CN111090635B CN201911199283.6A CN201911199283A CN111090635B CN 111090635 B CN111090635 B CN 111090635B CN 201911199283 A CN201911199283 A CN 201911199283A CN 111090635 B CN111090635 B CN 111090635B
Authority
CN
China
Prior art keywords
early warning
warning scheme
data source
database
scheme
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201911199283.6A
Other languages
Chinese (zh)
Other versions
CN111090635A (en
Inventor
林海
张毅然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Mininglamp Software System Co ltd
Original Assignee
Beijing Mininglamp Software System Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Mininglamp Software System Co ltd filed Critical Beijing Mininglamp Software System Co ltd
Priority to CN201911199283.6A priority Critical patent/CN111090635B/en
Publication of CN111090635A publication Critical patent/CN111090635A/en
Application granted granted Critical
Publication of CN111090635B publication Critical patent/CN111090635B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/21Design, administration or maintenance of databases
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/25Integrating or interfacing systems involving database management systems
    • G06F16/252Integrating or interfacing systems involving database management systems between a Database Management System and a front-end application

Abstract

A method, a device and a computer readable storage medium for configuring an early warning scheme comprise: acquiring an early warning scheme of a pre-configured database as a first early warning scheme; and configuring the early warning scheme of the data source under the database and the data table under the data source according to the first early warning scheme. Because the pre-warning schemes of the data sources under the database and the data tables under the data sources are configured according to the pre-configured first pre-warning scheme of the database, the automatic configuration of the pre-warning scheme is realized, thereby saving the labor cost and improving the configuration efficiency.

Description

Configuration method and device of early warning scheme and computer readable storage medium
Technical Field
The present disclosure relates to information processing technologies, and in particular, to a method and apparatus for configuring an early warning scheme, and a computer readable storage medium.
Background
Along with the coming of the big data age, the data becomes a precious resource, and the data needs to guarantee the quality (effectiveness, accuracy, consistency and the like) of the data to play a practical role, and in this regard, the technical means of configuring an early warning scheme for the data are often adopted.
In the related art, the architecture of data includes: the database, the data sources under the database and the data tables under the data sources are often configured in a one-to-one mode by adopting a manual mode aiming at the configuration of the early warning scheme.
However, this method is very labor-intensive and inefficient in configuration because it relies entirely on manual means.
Disclosure of Invention
The application provides a configuration method and device of an early warning scheme and a computer readable storage medium, which can save labor cost and improve configuration efficiency.
The application provides a configuration method of an early warning scheme, which comprises the following steps:
acquiring an early warning scheme of a pre-configured database as a first early warning scheme;
and configuring the pre-warning scheme of the data source under the database and the data table under the data source according to the first pre-warning scheme.
The pre-warning scheme for configuring the data source under the database and the data table under the data source according to the first pre-warning scheme comprises the following steps:
and configuring an early warning scheme of the data source under the database as the first early warning scheme, and configuring an early warning scheme of the data table under the data source as the first early warning scheme.
When a second early warning scheme different from the first early warning scheme of the database exists in the first target data source under the database, after the early warning scheme of the data source under the database is configured as the first early warning scheme and the early warning scheme of the data table under the data source is configured as the first early warning scheme, the method further comprises the steps of:
and changing and configuring the early warning scheme of the first target data source into the second early warning scheme, and changing and configuring the early warning scheme of the data table under the first target data source into the second early warning scheme.
When a third pre-warning scheme different from the second pre-warning scheme of the first target data source exists in the first target data table under the first target data source, after the pre-warning scheme of the first target data source is changed and configured to be the second pre-warning scheme, the method further comprises the steps of:
and changing and configuring the early warning scheme of the first target data table into the third early warning scheme.
When a fourth pre-warning scheme different from the pre-warning scheme of the second target data source exists in the second target data table under the second target data source under the database, after the pre-warning scheme of the data source under the database is configured as the first pre-warning scheme and the pre-warning scheme of the data table under the data source is configured as the first pre-warning scheme, the method further comprises:
and changing and configuring the early warning scheme of the second target data table into the fourth early warning scheme.
The application also provides a server, comprising:
the acquisition module is used for acquiring an early warning scheme of a pre-configured database as a first early warning scheme;
and the processing module is used for configuring the pre-warning scheme of the data source under the database and the data table under the data source according to the first pre-warning scheme.
The processing module is specifically configured to configure an early warning scheme of a data source under the database as the first early warning scheme, and configure an early warning scheme of a data table under the data source as the first early warning scheme.
When a second early warning scheme different from the first early warning scheme of the database exists in the first target data source under the database, the processing module is further configured to change the early warning scheme of the first target data source to be configured as the second early warning scheme, and change the early warning scheme of the data table under the first target data source to be configured as the second early warning scheme.
The application also provides a configuration device of the early warning scheme, which comprises: a processor and a memory, wherein the memory stores therein the following commands executable by the processor:
acquiring an early warning scheme of a pre-configured database as a first early warning scheme;
and configuring the pre-warning scheme of the data source under the database and the data table under the data source according to the first pre-warning scheme.
The present application also provides a computer-readable storage medium having stored thereon computer-executable instructions for performing the steps of:
acquiring an early warning scheme of a pre-configured database as a first early warning scheme;
and configuring the pre-warning scheme of the data source under the database and the data table under the data source according to the first pre-warning scheme.
Compared with the related art, the application comprises the following steps: acquiring an early warning scheme of a pre-configured database as a first early warning scheme; and configuring the early warning scheme of the data source under the database and the data table under the data source according to the first early warning scheme. Because the pre-warning schemes of the data sources under the database and the data tables under the data sources are configured according to the pre-configured first pre-warning scheme of the database, the automatic configuration of the pre-warning scheme is realized, thereby saving the labor cost and improving the configuration efficiency.
Additional features and advantages of the application will be set forth in the description which follows, and in part will be obvious from the description, or may be learned by practice of the application. The objectives and other advantages of the application will be realized and attained by the structure particularly pointed out in the written description and claims hereof as well as the appended drawings.
Drawings
The accompanying drawings are included to provide an understanding of the principles of the application, and are incorporated in and constitute a part of this specification, illustrate embodiments of the application and together with the description serve to explain, without limitation, the principles of the application.
Fig. 1 is a flow chart of a configuration method of an early warning scheme according to an embodiment of the present application;
fig. 2 is a flow chart of a configuration method of another early warning scheme according to an embodiment of the present application;
