CN101660419B - 一种特殊地层中盾构进洞的施工方法 - Google Patents

一种特殊地层中盾构进洞的施工方法 Download PDF

Info

Publication number
CN101660419B
CN101660419B CN 200810042120 CN200810042120A CN101660419B CN 101660419 B CN101660419 B CN 101660419B CN 200810042120 CN200810042120 CN 200810042120 CN 200810042120 A CN200810042120 A CN 200810042120A CN 101660419 B CN101660419 B CN 101660419B
Authority
CN
China
Prior art keywords
hole
shield
portal
soil
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200810042120
Other languages
English (en)
Other versions
CN101660419A (zh
Inventor
金福强
王恺华
沈得发
蔡国良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Co Ltd filed Critical Shanghai Mechanized Construction Co Ltd
Priority to CN 200810042120 priority Critical patent/CN101660419B/zh
Publication of CN101660419A publication Critical patent/CN101660419A/zh
Application granted granted Critical
Publication of CN101660419B publication Critical patent/CN101660419B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本发明涉及一种特殊地层中盾构进洞的施工方法。其特征在于有下列步骤组成:盾构进洞前,盾构逐渐接近洞门,向外层的土层中注入双液浆,凿除洞门钢圈内厚的地下连续墙砼,进行地面垂直分段探孔检查,在洞门钢圈上焊接预先准备好的双层弹簧钢板,洞门钢圈外侧安装进洞装置,切割地下连续墙内排钢筋,盾构推进破除砼保护层进洞,对加固土和未加固土体之间的接缝处再次进行双液浆的注入,盾构进洞时双层弹簧钢板和进洞装置紧贴盾构机壳体,盾构机头进入橡胶帘布板后停止推进,向外层的土层中注入单液或双液浆补浆。本发明优点是采用内外结合的措施确保盾构在特殊土层中安全进洞,减少土体流失、控制好地面沉降和有效保护好进洞处地下管线。

