With the large-size face brick is the heat insulation system wall body of finish coat Download PDF

Info

Publication number
CN101614048A
CN101614048A CN200910181432A CN200910181432A CN101614048A CN 101614048 A CN101614048 A CN 101614048A CN 200910181432 A CN200910181432 A CN 200910181432A CN 200910181432 A CN200910181432 A CN 200910181432A CN 101614048 A CN101614048 A CN 101614048A
Authority
CN
China
Prior art keywords
wall
face brick
steel frame
basic unit
heat insulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200910181432A
Other languages
Chinese (zh)
Inventor
张建忠
周健
蔡国新
温惠清
钱晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JiangSu Gold Civil Construction Group Co Ltd
Original Assignee
JiangSu Gold Civil Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JiangSu Gold Civil Construction Group Co Ltd filed Critical JiangSu Gold Civil Construction Group Co Ltd
Priority to CN200910181432A priority Critical patent/CN101614048A/en
Publication of CN101614048A publication Critical patent/CN101614048A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Finishing Walls (AREA)

Abstract

The invention discloses a kind of is the heat insulation system wall body of finish coat with the large-size face brick, and it comprises: body of wall basic unit, heat insulating material, steel frame, face brick; Described steel frame is installed in the body of wall basic unit, is pasted with face brick on it; Fill out in the space between face brick, body of wall basic unit and steel frame to irritate heat insulating material is arranged; The advantage of body of wall of the present invention is: improve efficiency of construction, large size ceramic tile facing system and the poly-mephenesin Carbamate exterior wall heat-preserving system of in-situ spraying are united two into one, the material that uses is less, reduce integrated cost, be connected between steel frame and the body of wall basic unit and can not damage, improve the heat insulation effect of body of wall insulation layer.