fig. 3 is a schematic configuration diagram of an early warning scheme according to an embodiment of the present application;
fig. 4 is a flow chart of a configuration method of another early warning scheme according to an embodiment of the present application;
FIG. 5 is a schematic diagram illustrating another embodiment of the present application;
FIG. 6 is a schematic diagram illustrating a configuration of another early warning scheme according to an embodiment of the present application;
fig. 7 is a flow chart of a configuration method of another early warning scheme according to an embodiment of the present application;
fig. 8 is a schematic structural diagram of a server according to an embodiment of the present application.
Detailed Description
The present application has been described in terms of several embodiments, but the description is illustrative and not restrictive, and it will be apparent to those of ordinary skill in the art that many more embodiments and implementations are possible within the scope of the described embodiments. Although many possible combinations of features are shown in the drawings and discussed in the detailed description, many other combinations of the disclosed features are possible. Any feature or element of any embodiment may be used in combination with or in place of any other feature or element of any other embodiment unless specifically limited.
The present application includes and contemplates combinations of features and elements known to those of ordinary skill in the art. The disclosed embodiments, features and elements of the present application may also be combined with any conventional features or elements to form a unique inventive arrangement as defined by the claims. Any feature or element of any embodiment may also be combined with features or elements from other inventive arrangements to form another unique inventive arrangement as defined in the claims. It is therefore to be understood that any of the features shown and/or discussed in the present application may be implemented alone or in any suitable combination. Accordingly, the embodiments are not to be restricted except in light of the attached claims and their equivalents. Further, various modifications and changes may be made within the scope of the appended claims.
Furthermore, in describing representative embodiments, the specification may have presented the method and/or process as a particular sequence of steps. However, to the extent that the method or process does not rely on the particular order of steps set forth herein, the method or process should not be limited to the particular sequence of steps described. Other sequences of steps are possible as will be appreciated by those of ordinary skill in the art. Accordingly, the particular order of the steps set forth in the specification should not be construed as limitations on the claims. Furthermore, the claims directed to the method and/or process should not be limited to the performance of their steps in the order written, and one skilled in the art can readily appreciate that the sequences may be varied and still remain within the spirit and scope of the embodiments of the present application.
An embodiment of the present application provides a method for configuring an alert scheme, as shown in fig. 1, including:
step 101, acquiring a pre-configured early warning scheme of a database as a first early warning scheme.
In an exemplary embodiment, the pre-warning scheme of the database may be one or more, which is not limited by the present application.
And 102, configuring the early warning schemes of the data sources under the database and the data tables under the data sources according to the first early warning scheme.
In an exemplary embodiment, the pre-warning scheme for configuring the data source under the database and the data table under the data source according to the first pre-warning scheme includes:
the method comprises the steps of configuring an early warning scheme of a data source under a database as a first early warning scheme, and configuring an early warning scheme of a data table under the data source as the first early warning scheme.
In an exemplary embodiment, after the first target data source under the database has a second pre-warning scheme different from the first pre-warning scheme of the database, the pre-warning scheme of the data source under the database is configured as the first pre-warning scheme, and the pre-warning scheme of the data table under the data source is configured as the first pre-warning scheme, the method further includes:
and changing and configuring the early warning scheme of the first target data source into a second early warning scheme, and changing and configuring the early warning scheme of the data table under the first target data source into the second early warning scheme.
In an exemplary embodiment, when the first target data table under the first target data source has a third pre-warning scheme different from the second pre-warning scheme of the first target data source, after configuring the pre-warning scheme modification of the first target data source to the second pre-warning scheme and configuring the pre-warning scheme modification of the data table under the first target data source to the second pre-warning scheme, the method further includes:
and changing and configuring the early warning scheme of the first target data table into a third early warning scheme.
In an exemplary embodiment, after the second target data table under the second target data source under the database has a fourth pre-warning scheme different from the pre-warning scheme of the second target data source, the pre-warning scheme of the data source under the database is configured as the first pre-warning scheme, and the pre-warning scheme of the data table under the data source is configured as the first pre-warning scheme, the method further includes:
and changing and configuring the early warning scheme of the second target data table into a fourth early warning scheme.
According to the configuration method of the early warning scheme, the early warning scheme of the data source under the database and the early warning scheme of the data table under the data source are configured according to the first early warning scheme of the pre-configured database, so that the automatic configuration of the early warning scheme is realized, the labor cost is saved, and the configuration efficiency is improved.
The embodiment of the application provides a configuration method of an early warning scheme, which comprises the following steps that M is assumed to represent a data type library, L is assumed to represent a data source under the database M, N is assumed to represent a data table under the data source L, and O is assumed to represent the early warning scheme:
early warning method for process I and configuration database
The process flow diagram may be as shown in fig. 2, including:
step 201, a data early warning scheme is established.
Step 202, configuring the established early warning scheme as an early warning scheme of a database.
A schematic of this step may be as shown in fig. 3.
Step two, configuring a data source and a pre-warning scheme of a data table according to the pre-warning scheme of the database
The process flow diagram may be as shown in fig. 4, including:
step 301, configuring an early warning scheme of a data source under a database as an early warning scheme of the database.
In this step, the pre-warning scheme of the data sources L1, L2 under the database M is configured as the pre-warning scheme of the database M, and the schematic diagram of this step may be as shown in fig. 5.
Step 302, configuring an early warning scheme of a data table under a data source as an early warning scheme of the data source.
In this step, the early warning schemes of the data tables N1, N2, N3, N4 are configured as the early warning schemes of the data sources L1, L2.
A schematic of this step may be as shown in fig. 6.
Process three, change and dispose the specific early warning scheme
The process flow diagram may be as shown in fig. 7, including:
step 401, changing the pre-warning scheme for configuring the specific data source.
And step 402, changing the early warning scheme changing configuration of the data table under the data source with the completed early warning scheme changing configuration into a new early warning scheme (namely, the early warning scheme after the data source changing configuration).
Step 403, changing the pre-warning scheme of the configuration specific data table.
According to the configuration method of the early warning scheme, firstly, the early warning scheme of the database M is configured, the early warning scheme of the data source L under the database M is configured as the early warning scheme of the database M, the early warning scheme of the data table N under the data source L is configured as the early warning scheme of the data source L, the early warning scheme of the configuration data source L is changed, the early warning scheme of the data table N under the data source L is changed and configured as the early warning scheme of the data source L instead of the early warning scheme of the database M, namely, the changed configuration of the early warning scheme only enables the cascaded next stage to be identical with the current stage of the early warning scheme, so that the specific early warning scheme can be configured for the specific data table, and meanwhile, the configuration can be fast carried out when the number of the data tables is numerous.
The embodiment of the present application further provides a server, as shown in fig. 8, where the server 8 includes:
the obtaining module 81 is configured to obtain an early warning scheme of a pre-configured database as a first early warning scheme.
The processing module 82 is configured to configure the pre-warning scheme of the data source under the database and the data table under the data source according to the first pre-warning scheme.
In an exemplary embodiment, the processing module 82 is specifically configured to configure the pre-warning scheme of the data source under the database as the first pre-warning scheme, and configure the pre-warning scheme of the data table under the data source as the first pre-warning scheme.
In an exemplary embodiment, the processing module 82 is further configured to configure the first pre-warning scheme modification of the first target data source to be the second pre-warning scheme, and configure the pre-warning scheme modification of the data table under the first target data source to be the second pre-warning scheme.
In an exemplary embodiment, when the first target data table under the first target data source has a third pre-warning scheme different from the second pre-warning scheme of the first target data source, the processing module 82 is further configured to change the pre-warning scheme of the first target data table to the third pre-warning scheme.
In an exemplary embodiment, the processing module 82 is further configured to configure the early warning scheme modification of the second target data table to be a fourth early warning scheme, where the fourth early warning scheme is different from the early warning scheme of the second target data source in the second target data table under the database.
According to the server provided by the embodiment of the application, the pre-warning schemes of the data source under the database and the data table under the data source are configured according to the pre-configured first pre-warning scheme of the database, so that the automatic configuration of the pre-warning scheme is realized, the labor cost is saved, and the configuration efficiency is improved.
In practical applications, the acquiring module 81 and the processing module 82 are implemented by a central processing unit (Central Processing Unit, CPU), a microprocessor (Micro Processor Unit, MPU), a digital signal processor (Digital Signal Processor, DSP), or a field programmable gate array (Field Programmable Gate Array, FPGA) located in a server, or the like.
The embodiment of the application also provides a configuration device of the early warning scheme, which comprises the following steps: a processor and a memory, wherein the memory stores a computer program which, when executed by the processor, performs the processing of the method as described in any of the above.
The embodiment of the application also provides a storage medium, on which a computer executable command is stored, the computer executable command being used to perform a process according to any one of the methods described above.
Those of ordinary skill in the art will appreciate that all or some of the steps, systems, functional modules/units in the apparatus, and methods disclosed above may be implemented as software, firmware, hardware, and suitable combinations thereof. In a hardware implementation, the division between the functional modules/units mentioned in the above description does not necessarily correspond to the division of physical components; for example, one physical component may have multiple functions, or one function or step may be performed cooperatively by several physical components. Some or all of the components may be implemented as software executed by a processor, such as a digital signal processor or microprocessor, or as hardware, or as an integrated circuit, such as an application specific integrated circuit. Such software may be distributed on computer readable media, which may include computer storage media (or non-transitory media) and communication media (or transitory media). The term computer storage media includes both volatile and nonvolatile, removable and non-removable media implemented in any method or technology for storage of information such as computer readable instructions, data structures, program modules or other data, as known to those skilled in the art. Computer storage media includes, but is not limited to, RAM, ROM, EEPROM, flash memory or other memory technology, CD-ROM, digital Versatile Disks (DVD) or other optical disk storage, magnetic cassettes, magnetic tape, magnetic disk storage or other magnetic storage devices, or any other medium which can be used to store the desired information and which can be accessed by a computer. Furthermore, as is well known to those of ordinary skill in the art, communication media typically embodies computer readable instructions, data structures, program modules or other data in a modulated data signal such as a carrier wave or other transport mechanism and includes any information delivery media.

Claims (6)

1. The configuration method of the early warning scheme is characterized by comprising the following steps:
acquiring an early warning scheme of a pre-configured database as a first early warning scheme;
configuring an early warning scheme of a data source under the database and a data table under the data source according to the first early warning scheme;
the pre-warning scheme for configuring the data source under the database and the data table under the data source according to the first pre-warning scheme comprises the following steps:
configuring an early warning scheme of a data source under the database as the first early warning scheme according to the early warning scheme of the database, and configuring an early warning scheme of a data table under the data source as the first early warning scheme according to the early warning scheme of the data source;
when a second early warning scheme different from the first early warning scheme of the database exists in the first target data source under the database, after the early warning scheme of the data source under the database is configured as the first early warning scheme and the early warning scheme of the data table under the data source is configured as the first early warning scheme, the method further comprises the steps of:
and changing and configuring the early warning scheme of the first target data source into the second early warning scheme, and changing and configuring the early warning scheme of the data table under the first target data source into the second early warning scheme.
2. The configuration method according to claim 1, wherein when a third pre-warning scheme different from the second pre-warning scheme of the first target data source exists in the first target data table under the first target data source, after the pre-warning scheme of the first target data source is changed to be configured as the second pre-warning scheme, and the pre-warning scheme of the data table under the first target data source is changed to be configured as the second pre-warning scheme, further comprising:
and changing and configuring the early warning scheme of the first target data table into the third early warning scheme.
3. The configuration method according to claim 1, wherein when a second target data table under a second target data source under the database has a fourth pre-warning scheme different from the pre-warning scheme of the second target data source, after the pre-warning scheme of the data source under the database is configured as the first pre-warning scheme, the configuration method further comprises:
and changing and configuring the early warning scheme of the second target data table into the fourth early warning scheme.
4. A server, comprising:
the acquisition module is used for acquiring an early warning scheme of a pre-configured database as a first early warning scheme;
the processing module is used for configuring the early warning scheme of the data source under the database and the data table under the data source according to the first early warning scheme;
the processing module is specifically configured to configure an early warning scheme of a data source under the database as the first early warning scheme according to the early warning scheme of the database, and configure an early warning scheme of a data table under the data source as the first early warning scheme according to the early warning scheme of the data source;
when a second early warning scheme different from the first early warning scheme of the database exists in the first target data source under the database, the processing module is further configured to change the early warning scheme of the first target data source to be configured as the second early warning scheme, and change the early warning scheme of the data table under the first target data source to be configured as the second early warning scheme.
5. The configuration device of the early warning scheme is characterized by comprising: a processor and a memory, wherein the memory stores therein the following commands executable by the processor:
acquiring an early warning scheme of a pre-configured database as a first early warning scheme;
configuring an early warning scheme of a data source under the database and a data table under the data source according to the first early warning scheme;
the memory has stored therein the following commands executable by the processor:
configuring an early warning scheme of a data source under the database as the first early warning scheme according to the early warning scheme of the database, and configuring an early warning scheme of a data table under the data source as the first early warning scheme according to the early warning scheme of the data source;
when a first target data source under the database has a second early warning scheme different from the first early warning scheme of the database, the following commands which can be executed by the processor are also specifically stored in the memory:
and changing and configuring the early warning scheme of the first target data source into the second early warning scheme, and changing and configuring the early warning scheme of the data table under the first target data source into the second early warning scheme.
6. A computer-readable storage medium having stored thereon computer-executable instructions for performing the steps of:
acquiring an early warning scheme of a pre-configured database as a first early warning scheme;
configuring an early warning scheme of a data source under the database and a data table under the data source according to the first early warning scheme;
the computer executable command is specifically configured to perform the steps of:
configuring an early warning scheme of a data source under the database as the first early warning scheme according to the early warning scheme of the database, and configuring an early warning scheme of a data table under the data source as the first early warning scheme according to the early warning scheme of the data source;
when a first target data source under the database has a second early warning scheme different from the first early warning scheme of the database, the computer executable command means is specifically configured to execute the following steps:
and changing and configuring the early warning scheme of the first target data source into the second early warning scheme, and changing and configuring the early warning scheme of the data table under the first target data source into the second early warning scheme.
CN201911199283.6A 2019-11-29 2019-11-29 Configuration method and device of early warning scheme and computer readable storage medium Active CN111090635B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911199283.6A CN111090635B (en) 2019-11-29 2019-11-29 Configuration method and device of early warning scheme and computer readable storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911199283.6A CN111090635B (en) 2019-11-29 2019-11-29 Configuration method and device of early warning scheme and computer readable storage medium

Publications (2)

Publication Number Publication Date
CN111090635A CN111090635A (en) 2020-05-01
CN111090635B true CN111090635B (en) 2023-11-07

Family

ID=70393789

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911199283.6A Active CN111090635B (en) 2019-11-29 2019-11-29 Configuration method and device of early warning scheme and computer readable storage medium

Country Status (1)

Country Link
CN (1) CN111090635B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101541021A (en) * 2008-03-18 2009-09-23 中国移动通信集团天津有限公司 Method for automatically generating capacity-warning reports
CN104063468A (en) * 2014-06-27 2014-09-24 北京思特奇信息技术股份有限公司 Data report automatic generating and extracting method and device
CN104281704A (en) * 2014-10-22 2015-01-14 新华瑞德(北京)网络科技有限公司 Database data copying method and device
CN106649226A (en) * 2015-10-29 2017-05-10 北京国双科技有限公司 Report generation method and device
CN107678907A (en) * 2017-05-22 2018-02-09 平安科技(深圳)有限公司 Database business logic monitoring method, system and storage medium
CN109542907A (en) * 2018-11-21 2019-03-29 万兴科技股份有限公司 Database caches construction method, device, computer equipment and storage medium
CN109656927A (en) * 2018-12-24 2019-04-19 成都四方伟业软件股份有限公司 Tables of data method for early warning and device
CN109814895A (en) * 2018-11-29 2019-05-28 广州因特信息科技有限公司 A kind of database update method and system of automation

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9442996B2 (en) * 2014-01-15 2016-09-13 International Business Machines Corporation Enabling collaborative development of a database application across multiple database management systems

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101541021A (en) * 2008-03-18 2009-09-23 中国移动通信集团天津有限公司 Method for automatically generating capacity-warning reports
CN104063468A (en) * 2014-06-27 2014-09-24 北京思特奇信息技术股份有限公司 Data report automatic generating and extracting method and device
CN104281704A (en) * 2014-10-22 2015-01-14 新华瑞德(北京)网络科技有限公司 Database data copying method and device
CN106649226A (en) * 2015-10-29 2017-05-10 北京国双科技有限公司 Report generation method and device
CN107678907A (en) * 2017-05-22 2018-02-09 平安科技(深圳)有限公司 Database business logic monitoring method, system and storage medium
CN109542907A (en) * 2018-11-21 2019-03-29 万兴科技股份有限公司 Database caches construction method, device, computer equipment and storage medium
CN109814895A (en) * 2018-11-29 2019-05-28 广州因特信息科技有限公司 A kind of database update method and system of automation
CN109656927A (en) * 2018-12-24 2019-04-19 成都四方伟业软件股份有限公司 Tables of data method for early warning and device

Also Published As

Publication number Publication date
CN111090635A (en) 2020-05-01

Similar Documents

Publication Publication Date Title
KR102125177B1 (en) Blockchain-based data processing method and device
US10831751B2 (en) Query parallelism method
CN106095592B (en) Foreground application program scene synchronization method, device and system
US20170161297A1 (en) Data synchronization in a storage network
US10045397B2 (en) Data complementing method and apparatus
US20200019559A1 (en) Synchronizing object in local object storage node
WO2017041486A1 (en) Cluster deployment implementation method and apparatus
US20170201566A1 (en) File downloading method, apparatus, and terminal device
US20170132020A1 (en) Code processing method and code processing device
CN109391512A (en) A kind of service issuing method, device and electronic equipment
CN109597678B (en) Task processing method and device
CN111124803A (en) Method and device for controlling state of indicator light and computer readable storage medium
CN111581239A (en) Cache refreshing method and electronic equipment
CN111143331A (en) Data migration method and device and computer storage medium
CN103150253A (en) Method and system for duration performance testing
CN110717050B (en) Knowledge graph database access method and device
CN115617799A (en) Data storage method, device, equipment and storage medium
CN111090635B (en) Configuration method and device of early warning scheme and computer readable storage medium
CN103176800A (en) Application program login method and device
CN109388644B (en) Data updating method and device
CN112181528B (en) Method and device for managing configuration file of micro-service
CN110674171A (en) Script generation method and device and data processing method and device
US10901972B2 (en) Table partition configuration method, apparatus and system for database system
CN108089904A (en) A kind of displayed page extended method and equipment
CN110020288A (en) A kind of page furbishing method and device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant