CN101541021B - Method for automatically generating capacity-warning reports - Google Patents

Method for automatically generating capacity-warning reports Download PDF

Info

Publication number
CN101541021B
CN101541021B CN2008100524571A CN200810052457A CN101541021B CN 101541021 B CN101541021 B CN 101541021B CN 2008100524571 A CN2008100524571 A CN 2008100524571A CN 200810052457 A CN200810052457 A CN 200810052457A CN 101541021 B CN101541021 B CN 101541021B
Authority
CN
China
Prior art keywords
data
capacity
warning
report
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2008100524571A
Other languages
Chinese (zh)
Other versions
CN101541021A (en
Inventor
王辉
李荣盛
张秀钰
康灿
柴华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Mobile Group Tianjin Co Ltd
Original Assignee
China Mobile Group Tianjin Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Mobile Group Tianjin Co Ltd filed Critical China Mobile Group Tianjin Co Ltd
Priority to CN2008100524571A priority Critical patent/CN101541021B/en
Publication of CN101541021A publication Critical patent/CN101541021A/en
Application granted granted Critical
Publication of CN101541021B publication Critical patent/CN101541021B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Data Exchanges In Wide-Area Networks (AREA)
  • Mobile Radio Communication Systems (AREA)

Abstract

The invention belongs to a method for automatically generating capacity-warning reports in the technical field of mobile communication network management. The method is realized through the following steps that: a common report-creating module transmits the name of a report to a public service module after the report is created; the public service module writes the name and a label of the report into a created data table; a data general-control module polls the created data table at regular time and calls a corresponding data-grasping module; the data-grasping module grasps capacity-warning data from a network management system database and stores the capacity-warning data into a capacity-warning database, and simultaneously writes a label of grasped report data into a grasped data table; and a warning-report general-control module polls the grasped data table at regular time and calls a capacity-warning report-creating module to create various types of capacity-warning reports. The method has the advantage of solving the problems of high maintenance complexity and high maintenance cost in the prior mobile communication network management system, and is convenient for the expansion of system functions.

