞迪建设科技有限公司 Long-and-short combined type drainage system for hydraulic reclamation sludge soft foundation shallow treatment
CN204112306U (en) * 2014-08-06 2015-01-21 中交第二航务工程局有限公司 Recently hydraulic reclamation soft foundation rapid reinforcement process structure
CN105239556A (en) * 2015-10-14 2016-01-13 水利部交通运输部国家能源局南京水利科学研究院 Method for processing super-soft soil foundation through one time of plate insertion sealing and two times of suction vacuumizing water drainage
CN105862712A (en) * 2016-04-21 2016-08-17 中交第三航务工程局有限公司江苏分公司 Method of strengthening non-sand vacuum preloading soft soil foundation
JP2016205027A (en) * 2015-04-24 2016-12-08 東亜建設工業株式会社 Soft ground improvement system, connection member, and soft ground improvement method
CN206512698U (en) * 2017-03-01 2017-09-22 杭州亿东岩土工程有限公司 A kind of layer of blowing-filling sludge superficial recently Quick uniform processing structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101906772A (en) * 2010-07-26 2010-12-08 李燕青 Fast consolidation method of blow-filled soft soil for land reclamation
CN203452064U (en) * 2013-07-26 2014-02-26 南京瑞迪建设科技有限公司 Long-and-short combined type drainage system for hydraulic reclamation sludge soft foundation shallow treatment
CN204112306U (en) * 2014-08-06 2015-01-21 中交第二航务工程局有限公司 Recently hydraulic reclamation soft foundation rapid reinforcement process structure
JP2016205027A (en) * 2015-04-24 2016-12-08 東亜建設工業株式会社 Soft ground improvement system, connection member, and soft ground improvement method
CN105239556A (en) * 2015-10-14 2016-01-13 水利部交通运输部国家能源局南京水利科学研究院 Method for processing super-soft soil foundation through one time of plate insertion sealing and two times of suction vacuumizing water drainage
CN105862712A (en) * 2016-04-21 2016-08-17 中交第三航务工程局有限公司江苏分公司 Method of strengthening non-sand vacuum preloading soft soil foundation
CN206512698U (en) * 2017-03-01 2017-09-22 杭州亿东岩土工程有限公司 A kind of layer of blowing-filling sludge superficial recently Quick uniform processing structure

Also Published As

Publication number Publication date
CN106677158A (en) 2017-05-17

Similar Documents

Publication Publication Date Title
CN106677158B (en) A kind of blowing-filling sludge superficial layer Quick uniform processing method and structure recently
CN102330424B (en) Vacuum preloading consolidation method for duplex vacuum tube well of blowing filling soft soil
CN101845811A (en) Improved 'high vacuum densification' soft foundation treatment method
CN111270663A (en) Positive and negative pressure combined vacuum preloading soft foundation reinforcing system and method
CN114108597A (en) Vacuum drainage grouting method
CN108277794B (en) Vacuum power consolidation composite drainage system for hydraulic filling soft soil foundation
CN205636721U (en) Strain equipment that well vacuum preloading consolidated deep soft soil foundation
CN108104104A (en) A kind of method for fluctuating supercharged vacuum pre-pressing and reinforcing soft earth foundation
CN201785743U (en) Vacuum preloading consolidated soft soil foundation for combining sand wells and water discharging plates
CN206512698U (en) A kind of layer of blowing-filling sludge superficial recently Quick uniform processing structure
CN109505211A (en) Reinforcement of Soft Soil Subgrade method
CN104110024B (en) Drainage consolidation method for reinforcement treatment of hydraulic filling soft clay
CN102912787B (en) Vacuum preloading method for fine sand mats and filter tube sealing
CN108442356B (en) Construction process of vacuum power consolidation composite drainage system for hydraulic filling soft soil foundation
CN205348204U (en) Light well point precipitation system
CN205917685U (en) Integral type well dotted arranges vacuum system
CN105970909B (en) Well point plastic strip vacuum preloading seepage consolidation joint precipitating, pre-pressing dynamic consolidation method
CN106013046B (en) Varying stress path well point plastic strip vacuum preloading seepage consolidation hierarchical loading method
CN105926577B (en) Vacuum preloading seepage consolidation method
CN205917709U (en) Integral type well dotted arranges house steward vacuum system
CN105862714B (en) Soft soil foundation covers water type integral type well point plastic strip vacuum system
CN105862716B (en) Integral type well point plastic strip pipe
CN212001021U (en) Soft soil foundation reinforcing structure in dredger fill area
CN105970910A (en) Well point plastic draining pipe film coating type vacuum preloading and dewatering preloading combined power consolidation method
CN205917683U (en) Soft soil foundation covers water type integral type well dotted arranges vacuum system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 311199 1203-1, Building 1, Hehe Fortune Center, Nanyuan Street, Linping District, Hangzhou, Zhejiang

Patentee after: Zhejiang Yidong Engineering Technology Co.,Ltd.

Address before: 311100 1203, Building 1, Hehe Fortune Center, Nanyuan Street, Yuhang District, Hangzhou, Zhejiang

Patentee before: HANGZHOU YIDONG GEOTECHNICAL ENGINEERING Co.,Ltd.