CN101591888B - 大桥主塔横梁施工支架预压的方法 - Google Patents
大桥主塔横梁施工支架预压的方法 Download PDFInfo
- Publication number
- CN101591888B CN101591888B CN2008100645951A CN200810064595A CN101591888B CN 101591888 B CN101591888 B CN 101591888B CN 2008100645951 A CN2008100645951 A CN 2008100645951A CN 200810064595 A CN200810064595 A CN 200810064595A CN 101591888 B CN101591888 B CN 101591888B
- Authority
- CN
- China
- Prior art keywords
- bracket
- iron
- support
- main tower
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
大桥主塔横梁施工支架预压的方法,由于大桥主塔上横梁体积大、重量大,上横梁施工时支架易产生塑性变形。大桥主塔横梁施工支架预压的方法,其组成包括:由万能杆件拼装而成的上横梁支架,用20cm的工字钢将所述的支架整体垫起,所述的支架底脚处垫有钢板,所述的钢板与所述的工字钢焊接,在支架两侧工字钢下方设置钢绞线锚具,在支架顶端相应的布置工字钢并与万能杆件连接为一体,再将钢绞线吊起并垂直下落,进行预压,先压支架的一侧立柱,采取4台千斤顶全对称均衡加载的方式,另一侧立柱采用相同的方式进行预压。本发明用于大桥主塔横梁施工中支架的预压。
Description
技术领域:
本发明涉及一种大桥主塔横梁施工支架预压的方法。
背景技术:
由于大桥主塔上横梁体积大、重量大,上横梁施工时支架易产生塑性变形。
发明内容:
本发明的目的是提供一种大桥主塔横梁施工支架预压的方法,可消除支架的塑性变形。
上述的目的通过以下的技术方案实现:
大桥主塔横梁施工支架预压的方法,其组成包括:由万能杆件拼装而成的上横梁支架,用20cm的工字钢将所述的支架整体垫起,所述的支架底脚处垫有钢板,所述的钢板与所述的工字钢焊接,在支架两侧工字钢下方设置钢绞线锚具,在支架顶端相应的布置工字钢并与万能杆件连接为一体,再将钢绞线吊起并垂直下落,进行预压,先压支架的一侧立柱,采取4台千斤顶全对称均衡加载的方式,另一侧立柱采用相同的方式进行预压。
所述的大桥主塔横梁施工支架预压的方法,所述的全对称均衡加载指先对称地张拉4个角的钢绞线,张拉每束3根钢绞线至设计吨位,再张拉中间两束钢绞线至设计吨位,中间两束全部张拉完后,再张拉4个角的剩余钢绞线至设计吨位,加载方式采用分级加载,每级持荷5分钟,达到终点拉力时,开始持荷直至用仪器观察沉降变形不再发生为止。
本发明的有益效果:
1.本发明在上横梁施工之前对支架进行预压,可以消除支架的塑性变形,并能在卸载后测出支架的弹性变形。
2.本发明通过用尺量取钢绞线至顶端杆件和底端杆件的距离,确保两距离相等,可以保证钢绞线的垂直度。
具体实施方式:
实施例1:
大桥主塔横梁施工支架预压的方法,其组成包括:由万能杆件拼装而成的上横梁支架,用20cm的工字钢将所述的支架整体垫起,所述的支架底脚处垫有钢板,所述的钢板与所述的工字钢焊接,在支架两侧工字钢下方设置钢绞线锚具,在支架顶端相应的布置工字钢并与万能杆件连接为一体,再将钢绞线吊起并垂直下落,进行预压,先压支架的一侧立柱,采取4台千斤顶全对称均衡加载的方式,另一侧立柱采用相同的方式进行预压。
所述的大桥主塔横梁施工支架预压的方法,所述的全对称均衡加载指先对称地张拉4个角的钢绞线,张拉每束3根钢绞线至设计吨位,再张拉中间两束钢绞线至设计吨位,中间两束全部张拉完后,再张拉4个角的剩余钢绞线至设计吨位,加载方式采用分级加载,每级持荷5分钟,达到终点拉力时,开始持荷直至用仪器观察沉降变形不再发生为止。
由于上横梁砼分两次浇筑,第一次浇筑75%,即329M3,则预压的荷载取实际荷载的75%即可,实际荷载为1200t,预压荷载1200×75%=900t。在支架的两立柱下,用高20cm的工字钢将钢梁及支架整体垫起。在支架6.0m长方向上,用GB45工字钢垫在立柱下面,工字钢长度为7.5m,工字钢翼板间净距为10cm,在工字钢上方,每个支架底脚处垫有一块30cm×30cm×2cm钢板,钢板与工字钢焊接。在支架两侧,距支架40cm处,工字钢下方设置一个钢绞线锚具,锚具类型为15-9。在支架顶端,支架6.0m长方向,也相应的布置工字钢。工字钢底板钻孔用螺栓将其与万能杆件连接,使其成为一体。在工字钢上方也设置15-9钢绞线锚具。用塔吊将钢绞线吊起,使其自然垂落。从钢绞线底端穿上锚具,用夹片固定,固定后从侧面将钢线穿入两工字钢之间,再用尺量取钢绞线至顶端杆件和底端杆件的距离是否为40cm,确保两距离相等,以保证钢绞线的垂直度。支架的天梁和第五道横梁不与塔柱连接,预压前将第四道横梁最外侧2m单元的竖斜向N5斜杆解除,使之处于几何可变状态。在预压观测时,将全站仪架设在T1点,用来观测支架的竖直变形和稳定性。在预压的全过程塔吊停止作业,同时用经纬仪观测塔吊是否产生倾斜、变形。