Description

A kind of method for automatically generating capacity-warning reports
Technical field
The invention belongs to the mobile network management technical field, especially a kind of method for automatically generating capacity-warning reports.
Background technology
From the angle of mobile communications network OA operation analysis, the capacity-warning function of mobile communications network is more and more important.The decision maker of mobile communications network can in time find the hidden danger that exists in the mobile communications network and make corresponding adjustment and improvement in view of the above that therefore comprehensive, accurate, timely, complete capacity-warning reports has vital directive function to the raising of mobile communications network production and mobile communications network service quality by capacity-warning reports.But, along with the continuous development of the communication technology, the continuous expansion of network size and the continuous increase of network element device kind, the performance index of various device are gathered and then generate capacity-warning reports need carry out a large amount of calculating and association analysis, therefore, the final capacity-warning reports that generates is often not comprehensive owing to the disappearance of part raw data.
When capacity-warning reports not full-time, present solution is that raw data is carried out making relevant form and capacity-warning reports again after the filling mining, each process of making form again is independent, dispersion, and simultaneously, the integrality of integrative analysis report and accuracy also are difficult to guarantee.In present stage, industry often adopts following two kinds of integrative analysis report generating modes: first kind of mode used by the network management system database, the integrative analysis report generation system that data-switching and computing module and group financial statements are made the module formation generates, its structure as shown in Figure 3, this mode is directly extracted the needed data of integrative analysis report from the network management system database, generate integrative analysis report through conversion and calculating back to different vendor's data, the shortcoming of this mode is that the data in the resulting group financial statements may not be complete, for example the integrative analysis report of made needs the data of 50 complete equipments, the data (the unsuccessful situation of part reported by network element equipment data promptly having occurred) of in certain time point network management system database of making integrative analysis report, having only 40 complete equipments, so only the integrative analysis report that generates according to the data of this 40 complete equipment can not reflect truth, the integrality of integrative analysis report reduces, through the maintainer missing data reason is judged, after the work of missing data filling mining, remaining 10 complete equipment data just can enter in the network management system database, but as the group financial statements producer, it does not also know that missing data is ready to, need make integrative analysis report again, so the integrality of integrative analysis report is difficult to guarantee; The second way is used by the network management system database, the database integrity checking module, the integrative analysis report generation system that data-switching and computing module and group financial statements are made the module formation generates, its structure as shown in Figure 4, this mode when making integrative analysis report at every turn, all to carry out integrity checking to the data in the database of need analysis, if all set, just carry out the conversion and the calculating of different vendor's data and generate form, otherwise, wait for that with regard to needs DSR just can carry out, the advantage of this mode is can guarantee to make the integrality of successful form, but the shortcoming of its existence is when the data of reported by network element equipment in database are incorrect, need gather again these data, but this moment, integrative analysis report was made according to previous incorrect database data, its report making personnel can't know that data have carried out again gathering, and the accuracy of integrative analysis report is difficult to be guaranteed.In sum, mainly there is following problem in existing integrative analysis report generation method: 1. pair different manufacturers, dissimilar network element devices need be write different data acquisition modules, but, development expansion along with network size, the quantity of data acquisition module constantly increases, and the operational management of data acquisition module is become more and more complicated; 2. a large amount of report-creating module are carried out the manual maintenance mode, there is big, the inefficient shortcoming of maintenance workload, especially when making form again, the independent Reports module that disperses has further increased workload, and the integrality of integrative analysis report and accuracy are difficult to be guaranteed; 3. need carry out new research and development for new statistics and analysis demand, lack the association analysis of institute's image data and utilization again, extensibility is lower.
Summary of the invention
The objective of the invention is to overcome the deficiencies in the prior art, a kind of method for automatically generating capacity-warning reports is provided, safeguard in a large number independently in order to solve in the existing mobile communication network management system, disperse the high complexity of form and the problem of high maintenance cost, make the generative process robotization of capacity-warning reports.
The present invention solves its technical matters and takes following technical scheme to realize:
A kind of method for automatically generating capacity-warning reports is characterized in that: this method comprises the steps:
(1). common report-creating module by adding a Shell calling interface calling public service module in common report-creating module, and sends the report name that generates to public service module as command line parameter after report making is finished;
(2). public service module has been finished mark with this report name and form and has been write and make in the tables of data;
(3). data top control module automatic regular polling has been made tables of data, and the form of form having been finished mark calls corresponding data capture module;
(4). data capture module grasps the capacity-warning data and stores in the capacity-warning database from the network management system database, remove the form made in the tables of data and finished mark, writes report data in the tables of data and has grasped mark grasping simultaneously;
(5). capacity-warning reports top control module automatic regular polling has grasped tables of data, the form that report data has been grasped mark calls the making that corresponding capacity-warning reports making module realizes all kinds of capacity-warning reports, removes the report data that has grasped in the tables of data simultaneously and has grasped mark.
And, described common report-creating module and public service module are installed on each report server, and described data top control module, data capture module, capacity-warning reports top control module and capacity-warning reports are made module and be installed in the capacity-warning server.
And described capacity-warning server and report server logically are separated, and described capacity-warning server is the entity that separates with report server physically, and perhaps capacity-warning server and arbitrary report server are same entity.
And, describedly make tables of data, grasped data table stores in application data base.
And described data top control module is a service module that resides in the capacity-warning server memory, automatically the data in the configuration file is read in the internal memory of capacity-warning server during its initialization.
And described data top control module is determined the extracting scope of form according to configuration file, and this configuration file is corresponding one by one with common report-creating module.
And the form that described data top control module has been finished mark to form adopts formation cache management mode, calls successively and the corresponding data capture module of this form.
And, also be provided with a plurality of zone bits of analyzing and adding up of being used in the tables of data making tables of data and grasped.
And described capacity-warning reports comprises the link load warning reports between the load warning reports that interconnects between link, inter-provincial link load warning reports, each MSC switch.
Advantage of the present invention and good effect are:
1. this method for automatically generating capacity-warning reports is set up a kind of corresponding relation with each common report-creating module and capacity-warning reports module in existing mobile communication network management system, thereby make a plurality of dispersions of existing in the former mobile communication network management system or independently interconnection is together, and then the automatic generation of realization capacity-warning reports, solved and safeguarded in a large number independently, disperseed the high complexity of form and the problem of high maintenance cost in the existing network management system.
2. this method for automatically generating capacity-warning reports adopts the automatic regular polling trigger mode, can solve the problem of doing for supplement capacity-warning reports effectively, full automation ground carries out the making of data extracting and capacity-warning reports, needn't carry out artificial judgment and association analysis, further reduce work difficulty and reduced the workload of O﹠M.
3. this method for automatically generating capacity-warning reports only carries out the modification of minimum zone to existing mobile communication network management system, the webmaster maintainer only need safeguard and can realize, not influence maintainer's use habit the common report-creating module in the report server.
4. the setting of this method for automatically generating capacity-warning reports has been made tables of data and has been grasped two tables of data of tables of data, in above-mentioned tables of data, also be provided with a plurality of zone bits of analyzing and adding up of being used to, make it not only can be applicable to present needed capacity-warning performance index, but also have favorable expansibility, be used for the expansion of systemic-function.
5. the invention provides a kind of warning reports and generate method automatically, solved the problem of safeguarding high complexity, high maintenance cost that exists in the existing mobile communication network management system, be convenient to the expansion of systemic-function simultaneously.
Description of drawings
Fig. 1 is the connection diagram that is applicable to capacity-warning reports automatic creation system of the present invention;
Fig. 2 is a process flow block diagram of the present invention;
Fig. 3 is a kind of integrative analysis report generation system of prior art;
Fig. 4 is the another kind of integrative analysis report generation system of prior art.
Embodiment
Below in conjunction with accompanying drawing the embodiment of the invention is further described.
As shown in Figure 1, the invention process is in the capacity-warning reports automatic creation system that is connected and composed by the network switch, network management data storehouse (network management system database and application data base), report server, capacity-warning server and capacity-warning database, wherein, the network switch, report server and network management data storehouse all are already present equipment in the existing network, the network management data storehouse comprises that telephone traffic network system database, transmission network management system database etc. preserve the database of raw information, and application data base is the database for application service.The present invention has increased the capacity-warning server and has deposited the capacity-warning database that generates the capacity-warning reports data in original system.Common report-creating module and public service module all are installed on each report server, data top control module, data capture module, capacity-warning reports top control module and capacity-warning reports then are installed in the capacity-warning server make module.
In said system connects, capacity-warning server and report server logically are separated, but capacity-warning server and report server can also can be that capacity-warning server and arbitrary report server are the structure of same entity for the structure of the entity that separates physically.No matter be which kind of structure, can realize the present invention.
The treatment scheme of this method for automatically generating capacity-warning reports as shown in Figure 2, implementation step is as follows:
(1). be installed on each report server common report-creating module after report making is finished, by in common report-creating module, adding a Shell calling interface to call public service module and to send the report name that generates to public service module as command line parameter.
(2). public service module is that a record is inserted in the making tables of data in the application data base with this report name arrangement of receiving on the command line parameter, simultaneously form is finished mark and be written to the relevant position, this has been made tables of data and has been used to store the current report messages that has completed, every record comprises that also form has been finished mark and other are used to expand the zone bit of use except that comprising report name.
(3). the data top control module is a service module that resides in the capacity-warning server memory, automatically the data in the configuration file are read in the internal memory of capacity-warning server during its initialization, data top control module automatic regular polling has been made tables of data, form having been finished the form of mark determines the extracting scope of form and calls corresponding data capture module according to configuration file, the data top control module has been finished the form employing formation cache management mode of mark to form when poll, call successively and the corresponding data capture module of this form.Configuration file has herein reflected the incidence relation of common form and integrative analysis report strictly according to the facts, this incidence relation normally a kind of table that obtains by the relation of analyzing concrete overall target and common form of system maintenance personnel with show between relation, and it is safeguarded by the system maintenance personnel, the mode of safeguarding has multiple: can be directly the content of new configuration file more, also can come the relation of allocation list and table by visual graphical interfaces, mode such as form that can also be by set form, text importing.
(4). data capture module grasps the capacity-warning data and stores in the capacity-warning database from the network management system database, remove the form of having made in the form and finished mark, write report data in the extracting tables of data in application data base simultaneously and grasped mark;
(5). capacity-warning reports top control module automatic regular polling has grasped tables of data, the form that report data has been grasped mark calls the making that corresponding capacity-warning reports making module realizes all kinds of capacity-warning reports, as the making of the capacity-warning reports such as link load between the load between link that interconnects, inter-provincial link load, each MSC switch, remove the report data that has grasped in the tables of data and grasped mark.
The technical program is that the common report-creating module in the former report server is revised, its ending in common report-creating module has increased the Shell calling interface, by this calling interface call public service module just finished with the capacity-warning server in data top control module, data capture module, capacity-warning reports top control module and capacity-warning reports make the interactive function of module.
Making tables of data and having grasped of the technical program also is provided with the expansion that a plurality of zone bits that are used to analyze and add up can be advantageously used in systemic-function in the tables of data, integrate for later and ETL instrument simultaneously and reserved interface.
In such scheme if because the failure of data disappearances report making, when doing for supplement, the maintainer needn't be concerned about the relevance of this report data and follow-up capacity-warning reports, only need safeguard that system is association of triggering following capacity-warning reports and making flow process automatically just to common report-creating module.
It is emphasized that; embodiment of the present invention is illustrative; rather than it is determinate; therefore the present invention is not limited to the embodiment described in the embodiment; every other embodiments that drawn by those skilled in the art's technical scheme according to the present invention belong to the scope of protection of the invention equally.

Claims (9)

1. method for automatically generating capacity-warning reports, it is characterized in that: this method comprises the steps:
(1). common report-creating module by adding a Shell calling interface calling public service module in common report-creating module, and sends the report name that generates to public service module as command line parameter after report making is finished;
(2). public service module has been finished mark with this report name and form and has been write and make in the tables of data;
(3). data top control module automatic regular polling has been made tables of data, and the form of form having been finished mark calls corresponding data capture module;
(4). data capture module grasps the capacity-warning data and stores in the capacity-warning database from the network management system database, remove the form made in the tables of data and finished mark, writes report data in the tables of data and has grasped mark grasping simultaneously;
(5). capacity-warning reports top control module automatic regular polling has grasped tables of data, the form that report data has been grasped mark calls the making that corresponding capacity-warning reports making module realizes all kinds of capacity-warning reports, removes the report data that has grasped in the tables of data simultaneously and has grasped mark.
2. a kind of method for automatically generating capacity-warning reports according to claim 1, it is characterized in that: described common report-creating module and public service module are installed on each report server, and described data top control module, data capture module, capacity-warning reports top control module and capacity-warning reports are made module and be installed in the capacity-warning server.
3. a kind of method for automatically generating capacity-warning reports according to claim 2, it is characterized in that: described capacity-warning server and report server logically are separated, described capacity-warning server is the entity that separates with report server physically, and perhaps capacity-warning server and arbitrary report server are same entity.
4. a kind of method for automatically generating capacity-warning reports according to claim 1 is characterized in that: describedly made tables of data, grasped data table stores in application data base.
5. a kind of method for automatically generating capacity-warning reports according to claim 1, it is characterized in that: described data top control module is a service module that resides in the capacity-warning server memory, automatically the data in the configuration file is read in the internal memory of capacity-warning server during its initialization.
6. a kind of method for automatically generating capacity-warning reports according to claim 1 is characterized in that: described data top control module is determined the extracting scope of form according to configuration file, and this configuration file is corresponding one by one with common report-creating module.
7. a kind of according to claim 1 or 5 method for automatically generating capacity-warning reports, it is characterized in that: the form that described data top control module has been finished mark to form adopts formation cache management mode, calls successively and the corresponding data capture module of this form.
8. according to claim 1 or 4 described a kind of method for automatically generating capacity-warning reports, it is characterized in that: also be provided with a plurality of zone bits of analyzing and adding up of being used in the tables of data making tables of data and grasped.
9. a kind of method for automatically generating capacity-warning reports according to claim 1 is characterized in that: described capacity-warning reports comprises the link load warning reports between the load warning reports that interconnects between link, inter-provincial link load warning reports, each MSC switch.
CN2008100524571A 2008-03-18 2008-03-18 Method for automatically generating capacity-warning reports Active CN101541021B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008100524571A CN101541021B (en) 2008-03-18 2008-03-18 Method for automatically generating capacity-warning reports

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008100524571A CN101541021B (en) 2008-03-18 2008-03-18 Method for automatically generating capacity-warning reports

Publications (2)

Publication Number Publication Date
CN101541021A CN101541021A (en) 2009-09-23
CN101541021B true CN101541021B (en) 2010-07-21

Family

ID=41123938

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008100524571A Active CN101541021B (en) 2008-03-18 2008-03-18 Method for automatically generating capacity-warning reports

Country Status (1)

Country Link
CN (1) CN101541021B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3014497B1 (en) * 2013-06-25 2018-05-30 Thomson Licensing Method and apparatus of processing for alarm clearing
CN111090635B (en) * 2019-11-29 2023-11-07 北京明略软件系统有限公司 Configuration method and device of early warning scheme and computer readable storage medium
CN112988743B (en) * 2021-02-25 2024-02-02 中国工商银行股份有限公司 Method, device, system and medium for pre-warning data table capacity

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1438591A (en) * 2002-02-10 2003-08-27 华为技术有限公司 Method for realizing intelligent report forms
CN1482766A (en) * 2002-09-13 2004-03-17 华为技术有限公司 Method for automatic generating of net management report form
CN1588369A (en) * 2004-09-06 2005-03-02 杭州恒生电子股份有限公司 Relation type data base system and its search and report method
CN101004758A (en) * 2007-01-26 2007-07-25 华为技术有限公司 Method and corresponding system for creating and obtaining report forms
CN101110858A (en) * 2007-08-29 2008-01-23 中兴通讯股份有限公司 Telecommunication report generation system and method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1438591A (en) * 2002-02-10 2003-08-27 华为技术有限公司 Method for realizing intelligent report forms
CN1482766A (en) * 2002-09-13 2004-03-17 华为技术有限公司 Method for automatic generating of net management report form
CN1588369A (en) * 2004-09-06 2005-03-02 杭州恒生电子股份有限公司 Relation type data base system and its search and report method
CN101004758A (en) * 2007-01-26 2007-07-25 华为技术有限公司 Method and corresponding system for creating and obtaining report forms
CN101110858A (en) * 2007-08-29 2008-01-23 中兴通讯股份有限公司 Telecommunication report generation system and method thereof

Also Published As

Publication number Publication date
CN101541021A (en) 2009-09-23

Similar Documents

Publication Publication Date Title
CN103123484B (en) Transformer station's Condition Monitoring Data standardization connecting system and method
CN102377246B (en) Graphic instantiation method based on IEC61850 fault analysis system
CN102929224B (en) Condition acquisition controller (CAC) for power transformer equipment and system control method
CN103501047A (en) Intelligent fault wave recording main station information management system
CN104362757B (en) Transformer substation on-line monitoring system based on IEC61850
CN102932195B (en) A kind of business diagnosis method for supervising of protocal analysis Network Based and system
CN103532744A (en) Information-communication integrated supporting platform of intelligent power grid
WO2018064843A1 (en) System and method for managing infrastructure of data center
CN103532749A (en) Main station information management system
CN108156225B (en) Micro-application monitoring system and method based on container cloud platform
CN103297517A (en) Distributed data transmission method of condition monitoring system
CN105183299A (en) Human-computer interface service processing system and method
CN102571413B (en) Method for resource management under cluster environment
CN102404760B (en) Method and device for real-time measurement of system performance
CN101541021B (en) Method for automatically generating capacity-warning reports
CN113778918A (en) USB device management system and management method
CN104320301A (en) Intranet special line flow monitoring method and system
CN106407072A (en) Monitoring system of big data platform
CN104065503A (en) Discriminant analysis method for fault sourcing of facilities in intelligent traffic internet of things
CN101820356A (en) Network fault diagnosis system based on ARM-Linux
CN104516839A (en) Embedded type application system
CN104601374A (en) Network fault processing method and device for numerical control machine tool
CN204288199U (en) Printing device LPT data virtual system
CN102034163A (en) Method and system for managing asset information of telecommunication equipment
CN104506939A (en) Information reporting method and television terminal

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant