CN101555693A - Reinforced core-enveloped structural slope protector - Google Patents
Reinforced core-enveloped structural slope protector Download PDFInfo
- Publication number
- CN101555693A CN101555693A CNA2009101319263A CN200910131926A CN101555693A CN 101555693 A CN101555693 A CN 101555693A CN A2009101319263 A CNA2009101319263 A CN A2009101319263A CN 200910131926 A CN200910131926 A CN 200910131926A CN 101555693 A CN101555693 A CN 101555693A
- Authority
- CN
- China
- Prior art keywords
- bag
- reinforcement material
- reinforced core
- filler
- geotechnological
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
The invention relates to a reinforced core-enveloped structural slope protector, which mainly comprises a unidirectional geotechnological grid, fillings, an anti-aging plant-growing geotextile bag and connecting pieces. The slope protector is made from the fillings reinforced with the unidirectional geotechnological grid. The structural slope protector can obtain the raw materials from local resources and can be constructed with the earth material on the construction site, thus significantly saving energy; the reinforced materials of the structural slope protector has good durability; the structural slope protector also has the advantages of convenient construction, lower construction cost and the like.
Description
Technical field
The present invention relates to a kind of side slope protection body, relate in particular to a kind of geo-grid sheet reinforcement bank protection body.
Background technology
Existing reinforcement bank protection body mainly by geotechnological reinforcement material 1, plant immature soil worker bag 2, pitman 4, filler 6 four parts and form, the geotechnological reinforcement material 1 of dispersed placement in filler 6 with plant immature soil worker bag 2, the conventional reinforcement body of filler 6 common compositions.Its cardinal principle is to adopt reinforcement material that soil stabilization in the unstable slip circle envelope is handled.Existing reinforced slope and retaining wall technology have the following disadvantages: because the reinforcement body of design need pass the unstable slip circle envelope of inside configuration certain-length, the reinforcement length that requires is relatively large, and when the construction operation face has in limited time, need excavate the scope of operation at filler backfill position earlier to stay enough muscle materials to lay, just can construct then, will increase the excavated volume and the amount of fill of engineering like this, increase the difficulty of construction, cause project total cost higher.In that to run into slope protection works higher, during the narrow and small more situation of the scope of operation, use conventional reinforced structure and will make construction costs very high, constructional difficulties, even can't construct owing to can't satisfy the structural entity stability requirement.
Summary of the invention
Technical problem to be solved by this invention has provided a kind of reinforced core-enveloped structural slope protector, at the slope protection works height, and under the narrow and small situation of the scope of operation, but safe construction still.
Reinforced core-enveloped structural slope protector provided by the invention, comprise geotechnological reinforcement material 1, plant immature soil worker bag 2, pitman 4, filler 6, geotechnique's reinforcement material 1 and filler 6 alternately pressings, following one deck geotechnique reinforcement material 1 is connected tension with geotechnological reinforcement material 1 by pitman 4 with last layer, the described immature soil worker bag 2 of planting is wrapped between the adjacent up and down two-layer geotechnological reinforcement material 1 of described reinforced core-enveloped structural slope protector free face, be wrapped in geotechnique bag 3 adjacent counter between the two-layer geotechnological reinforcement material 1 up and down of described reinforced core-enveloped structural slope protector structure behind, and adjacent geotechnological reinforcement material 1 linked together by junction button 5.
As improvement of the present invention, described reinforced core-enveloped structural slope protector structure is provided with drainage network 7 behind and between the sloping body, and drainage network 7 is a kind of adrainage material.
As improvement of the present invention, described geotechnological reinforcement material 1 is mesh type or flaky material.
As improvement of the present invention, the described sack that definite size arranged of immature soil worker bag 2 of planting for adopting the durability synthetic materials to make, interior dress is ploughed and is planted soil and grass-seed; Described geotechnique's bag 3 woven bags of making for common synthetic materials, the existing earth material in filling job site.
As improvement of the present invention, filler 6 is the filler that carries out backfill reinforcement bag core structure according to the parameters selection of reinforcement bag core structure designing requirement, need be by backfilling of earthwork requirement compacting during backfill.
Reinforced core-enveloped structural slope protector of the present invention has utilized the soil principle that its supporting capacity improves under lateral deformation is tied condition, plant by geotechnological reinforcement material 1 and both sides that the soil body retrains in 3 pairs of bags of immature soil worker bag 2 and geotechnique's bag core structure bodies, make the dispersion soil body form the robust structure unit.When each firm block construction vertically is superimposed, formed the gravity retaining structure of a flexibility---slope sticking type reinforced soil retaining wall.The slope sticking type reinforced soil retaining wall can apply active force in protected side slope, improves the stability against sliding of side slope.Lay form because the present invention has changed reinforcement material, reduced the design length of reinforcement body.The present invention and existing conventional reinforced structure major different are the form that bank protection body structure behind anti-package is wrapped up in, thereby cut off unstable curved stroke.The bank protection body of this form of structure and concrete and stone masonry gravity retaining wall mechanics principle are similar, but changed the material of main part that is used for body of wall, the main body filler of this structure is earth material and reinforcement geotechnique material, and then the main body filler of two class formation form barricades is concrete and stone.This reinforcement bag heart bank protection body can freely be selected between 0 °~90 °.
Compare with existing reinforcement technology, the present invention has the low characteristics of engineering comprehensive cost, when the reinforcement technology construction of adopting routine, runs into when needing the former side slope of excavation to carry out the cloth muscle, substitutes the advantage that also has easy construction concurrently with the present invention.Now illustrate:
High 2 meters to build, long 100 meters escape canal is an example, and selecting the material parameter of banketing for use is γ=14kn/m
3, φ=10 °, levee crown evenly distributed load are got 10kpa, calculate the used operating expenses that adopts earth structure and reinforcement bag core structure respectively, carry out the construction cost expense at last relatively.
As calculated:
1. according to conventional reinforced structure way, then needing reinforcement length is 5.8 meters, and its every linear meter(lin.m.) Master Cost is as follows:
Sequence number | Title material and specification | Unit | | Unit price | |
1 | Unidirectional geo-grid | m 2 | 30 | 10 | |
2 | Plant immature soil worker bag | Bar | 20 | 18.00 | |
3 | Pitman | |
3 | 15 | |
4 | Banket | m 3 | 11.6 | 15 | |
Subtotal | Unit | 879 |
2. press reinforcement bag core structure way, the every linear meter(lin.m.) Master Cost of bank protection body is as follows:
Sequence number | Title material and specification | Unit | | Unit price | |
1 | Unidirectional geo-grid | m 2 | 13 | 10 | |
2 | Plant immature soil worker bag | Bar | 20 | 18.00 | |
3 | Pitman | |
3 | 15 | |
4 | Geotechnique's bag | Bar | 20 | 1 | |
5 | Junction button | Individual | 5 | 0.85 | |
6 | | m | 3 | 2 | 15 |
7 | Connection cord | m | 8 | 0.45 |
Subtotal | Unit | 592.85 |
Both compare: 592.85/879=67.45%.
By above comparative result as can be seen, adopt the saving of bag core structure engineering direct cost to reach 1/3, this does not also comprise because reduce the expense that amount of excavation is saved of opening.
Description of drawings
Fig. 1 is used for whole structure figure on the channel bank protection for the technology of the present invention;
Fig. 2 is the drawing in side sectional elevation of vertical type reinforcement bag core structure bank protection;
Fig. 3 is the drawing in side sectional elevation of abrupt slope formula reinforcement bag core structure bank protection;
Fig. 4 is the connection layout of pitman with geo-grid;
Fig. 5 is the junction button of hook shape;
Fig. 6 is the connection diagram that pitman, junction button are followed geo-grid;
1 is geotechnological reinforcement material among the figure, and 2 for planting immature soil worker bag, and 3 is geotechnique's bag, and 4 is pitman, and 5 is junction button, and 6 is filler, and 7 is the drainage network.
The specific embodiment
Extremely shown in Figure 6 as Fig. 1, reinforced core-enveloped structural slope protector of the present invention, comprise geotechnological reinforcement material 1, plant immature soil worker bag 2, pitman 4, filler 6, geotechnique's reinforcement material 1 and filler 6 alternately pressings, following one deck geotechnique reinforcement material 1 is connected tension with geotechnological reinforcement material 1 by pitman 4 with last layer, the described immature soil worker bag 2 of planting is wrapped between the adjacent up and down two-layer geotechnological reinforcement material 1 of described reinforced core-enveloped structural slope protector free face, be wrapped in geotechnique bag 3 adjacent counter between the two-layer geotechnological reinforcement material 1 up and down of described reinforced core-enveloped structural slope protector structure behind, and adjacent geotechnological reinforcement material 1 linked together by junction button 5.The structure installation steps are as follows:
1, plant the preparation of immature soil worker bag 2: the filler of planting in the immature soil worker bag 2 should adopt the matrix soil that is mixed with grass seeds, and wherein plain native content should be not less than 80% of filler.And should fill up fully, carry out envelope with special-purpose band.Single plant immature soil worker packed fill out back facade projection area should be less than 0.10m
2Whenever stack one deck and plant immature soil worker bag, should make the immature soil worker bag compactness of planting of filling be not less than 70% by marking time, ram modes such as pier or other static pressure.
2, clean out by the design elevation ground grading, and with domatic surface dust.
3, outside domatic, set up interim mould bases, guarantee domatic neat by design grade.
4, press design length cutting geotechnique reinforcement material 1, lay bottom geotechnique reinforcement material 1.
5, pile up at structure free face leading portion and plant immature soil worker bag, the free end by geotechnological reinforcement material 1 is tensioned to it smooth-going then, it is fixed with timber wedge, and compress with geotechnique's bag 3, and structure is inboard reserves turn-up section and along domatic bending in pasting upwards.
6,,, layered backfill, roll until next geotechnological reinforcement material 1 at shop, bag core structure center filler 6 according to the filler requirement of design.
7, compacting machinary adopts hand steered small vibrating rolling machine or artificial compacting filling soil.
8, cut out down one deck geotechnique reinforcement material 1, and lay the position in accordance with regulations.As shown in Figure 4, the front end that this layer reinforcement material and lower floor's reinforcement material is bent towards with pitman 4 interts and links together, back segment usefulness junction button 5 two-layer geotechnological reinforcement material 1 up and down closely connects, method of attachment is: hook geotechnological reinforcement material 1 with a junction button 5, hook lower floor's 1, two junction button of geotechnique's reinforcement material with another junction button and connect with connection cord, tighten up a rope then, fasten, thereby make geotechnological reinforcement material 1 tensioning of upper and lower layer, make structure be tending towards firm.
9, repeat above step until finishing the entire infrastructure construction that adheres to specification.
10, top layer geotechnique reinforcement material 1 should be pressed and is embedded in 20cm under the face of banketing, and the restraint forces that guaranteeing bankets can provide enough is with the geotechnique of anchoring permanently reinforcement material 1.
Embodiment 2 bankets when expecting for clay, and band drain need be set
Extremely shown in Figure 6 as Fig. 1, reinforced core-enveloped structural slope protector of the present invention, comprise geotechnological reinforcement material 1, plant immature soil worker bag 2, pitman 4, filler 6, geotechnique's reinforcement material 1 and filler 6 alternately pressings, following one deck geotechnique reinforcement material 1 is connected tension with geotechnological reinforcement material 1 by pitman 4 with last layer, the described immature soil worker bag 2 of planting is wrapped between the adjacent up and down two-layer geotechnological reinforcement material 1 of described reinforced core-enveloped structural slope protector free face, be wrapped in geotechnique bag 3 adjacent counter between the two-layer geotechnological reinforcement material 1 up and down of described reinforced core-enveloped structural slope protector structure behind, and adjacent geotechnological reinforcement material 1 linked together by junction button 5.The structure installation steps are as follows:
1, plant the filler that the preparation of immature soil worker bag 2 plants in the immature soil worker bag 2 and should adopt the matrix soil that is mixed with grass seeds, wherein plain native content should be not less than 80% of filler.And should fill up fully, carry out envelope with special-purpose band.Single plant immature soil worker packed fill out back facade projection area should be less than 0.10m
2Whenever stack one deck and plant immature soil worker bag, should make the immature soil worker bag compactness of planting of filling be not less than 70% by marking time, ram modes such as pier or other static pressure.
2, clean out by the design elevation ground grading, and with domatic surface dust.
3, on domatic, lay the drainage network.
4, outside domatic, set up interim mould bases, guarantee domatic neat by design grade.
5, press design length cutting geotechnique reinforcement material 1, lay bottom geotechnique reinforcement material 1.
6, pile up at structure free face leading portion and plant immature soil worker bag, the free end by geotechnological reinforcement material 1 is tensioned to it smooth-going then, it is fixed with timber wedge, and compress with geotechnique's bag, and structure is inboard reserves turn-up section and along domatic bending in pasting upwards.
7,,, layered backfill, roll until next geotechnological reinforcement material 1 at shop, bag core structure center filler 6 according to the filler requirement of design.
8, compacting machinary adopts hand steered small vibrating rolling machine or artificial compacting filling soil.
9, cut out down one deck geotechnique reinforcement material 1, and lay the position in accordance with regulations.As shown in Figure 4, the front end that this layer reinforcement material and lower floor's reinforcement material is bent towards with pitman 4 interts and links together, back segment usefulness junction button 5 two-layer geotechnological reinforcement material 1 up and down closely connects, method of attachment is: hook geotechnological reinforcement material 1 with a junction button 5, hook lower floor's 1, two junction button of geotechnique's reinforcement material with another junction button and connect with connection cord, tighten up a rope then, fasten, thereby make geotechnological reinforcement material 1 tensioning of upper and lower layer, make structure be tending towards firm.
10, repeat above step until finishing the entire infrastructure construction that adheres to specification.
11, top layer geotechnique reinforcement material 1 should be pressed and is embedded in 20cm under the face of banketing, and the restraint forces that guaranteeing bankets can provide enough is with the geotechnique of anchoring permanently reinforcement material 1.
Claims (5)
1. reinforced core-enveloped structural slope protector, comprise geotechnological reinforcement material (1), plant immature soil worker bag (2), pitman (4), filler (6), geotechnique's reinforcement material (1) and alternately pressing of filler (6), following one deck geotechnique's reinforcement material (1) is connected tension with geotechnological reinforcement material (1) by pitman (4) with last layer, the described immature soil worker bag (2) of planting is wrapped between the adjacent up and down two-layer geotechnological reinforcement material (1) of described reinforced core-enveloped structural slope protector free face, it is characterized in that: be wrapped in geotechnique bag (3) adjacent counter between the two-layer geotechnological reinforcement material (1) up and down of described reinforced core-enveloped structural slope protector structure behind, and adjacent geotechnological reinforcement material (1) linked together by junction button (5).
2. according to the described reinforced core-enveloped structural slope protector of claim 1, it is characterized in that: when filler (6) was cohesive soil, described reinforced core-enveloped structural slope protector structure was provided with drainage network (7) behind and between the sloping body, and drainage network (7) are a kind of adrainage material.
3. according to the described reinforced core-enveloped structural slope protector of claim 1, it is characterized in that: described geotechnological reinforcement material (1) is mesh type or flaky material.
4. according to claim 1,2 or 3 described any reinforced core-enveloped structural slope protectors, it is characterized in that: the described sack that definite size arranged of immature soil worker bag (2) of planting for adopting the durability synthetic materials to make, interior dress is ploughed and is planted soil and grass-seed; The woven bag that described geotechnique's bag (3) is made for common synthetic materials, the existing earth material in filling job site.
5. according to claim 1,2 or 3 described any reinforced core-enveloped structural slope protectors, it is characterized in that: filler (6) is the filler that carries out backfill reinforcement bag core structure according to the parameters selection of reinforcement bag core structure designing requirement, need be during backfill by backfilling of earthwork requirement compacting, the free face compacting has specific (special) requirements.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA2009101319263A CN101555693A (en) | 2009-03-27 | 2009-03-27 | Reinforced core-enveloped structural slope protector |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA2009101319263A CN101555693A (en) | 2009-03-27 | 2009-03-27 | Reinforced core-enveloped structural slope protector |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101555693A true CN101555693A (en) | 2009-10-14 |
Family
ID=41173955
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNA2009101319263A Pending CN101555693A (en) | 2009-03-27 | 2009-03-27 | Reinforced core-enveloped structural slope protector |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101555693A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101851928A (en) * | 2010-06-08 | 2010-10-06 | 中国科学院地质与地球物理研究所 | Method for improving and protecting collapsible loess slope project |
CN101851894A (en) * | 2010-07-01 | 2010-10-06 | 中国科学院地质与地球物理研究所 | Protection method for improving salt expansion or dissolution sink of salty soil |
CN102561368A (en) * | 2012-01-09 | 2012-07-11 | 长沙理工大学 | Flexible supporting construction of pre-compaction reinforced soil piece |
CN104831747A (en) * | 2015-04-16 | 2015-08-12 | 长沙理工大学 | Concrete mould bag retaining wall |
CN105735327A (en) * | 2016-04-13 | 2016-07-06 | 山东省水利科学研究院 | Riverway or construction cofferdam protection slope and construction method |
CN106223348A (en) * | 2016-07-18 | 2016-12-14 | 河海大学 | A kind of microorganism GSZ associating reinforcement method |
CN107354911A (en) * | 2017-08-31 | 2017-11-17 | 郑州大学 | A kind of ecological flexible geogrid reinforcement Wharf Construction method |
CN114541325A (en) * | 2022-02-21 | 2022-05-27 | 福建江隆水利水电工程有限公司 | Hydraulic engineering ecological slope protection and construction method thereof |
-
2009
- 2009-03-27 CN CNA2009101319263A patent/CN101555693A/en active Pending
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101851928A (en) * | 2010-06-08 | 2010-10-06 | 中国科学院地质与地球物理研究所 | Method for improving and protecting collapsible loess slope project |
CN101851894A (en) * | 2010-07-01 | 2010-10-06 | 中国科学院地质与地球物理研究所 | Protection method for improving salt expansion or dissolution sink of salty soil |
CN101851894B (en) * | 2010-07-01 | 2012-07-25 | 中国科学院地质与地球物理研究所 | Protection method for improving salt expansion or dissolution sink of salty soil |
CN102561368A (en) * | 2012-01-09 | 2012-07-11 | 长沙理工大学 | Flexible supporting construction of pre-compaction reinforced soil piece |
CN102561368B (en) * | 2012-01-09 | 2014-08-06 | 长沙理工大学 | Flexible supporting construction of pre-compaction reinforced soil piece |
CN104831747B (en) * | 2015-04-16 | 2017-06-06 | 长沙理工大学 | A kind of concrete film bag retaining wall |
CN104831747A (en) * | 2015-04-16 | 2015-08-12 | 长沙理工大学 | Concrete mould bag retaining wall |
CN105735327A (en) * | 2016-04-13 | 2016-07-06 | 山东省水利科学研究院 | Riverway or construction cofferdam protection slope and construction method |
CN105735327B (en) * | 2016-04-13 | 2017-09-15 | 山东省水利科学研究院 | A kind of construction method of river course or construction cofferdam bank protection |
CN106223348A (en) * | 2016-07-18 | 2016-12-14 | 河海大学 | A kind of microorganism GSZ associating reinforcement method |
CN106223348B (en) * | 2016-07-18 | 2018-10-02 | 河海大学 | A kind of microorganism-TGXG joint reinforcement method |
CN107354911A (en) * | 2017-08-31 | 2017-11-17 | 郑州大学 | A kind of ecological flexible geogrid reinforcement Wharf Construction method |
CN107354911B (en) * | 2017-08-31 | 2023-09-29 | 郑州大学 | Construction method for ecological flexible geogrid reinforced wharf |
CN114541325A (en) * | 2022-02-21 | 2022-05-27 | 福建江隆水利水电工程有限公司 | Hydraulic engineering ecological slope protection and construction method thereof |
CN114541325B (en) * | 2022-02-21 | 2024-04-05 | 福建江隆水利水电工程有限公司 | Ecological slope protection of hydraulic engineering and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101555693A (en) | Reinforced core-enveloped structural slope protector | |
KR100924933B1 (en) | Construction method of retaining wall using soil sack block for vegetation and fixed device and Structure for installation thereof | |
CN201534975U (en) | Slope protection body with ribbed and core-wrapped structure | |
CN210104766U (en) | Ecological slope protection structure | |
CN108708239A (en) | One kind returning packet mode TGXG Steep Slope Embankment structure and construction method | |
CN201158826Y (en) | Earth work grille reinforced retaining wall | |
CN113322984A (en) | Quick repairing structure for shallow landslide of soil slope with more than two levels and construction method thereof | |
CN203924075U (en) | The high embankment edge slope structure of anti-package formula Fill Reinforced With Geogrids Green ecological flexible | |
CN203429660U (en) | Stereo stiffened rigid-flexible combined ecological retaining wall | |
CN208748665U (en) | Wide ecological slope protection structure is spelled suitable for long and narrow space | |
KR100679873B1 (en) | Construction method of breast wall for tree planting | |
CN109083161A (en) | Wide ecological slope protection structure and its construction method are spelled suitable for long and narrow space | |
CN201746828U (en) | Geogrid enclosed type reinforced road embankment | |
KR20100067565A (en) | Eco gabion | |
CN110656652A (en) | Three-dimensional ecological bag slope protection structure | |
CN101705695B (en) | Ecological bag reinforced retaining wall | |
CN101967830A (en) | Ecological net cages and side slope retaining wall using same | |
CN110080282A (en) | A kind of self-anchored type band tooth grid reinforced retaining wall structure and its reinforcement means | |
CN112049134A (en) | Grid for ecological slope protection and construction method thereof | |
CN218292029U (en) | Full-flexible composite reinforced earth retaining wall structure | |
CN214993514U (en) | Landscape river levee reinforced retaining wall | |
CN113322895A (en) | Three-dimensional water and soil protection revetment and construction method thereof | |
CN203222803U (en) | Opposite-pulling supporting structure of assembly type ecological net surface geo-grid | |
CN217078846U (en) | Geogrid reverse-wrapping ecological bag reinforced retaining wall | |
CN106988338A (en) | Gabion box retaining wall and its construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Open date: 20091014 |