Description

With the large-size face brick is the heat insulation system wall body of finish coat
Technical field
The present invention relates to a kind of body of wall of building, particularly a kind of is the heat insulation system wall body of finish coat with the large-size face brick.
Background technology
General face brick specification is less when adopting ceramic tile as finish coat in the common building exterior wall heat-preserving system, and stock size is no more than 150*60*8mm, focuses on 15Kg/m certainly 2About, and in the decoration for vertical face of outer wall of some top-grade buildings, adopt large size ceramic tile or stone material usually as finish coat, and its length of side can reach 1000mm, and 30 ~ 50Kg/m certainly weighs 2This big specification ceramic tile need add steel frame as bearing system when constructing outside heat-insulation system, its section as shown in Figure 1, such wall insulation system is often finished by different operation teams and groups even subpackage unit with Ceramic Tiles facing system, efficiency of construction is low, high material consumption, integrated cost height, connector can cause certain destruction to insulation layer between steel frame and the agent structure when passing through heat-insulation system, reduces the heat insulation effect of body of wall.
Summary of the invention
What technical problem to be solved by this invention provided a kind of safe and reliable, economic environmental protection is the heat insulation system wall body of finish coat with the large-size face brick.
For solving the problems of the technologies described above, technical scheme of the present invention is: a kind of is the heat insulation system wall body of finish coat with the large-size face brick, and it comprises: body of wall basic unit, heat insulating material, steel frame, face brick; Described steel frame is installed in the body of wall basic unit, is pasted with face brick on it; In the space that face brick, body of wall basic unit and steel frame constitute, fill out to irritate heat insulating material is arranged.
Described heat insulating material is poly-mephenesin Carbamate heat insulating material.
The advantage of body of wall of the present invention is: improve efficiency of construction, large-size face brick facing system and in-situ spraying polyurethane external wall thermal-insulation system are united two into one, the material that uses is less, reduce integrated cost, be connected between steel frame and the body of wall basic unit and can not damage, improve the heat insulation effect of body of wall insulation layer.
Description of drawings
Fig. 1 is a common building exterior wall heat-preserving system structural representation;
Fig. 2 is the structural representation of body of wall of the present invention.
The specific embodiment
Below in conjunction with specific embodiment the present invention is described in further details.
General face brick specification is less when adopting ceramic tile as finish coat in the common building exterior wall heat-preserving system, and in the decoration for vertical face of outer wall of some top-grade buildings, usually adopt large size ceramic tile or stone material as finish coat, as shown in Figure 1, this large-size face brick that uses outside body of wall 14 need add steel frame 3 as bearing system when constructing outside heat-insulation system 2, the interspersed again connector 5 in centre, heat-insulation system is often finished by different operation teams and groups even subpackage unit with Ceramic Tiles facing system, efficiency of construction is low, high material consumption, the integrated cost height, connector 5 can cause certain destruction to insulation layer between 3 of reinforcing bars and the agent structure when passing through heat-insulation system, reduces heat insulation effect.
The present invention includes body of wall basic unit 1, heat insulating material 2, steel frame 3, face brick 4, steel frame 3 is installed in the body of wall basic unit 1, is pasted with face brick 4 on it; In the space of 3 of face brick 4, body of wall basic unit 1 and steel frames, fill out to irritate heat insulating material 2 is arranged.Large size ceramic tile facing system and in-situ spraying polyurethane external wall thermal-insulation system are united two into one, and the material of use is less, reduces integrated cost, is connected between steel frame and the body of wall basic unit not damage the heat insulation effect of raising body of wall to insulation layer.
The concrete construction sequence that the present invention makes is as follows: in-depth design → unwrapping wire and base treatment → installing and locating part (dividing pre-buried and rear-mounted two kinds) → installation steel frame → bonding applique surface brick → fill out filling polyurethane → surfacing.
1, in-depth design: by consulting architectural design drawing and reconnaissance trip, deepen design, determine the specification, spacing of face brick 4, steel frame 3, keeper etc.
2, unwrapping wire and base treatment: according to designing requirement, on agent structure, eject steel frame 3 and locating piece position line, and body of wall basic unit 1 is repaired, satisfy the requirement of surface finish allowable variation ± 5mm.If what keeper adopted pre-buried mode only need check the keeper dimensional errors.
3, installing and locating part: keeper by the unit of plastic that is used for bridge cut-off, be used to install the steel sheet of steel frame 3 and be used for being fixedly coupled three of parts (being generally bolt) part and form with body of wall, connect by prepared screw-bolt hole, connecting bolt is embedded in the body of wall when main structure construction, guarantees that by regulating unit of plastic thickness the keeper steel sheet is on same vertical plane when keeper is installed.
Conditions permit, keeper should be embedded in the main body when main structure construction, should control the installation site of keeper when pre-buried well, particularly vertical and upright position, keeper and steel plate connecting hole should be preset U type hole.
4, steel frame 3 is installed: steel frame 3 is fixed on the agent structure by keeper, its two ends must be provided with keeper, vertical skeleton spacing L should determine according to face brick 4 specifications when design, make face brick 4 seams all in centre position, vertical skeleton surface, and satisfy the requirement that face brick 4 is resisted horizontal impact loads and wind load, generally about 400mm.This paper selects for use the T Zee bar steel Z as vertical skeleton, and the T Zee bar steel Z utilizes bolt to link to each other with agent structure by keeper.Cross binding welds at vertical skeleton, and the one side surface keeps concordant with vertical skeleton, keeps a determining deviation between opposite side and the body of wall, guarantees can flow freely when polyurethane is filled out filling.The reply welding position carried out preservative treatment after steel frame 3 installed.
5, the bonding applique surface brick 4: face brick 4 can adopt special-purpose adhesive, and structure glue is adopted in suggestion, directly sticks on the steel frame 3, and the Ceramic Tiles intermediate position points is sticking, the not little 6cm of bonding area 2, the both sides seam crossing is completely sticking, prevent to overflow the pollution metope when irritating polyurethane filling out, during stickup from down and on successively carry out.
6, fill out filling polyurethane: poly-mephenesin Carbamate is formed by two kinds of raw material scenes of AB system of mixing, and the A component is polyalcohol (a white material), and the B component is the isocyanates (black material) of import, when system is mixed at the scene, ratio stirs A, B material in bucket according to the rules, and proportional error is controlled within 4%.After treating face brick 4 bonding adhesive setting and hardenings, 4 transverse joint places completely tape at face brick, prevent that polyurethane from overflowing, then with nozzle specially used insertion face brick 4 in the polyurethane coating construction and the space between the body of wall basic unit 1, carry out polyurethane and fill out filling, once fill out filling and be no more than 3 face brick height, and be no more than 1.5m.
7, surfacing: face brick 4 surfaces are found to pollute and should be cleaned immediately, treat to carry out after other operations are finished jointing and handle, and with rag face brick 4 surfaces are wiped clean at last.
The foregoing description does not limit the present invention in any way, and every employing is equal to replaces or technical scheme that the mode of equivalent transformation obtains all drops in protection scope of the present invention.

Claims (2)

1, a kind of is the heat insulation system wall body of finish coat with the large-size face brick, it is characterized in that comprising: body of wall basic unit (1), heat insulating material (2), steel frame (3), face brick (4); Described steel frame (3) is installed in the body of wall basic unit (1), is pasted with face brick (4) on it; In the space that face brick (4), body of wall basic unit (1) and steel frame (3) constitute, be provided with heat insulating material (2).
2, according to claim 1 is the heat insulation system wall body of finish coat with the large-size face brick, it is characterized in that: described heat insulating material (2) is a polyurethane heat insulation material.
CN200910181432A 2009-07-16 2009-07-16 With the large-size face brick is the heat insulation system wall body of finish coat Pending CN101614048A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910181432A CN101614048A (en) 2009-07-16 2009-07-16 With the large-size face brick is the heat insulation system wall body of finish coat

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910181432A CN101614048A (en) 2009-07-16 2009-07-16 With the large-size face brick is the heat insulation system wall body of finish coat

Publications (1)

Publication Number Publication Date
CN101614048A true CN101614048A (en) 2009-12-30

Family

ID=41493918

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910181432A Pending CN101614048A (en) 2009-07-16 2009-07-16 With the large-size face brick is the heat insulation system wall body of finish coat

Country Status (1)

Country Link
CN (1) CN101614048A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110359685A (en) * 2019-07-24 2019-10-22 青岛东建建设有限公司 A kind of polyurethane thermal insulation and decoration integrated board construction technology based on full bonding

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110359685A (en) * 2019-07-24 2019-10-22 青岛东建建设有限公司 A kind of polyurethane thermal insulation and decoration integrated board construction technology based on full bonding

Similar Documents

Publication Publication Date Title
CN102251606B (en) Outer partition wall built by adopting light concrete partition wall boards and construction method thereof
CN108797847A (en) A kind of assembled steel frame wall filled with masonry structural system and its construction method
CN105484391A (en) Construction method for manufacturing heat-preservation waterproof wall through light heat-preservation GRC disassembling-free formworks
HRP20050884A2 (en) Method for bonding bricks to form a brick composite and corresponding brick composite
KR101348379B1 (en) The building wall structure and the constructing method thereof
CN207063247U (en) A kind of enhanced compound external mold plate cast-in-place concrete heat-insulation system
CN110552440B (en) Safe and environment-friendly construction process for high-strength assembled integral sandwich heat-insulating shear wall
CN103806577A (en) Installation method for super-large-area unit type slabstone curtain wall
CN1298947C (en) Wall body heat insulating construction method
CN101666143B (en) Construction method of polyurethane thermal insulation system by taking large-size face brick as finishing coat
CN201447785U (en) Thermal insulation system wall using large-specification facing bricks as facing layers
CN202090619U (en) Combination reinforcing structure of building roofing concrete beam
CN107190889A (en) The integrated wall of steel frame lightweight sandwich boards and its construction method
CN207919816U (en) The compound retaining wall of sandwich
CN211447322U (en) Novel horizontal seam connection structure of assembled shear force wall
CN101614048A (en) With the large-size face brick is the heat insulation system wall body of finish coat
CN204919881U (en) Whole wall of assembly spouting lightweight concrete
CN201250461Y (en) Concrete external wall insulation structure
Walliman et al. Thin-joint glued brickwork: Building in the British context
CN210263608U (en) Light assembled panel with connection structure
CN201250462Y (en) Spraying concrete bearing wall without support template
KR101259097B1 (en) Method of continual concrete pavement and structure produced using the same
CN204343494U (en) A kind of sand aerating inner partition plate installation structure
CN111379337B (en) Secondary structure anti-seepage and anti-leakage construction method
CN210685052U (en) Mounting structure of prefabricated non-bearing wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20091230