Description

一种特殊地层中盾构进洞的施工方法
技术领域
本发明涉及一种特殊地层中盾构进洞的施工方法。
背景技术
随着经济社会的快速发展,上海的轨道交通建设也随之不断深入地发展。新一轮轨道交通建设的高潮迭起必然带来一系列问题,尤其是盾构进洞的问题将逐渐被人们重视。在上海软土地基下,盾构进洞所处土层复杂,多个隧道的进洞埋设于浅层土,土层地质条件差、含水量高、低强度在一定的动力作用下易发生流变,破坏主体结构,使土体的强度突然降低,从而产生漏水涌砂等现象,造成地面的沉降量加大,严重时会造成地面塌陷破坏周围地下管线。在隧道掘进施工时,盾构一般是从一个工作井推进至另一个工作井,盾构机从工作井出发穿过预留洞圈进入土层,即为盾构出洞,再从土层中推进进入另一个预留工作井,即为盾构进洞。如果盾构推进地区土质较差或者含砂率较高,那么盾构进洞时就会发生涌水漏砂现象,严重时盾尾的土体在盾构进洞时会大量涌入工作井,造成地面沉降和塌陷。
为了确保地下已有管线的安全及保持良好的运行状态,通常在盾构进洞前进行管线搬迁和对端头井外侧进行地基加固。由于地基加固所使用的各种施工工艺都有一定的局限性,特别是在特殊地层中表现尤为明显,因此亟待发明既能保证盾构顺利安全地进洞又能降低地面沉降量、减少盾构进洞时土体流失的施工工艺。
发明内容
本发明的目的是解决已有技术中,在特殊地层中盾构进洞时易产生的流水涌砂现象给地面和周围地下管线带来的风险。为减少盾构进洞风险,现提供一种在特殊地层中盾构进洞的施工方法。本发明设计一种特殊地层中盾构进洞的施工方法,其特征在于有下列步骤组成:
(1)盾构进洞前,对盾构轴线进行多次复测,使其符合设计轴线,并进行洞门复核。
(2)盾构逐渐接近洞门,经验算盾构刀尖基本碰到地下连续墙墙壁,这时盾构机头部已停在加固土上,
(3)从位于盾尾后一到二环管片的注浆孔内向外层的土层中注入双液浆,
(4)凿除洞门钢圈内厚650mm~700mm的地下连续墙砼,直至内排钢筋和砼保护层,
(5)进行地面垂直分段探孔检查地基加固土体的情况,
(6)清除洞门凿除的砼和剩余垃圾,在洞门钢圈上焊接预先准备好的双层弹簧钢板,
(7)洞门钢圈外侧安装进洞装置,所述的进洞装置由扇形板和橡胶帘布板构成,并在扇形板上焊螺帽,进行细钢丝串联并用手动葫芦抽紧紧贴管片外弧面上,
(8)上述二道封板完成后,切割地下连续墙内排钢筋,
(9)盾构推进破除砼保护层进洞,盾构机头部已上接收架,盾尾仍留在加固土内,
(10)对加固土和未加固土体之间的接缝处再次进行双液浆的注入,进一步截断后面土体中的水涌向前面的洞口,
(11)盾构进洞时双层弹簧钢板和进洞装置紧贴盾构机壳体,当盾构脱离洞门后两道封板紧贴于管片外部,集中进洞装置收紧,减少土体的流失,
(12)盾构机头进入橡胶帘布板后停止推进,在盾尾钢丝刷后的环管片注浆孔内向外层的土层中注入单液或双液浆补浆。本发明优点是采用内外结合的措施确保盾构在特殊土层中安全进洞,减少土体流失、控制好地面沉降和有效保护好进洞处地下管线。
附图说明
附图1为本发明的双层弹簧钢板示意图,
附图2为本发明的扇形板和橡胶帘布板示意图,
附图3为本发明的盾构在盾构刀尖基本碰到地下连续墙墙壁时的示意图,
附图4为本发明的盾构穿越地下连续墙墙壁时的示意图,
附图5为本发明的盾构进洞后的示意图,
图中说明:图1中,1为弹簧钢板,2为填充的海棉,3为安装底板。图2中,4为帘布橡胶板,5为扇形压板,6为圆环板,7为固定螺栓螺母。图3、4、5中,8为盾构机,9为管片,11为内衬墙,12为地下连续墙砼,13为三重旋喷加固层(水泥掺量500公斤/立方米),14三重管高压旋喷桩加固层(水泥掺量500公斤/立方米),15三重管高压旋喷桩加固层(水泥掺量250公斤/立方米),16洞门钢圈,17双层弹簧钢板,18扇形板和橡胶帘布板。
下面结合附图和实例对本发明作详细说明。
具体实施方式
本发明适合于在区间地质相对较差,如砂质粉土,砂性土等极易产生涌水、流砂等土层处的隧道掘进施工,
首先在盾构进洞前,对盾构轴线进行多次复测,使其符合设计轴线,并进行洞门复核,然后使盾构逐渐接近洞门,经验算盾构刀尖基本碰到地下连续墙墙壁时,盾构机头部已停在加固土上,从盾尾后一到二环管片的注浆孔内向外层的土层中注入双液浆,目的是截断特殊土层中的水涌向前面的洞门,俗称第一道环箍挡水挡环,同时起到控制隧道沉降的作用,开始凿除洞门钢圈内厚650mm~700mm的地下连续墙砼,直至内排钢筋和砼保护层,进行地面垂直分段探孔检查地基加固土体的情况,清除洞门凿除的砼和剩余垃圾,在洞门钢圈上焊接预先准备好的双层弹簧钢板,防止盾构进洞过程中出现涌水涌砂现象,在洞门钢圈外侧安装进洞装置,即扇形板和橡胶帘布板,并在扇形板上焊螺帽,进行细钢丝串联并用5t手动葫芦抽紧紧贴管片外弧面上,上述二道封板完成后,切割地下连续墙内排钢筋,盾构推进破除砼保护层进洞,盾构机头部已上接收架,盾尾仍留在加固土内,盾构进行两次进洞,对加固土和未加固土体之间的接缝处再次进行双液浆的注入,进一步截断后面的土体中的水涌向前面的洞口,俗称第二道环箍挡水挡砂,盾构进洞时双层弹簧钢板和进洞装置紧贴盾构机壳体。当盾构脱离洞门后两道封板紧贴于管片外部,集中进洞装置收紧,减少土体的流失,因为区间地质相对较差,如砂质粉土,砂性土等极易产生涌水、流砂,为保证盾构进洞的安全故采用“二次进洞”,视打开洞门的漏水情况严重与否,盾构机头进入橡胶帘布板后停止推进,在盾尾钢丝刷后进行单液或双液浆补浆。

Claims (1)

1.一种特殊地层中盾构进洞的施工方法,其特征在于有下列步骤组成:
(1)盾构进洞前,对盾构轴线进行多次复测,使其符合设计轴线,并进行洞门复核;
(2)盾构逐渐接近洞门,经验算盾构刀尖基本碰到地下连续墙墙壁,这时盾构机头部已停在加固土上;
(3)从位于盾尾后一到二环管片的注浆孔内向外层的土层中注入双液浆;
(4)凿除洞门钢圈内厚650mm~700mm的地下连续墙砼,直至内排钢筋和砼保护层;
(5)进行地面垂直分段探孔检查地基加固土体的情况;
(6)清除洞门凿除的砼和剩余垃圾,在洞门钢圈上焊接预先准备好的双层弹簧钢板;
(7)洞门钢圈外侧安装进洞装置,所述的进洞装置由扇形板和橡胶帘布板构成,并在扇形板上焊螺帽,进行细钢丝串联并用手动葫芦抽紧紧贴管片外弧面上;
(8)上述双层弹簧钢板及进洞装置安装完成后,切割地下连续墙内排钢筋;
(9)盾构推进破除砼保护层进洞,盾构机头部已上接收架,盾尾仍留在加固土内;
(10)对加固土和未加固土体之间的接缝处再次进行双液浆的注入,进一 步截断后面的土体中的水涌向前面的洞口;
(11)盾构进洞时双层弹簧钢板和进洞装置紧贴盾构机壳体,当盾构脱离洞门后上述双层弹簧钢板及进洞装置紧贴于管片外部,集中进洞装置收紧,减少土体的流失;
(12)盾构机头进入橡胶帘布板后停止推进,在盾尾钢丝刷后的环管片注浆孔内向外层的土层中注入单液或双液浆补浆。 
CN 200810042120 2008-08-27 2008-08-27 一种特殊地层中盾构进洞的施工方法 Expired - Fee Related CN101660419B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200810042120 CN101660419B (zh) 2008-08-27 2008-08-27 一种特殊地层中盾构进洞的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200810042120 CN101660419B (zh) 2008-08-27 2008-08-27 一种特殊地层中盾构进洞的施工方法

Publications (2)

Publication Number Publication Date
CN101660419A CN101660419A (zh) 2010-03-03
CN101660419B true CN101660419B (zh) 2013-05-29

Family

ID=41788659

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200810042120 Expired - Fee Related CN101660419B (zh) 2008-08-27 2008-08-27 一种特殊地层中盾构进洞的施工方法

Country Status (1)

Country Link
CN (1) CN101660419B (zh)

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101975067B (zh) * 2010-10-20 2012-11-21 中铁隧道集团二处有限公司 小断面泥水盾构粉细砂层接收方法
CN102518441B (zh) * 2011-12-14 2014-10-08 中铁十二局集团有限公司 一种溶沟地层盾构进洞施工方法
CN102425423B (zh) * 2011-12-31 2014-08-06 上海市机械施工集团有限公司 一种盾构在穿越管线过程中进洞的施工方法
CN102635361B (zh) * 2012-05-06 2014-04-30 上海城建市政工程(集团)有限公司 一种盾构机进洞及上井的施工方法
CN103527205A (zh) * 2013-09-29 2014-01-22 深圳中海建筑有限公司 盾构水下斜交进洞施工方法
CN104806254A (zh) * 2014-01-26 2015-07-29 宏润建设集团股份有限公司 盾构机到达接收位置的辅助装置及辅助接收施工方法
CN103953350B (zh) * 2014-05-20 2017-02-15 中铁四局集团有限公司 一种流砂地层盾构机洞门破除方法
CN104500082B (zh) * 2014-12-29 2016-09-28 上海市基础工程集团有限公司 矿山法隧道内盾构接收施工方法
CN105201518B (zh) * 2015-10-13 2017-12-15 铁道第三勘察设计院集团有限公司 一种大直径泥水平衡盾构洞内接收解体方法
CN105221158B (zh) * 2015-10-28 2018-09-11 广东广隧建恒机电设备有限公司 盾构进出洞注双液浆施工方法
CN108756908B (zh) * 2018-04-03 2019-10-11 中铁十二局集团有限公司 一种自行破除洞门的盾构设备及出洞方法
CN109403988A (zh) * 2018-12-27 2019-03-01 中铁隧道集团三处有限公司 一种特殊地层盾构到达多次接收的施工工法
CN109779640A (zh) * 2019-02-22 2019-05-21 中铁隧道集团二处有限公司 一种盾构始发洞门破除施工方法
CN109826634B (zh) * 2019-03-08 2020-09-15 中铁十二局集团有限公司 富水液化砂层盾构始发和盾构接收的施工方法
CN110284908B (zh) * 2019-07-26 2021-02-12 济南城建集团有限公司 一种盾构接收井内环向注浆堵漏方法
CN112127950A (zh) * 2020-09-18 2020-12-25 佛山轨道交通设计研究院有限公司 一种盾构区间的洞门结构
CN117968615B (zh) * 2024-04-02 2024-05-28 深圳市厚德检测技术有限公司 一种地下管线检测装置

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1210504A1 (en) * 1999-08-12 2002-06-05 Mbt Holding Ag Tunnel boring method
CN1693666A (zh) * 2005-05-25 2005-11-09 余彬泉 一种管节盾构机施工法
CN1807839A (zh) * 2005-12-27 2006-07-26 上海市隧道工程轨道交通设计研究院 盾构隧道的进洞防水方法
CN1995701A (zh) * 2006-12-30 2007-07-11 广东省基础工程公司 一种盾构机到达隧道洞门的机械破除施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1210504A1 (en) * 1999-08-12 2002-06-05 Mbt Holding Ag Tunnel boring method
CN1693666A (zh) * 2005-05-25 2005-11-09 余彬泉 一种管节盾构机施工法
CN1807839A (zh) * 2005-12-27 2006-07-26 上海市隧道工程轨道交通设计研究院 盾构隧道的进洞防水方法
CN1995701A (zh) * 2006-12-30 2007-07-11 广东省基础工程公司 一种盾构机到达隧道洞门的机械破除施工方法

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
曾华波等.砂层地段土压平衡盾构施工技术探讨.《人民珠江》.2006,(第04期),
特殊地质情况下土压平衡盾构掘进施工技术;韩风险;《铁道建筑技术》;20070820(第04期);第9-12、19页 *
砂层地段土压平衡盾构施工技术探讨;曾华波等;《人民珠江》;20060825(第04期);第22-24、42页 *
韩风险.特殊地质情况下土压平衡盾构掘进施工技术.《铁道建筑技术》.2007,(第04期),

Also Published As

Publication number Publication date
CN101660419A (zh) 2010-03-03

Similar Documents

Publication Publication Date Title
CN101660419B (zh) 一种特殊地层中盾构进洞的施工方法
CN101781993B (zh) 富含承压水软土层盾构进洞施工方法
CN106761785B (zh) 一种地铁隧道盾构始发施工工艺
CN105804758B (zh) 浅覆土大断面小间距的矩形顶管上跨地铁隧道施工方法
CN109881694A (zh) 一种针对基坑基底涌水涌砂进行封堵的施工结构及方法
CN102277898B (zh) 排水管顶进施工方法
CN102352753B (zh) 采用冻结加固和堆土灌水的盾构到达接收方法
CN112012753B (zh) 基于异形延伸钢环的盾构机始发方法
CN106869949A (zh) 一种用钢套筒接收盾构机的方法
CN205154194U (zh) 一种盾构隧道洞门处的止水止沙结构
CN103015519A (zh) 排水管顶管施工
CN109024641A (zh) 三重管双液旋喷用于深基坑堵漏的施工方法
CN105179875A (zh) 一种软弱地层排水管道变形塌陷的非开挖修复方法
CN113638421A (zh) 一种富水砂层中基坑开挖方法
CN103628507B (zh) 顶管穿越海底浅覆土抗浮施工方法
CN105350526A (zh) 钢平台的搭设方法
CN105221158B (zh) 盾构进出洞注双液浆施工方法
CN203175569U (zh) 一种盾构法隧道贯通钢管片洞门防水密封结构
CN114109442B (zh) 隧道岩溶破碎带溜塌半断面帷幕前进式注浆加固处理方法
CN111075457A (zh) 一种复杂地质条件下盾构机尾盾变形的洞内修复方法
CN113373962B (zh) 一种深基坑组合堵漏施工方法
CN102535518B (zh) 一种地下连续墙大接缝的封堵方法
CN103604000B (zh) 江海底钢顶管对接施工方法
CN109026022B (zh) 一种用于漂卵石地层盾构穿越河流的加固结构及加固方法
CN102536270B (zh) 软土地层既有盾构法隧道防渗漏保护方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: SHANGHAI MECHANIZED CONSTRUCTION CO., LTD.

Free format text: FORMER NAME: SHANGHAI CITY MACHINERY CONSTRUCTION CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 201802 Shanghai City, Jiading District Nanxiang Town, Shanghai Yi Road No. 1255

Patentee after: SHANGHAI MECHANIZED CONSTRUCTION GROUP Co.,Ltd.

Address before: 201802 Shanghai City, Jiading District Nanxiang Town, Shanghai Yi Road No. 1255

Patentee before: SHANGHAI MECHANIZED CONSTRUCTION Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130529

Termination date: 20210827

CF01 Termination of patent right due to non-payment of annual fee