CN101532292A - Construction process for jet grouting anchor rod - Google Patents

Construction process for jet grouting anchor rod Download PDF

Info

Publication number
CN101532292A
CN101532292A CN 200810034670 CN200810034670A CN101532292A CN 101532292 A CN101532292 A CN 101532292A CN 200810034670 CN200810034670 CN 200810034670 CN 200810034670 A CN200810034670 A CN 200810034670A CN 101532292 A CN101532292 A CN 101532292A
Authority
CN
China
Prior art keywords
rod
whitewashing
drilling
promotes
churning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200810034670
Other languages
Chinese (zh)
Other versions
CN101532292B (en
Inventor
李耀良
赵伟成
袁芬
张晓锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jianhao Engineering Consultancy Co., Ltd.
Shanghai Foundation Engineering Group Co Ltd
Original Assignee
FOUNDATION ENGINEERING Co OF SHANGHAI CITY
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FOUNDATION ENGINEERING Co OF SHANGHAI CITY filed Critical FOUNDATION ENGINEERING Co OF SHANGHAI CITY
Priority to CN200810034670XA priority Critical patent/CN101532292B/en
Publication of CN101532292A publication Critical patent/CN101532292A/en
Application granted granted Critical
Publication of CN101532292B publication Critical patent/CN101532292B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to a construction process for jet grouting anchor rod, which comprises the following detailed steps of: 1. setting out according to design requirements; 2. positioning a drilling machine; 3. drilling; 4. guniting; 5. lifting by jet grouting; 6. drilling for a second time; 7. guniting for a second time; 8. lifting by jet grouting for a second time; 9. installing and embedding a rod body; and 10. pouring and capping. The construction process can overcome the technical problem that the anchoring effect of slip-casting type or mechanical type anchoring is poor, and breaks through the tradition, and the test demonstrates that the anchoring effect is better than that of slip-casting anchoring.

Description

Construction process for jet grouting anchor rod
Technical field
The present invention relates to a kind of in engineering constructions such as side slope, tunnel, underground construction, mine the ground anchorage job practices.
Background technology
At present, the ground anchorage technology is used widely in engineering constructions such as side slope, tunnel, underground construction, mine, is the effective ways that improve geotechnical engineering stability and solve complicated geotechnical engineering stable problem.Usually rock soil anchor employing slip casting type or mechanical type are two types.Its ground anchorage weak effect.Therefore, need open up thinking, break traditions, exploitation one cover construction process for jet grouting anchor rod, through experimental examination, anchoring effect is good slightly than grouted rock bolt.
The scope of application:
Jet grouting anchor rod is as slope reinforcement and the outer a kind of new technical measures of supporting of excavation of foundation pit, and effect is remarkable, is different from slip casting type and mechanical type prestressed anchor, for geotechnical anchor engineering provides new method.
Summary of the invention
The present invention will provide a kind of construction process for jet grouting anchor rod, and this technology can solve the technical problem of slip casting type or two kinds of anchoring types of mechanical type anchoring effect difference.
For achieving the above object, technical scheme of the present invention is:
A kind of construction process for jet grouting anchor rod, its concrete steps are as follows:
1. carry out setting-out by construction drawing
2. rig is located
3. boring: rig is according to the boring of designed inclination angle degree, and the degree of depth is controlled at the following 20cm of projected depth, and drilling rod adopts double pipe;
4. whitewashing
Slurry configurations: cement adopts 32.5 grades of Portland cements, water/binder ratio 0.75~0.85.
Once whitewashing, grouting pressure generally is controlled at 22~25MPa, and every 150cm section grouting pressure is increased to 25~30MPa, air pressure 0.6~0.8MPa.
5. churning promotes
Reach the schematic design required pressure normal after, the beginning churning promotes, every 150cm promotes and was controlled at 22 rev/mins of rotating speeds 20cm/ minute.Every meter 500kg of cement mixing content, rotary churning pile footpath 80cm, local 100cm.Whitewashing length stops whitewashing after reaching the design anchorage length.
6. secondary drilling: secondary drilling is at the bottom of the hole;
7. secondary whitewashing: every meter 200kg of secondary whitewashing cement mixing content;
8. the secondary churning promotes: churning promotes drilling rod and all releases boring, and rig is displaced to next hole;
9. the body of rod is assembled and is buried underground
Anchor rod body adopts φ 50 finish rolling deformed bars, and the joint of reinforcing bar adopts the screw-thread steel sleeve; When burying the body of rod underground along body of rod axis direction installation bracket; The free section of the body of rod ties with galvanized wire with the anchor bar body junction with the Polypropylence Sheet parcel, and fracture seals with electrician's infantees, prevents that cement grout from flowing into;
10. cast is beared down on one
The invention has the beneficial effects as follows: this technology can solve the technical problem of slip casting type or two kinds of anchoring types of mechanical type anchoring effect difference, and has broken tradition, and through experimental examination, anchoring effect is good than grouted rock bolt.
The specific embodiment
Below in conjunction with specific embodiment, further set forth the present invention.Should be understood that these embodiment only to be used to the present invention is described and be not used in and limit the scope of the invention.Should be understood that in addition those skilled in the art can make various changes or modifications the present invention after the content of having read the present invention's instruction, these equivalent form of values fall within the application's appended claims institute restricted portion equally.
Construction process for jet grouting anchor rod of the present invention: may further comprise the steps:
1. by the designing requirement setting-out
2. rig is located
3. boring
4. whitewashing
5. churning promotes
6. secondary drilling
7. secondary whitewashing
8. the secondary churning promotes
9. the body of rod is assembled and is buried underground
10. cast is beared down on one
Jet grouting anchor rod construction concrete grammar of the present invention is:
At first press construction drawing setting-out location, special drilling machine is holed according to the designed inclination angle degree, and drilling depth is controlled at the following 20cm of projected depth, and drilling rod adopts double pipe.
Slurry configurations: cement adopts 32.5 grades of Portland cements, water/binder ratio 0.75~0.85.
Once whitewashing, grouting pressure generally is controlled at 22~25MPa.Every 150cm section grouting pressure is increased to 25~30MPa, air pressure 0.6~0.8MPa.Reach the schematic design required pressure normal after, the beginning churning promotes, every 150cm promotes and was controlled at 22 rev/mins of rotating speeds 20cm/ minute.Every meter 500kg of cement mixing content, rotary churning pile footpath 80cm, local 100cm.Whitewashing length stops whitewashing after reaching the design anchorage length.
Secondary drilling at the bottom of the hole, every meter 200kg of secondary whitewashing cement mixing content, churning promotes drilling rod and all releases boring, rig is displaced to next hole.
The assembling of the body of rod and burying underground: anchor rod body adopts φ 50 finish rolling deformed bars (rank 735/935).The anchor pole reinforcing bar should be straight, oil removing and rust cleaning.The joint of reinforcing bar adopts the screw-thread steel sleeve.Along body of rod axis direction installation bracket, when preventing to lay the body of rod, the body of rod is turned round pressure, bending when burying the body of rod underground.The free section of the body of rod ties with galvanized wire with the anchor bar body junction with the Polypropylence Sheet parcel, and fracture seals with electrician's infantees, prevents that cement grout from flowing into.
This jet grouting anchor rod is used first by No. three lines of the emerging shipbuilding of the Yu Zhong captain of Foundation Engineering Co. of Shanghai City base first phase, and through basic tensile test and creep test, anchoring effect is good, has promotional value.

Claims (1)

1. construction process for jet grouting anchor rod is characterized in that concrete steps are as follows:
(1) carries out setting-out by construction drawing
(2) rig location
(3) boring: rig is according to the boring of designed inclination angle degree, and the degree of depth is controlled at the following 20cm of projected depth, and drilling rod adopts double pipe;
(4) whitewashing
Slurry configurations: cement adopts 32.5 grades of Portland cements, water/binder ratio 0.75~0.85;
Once whitewashing, grouting pressure generally is controlled at 22~25MPa; Every 150cm section grouting pressure is increased to 25~30MPa, air pressure 0.6~0.8MPa;
(5) churning promotes
Reach the schematic design required pressure normal after, the beginning churning promotes, every 150cm promotes and was controlled at 22 rev/mins of rotating speeds 20cm/ minute; Every meter 500kg of cement mixing content, rotary churning pile footpath 80cm, local 100cm; Whitewashing length stops whitewashing after reaching the design anchorage length;
(6) secondary drilling: secondary drilling is at the bottom of the hole;
(7) secondary whitewashing: every meter 200kg of secondary whitewashing cement mixing content;
(8) the secondary churning promotes: churning promotes drilling rod and all releases boring, and rig is displaced to next hole;
(9) body of rod is assembled and is buried underground
Anchor rod body adopts φ 50 finish rolling deformed bars, and the joint of reinforcing bar adopts the screw-thread steel sleeve; When burying the body of rod underground along body of rod axis direction installation bracket; The free section of the body of rod ties with galvanized wire with the anchor bar body junction with the Polypropylence Sheet parcel, and fracture seals with electrician's infantees, prevents that cement grout from flowing into;
(10) cast is beared down on one.
CN200810034670XA 2008-03-14 2008-03-14 Construction process for jet grouting anchor rod Active CN101532292B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200810034670XA CN101532292B (en) 2008-03-14 2008-03-14 Construction process for jet grouting anchor rod

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200810034670XA CN101532292B (en) 2008-03-14 2008-03-14 Construction process for jet grouting anchor rod

Publications (2)

Publication Number Publication Date
CN101532292A true CN101532292A (en) 2009-09-16
CN101532292B CN101532292B (en) 2011-07-13

Family

ID=41103142

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200810034670XA Active CN101532292B (en) 2008-03-14 2008-03-14 Construction process for jet grouting anchor rod

Country Status (1)

Country Link
CN (1) CN101532292B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182196A (en) * 2011-03-28 2011-09-14 北京鑫实路桥建设有限公司 Reverse circulation grouting anchor rod reinforcing method for road rock side slope
CN103088819A (en) * 2013-02-22 2013-05-08 北京市公路桥梁建设集团有限公司 Pre-stressed anchor cable construction method
CN105178328A (en) * 2015-07-30 2015-12-23 葛加君 High-pressure jet grouting expansion hot-melting anchor bolt foundation pit supporting method
CN106120808A (en) * 2016-07-28 2016-11-16 上海宝冶集团有限公司 A kind of in the soft comprehensive support method moulded in clay foundation ditch
CN109208592A (en) * 2018-10-19 2019-01-15 中国黄金集团建设有限公司 A kind of anchor rod construction method
CN111395332A (en) * 2020-03-30 2020-07-10 胡美玲 Rotary excavating and anchor cable construction method for hard rock stratum
CN113173766A (en) * 2021-03-23 2021-07-27 远强地基工程(天津)股份有限公司 Soil body curing agent and jet grouting anchor pile construction process applying same
CN113309374A (en) * 2021-05-25 2021-08-27 中国一冶集团有限公司 Device and method for quickly recovering slurry of assembled wall component

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5575593A (en) * 1994-07-11 1996-11-19 Atlas Systems, Inc. Method and apparatus for installing a helical pier with pressurized grouting
CN1110754A (en) * 1994-08-08 1995-10-25 何庆林 Large-head anchor rod construction method and special drilling machine
CN1204713A (en) * 1998-07-24 1999-01-13 黄运飞 Multifunction stirring rotation spray roofbolt rig and construction method
CN1657711A (en) * 2005-03-21 2005-08-24 严平 Rotary spray anchoring pile construction process
KR100729661B1 (en) * 2005-09-23 2007-06-18 주식회사 에스에스씨컨설턴트 Construction method for soil improvement anchor system
JP3954628B2 (en) * 2006-01-16 2007-08-08 新技術工営株式会社 Underground anchor placement method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182196A (en) * 2011-03-28 2011-09-14 北京鑫实路桥建设有限公司 Reverse circulation grouting anchor rod reinforcing method for road rock side slope
CN103088819A (en) * 2013-02-22 2013-05-08 北京市公路桥梁建设集团有限公司 Pre-stressed anchor cable construction method
CN105178328A (en) * 2015-07-30 2015-12-23 葛加君 High-pressure jet grouting expansion hot-melting anchor bolt foundation pit supporting method
CN106120808A (en) * 2016-07-28 2016-11-16 上海宝冶集团有限公司 A kind of in the soft comprehensive support method moulded in clay foundation ditch
CN109208592A (en) * 2018-10-19 2019-01-15 中国黄金集团建设有限公司 A kind of anchor rod construction method
CN111395332A (en) * 2020-03-30 2020-07-10 胡美玲 Rotary excavating and anchor cable construction method for hard rock stratum
CN113173766A (en) * 2021-03-23 2021-07-27 远强地基工程(天津)股份有限公司 Soil body curing agent and jet grouting anchor pile construction process applying same
CN113309374A (en) * 2021-05-25 2021-08-27 中国一冶集团有限公司 Device and method for quickly recovering slurry of assembled wall component
CN113309374B (en) * 2021-05-25 2023-07-18 中国一冶集团有限公司 Rapid slurry recycling device and method for assembled wall components

Also Published As

Publication number Publication date
CN101532292B (en) 2011-07-13

Similar Documents

Publication Publication Date Title
CN101532292B (en) Construction process for jet grouting anchor rod
CN202559345U (en) Bottom-expanded pre-stress anti-floating anchor rod
CN202509532U (en) Multi-rib tension type anti-floating anchor
CN103015413B (en) Construction method of composite pile with implanting-in rigid-body embedded into hard bearing stratum
CN103133026A (en) Novel expansion shell inverted wedge type grouting anchor rod
CN105239561A (en) Long spiral mix spray pre-grouting press concrete post-inserted steel reinforcement cage cast-in-place pile construction process
CN101070702A (en) Single-hole composite anchoring pile
CN101806059A (en) Drilling, grouting and sand-throwing process of ground surface of mined-out region under highway
CN103669346A (en) Sleeve valve pipe and application to landslide control
CN102995651B (en) Gravity-type onshore/offshore wind turbine foundation with anchor rod
CN203230443U (en) Novel case expanding reverse wedging type slip casting anchor rod
CN103911993B (en) A kind of PHA anchor pole and construction method thereof
CN104314076A (en) Recycled type prestressed anchor cable structure for soft soil foundation and construction method
CN204174618U (en) Soft foundation recoverable prestressed anchor Cable Structure
CN102031795A (en) Short pile reinforcing technology in narrow space
CN110468828A (en) A kind of construction method of pattern foundation pit supporting structure water-stop continuous wall
CN201649076U (en) Inversed Y-type single-row unidirectional rotary spraying, mixing and reinforcing combined tangent pile
CN203613568U (en) Anti-floating cement soil pile and anti-floating anchor rod combined anti-floating system
CN208803460U (en) A kind of enhancing cement mixing method intercepts water the Prefabricated Concrete sheet pile of effect
CN203113332U (en) Anchor rod construction structure device after construction
CN201183950Y (en) Self-propelling type anchor rod of seamless steel pipe
CN109854281A (en) The method for protecting support of the lower rock compound cross-section stratum jacking construction of upper soil
CN202755385U (en) Anti-floating structure of shallow-buried shield tunnel
CN206581314U (en) Screw head muscle body posttension pile foundation
CN202989919U (en) Pressure-bearing water-sand-layer anchor rod mounting structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHANGHAI JIANHAO ENGINEERING CONSULTANCY CO., LTD.

Effective date: 20130522

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Li Yaoliang

Inventor after: Zhao Weicheng

Inventor after: Yuan Fen

Inventor after: Li Haiguang

Inventor before: Li Yaoliang

Inventor before: Zhao Weicheng

Inventor before: Yuan Fen

Inventor before: Zhang Xiaofeng

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: LI YAOLIANG ZHAO WEICHENG YUAN FEN ZHANG XIAOFENG TO: LI YAOLIANG ZHAO WEICHENG YUAN FEN LI HAIGUANG

TR01 Transfer of patent right

Effective date of registration: 20130522

Address after: 200433 Yangpu District, Shanghai Star Road, No. 231

Patentee after: Shanghai Foundation Engineering Co., Ltd.

Patentee after: Shanghai Jianhao Engineering Consultancy Co., Ltd.

Address before: 200433 Yangpu District, Shanghai Star Road, No. 231

Patentee before: Shanghai Foundation Engineering Co., Ltd.

C56 Change in the name or address of the patentee

Owner name: SHANGHAI FOUNDATION ENGINEERING GROUP CO., LTD.

Free format text: FORMER NAME: SHANGHAI FOUNDATION ENGINEERING CO., LTD.

CP03 Change of name, title or address

Address after: 200433, Shanghai, Yangpu District Star Road No. 231

Patentee after: Shanghai Foundation Engineering Group Co., Ltd.

Patentee after: Shanghai Jianhao Engineering Consultancy Co., Ltd.

Address before: 200433 Yangpu District, Shanghai Star Road, No. 231

Patentee before: Shanghai Foundation Engineering Co., Ltd.

Patentee before: Shanghai Jianhao Engineering Consultancy Co., Ltd.