每根钢绞线设计吨位为10.7t,伸长量为29.6cm,加载方式采用分级加载,每级加载吨位为85.6t,85.6t,85.6t,42.8t,42.8t,42.8t,42.8t,22t,每级持荷5分钟,达到终点拉力450t时,开始持荷直至用仪器观察沉降变形不再发生为止。观测并记录逐级加载变形数据。卸载后,测出塑性变形压缩量。
卸载时用两个小千斤顶单根卸载,卸载时利用撑脚将千斤顶撑起拉出钢绞线,褪出夹片,回油放束卸载,达到千斤顶油缸行程时,塞紧夹片,重复放束,同时要保持两侧均匀卸载和支架的稳定。观测数据在加载前支架顶面标高、达到设计荷载的稳定标高,卸载后支架顶面标高。
Claims (1)
1.一种大桥主塔横梁施工支架预压的方法,其组成包括:由万能杆件拼装而成的上横梁支架,其特征是:用高20cm的工字钢将所述的支架整体垫起,所述的支架底脚处垫有钢板,所述的钢板与所述的工字钢焊接,在支架两侧工字钢下方设置钢绞线锚具,在支架顶端相应的布置工字钢并与万能杆件连接为一体,再将钢绞线吊起并垂直下落,进行预压,先压支架的一侧立柱,采取4台千斤顶全对称均衡加载的方式,另一侧立柱采用相同的方式进行预压。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008100645951A CN101591888B (zh) | 2008-05-28 | 2008-05-28 | 大桥主塔横梁施工支架预压的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008100645951A CN101591888B (zh) | 2008-05-28 | 2008-05-28 | 大桥主塔横梁施工支架预压的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101591888A CN101591888A (zh) | 2009-12-02 |
CN101591888B true CN101591888B (zh) | 2012-03-07 |
Family
ID=41406756
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2008100645951A Active CN101591888B (zh) | 2008-05-28 | 2008-05-28 | 大桥主塔横梁施工支架预压的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101591888B (zh) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102023092B (zh) * | 2010-10-29 | 2012-02-29 | 中国一冶集团有限公司 | 手推移动式预制构件对桥梁支撑架进行加载试验的方法 |
CN102518049A (zh) * | 2011-12-06 | 2012-06-27 | 中交第四公路工程局有限公司 | 悬浇梁0号块托架反支点预压施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0501730A1 (en) * | 1991-02-28 | 1992-09-02 | Stanley Joseph Grossman | Composite, prestressed structural member and method of forming same |
CN1609342A (zh) * | 2004-11-25 | 2005-04-27 | 中铁大桥局集团有限公司 | 下导梁式架桥机及其架梁方法 |
CN1811070A (zh) * | 2005-01-28 | 2006-08-02 | 上海市第七建筑有限公司 | 下承式钢管混凝土系杆拱桥先拱后梁劲性骨架施工方法 |
CN1900423A (zh) * | 2006-07-10 | 2007-01-24 | 中铁大桥局股份有限公司 | 钢桁梁整体节段架设方法 |
CN101029471A (zh) * | 2007-04-03 | 2007-09-05 | 天津市市政工程设计研究院 | 独塔无背索斜拉桥 |
CN101139819A (zh) * | 2007-08-03 | 2008-03-12 | 中铁一局集团有限公司 | 钢绞线反向支点预压方法 |
-
2008
- 2008-05-28 CN CN2008100645951A patent/CN101591888B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0501730A1 (en) * | 1991-02-28 | 1992-09-02 | Stanley Joseph Grossman | Composite, prestressed structural member and method of forming same |
CN1609342A (zh) * | 2004-11-25 | 2005-04-27 | 中铁大桥局集团有限公司 | 下导梁式架桥机及其架梁方法 |
CN1811070A (zh) * | 2005-01-28 | 2006-08-02 | 上海市第七建筑有限公司 | 下承式钢管混凝土系杆拱桥先拱后梁劲性骨架施工方法 |
CN1900423A (zh) * | 2006-07-10 | 2007-01-24 | 中铁大桥局股份有限公司 | 钢桁梁整体节段架设方法 |
CN101029471A (zh) * | 2007-04-03 | 2007-09-05 | 天津市市政工程设计研究院 | 独塔无背索斜拉桥 |
CN101139819A (zh) * | 2007-08-03 | 2008-03-12 | 中铁一局集团有限公司 | 钢绞线反向支点预压方法 |
Also Published As
Publication number | Publication date |
---|---|
CN101591888A (zh) | 2009-12-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102051858B (zh) | 一种千斤顶加载三角桁架挂篮以及荷载试验施工方法 | |
CN203923924U (zh) | 0号段托架预压装置 | |
CN206607614U (zh) | 一种用于混凝土管桩承载力检测的反力装置 | |
CN102162774A (zh) | 钢结构分配梁式双线整孔箱梁静载试验装置及其施工方法 | |
CN110398429B (zh) | 一种考虑施工过程影响的钢管混凝土抗震性能试验装置及试验方法 | |
CN101537976A (zh) | 双塔桅巨型自升降起重设备及其跟携吊装方法 | |
CN201106155Y (zh) | 斜拉索辅助全悬臂架设钢桁梁装置 | |
CN201376848Y (zh) | 双塔桅巨型自升降起重设备 | |
CN105259043A (zh) | 批量钢管混凝土自平衡加载装置 | |
CN105714692A (zh) | 一种悬臂浇筑梁钢管混凝土临时固结系统 | |
CN111778834A (zh) | 一种大跨度桥梁边墩、辅助墩的抗拉装置 | |
CN101591888B (zh) | 大桥主塔横梁施工支架预压的方法 | |
CN201310102Y (zh) | 静载试验转换梁 | |
CN202787086U (zh) | 悬臂浇筑施工挂篮预压装置 | |
CN214695184U (zh) | 一种用于双薄壁墩梁托支架的预压系统 | |
CN201945464U (zh) | 钢结构分配梁式双线整孔箱梁静载试验装置 | |
CN201110804Y (zh) | 多功能试验架 | |
CN205676784U (zh) | 托架反拉加载预压装置 | |
CN111794227A (zh) | 一种抗拔抱箍式锚杆静压桩装置及施工方法 | |
CN201695337U (zh) | 悬灌连续梁边墩直线段托架 | |
CN217688351U (zh) | 一种框架梁支座受弯性能试验构造及装置 | |
CN213951948U (zh) | 一种装配式牛腿的预压试验结构 | |
CN201901847U (zh) | 一种千斤顶加载三角桁架挂篮 | |
CN214459535U (zh) | 斜拉桥不对称悬臂梁的施工系统 | |
CN114855639A (zh) | 高空索塔横梁施工托架预压组件 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |