CN101591913B - 围护桶套接式吊桩方法和设备 - Google Patents

围护桶套接式吊桩方法和设备 Download PDF

Info

Publication number
CN101591913B
CN101591913B CN2009101365986A CN200910136598A CN101591913B CN 101591913 B CN101591913 B CN 101591913B CN 2009101365986 A CN2009101365986 A CN 2009101365986A CN 200910136598 A CN200910136598 A CN 200910136598A CN 101591913 B CN101591913 B CN 101591913B
Authority
CN
China
Prior art keywords
bucket
guard
pressure
old
stanchion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009101365986A
Other languages
English (en)
Other versions
CN101591913A (zh
Inventor
裘苗全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHONGSHA CONSTRUCTION GROUP CO., LTD.
Original Assignee
裘苗全
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 裘苗全 filed Critical 裘苗全
Priority to CN2009101365986A priority Critical patent/CN101591913B/zh
Publication of CN101591913A publication Critical patent/CN101591913A/zh
Application granted granted Critical
Publication of CN101591913B publication Critical patent/CN101591913B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

一种围护桶套接式吊桩方法和设备,首先将旧柱桩上部的泥土挖去大约2~3米,将一节围护桶套在旧柱桩的周围的泥土内;用振动器振动该旧柱桩,并用高压喷水泵向围护桶内高压喷水,并用搅拌机和搅拌浆搅拌成泥浆;用高压污泥泵将该泥浆排出围护桶;用吊桩葫芦和汽压提升装置提升旧柱桩;当一节围护桶沉入地面一定深度后,在其上面连接另一节围护桶,并重复上述过程,直至将整个旧柱桩拔出地基。本发明的有益效果是:利用围护桶套接式的随其深度的增深而向上套接,高压水泵冲注,旧柱桩振动式,搅拌机浑浆,高压泵抽污泥,压力泵提升技术,实行自动化吊柱桩。具有节省劳力,无噪音污染,施工简便,有利加快工程进度,节省工程造价。

Description

围护桶套接式吊桩方法和设备
技术领域
本发明涉及用于旧柱桩挖掘的吊桩方法和设备,尤其是一种围护桶套接式吊桩方法和设备。
背景技术
目前,公知的在旧柱桩基地上建造新的房屋,已成为设计师和施工者头痛的事情,由于没有专用的吊桩设备,使旧柱挖除比新打桩还要难,常常是桩基公司业务上接与不接的工作难题。因为,它对增加工程造价和延长施工的进度,对双方的经济效益都有直接的影响。
发明内容
本发明的目的就是提供一种围护桶套接式吊桩方法和设备,以解决设计师和施工者头痛的难题,这对于节约工程造价,加快施工进度都具有直接的影响。
本发明的技术方案是:
一种围护桶套接式吊桩方法,其特征在于:首先将旧柱桩上部的泥土挖去大约2~3米,将一节围护桶套在旧柱桩的周围的泥土内;振动该旧柱桩,并向围护桶内高压喷水并进行搅拌成泥浆;将该泥浆排出围护桶;提升旧柱桩;当一节围护桶的沉入地面一定深度后,在其上面连接另一节围护桶,并重复上述过程,直至将整个旧柱桩拔出地基。
一种实施权所述的围护桶套接式吊桩方法所使用的设备,其特征在于:包括振动器、夹柱装置、汽压提升装置、围护桶、高压喷水泵、高压喷头、高压水管、搅拌机、搅拌浆、高压污泥泵、污泥输管、污泥排放管道、提升架和吊桩葫芦,围护桶由多节套接构成,振动器安装在被拆除的旧柱桩的顶端,振动器的顶端与安装在上方的提升架上的吊桩葫芦连接;在所述的旧柱桩的上部固定夹柱装置,在该夹柱装置的两端与围护桶的顶端平台之间分别安装一汽压提升装置;在所述的围护桶内的底部装有搅拌机、搅拌浆、高压喷头和高压污泥泵,搅拌机驱动搅拌浆,高压喷头的进水口通过高压水管与安装在围护桶上部的高压喷水泵的出水口连接;高压污泥泵通过污泥输管与设在围护桶顶端的污泥排放管道连接。
本发明的有益效果是:利用围护桶套接式的随其深度的增深而向上套接,高压水泵冲注,旧柱桩振动式,搅拌机浑浆,高压泵抽污泥,压力泵提升技术,实行自动化吊柱桩。具有节省劳力,无噪喑污染,施工简便,有利加快工程进度,节省工程造价的优点。
附图说明
图1为本发明的设备结构和施工方法的示意图。
附图标记:旧柱桩1、围护桶顶端平台2、振动器3、夹柱装置4、汽压提升装置5、围护桶6、高压喷水泵7、高压喷头8、高压水管9、搅拌机10、搅拌浆11、高压污泥泵12、污泥输管13、污泥排放管道14、提升架15、吊桩葫芦16。
具体实施方式
参见图1,本发明一种围护桶套接式吊桩设备,包括振动器3、夹柱装置4、汽压提升装置5、围护桶6、高压喷水泵7、高压喷头8、高压水管9、搅拌机10、搅拌浆11、高压污泥泵12、污泥输管13、污泥排放管道14、提升架15和吊桩葫芦16,围护桶6由多节套接构成,振动器3安装在被拆除的旧柱桩的顶端,振动器3的顶端与安装在上方的提升架15上的吊桩葫芦16连接;在所述的旧柱桩的上部固定夹柱装置4,在该夹柱装置4的两端与围护桶6的顶端平台2之间分别安装一汽压提升装置5;在所述的围护桶6内的底部装有搅拌机10、搅拌浆11、高压喷头8和高压污泥泵12,搅拌机10驱动搅拌浆11,高压喷头8的进水口通过高压水管9与安装在围护桶6上部的高压喷水泵7的出水口连接;高压污泥泵12通过污泥输管13与设在围护桶6顶端的污泥排放管道14连接。每节围护桶6的两端设有内外径相互配合套接的连接端。
因为有旧柱桩1的地方都污泥地基,本发明的施工方法是:首先,将旧柱桩1上部的泥土挖去大约二、三公尺,将振动器3安上,振动器3开始工作,振动旧柱桩1;而后高压喷水泵7注水,开动搅拌机10驱动搅拌浆11,冲浑污泥,高压污泥泵12将该污泥抽出排放,使旧柱桩1悬动;汽压提升装置5工作,顶起夹柱装置4,使旧柱桩1悬起;然后,利用吊桩葫芦16将旧柱桩1拨起,完成旧柱桩1的拔除任务。当一节围护桶6的沉入地基一定深度后,在其上面连接另一节围护桶,并重复上述过程,直至将整个旧柱桩1拔出地基。

Claims (2)

1.一种围护桶套接式吊桩方法,其特征在于:首先将旧柱桩上部的泥土挖去大约2~3米,将一节围护桶套在旧柱桩的周围的泥土内;振动该旧柱桩,并向围护桶内高压喷水并进行搅拌成泥浆;将该泥浆排出围护桶;提升旧柱桩;当一节围护桶的沉入地面一定深度后,在其上面连接另一节围护桶,并重复上述过程,直至将整个旧柱桩拔出地基。
2.一种实施权利要求1所述的围护桶套接式吊桩方法所使用的设备,其特征在于:包括振动器、夹柱装置、汽压提升装置、围护桶、高压喷水泵、高压喷头、高压水管、搅拌机、搅拌浆、高压污泥泵、污泥输管、污泥排放管道、提升架和吊桩葫芦,围护桶由多节套接构成,振动器安装在被拆除的旧柱桩的顶端,振动器的顶端与安装在上方的提升架上的吊桩葫芦连接;在所述的旧柱桩的上部固定夹柱装置,在该夹柱装置的两端与围护桶的顶端的平台之间分别安装一汽压提升装置;在所述的围护桶内的底部装有搅拌机、搅拌浆、高压喷头和高压污泥泵,搅拌机驱动搅拌浆,高压喷头的进水口通过高压水管与安装在围护桶上部的高压喷水泵的出水口连接;高压污泥泵通过污泥输管与设在围护桶顶端的污泥排放管道连接。
CN2009101365986A 2009-05-08 2009-05-08 围护桶套接式吊桩方法和设备 Expired - Fee Related CN101591913B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009101365986A CN101591913B (zh) 2009-05-08 2009-05-08 围护桶套接式吊桩方法和设备

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009101365986A CN101591913B (zh) 2009-05-08 2009-05-08 围护桶套接式吊桩方法和设备

Publications (2)

Publication Number Publication Date
CN101591913A CN101591913A (zh) 2009-12-02
CN101591913B true CN101591913B (zh) 2010-09-15

Family

ID=41406780

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009101365986A Expired - Fee Related CN101591913B (zh) 2009-05-08 2009-05-08 围护桶套接式吊桩方法和设备

Country Status (1)

Country Link
CN (1) CN101591913B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102108705B (zh) * 2011-03-07 2012-11-21 江苏现代造船技术有限公司 海上风力发电机安装运输船桩腿出泥喷气冲刷装置及方法
CN103266611A (zh) * 2012-10-17 2013-08-28 广东省长大公路工程有限公司 一种水中打桩用的高效减振装置

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3112849A1 (de) * 1981-03-31 1982-10-14 Fritz 5600 Wuppertal Stumpmeier Vorrichtung zum ziehen von im wesentlichen lotrecht stehenden verbauplatten, wie kanaldielen und dgl.
EP1857597A2 (en) * 2006-05-19 2007-11-21 Johannes Cornelis Van Vliet Method and pile-driving device for inserting foundation piles into the ground
CN101130988A (zh) * 2007-08-16 2008-02-27 江苏华东建设基础工程总公司 一种拔桩机及其拔桩的施工方法
CN101148880A (zh) * 2007-11-09 2008-03-26 上海市基础工程公司 预制桩下节桩拔除中的套箍方法
CN101173517A (zh) * 2006-10-31 2008-05-07 上海市基础工程公司 一种拔桩施工方法
CN101196006A (zh) * 2007-12-28 2008-06-11 同济大学 粉喷桩拔桩装置

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3112849A1 (de) * 1981-03-31 1982-10-14 Fritz 5600 Wuppertal Stumpmeier Vorrichtung zum ziehen von im wesentlichen lotrecht stehenden verbauplatten, wie kanaldielen und dgl.
EP1857597A2 (en) * 2006-05-19 2007-11-21 Johannes Cornelis Van Vliet Method and pile-driving device for inserting foundation piles into the ground
CN101173517A (zh) * 2006-10-31 2008-05-07 上海市基础工程公司 一种拔桩施工方法
CN101130988A (zh) * 2007-08-16 2008-02-27 江苏华东建设基础工程总公司 一种拔桩机及其拔桩的施工方法
CN101148880A (zh) * 2007-11-09 2008-03-26 上海市基础工程公司 预制桩下节桩拔除中的套箍方法
CN101196006A (zh) * 2007-12-28 2008-06-11 同济大学 粉喷桩拔桩装置

Also Published As

Publication number Publication date
CN101591913A (zh) 2009-12-02

Similar Documents

Publication Publication Date Title
CN100535261C (zh) 一种用拔桩机进行拔桩的施工方法
CN100591859C (zh) 一种用拔桩机进行拔桩的施工方法
CN203270577U (zh) 设有门板夹的地下桩基拔除装置
CN101591913B (zh) 围护桶套接式吊桩方法和设备
CN104120723B (zh) 冲掏静压沉桩方法
CN201826302U (zh) 用于大直径现浇薄壁混凝土复合桩的成孔器
CN202492847U (zh) 高压水射流套管拔桩工具
CN106351272A (zh) 铣槽机铣轮冲洗装置
CN102926654B (zh) 桩孔环切系统及桩孔环切方法
CN110549480A (zh) 一种蒸压加气混凝土砌块浆料加注装置
JP5872724B1 (ja) 水中の仮締切構造の施工方法
CN109024660A (zh) 桩基拆卸方法及海上基础拆卸方法
CN105586998A (zh) 新型冲吸式抽沙头
CN102345287A (zh) 大直径现浇薄壁混凝土复合桩的施工方法及专用成孔器
CN201411695Y (zh) 围护桶套接式吊桩设备
CN207959196U (zh) 一种长螺旋三轴高压喷搅装置
CN106193080B (zh) 一种沉井下沉装置及其施工方法
JP2003147771A (ja) 杭抜き工法およびその装置、改良地盤ならびに地盤改良工法
KR100829872B1 (ko) 맨홀터파기용 입갱 추진 교체 공법 및 그 장치
CN202323934U (zh) 用于现浇三角形复合地基桩的成孔器
CN209555908U (zh) 一种适用于非饱和粉细砂的振冲装置
CN102605787A (zh) 一种拔除钢板桩时可抑制地基土扰动的装置及其应用方法
JP2009263860A (ja) 中空杭内面の付着物除去装置およびその装置を用いた中空杭内面の付着物除去方法
CN206815338U (zh) 水力插板作业射流装置
JP2004308338A (ja) 既設杭の引抜き工法及び引抜き装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: ZHONGSHA CONSTRUCTION GROUP CO., LTD.

Free format text: FORMER OWNER: QIU MIAOQUAN

Effective date: 20101119

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Qiu Miaoquan

Inventor after: Yang Xuefu

Inventor after: Lou Weimin

Inventor before: Qiu Miaoquan

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: QIU MIAOQUAN TO: QIU MIAOQUAN YANG XUEFU LOU WEIMIN

Free format text: CORRECT: ADDRESS; FROM: 312400 SHENGZHOU INFORMATION PORT, NO. 369, BEIZHI STREET, SHENGZHOU CITY, ZHEJIANG PROVINCE TO: 312050 NO. 41, PINGSHUI TOWN, SHAOXING COUNTY, ZHEJIANG PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20101119

Address after: 312050 No. 41 Ping Town, Shaoxing County, Zhejiang Province

Patentee after: ZHONGSHA CONSTRUCTION GROUP CO., LTD.

Address before: 312400 Shengzhou information port, 369 North straight street, Zhejiang, Shengzhou

Patentee before: Qiu Miaoquan

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100915

Termination date: 20160508

CF01 Termination of patent right due to non-payment of annual fee