CN101498221A - City underground engineering construction safety risk dynamic control method - Google Patents

City underground engineering construction safety risk dynamic control method Download PDF

Info

Publication number
CN101498221A
CN101498221A CNA2009100782351A CN200910078235A CN101498221A CN 101498221 A CN101498221 A CN 101498221A CN A2009100782351 A CNA2009100782351 A CN A2009100782351A CN 200910078235 A CN200910078235 A CN 200910078235A CN 101498221 A CN101498221 A CN 101498221A
Authority
CN
China
Prior art keywords
construction
safety
control
scheme
monitoring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2009100782351A
Other languages
Chinese (zh)
Other versions
CN101498221B (en
Inventor
张顶立
张成平
房倩
骆建军
侯艳娟
苏洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jiaotong University
Original Assignee
Beijing Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Jiaotong University filed Critical Beijing Jiaotong University
Priority to CN2009100782351A priority Critical patent/CN101498221B/en
Publication of CN101498221A publication Critical patent/CN101498221A/en
Application granted granted Critical
Publication of CN101498221B publication Critical patent/CN101498221B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a dynamic control method for construction safety risk of city underground engineering, which includes the following steps of estimating the prior condition of the original structure and evaluating the safety, determining the safety control standard of the important building in the range influenced by the construction, predicating the construction influence, determining the construction scheme, determining the optimized construction scheme of the minimum additional influence, enacting and implementing the process control scheme, namely degrading the control object of deposition or stress under the set construction scheme, clearing the control object of each step, monitoring measurement, feeding back information, particularly monitoring the key construction part and the key construction step, judging the engineering safety, making reaction on the construction measure in time, and estimating after the construction and repairing the structural state, namely, after the construction is completed, the necessity, the feasibility and the economic reasonability of the repair are analyzed and estimated to provide corresponding schemes, measures and proposals. The invention is suitable for the safety risk control of the construction of the complex city underground engineering and enables the risk management to be scientific and standardized.

Description

A kind of city underground engineering construction safety risk dynamic control method
Technical field
The present invention relates to a kind of city underground engineering construction safety risk dynamic control method, belong to the underground structrue engineering technical field.
Background technology
City underground engineering is compared with the ground surface works project, because the complexity and the uncertainty of its medium of living in, and urban population density is excessive with building density, thereby in the very big risk of construction period existence.In the engineering construction because artificial or non-artificial factor causes engineering accident, thereby cause tremendous economic loss, cause that the example of serious social influence is too numerous to enumerate.Both at home and abroad in the exploitation of urban underground space big accident takes place repeatedly, cause great casualties and heavy economic loss, and society stable brought certain negative influence in recent years.
Because China's urban underground space developing history is shorter, lack experience, in construction, exist some problem that can not be ignored and hidden dangers, the potential technology risk is lacked essential analysis and demonstration, and people are not enough to objective law understanding, manage not in place, in Shanghai, subway engineering security incident in various degree all appearred in Beijing and other cities, great casualties and heavy economic loss have been caused, and society stable brought certain negative influence, these engineering accidents also are our alarm bell that city underground engineering safety builds of having rung when leaving people's bitter lesson for.Under these circumstances, carry out urban underground engineering construction security risk Research on Control, inquire into the content of underground construction safety and risk management, the technological means of research risk evaluation index, standard and risk averse and method are set up urban underground engineering construction security evaluation management system, adopt scientific and rational technological means and method, various risks are controlled, by prediction and prevention, the incidence of risk and risk loss are reduced to bottom line, be very in good time and necessary.
The research of the environmental risk that underground engineering construction is caused at present mainly concentrates on risk discrimination method and the methods of risk assessment, risk assessment and analytical method commonly used mainly contain: based on the expert survey of confidence index, fuzzy comprehensive evaluation method, analytic hierarchy process (AHP), failure tree analysis (FTA) method etc.And after assessment, how provide aspect corresponding risk control measure and the bypassing method also imperfection from technological layer, can not form complete risk control system.
The present invention is directed to the risk in the city underground engineering construction, proposed to distribute the security risk control method that is controlled to be core, by the construction safety in feedback information, process control and the construction of process recovery assurance city underground engineering with heterotaxis.In order to overcome the deficiency of prior art structure, the invention provides a kind of city underground engineering security risk kinetic controlling equation method.
Summary of the invention
The objective of the invention is to be achieved through the following technical solutions.
City underground engineering construction safety risk dynamic control method comprises following five steps:
Step 1: the As-Is Assessment of existing structure and safety evaluatio, carry out on-site investigation for the existing important building in the construction infection scope: the position relation in building type, present circumstances and tunnel, carrying out safety analysis under various typical variant patterns calculates, draw building non-deformability P, determine ultimate strength thus, can provide control criterion after taking all factors into consideration safety factor; For complex large-sized underground structure, should provide the distortion and the stressed control criterion of temporary structure under the various unfavoured states, thereby in work progress, early warning and warning be carried out in safety by monitoring.
Step 2: construction infection prediction and constructure scheme are determined, take all factors into consideration geological conditions, Tunnel Design parameter and condition of construction and carry out analytical calculation, draw constructing tunnel and cause malformation predicted value S.Based on feasible constructure scheme influence is predicted, to determine the constructure scheme of added influence minimum, and when the construction added influence can not satisfy requiring of control criterion, then should take preliminary treatment measures such as grouting and reinforcing, also can propose reinforce requirement to structure, its target is that added influence reaches construction standard and can accept, and controls when requiring when added influence can't reach whole, can consider to adopt " process recovery " means, to guarantee that totally controlling target does not transfinite.
Step 3: the formulation of process control scheme and enforcement, when building non-deformability P causes malformation predicted value S more than or equal to constructing tunnel, formulate each stage controlling value C according to the displacement distribution principle i, improve construction otherwise need to adopt, improve the building consolidation effect, means such as fulfillment process recovery guarantee the safety of existing structure in construction.
Step 4: monitoring measurement and feedback information: i is construction step preface, when i=1, begin construction, to each construction step, according to engineering characteristic and control emphasis, select the emphasis control index enforcement overall process monitoring of key position, can carry out online or remote real time monitoring, monitored data is handled also feedback in time in real time in the crucial construction stage; According to construction monitoring value M iMonitoring result is worked as M i≤ C iThe time, analyze reason and strengthen working measure, and combine with work progress, the safety of engineering is made an appraisal and judge by network analysis, thereby on working measure, in time react.
Step 5: assessment and structural behavior reparation behind the worker, after constructing tunnel is finished, objectively to impact existing subway structure inevitably, or the function of use of structure is caused some infringements, therefore tackle the degree that is impacted and make an appraisal; According to the degree of infringement necessity, feasibility and the economic rationality recovered are made simultaneously and analyzing and assessment, and provide corresponding recovery scheme, measure and suggestion in view of the above.
The invention has the beneficial effects as follows:
(1) is applicable to the control of complicated urban underground engineering construction security risk, passes through existing building, pipeline, plastid etc. poorly such as: tunnel;
(2) it is scientific the city underground engineering risk management to be had more, and makes and the operability of control measure finally realize the standardization of underground engineering construction safety risk management;
(3) under job practices of drafting and engineering specifications, in conjunction with engineering reality, monitoring achievement and theory analysis and the numerical simulation result of the past, deflection to each construction stage decomposes, being about to overall goal is decomposed into phase targets and controls, realization by stage control target reaches the control to overall goal, thereby has guaranteed the Environmental security of city underground engineering construction.
Description of drawings
The working plan that Fig. 1 dynamically controls for city underground engineering construction safety risk of the present invention;
Fig. 2 is prediction, the monitoring curve figure of existing structure sedimentation in the work progress of the present invention.
The specific embodiment
The invention will be further described below in conjunction with the drawings and specific embodiments.
Wear the subway interval under certain city underground station and be listed in superfine risk point, the shallow burial hidden digging construction is adopted at this station, strides formula tunneling station, island for twin columns three, and the two ends, station are double-decker, and the centre is a single layer structure, station overall width 24.2m.The width that the station individual layer passes through existing subway is 16.5m, and clear distance 1.98m only applies big pipe shed support between the old and new's structure between two structures.In order to guarantee that newly-built station passes through the safety in existing interval, adopted the security risk kinetic controlling equation method among the present invention.
(1) as shown in Figure 1, the As-Is Assessment of existing structure and safety evaluatio, take all factors into consideration existing subway type, relation between existing subway present circumstances and existing subway and the newly-built station, analysis by existing structure and operation security, provided structure sediment respectively, the control criterion of horizontal distortion and railway roadbed disengaging value, the maximum settlement value of final selected structure and relative settlement value are as the control index, wherein the maximum settlement permissible value is 40mm, consider certain safety stock, adopt 36mm as the settlement Control value at last, early warning value 22mm, alarming value are 32mm.
(2) construction infection prediction and constructure scheme are determined, big section shallow buried covered excavation subway station can be adopted post hole method, middle hole method and the construction of side hole method usually, maximum settlement amount with existing structure is a target for this reason, these three kinds of feasible constructure scheme are carried out forecast analysis, realize optimization thus job practices.Adopt above-mentioned three kinds of constructure scheme, the final settlement of existing line structure is respectively: 35mm, 47mm, 62mm.As seen the settling amount minimum of structure when adopting the method construction of post hole.Therefore choose the construction of post hole method as final newly-built station.
(3) shown in the curve among Fig. 21, the formulation of process control scheme and enforcement, in the digging process of subway station, the final settlement of existing interval structure is formed by all multiple operation accumulative total, and all there is its corresponding sedimentation value control criterion in each stage.Draft out the existing structure Deformation control desired value of different construction stages by computational analysis, form the control scheme, at this moment can carry out the construction of subway station according to the scheme of drafting.
(4) shown in the curve among Fig. 22, monitoring measurement and feedback information, in work progress, sedimentation and distortion to existing structure of the subway adopt hydrostatic level to carry out real-time monitoring, finish when hole, both sides Guan Peng applies, and the structure sediment value reaches 30mm, still in control range, but at this moment implemented structure lifting slip casting before digging for the operation standard that improves circuit in that side is wide open, i.e. " process recovery " makes that side is wide open to dig, support the back structure sediment value that finishes and return to 14.76mm.
(5) shown in the curve among Fig. 22, assessment and structural behavior reparation behind the worker, after newly-built station construction was finished, existing interval structure sedimentation value was 18.42mm; After implemented side hole slip-casting lifting once more after the assessment behind the worker, promptly " recover behind the worker ", the final structure sedimentation value is 14.85mm.

Claims (1)

1. city underground engineering construction safety risk dynamic control method, it is characterized in that: this method comprises following five steps:
Step 1: the As-Is Assessment of existing structure and safety evaluatio, carry out on-site investigation for the existing important building in the construction infection scope: the position relation in building type, present circumstances and tunnel, carrying out safety analysis under various typical variant patterns calculates, draw building non-deformability P, determine ultimate strength thus, consider to provide control criterion after the safety factor; For complex large-sized underground structure, should provide the distortion and the stressed control criterion of temporary structure under the various unfavoured states, thereby in work progress, early warning and warning be carried out in safety by monitoring;
Step 2: construction infection prediction and constructure scheme are determined, influence factor determines to take all factors into consideration geological conditions, Tunnel Design parameter and condition of construction are carried out analytical calculation, draw constructing tunnel and cause malformation predicted value S, based on feasible constructure scheme influence is predicted, to determine the constructure scheme of added influence minimum, and when the construction added influence can not satisfy requiring of control criterion, then should take preliminary treatment measures such as grouting and reinforcing, also can propose to reinforce requirement to structure, its target is that added influence reaches construction standard and can accept, and when added influence can't reach whole control and requires, can consider to adopt " process recovery " means, to guarantee that totally controlling target does not transfinite;
Step 3: the formulation of process control scheme and enforcement, when building non-deformability P causes malformation predicted value S more than or equal to constructing tunnel, formulate each stage controlling value C according to the displacement distribution principle i, improve construction otherwise need to adopt, improve the building consolidation effect, means such as fulfillment process recovery guarantee the safety of existing structure in construction;
Step 4: monitoring measurement and feedback information, i is construction step preface, when i=1, begin construction, to each construction step,, select the emphasis control index of key position to implement the overall process monitoring according to engineering characteristic and control emphasis, can carry out online or remote real time monitoring in the crucial construction stage, monitored data is handled and timely feedback in real time; According to construction monitoring value M iMonitoring result is worked as M i≤ C iThe time, analyze reason and strengthen working measure, and combine with work progress, the safety of engineering is made an appraisal and judge by network analysis, thereby on working measure, in time react;
Step 5: assessment and structural behavior reparation behind the worker, after constructing tunnel is finished, objectively to impact existing subway structure inevitably, or the function of use of structure is caused some infringements, therefore tackle the degree that is impacted and make an appraisal; According to the degree of infringement necessity, feasibility and the economic rationality recovered are made simultaneously and analyzing and assessment, and provide corresponding recovery scheme, measure and suggestion in view of the above.
CN2009100782351A 2009-02-23 2009-02-23 Risk dynamic control method for construction safety of city underground engineering Expired - Fee Related CN101498221B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100782351A CN101498221B (en) 2009-02-23 2009-02-23 Risk dynamic control method for construction safety of city underground engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100782351A CN101498221B (en) 2009-02-23 2009-02-23 Risk dynamic control method for construction safety of city underground engineering

Publications (2)

Publication Number Publication Date
CN101498221A true CN101498221A (en) 2009-08-05
CN101498221B CN101498221B (en) 2011-04-27

Family

ID=40945472

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100782351A Expired - Fee Related CN101498221B (en) 2009-02-23 2009-02-23 Risk dynamic control method for construction safety of city underground engineering

Country Status (1)

Country Link
CN (1) CN101498221B (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102434209A (en) * 2011-11-03 2012-05-02 上海理工大学 Monitoring method for influence on adjacent existing structures from tunnel excavation
CN102609774A (en) * 2012-01-31 2012-07-25 华中科技大学 System and method for identifying and reasoning security risks of metro construction
CN102619531A (en) * 2012-03-06 2012-08-01 北京交通大学 Multi-step sequence construction deformation control method for shallow-buried tunnel with big cross section
CN102900441A (en) * 2012-09-18 2013-01-30 铁道部经济规划研究院 China tunnel construction method based on complete deformation control of surrounding rocks
CN102999695A (en) * 2012-10-31 2013-03-27 华中科技大学 Subway construction safety risk identification and evaluation system and working method thereof
CN103093400A (en) * 2013-01-24 2013-05-08 华中科技大学 Adjacent building safety quantitative evaluation method in tunnel construction
CN103225510A (en) * 2013-03-22 2013-07-31 上海建科工程咨询有限公司 Construction method of tunnel construction risk map for TBM (tunnel boring machine)
CN106649912A (en) * 2016-09-06 2017-05-10 中铁十六局集团北京轨道交通工程建设有限公司 Settlement prediction method for metro tunnel shield undercrossing existing railway facilities
CN108520355A (en) * 2018-04-09 2018-09-11 中铁十二局集团第二工程有限公司 Building As-Is Assessment method is worn under complex conditions hydraulic tunnel
CN108643937A (en) * 2018-04-27 2018-10-12 中铁十二局集团有限公司 The prevention restoration methods of residential area are worn under hydraulic tunnel
CN109978378A (en) * 2019-03-28 2019-07-05 北京市市政工程研究院 A kind of new construction passes through the work post evaluation method of existing road equipment
CN110008562A (en) * 2019-03-28 2019-07-12 北京交通大学 Damaging judge method after the work of existing road equipment based on monitoring control irrelevance
CN111058855A (en) * 2019-11-11 2020-04-24 北京住总集团有限责任公司 Deformation control method and evaluation system for shield underpassing structure
CN111368016A (en) * 2020-02-28 2020-07-03 重庆市勘测院 Multi-threshold-constrained rail transit control protection area spatial information extraction and analysis method
CN111457889A (en) * 2020-06-02 2020-07-28 中际物联科技(深圳)有限公司 Method for monitoring subway tunnel settlement through optical fiber static level
CN112257154A (en) * 2020-10-20 2021-01-22 北京交通大学 Urban tunnel transparent construction monitoring method and system
CN112983548A (en) * 2021-03-05 2021-06-18 四川省建筑科学研究院有限公司 Underground construction monitoring and early warning method, device, server and system
CN113886913A (en) * 2021-09-18 2022-01-04 中铁十八局集团有限公司 Method for reinforcing equivalent stiffness of underground engineering connection

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102434209A (en) * 2011-11-03 2012-05-02 上海理工大学 Monitoring method for influence on adjacent existing structures from tunnel excavation
CN102609774A (en) * 2012-01-31 2012-07-25 华中科技大学 System and method for identifying and reasoning security risks of metro construction
CN102609774B (en) * 2012-01-31 2014-05-07 华中科技大学 System and method for identifying and reasoning security risks of metro construction
CN102619531A (en) * 2012-03-06 2012-08-01 北京交通大学 Multi-step sequence construction deformation control method for shallow-buried tunnel with big cross section
CN102900441A (en) * 2012-09-18 2013-01-30 铁道部经济规划研究院 China tunnel construction method based on complete deformation control of surrounding rocks
CN102900441B (en) * 2012-09-18 2016-01-20 铁道部经济规划研究院 Based on country rock be badly deformed control China tunnel construction method
CN102999695A (en) * 2012-10-31 2013-03-27 华中科技大学 Subway construction safety risk identification and evaluation system and working method thereof
CN103093400B (en) * 2013-01-24 2017-04-26 华中科技大学 Adjacent building safety quantitative evaluation method in tunnel construction
CN103093400A (en) * 2013-01-24 2013-05-08 华中科技大学 Adjacent building safety quantitative evaluation method in tunnel construction
CN103225510A (en) * 2013-03-22 2013-07-31 上海建科工程咨询有限公司 Construction method of tunnel construction risk map for TBM (tunnel boring machine)
CN103225510B (en) * 2013-03-22 2016-05-18 上海建科工程咨询有限公司 A kind of construction method of rock tunnel(ling) machine the risk of tunnel construction map
CN106649912A (en) * 2016-09-06 2017-05-10 中铁十六局集团北京轨道交通工程建设有限公司 Settlement prediction method for metro tunnel shield undercrossing existing railway facilities
CN108520355A (en) * 2018-04-09 2018-09-11 中铁十二局集团第二工程有限公司 Building As-Is Assessment method is worn under complex conditions hydraulic tunnel
CN108643937A (en) * 2018-04-27 2018-10-12 中铁十二局集团有限公司 The prevention restoration methods of residential area are worn under hydraulic tunnel
CN108643937B (en) * 2018-04-27 2020-01-31 中铁十二局集团有限公司 Prevention and recovery method for hydraulic tunnel lower-crossing residential area
CN109978378A (en) * 2019-03-28 2019-07-05 北京市市政工程研究院 A kind of new construction passes through the work post evaluation method of existing road equipment
CN110008562A (en) * 2019-03-28 2019-07-12 北京交通大学 Damaging judge method after the work of existing road equipment based on monitoring control irrelevance
CN109978378B (en) * 2019-03-28 2020-11-20 北京市市政工程研究院 Post-construction evaluation method for new construction to pass through existing road facilities
CN113153335A (en) * 2019-11-11 2021-07-23 北京住总集团有限责任公司 Safety management system for shield downward penetration
CN111058855A (en) * 2019-11-11 2020-04-24 北京住总集团有限责任公司 Deformation control method and evaluation system for shield underpassing structure
CN111058855B (en) * 2019-11-11 2021-03-16 北京住总集团有限责任公司 Deformation control method and evaluation system for shield underpassing structure
CN111368016A (en) * 2020-02-28 2020-07-03 重庆市勘测院 Multi-threshold-constrained rail transit control protection area spatial information extraction and analysis method
CN111368016B (en) * 2020-02-28 2023-04-11 重庆市勘测院 Multi-threshold-value-constrained rail transit control protection area spatial information extraction and analysis method
CN111457889A (en) * 2020-06-02 2020-07-28 中际物联科技(深圳)有限公司 Method for monitoring subway tunnel settlement through optical fiber static level
CN111457889B (en) * 2020-06-02 2022-07-12 中际物联科技(深圳)有限公司 Method for monitoring subway tunnel settlement through optical fiber static level
CN112257154A (en) * 2020-10-20 2021-01-22 北京交通大学 Urban tunnel transparent construction monitoring method and system
CN112257154B (en) * 2020-10-20 2023-12-01 北京交通大学 Transparent construction monitoring method and system for urban tunnel
CN112983548A (en) * 2021-03-05 2021-06-18 四川省建筑科学研究院有限公司 Underground construction monitoring and early warning method, device, server and system
CN113886913A (en) * 2021-09-18 2022-01-04 中铁十八局集团有限公司 Method for reinforcing equivalent stiffness of underground engineering connection
CN113886913B (en) * 2021-09-18 2024-02-06 中铁十八局集团有限公司 Method for reinforcing equivalent rigidity of underground engineering connection

Also Published As

Publication number Publication date
CN101498221B (en) 2011-04-27

Similar Documents

Publication Publication Date Title
CN101498221B (en) Risk dynamic control method for construction safety of city underground engineering
Wu et al. A dynamic Bayesian network based approach to safety decision support in tunnel construction
Lin et al. Novel model for risk identification during karst excavation
CN105095679A (en) Security risk early warning measurement and judgment method of foundation pit tunnel engineering
CN106193083B (en) A kind of subsidence control method of more pilot tunnel tunnel underbridge stakes
CN102900441A (en) China tunnel construction method based on complete deformation control of surrounding rocks
CN108256172B (en) Dangerous case early warning and forecasting method in process of pipe jacking and downward passing existing box culvert
CN111178712B (en) Rescue early warning method and system for diversion project accident
CN111898184A (en) Method for analyzing influence of shallow-buried subsurface tunnel pipe curtain reinforcement on ground and pile foundation
Wu et al. A dynamic decision approach for risk analysis in complex projects
Luo et al. Research on construction safety risk assessment of new subway station close-attached undercrossing the existing operating station
CN114881440A (en) Risk control method and system for shield tunnel to pass through high-speed railway bridge downwards
CN117035431B (en) Airport engineering project construction risk assessment method based on artificial intelligence
Yang et al. Analysis on security risks in tunnel construction based on the fault tree analysis
CN116993163A (en) Water conservancy and hydropower engineering construction safety supervision system and method
An et al. Comparison and Economic Envelope Structure Schemes for Deep Foundation Pit of Subway Stations Based on Fuzzy Logic
CN112257154B (en) Transparent construction monitoring method and system for urban tunnel
CN110245785A (en) A kind of intelligence active servo foundation pit axle power control method
CN111125961A (en) Fine step-by-step control method for bridge settlement deformation in subway tunnel construction
Xu et al. Safety analysis of deep foundation excavation in water-rich soft soils based on BIM
Li et al. Ahp-fse-based risk assessment and mitigation for slurry balancing shield tunnel construction
CN111062084A (en) Municipal bridge engineering construction supervision system
Li et al. Tunnel water burst disaster management engineering based on artificial intelligence technology–taking Yonglian Tunnel in Jiangxi Province as the object in China
CN117877198B (en) Safe operation and maintenance system applied to construction site
Chen et al. Modeling the dynamic safety management of buildings adjacent to karst shield construction: An improved cloud Bayesian network

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Zhang Dingli

Inventor after: Zhang Chengping

Inventor after: Fang Qian

Inventor after: Luo Jianjun

Inventor after: Hou Yanjuan

Inventor after: Su Jie

Inventor after: Huang Jun

Inventor after: Li Hong

Inventor after: Chen Tielin

Inventor before: Zhang Dingli

Inventor before: Zhang Chengping

Inventor before: Fang Qian

Inventor before: Luo Jianjun

Inventor before: Hou Yanjuan

Inventor before: Su Jie

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: ZHANG DINGLI ZHANG CHENGPING FANG QIAN LUO JIANJUN HOU YANJUAN SU JIE TO: ZHANG DINGLI ZHANG CHENGPING FANG QIAN LUO JIANJUN HOU YANJUAN SU JIE HUANG JUN LI HONG CHEN TIELIN

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110427

Termination date: 20150223

EXPY Termination of patent right or utility model