CN101457853B - 非开挖拉管施工工法 - Google Patents

非开挖拉管施工工法 Download PDF

Info

Publication number
CN101457853B
CN101457853B CN2008102340572A CN200810234057A CN101457853B CN 101457853 B CN101457853 B CN 101457853B CN 2008102340572 A CN2008102340572 A CN 2008102340572A CN 200810234057 A CN200810234057 A CN 200810234057A CN 101457853 B CN101457853 B CN 101457853B
Authority
CN
China
Prior art keywords
pipe
pipeline
tube
construction method
pulling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2008102340572A
Other languages
English (en)
Other versions
CN101457853A (zh
Inventor
马晓波
展宏宇
季政
周宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU GUANGYU CONSTRUCTION GROUP CO Ltd
Original Assignee
JIANGSU GUANGYU CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU GUANGYU CONSTRUCTION GROUP CO Ltd filed Critical JIANGSU GUANGYU CONSTRUCTION GROUP CO Ltd
Priority to CN2008102340572A priority Critical patent/CN101457853B/zh
Publication of CN101457853A publication Critical patent/CN101457853A/zh
Application granted granted Critical
Publication of CN101457853B publication Critical patent/CN101457853B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

本发明涉及一种非开挖拉管施工工法,包括下列步骤:(1)准备工作:了解地层和地下情况,计算扩孔次数和回扩器规格,制定管道中线和高程的控制数据和纠偏措施;(2)测量平面控制放线并测出各桩高程;(3)设置工作井和接受井并安置钻机;(4)配置钻液;(5)导向钻孔;(6)采用扩孔器扩孔,同时清孔,泥浆护壁;(7)管道焊接;(8)拉管同时一并拉入与管等长的钢管;(9)注浆加固;(10)管件安装;(11)试压冲洗。根据本发明可以有效提高经济效益、社会效益,环保、节能效益。

Description

非开挖拉管施工工法
技术领域
本发明公开了一种管道铺设技术领域的拉管施工工法,尤其是一种非开挖拉管施工工法。
背景技术
随着国民生活水平的不断提高,城市的市政管网更新改造步伐加快,常规的地下管道铺设方法采用的是明挖法布管。但由于受到地理、环境影响,以及地下建筑物阻挡,交通拥挤,地下管线布置的错纵复杂,明挖法布管已不能满足施工条件的要求,有时甚至是无法施工。
发明内容
为了克服上述现有技术中存在的缺点,本发明提供了一种不受地下、地上建筑物、管网线等障碍物及地下水位高低的影响,且方便、快捷、不破坏城市路面、工期短、效率高的非开挖拉管施工工法。
为了实现上述目的,本发明所采用的技术方案为:非开挖拉管施工工法,该方法包括以下步骤:
(1)准备工作:施工前地层和地下情况的了解(主要包括土层标准分类、孔隙度、含水性、透水性及地下水位、基岩深度和含卵砾,以及地下已有管线和其它埋设物的位置,为钻进方法和配制钻液及设计钻进轨迹提供依据)。根据敷设管道管径,计算出管道孔的扩孔次数和每次回扩所使用的回扩器规格,制定管道中线和高程的控制数据和纠偏措施。
(2)测量放线;平面控制放线,依据现有边线,通过控制点引测本工程定位点。用全站仪沿地面管道中心线每3米设置一桩(有障碍物除外),沿管道中心线放线并测出各桩高程,计算各桩高程与设计管道流水面的关系。
(3)设备就位:入土钻入处和出土钻出处分别设置带斜坡的工作井和接收井,并确定井壁坡度和支护,标准水平段工作井和接收井为矩形坑。工作井施工完后,根据北高南低的管道设计坡度和支护,然后在工作井中安置钻机。
(4)钻液配置:钻液由水、膨润土和聚合物等组成。为改善泥浆性能,钻液可加入适量化学处理剂烧碱,可增加粘性、增加静切力、调节PH值。
(5)导向钻孔:钻机就位后,调整钻机导向杆至略高于设计管位中心高程的位置(避免PE管在孔内拉动过程中受重力的作用发生管道下沉现象),水平钻入土中(入土、出土处为斜向钻入、钻出)。为保证导向钻头能严格按操作人员发出的指令前进,需在管道线路初步布点后对控制点进行加密,间隔3米设中线,高程控制点,用木桩做出标志并严加保护。
(6)扩孔、泥浆护壁:根据现场地质情况,采用扩孔器进行扩孔,扩孔结束后进行清孔,清孔可以降低孔内压力,减小管线回拖拉力(阻力)。
(7)管道焊接:利用熔接机进行焊接,如果施工现场条件允许,可在沟槽上进行焊接。管口应临时堵封。焊接结束冷却时,不得移动连接件或连接件上不得施加任何外力。
(8)拉管:管线焊缝和管道强度检验合格后,进行拉管施工。管头用封套密封,管头后端接上扩孔器,以保证管线回拖时不出现卡管现象。
(9)注浆加固:管道拉通后,为了避免地面沉降,需注浆加固。移动拉管机到接收井,和钢管连接并回拽。每拽入6m,把钢管和拉管机连接取消,换成和高压注浆泵连接。注入1∶1水泥、粉煤灰浆液(0.4Mpa),置换泥浆,补充PE管周围的空隙。然后再换再拉,再拉再注浆,反复进行,直到把钢管全部拉出接收井,注浆过程结束。
(10)管件安装:管线穿越完成后,按设计图纸安装三通、阀门、检查井等管件配套
(11)试压冲洗:连续对管道冲洗,冲洗后用漂白粉溶液注入管道内浸泡消毒,然后进行管道试压,其程序为:串水→浸泡→水压严密性试验→强度试验→排水。
根据上述方案的进一步设置,步骤(1)所述的工作井和接收井为矩形坑,便于钻机入土开钻,并且还可作为泥浆的排放和收集点,若泥浆过多可采用泥浆车外运。
步骤(2)所述的高程控制点根据水准点引测,精度用仪器两次高程前后视等距测法保持。用经纬仪进行引测设计方向、位置的正确性,控制线传递。
步骤(3)所述的工作井和接收井深度根据管道流水面高程确定,同时在其附近设泥浆沉淀池,以保证工作井内干燥和扩孔施工。
步骤(3)所述钻机的底脚可以安置在20cm厚C15平基砼上,并在平基砼内预埋φ20钢筋(地锚)和钻机焊接牢固,以防因土质较软,拉管距离长,拉力较大而造成的地基沉降而影响钻机稳定。
步骤(4)所述的钻液具有冷却钻头,润滑钻具的作用,更主要的是可以悬浮和携带钻屑,使混合后的钻屑成为流动的泥浆顺利排出孔外,既为回拖管线提供足够的环形空间,又可减少回拖管线的重量和阻力。残流在孔中的泥浆可以起到护壁作用。
步骤(5)所述的导向钻头中安装发射器,通过地面接收器,测得钻头深度,鸭嘴板面向角、钻孔顶角、钻头温度和电池状况等参数,将测得参数与钻孔轨迹进行对比,以便及时纠正。操作手根据信号反馈操纵钻机按正确的轨迹钻进。同时技术人员根据探测器所发回的信号,判断导向钻头位置与钻进路线图的偏差,随时调整,并把调整数值记录在“钻进位置”相应表格。
步骤(6)所述的扩孔器为刮刀式,其尺寸为铺设管径的1.2~1.5倍,这样既能够保持泥浆流动畅通,又能保证管线安全顺利拖入孔中。
步骤(8)所述的拉管过程中,在拉管施工前,在管前端连接两根与管同长度的钢管,与管一同拉入土中并一同到达拉管设计终点桩号,然后解除与PE管的连接,以便进行后续的注浆加固施工。
步骤(11)所述的冲洗程序中,冲洗流量不应小于设计流量或不小于1.5m/s的流速。
本发明所述的非开挖拉管施工工法的有益效果是,改变了传统明挖埋管施工方法,减少大量的土方开挖量、回填工作量,减少了土方扬尘污染,无需地下降水,减少了降排水污染,不受气候影响,不受地下、地上障碍物及周围环境影响,施工速度快,工程质量好,降低了劳动强度,节约了大量的挖、回土方人工费,经济效益可观,社会效益明显,环保、节能效益显著。
本发明所述的非开挖拉管施工工法特别适用于城市的市政管网的铺设,尤其适用松软土层或富水松软地层中敷设直径≤800mm的管道施工。
附图说明
图1:为施工工艺流程图;
图2:拉管施工立面布置图;
图3a:钻进示意图;
图3b:图3a的左视图;
图4a:扩孔钻进示意图;
图4b:图4a的左视图;
图5a:管道周围加固示意图;
图5b:图5a的左视图;
具体实施方式
下面结合附图和具体的实施方式对本发明作进一步详细的说明:
图1:为施工工艺流程图;图2:拉管施工立面布置图;图3a:钻进示意图;图3b:图3a的左视图;图4a:扩孔钻进示意图;图4b:图4a的左视图;图5a:管道周围加固示意图;图5b:图5a的左视图;
如图1所示,本发明非开挖拉管施工工法的具体实施步骤如下:
(1)施工前准备:了解地层和地下水的情况,以及地下已有管线和其它埋设物的位置;解决施工用电、用水;计算出管道孔的扩孔次数和每次回扩所使用的回扩器规格,向施工作业人员交底;制定管道中线和高程的控制数据和纠偏措施。
(2)测量放线:平面控制放线,依据现有边线,通过控制点引测本工程定位点。用全站仪沿地面管道中心线每3米设置一桩,沿管道中心线放线并测出各桩高程,计算各桩高程与设计管道流水面的关系。用经纬仪引测施工现场的高程控制点。对控制点进行加密,间隔3米设中线、高程控制点,用木桩做出标志并严加保护。
(3)设备就位:如图2所示,入土钻入处和出土钻出处分别设置带斜坡的工作井和接收井,标准水平段工作井和接收井为矩形坑,在工作井附近设泥浆沉淀池。按1∶0.5放坡,不加支护。然后安装钻机。钻机底脚要安置在20cm厚C15平基砼上,并在平基砼内预埋φ20钢筋(地锚)和钻机焊接牢固。
(4)钻液配置:钻液配合比为:膨润土20%,转液宝1%,水75%,浇碱4%。
(5)导向钻孔:如图3a和3b所示,调整钻机导向杆至略高于设计管位中心高程的位置,水平钻入土中(入土、出土处为斜向钻入、钻出)。在导向钻头中安装发射器,通过地面接收器,测得钻头深度,鸭嘴板面向角、钻孔顶角、钻头温度和电池状况等参数,将测得参数与钻孔轨迹进行对比,根据信号反馈操纵钻机按正确的轨迹钻进。同时技术人员根据探测器所发回的信号,判断导向钻头位置与钻进路线图的偏差,随时调整,并把调整数值记录在“钻进位置”相应表格。
(6)扩孔、泥浆护壁:如图4a和4b所示,采用刮刀式扩孔器,扩孔器尺寸为辅设管径的1.2~1.5倍(管径为500mm,最大扩孔φ730mm)。扩孔顺序为φ230→φ330→φ430→φ530→φ630→φ730,随着扩孔径增大,控制扩孔速度.扩孔结束后进行清孔。
在上述实施例中,所使用的钻机具有其特定的施工工艺参数(见表1):
表1:钻机施工工艺参数
  工艺参数   导向孔施工参数   扩孔拉管参数
  动力头转数   30~600r/min   20~500r/min
扭距 0~1000N·m 1500~2500N·m
  给进力   20~50KN
给进速度 0~5m/min
  提升力   10~50KN   65~100KN
  提升速度   0~5m/min   0~3m/min
  水泵流量   100L/min   150~200L/min
(7)管道焊接:本实施例所使用管线为PE管,采用熔接机焊接,焊接时间为5min。焊接温度为200°,冷却时间为45min~60min。焊接结束冷却时,不得移动连接件或连接件上不得施加任何外力。
(8)拉管:管线焊缝和管道强度检验合格后,PE管管头用封套密封,管头后端接上φ730扩孔器,在PE管前端连接两根与PE管同长度的φ25钢管,与PE管一同拉入土中并一同到达拉管设计终点桩号,然后解除钢管与PE管的连接。
(9)注浆加固:如图5a和5b所示,PE管道拉通后,移动拉管机到接收井,和φ25钢管连接并回拽。每拽入6m,把钢管和拉管机连接取消,换成和高压注浆泵连接。注入1∶1水泥、粉煤灰浆液(0.4Mpa),置换泥浆,补充PE管周围的空隙。然后再换再拉,再拉再注浆,反复进行,直到把钢管全部拉出接收井,注浆过程结束。
(10)管件安装:管线穿越完成后,按设计图纸安装三通、阀门、检查井等管件配套。
(11)试压冲洗:管道冲洗时流量不应小于设计流量或不小于1.5m/s的流速。冲洗应连续进行。冲洗后用漂白粉溶液注入管道内浸泡消毒。管道试压程序:串水→浸泡→水压严密性试验→强度试验→排水。试验压力1.0Mpa持续10分钟,接口管身检查无破损及漏水现象,渗水试验标准1.1L/mim/Km。
本发明在施工过程中严格遵守国家和地方政府下发的有关环境保护的法律、法规和规章,加强对施工燃油、工程材料、设备、废水、生产生活垃圾、丢渣的控制和治理,遵守防火及废弃物处理的规章制度,随时接受相关单位的监督检查。
上述实施例不以任何形式限定本发明,凡采用等同替换或等效变换的形式所获得的技术方案,均落在本发明的保护范围之内。
应用实例
实例1.某厂,中水桩号为2+760~3+096,管线长度336m,原设计DN500球墨铸铁管开槽施工,流水面高程为9.996~11.086,管道埋深平均为2m,因现况建筑物无法拆迁,故该处采用拉管施工,336m长分两段拉管,200m为一段,136m为一段,管材改为φ500PE管。拉管施工过程中,没有该厂的正常营业,房屋结构质量没有任何破坏。施工节约土方开挖、回填量3500方,节约人工费12万元,节约造价42万元,工期提前15天,工程竣工验收合格。
实例2.某厂再生水(中水)回用工程穿越游泳池,中水桩号为3+504~3+700,管线长度196m,流水面高层为9.193~9.000,管道埋深平均为3.2m,采用拉管施工,196m一次拉管,管材为φ500PE管。减少土方开挖、回填量2000方,节约人费8万元,节约造价25万元,提前工期10天,工程竣工验收合格。
实例3.某污水管网拉顶管工程,桩号:0+035~1+500,另加300m。主管位于道路慢车道下,采用拉管施工,管材为φ500PE管。节约土方开挖、回填量1900方,节约人工费8万元,节约造价25万元,工期提前10天,工程竣工验收合格。

Claims (8)

1.非开挖拉管施工工法,包括下列步骤:
(1)准备工作:施工前地层和地下情况的了解,根据敷设管道管径,计算出管道孔的扩孔次数和每次回扩所使用的回扩器规格,制定管道中线和高程的控制数据和纠偏措施;
(2)测量放线;平面控制放线,依据现有边线,通过控制点引测本工程定位点;用全站仪沿地面管道中心线每3米设置一桩,沿管道中心线放线并测出各桩高程,计算各桩高程与设计管道流水面的关系;
(3)设备就位:入土钻入处和出土钻出处分别设置带斜坡的工作井和接收井,并确定井壁坡度和支护,标准水平段工作井和接收井为矩形坑;工作井施工完后,根据北高南低的管道设计坡度和支护,同时在工作井中安置钻机;
(4)钻液配置:钻液由水、膨润土和聚合物组成;
(5)导向钻孔:钻机就位后,调整钻机导向杆至略高于设计管位中心高程的位置,水平钻入土中,其中入土、出土处为斜向钻入、钻出;
(6)扩孔、泥浆护壁:根据现场地质情况,采用扩孔器进行扩孔,扩孔结束后进行清孔;
(7)管道焊接:利用熔接机进行焊接,焊接时管口应临时堵封;焊接结束冷却时,不得移动连接件且连接件上不得施加任何外力;
(8)拉管:管线焊缝和管道强度检验合格后,进行拉管施工,管头用封套密封,管头后端接上扩孔器,同时在PE管前端连接两根与PE管同长度的φ25钢管,与PE管一同拉入土中并一同到达拉管设计终点桩号,然后解除钢管与PE管的连接;
(9)注浆加固:管道拉通后,移动拉管机到接收井,和钢管连接并回拽,每拽入6m,将钢管和拉管机连接取消,换成和高压注浆泵连接;注入水泥、粉煤灰浆液,置换泥浆,补充PE管周围的空隙,然后再换再拉,再拉再注浆,反复进行,直到把钢管全部拉出接收井,注浆过程结束;
(10)管件安装:管线穿越完成后,按设计图纸安装三通、阀门、检查井的管件配套;
(11)试压冲洗:连续对管道冲洗,冲洗后用漂白粉溶液注入管道内浸泡消毒,然后进行管道试压,其程序为:串水→浸泡→水压严密性试验→强度试验→排水。
2.根据权利要求1所述的非开挖拉管施工工法,其特征为步骤(2)中为保证导向钻头能严格按操作人员发出的指令前进,需在管道线路初步布点后对控制点进行加密,间隔3米设中线、高程控制点,用木桩做出标志并严加保护。
3.根据权利要求1所述的非开挖拉管施工工法,其特征为步骤(3)的工作井和接收井附近设泥浆沉淀池,且钻机底脚要安置在20cm厚C15平基砼上,并在平基砼内预埋φ20钢筋,和钻机焊接牢固。
4.根据权利要求1所述的非开挖拉管施工工法,其特征为步骤(4)中的钻液加入适量处理剂烧碱。
5.根据权利要求1所述的非开挖拉管施工工法,其特征为步骤(5)中的导向钻头中安装发射器,通过地面接收器,测得钻头深度、鸭嘴板面向角、钻孔顶角、钻头温度和电池状况的参数,将测得参数与钻孔轨迹进行对比,操作手根据信号反馈,操纵钻机按正确的轨迹钻进,同时根据探测器所发回的信号,判断导向钻头位置与钻进路线图的偏差,随时调整,并把调整数值记录在“钻进位置”相应表格。
6.根据权利要求1所述的非开挖拉管施工工法,其特征为步骤(6)中所用的扩孔器为刮刀式扩孔器,扩孔器尺寸为辅设管径的1.2~1.5倍。
7.根据权利要求1所述的非开挖拉管施工工法,其特征为步骤(7)焊接时间为5min;焊接温度为200°,冷却时间为45min~60min。
8.根据权利要求1所述的非开挖拉管施工工法,其特征为步骤(11)冲洗流量不应小于设计流量或不小于1.5m/s的流速,冲洗连续进行,试压时的试验压力为1.0Mpa持续10分钟,接口管身检查无破损及漏水现象,渗水试验标准1.1L/mim/Km。
CN2008102340572A 2008-11-20 2008-11-20 非开挖拉管施工工法 Expired - Fee Related CN101457853B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008102340572A CN101457853B (zh) 2008-11-20 2008-11-20 非开挖拉管施工工法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008102340572A CN101457853B (zh) 2008-11-20 2008-11-20 非开挖拉管施工工法

Publications (2)

Publication Number Publication Date
CN101457853A CN101457853A (zh) 2009-06-17
CN101457853B true CN101457853B (zh) 2012-04-25

Family

ID=40768881

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008102340572A Expired - Fee Related CN101457853B (zh) 2008-11-20 2008-11-20 非开挖拉管施工工法

Country Status (1)

Country Link
CN (1) CN101457853B (zh)

Families Citing this family (46)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101793332B (zh) * 2010-03-18 2011-10-19 中国石油化工集团公司 水平定向钻复合弯管道穿越施工方法
CN101793333A (zh) * 2010-03-18 2010-08-04 中国石油化工集团公司 单边定向钻管道穿越施工方法
CN102468637B (zh) * 2010-11-18 2014-07-02 国家电网公司 拉管施工电缆管的连接密封装置
CN102606805A (zh) * 2012-03-21 2012-07-25 苏州际能环境能源技术有限公司 一种带灌浆功能的下管装置
CN103791159A (zh) * 2012-11-02 2014-05-14 成张佳宁 小直径管道的顶管施工方法
CN103453216B (zh) * 2013-08-19 2015-06-17 广州市恒盛建设工程有限公司 一种多管孔高密度聚乙烯管道的非开挖施工方法
CN103441463A (zh) * 2013-09-10 2013-12-11 天津世纪东大管道穿越工程有限公司 一种长距离集束pe管道非开挖穿越方法
CN103527849B (zh) * 2013-11-01 2016-01-27 甘肃先锋管道制造有限公司 超大口径pe排水管的非开挖施工方法
CN103527850B (zh) * 2013-11-01 2016-02-03 甘肃先锋管道制造有限公司 超大口径pe排水管的非开挖施工系统
CN103603997B (zh) * 2013-11-19 2015-12-30 厦门水务集团有限公司 顶管后退纠偏的施工方法
CN104595578A (zh) * 2015-01-16 2015-05-06 天津穿越工程技术有限公司 一种室内管道更新方法
CN105422016B (zh) * 2015-12-25 2017-12-05 辽宁工程技术大学 一种钻孔清理系统及清理方法
CN105864564B (zh) * 2016-06-15 2018-08-28 长春高祥特种管道有限公司 一种等径穿插修复地下玻璃钢管的方法
CN105952992A (zh) * 2016-06-23 2016-09-21 江苏中达建设工程有限公司 一种拉管工法用管道焊接结构
CN107191675A (zh) * 2017-07-21 2017-09-22 中铁二十三局集团第二工程有限公司 铁路站场电化区段管道铺设施工工法
CN108071341A (zh) * 2017-12-13 2018-05-25 中国二冶集团有限公司 长距离定向穿越施工方法
CN108222221B (zh) * 2018-02-01 2020-06-26 杭州大江东城市设施管养有限公司 一种用于市政排污管的维修工艺
CN108548009B (zh) * 2018-04-19 2020-06-12 哈尔滨广瀚非开挖管道工程有限公司 排水管道铺设方法
CN108591614B (zh) * 2018-05-15 2020-02-11 上海煤气第一管线工程有限公司 燃气旧管道内多管穿越施工方法
CN108678130A (zh) * 2018-06-22 2018-10-19 上海景铭建设发展有限公司 一种非开挖拖拉管施工方法
CN109027420A (zh) * 2018-09-07 2018-12-18 中水电第十工程局(郑州)有限公司 一种市政管线非开挖定向钻施工方法
CN110145230A (zh) * 2019-04-23 2019-08-20 上海勃利燃气设备有限公司 一种水平定向钻进拉管方法
CN110319274A (zh) * 2019-07-08 2019-10-11 新兴铸管股份有限公司 一种新的球墨铸铁管拖拉管施工工艺
CN110778323A (zh) * 2019-09-05 2020-02-11 青岛安装建设股份有限公司 埋地管道牵引穿越施工方法
CN110778272B (zh) * 2019-10-28 2021-09-24 中国电建集团河南工程有限公司 大管径热网管道非开挖方式敷设施工方法
CN110847325A (zh) * 2019-12-12 2020-02-28 南通华新建工集团有限公司 水平定向钻在乡镇污水管网施工工艺
CN111287653A (zh) * 2020-01-15 2020-06-16 安徽建筑大学 水平定向钻硬岩大口径正向扩孔施工方法
CN111236390A (zh) * 2020-01-19 2020-06-05 中建四局安装工程有限公司 一种拉顶管非开挖施工方法
CN111306360A (zh) * 2020-02-24 2020-06-19 广东省第四建筑工程有限公司 一种非开挖管道拉顶铺设施工方法
CN111585239B (zh) * 2020-05-26 2021-02-19 中国建筑第八工程局有限公司 一种机场管线不停航迁改的施工方法
CN112227514A (zh) * 2020-07-15 2021-01-15 杭州市市政工程集团有限公司 一种污水调配主管网施工方法
CN112727365B (zh) * 2020-12-30 2023-02-21 中铁六局集团北京铁路建设有限公司 一种下穿既有铁路非开挖水平定向钻进的施工方法
CN112848332B (zh) * 2020-12-31 2022-07-12 北京易成市政工程有限责任公司 一种拉管施工用热熔焊接机及一种拉管施工方法
CN112814650B (zh) * 2021-01-05 2022-07-26 四川石油天然气建设工程有限责任公司 定向钻无线探棒的测孔工艺及管道回拖风险评估方法
CN112923129B (zh) * 2021-01-21 2022-10-14 四川石油天然气建设工程有限责任公司 油气管道对接式拖管施工工艺及系统
CN116006080A (zh) * 2021-02-10 2023-04-25 江西建工第一建筑有限责任公司 一种快速更换的回扩装置及扩孔方法
CN112780834B (zh) * 2021-02-23 2022-11-18 广东保辉建筑工程有限公司 一种管道连续接长顶拉施工方法
CN112983456B (zh) * 2021-04-01 2023-01-06 中铁四局集团第四工程有限公司 一种富水砂层多排顶管地表变形控制方法
CN113572082A (zh) * 2021-07-22 2021-10-29 西宁方盛电力设计有限公司 一种老旧小区升级改造电缆预埋施工方法
CN114704688A (zh) * 2021-08-13 2022-07-05 中铁三局集团有限公司 一种大跨度倒虹吸斜坡段压力钢管施工方法
CN113933878B (zh) * 2021-12-16 2022-03-08 中建安装集团有限公司 一种基于卫星通信技术的深长越江顶管纠偏系统及方法
CN114658952B (zh) * 2022-03-29 2022-11-08 广州易探科技有限公司 一种热塑成型管道非开挖修复的牵拉装置
CN114992385A (zh) * 2022-05-30 2022-09-02 中建一局集团建设发展有限公司 一种大直径长距离钢制输水管道多接一拖拉施工方法
CN115059055A (zh) * 2022-06-21 2022-09-16 中国五冶集团有限公司 一种牵拉管道施工的土质加固方法
CN116255504B (zh) * 2023-05-15 2023-08-11 中铁四局集团有限公司 一种单侧造斜的水平定向钻管道施工方法
CN116951171A (zh) * 2023-05-26 2023-10-27 中国水电基础局有限公司 一种分布式管道系统

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1218160A (zh) * 1997-11-06 1999-06-02 法国天然气国家服务公司 连接管道的方法
CN1247285A (zh) * 1999-08-24 2000-03-15 范中明 不开挖地表的地下管线安装工程施工方法
CN1280263A (zh) * 1999-07-12 2001-01-17 四川石油管理局川东钻探公司 钻孔牵引套管穿越施工方法
US6896077B1 (en) * 2002-11-04 2005-05-24 The Charles Machines Works, Inc. Rotary driven pipe-bursting tool
CN1865650A (zh) * 2006-06-22 2006-11-22 刘明明 水平螺旋钻机与水平定向钻机协同工作顶管施工方法
CN101158270A (zh) * 2007-11-19 2008-04-09 上海煤气第二管线工程有限公司 水平定向钻进中的原孔倒推施工方法及原孔倒推器

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1218160A (zh) * 1997-11-06 1999-06-02 法国天然气国家服务公司 连接管道的方法
CN1280263A (zh) * 1999-07-12 2001-01-17 四川石油管理局川东钻探公司 钻孔牵引套管穿越施工方法
CN1247285A (zh) * 1999-08-24 2000-03-15 范中明 不开挖地表的地下管线安装工程施工方法
US6896077B1 (en) * 2002-11-04 2005-05-24 The Charles Machines Works, Inc. Rotary driven pipe-bursting tool
CN1865650A (zh) * 2006-06-22 2006-11-22 刘明明 水平螺旋钻机与水平定向钻机协同工作顶管施工方法
CN101158270A (zh) * 2007-11-19 2008-04-09 上海煤气第二管线工程有限公司 水平定向钻进中的原孔倒推施工方法及原孔倒推器

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JP特开2000-248884A 2000.09.12

Also Published As

Publication number Publication date
CN101457853A (zh) 2009-06-17

Similar Documents

Publication Publication Date Title
CN101457853B (zh) 非开挖拉管施工工法
Chen et al. Long rectangular box jacking project: a case study
CN101737060B (zh) 土质下穿隧道超大直径管幕施工方法
CN100410485C (zh) 水平螺旋钻机与水平定向钻机协同工作顶管施工方法
CN108678130A (zh) 一种非开挖拖拉管施工方法
CN109723443B (zh) 隧道施工方法
CN105240019A (zh) 一种顶管施工方法
CN111119940B (zh) 一种注浆施工处理方法
CN106088099B (zh) 一种地铁基坑锚索处理方法
CN103791159A (zh) 小直径管道的顶管施工方法
CN203846485U (zh) 长桩冲击钻成孔施工装置
AU2021106928A4 (en) Construction method for excavation of deep pit with triaxial mixing pile waterstop curtains and rotary bored cast-in-place pile supports
CN104631470A (zh) 高水位大粒径砂砾石地质深基坑组合支护施工方法
Nikiforova et al. Geotechnical cut-off diaphragms for built-up area protection in urban underground development
CN103835651A (zh) 一种单孔定向钻进局部注浆反井钻井工艺
CN108071341A (zh) 长距离定向穿越施工方法
CN107191675A (zh) 铁路站场电化区段管道铺设施工工法
CN102337732A (zh) 顶管穿越块石海堤施工方法
CN112727365A (zh) 一种下穿既有铁路非开挖水平定向钻进的施工方法
CN102623931A (zh) 一种过道地下管线敷设方法及其专用设备
CN113669073B (zh) 一种控制临近建筑变形的富水砂性地层先隧后站施工方法
CN113216142A (zh) 一种岩溶发育区水下溶洞注浆处理方法及系统
CN112252310A (zh) 采用高压旋喷桩机进行深基坑止水帷幕施工的方法
CN110512594A (zh) 旋挖钻机遇空洞成孔成桩的简易方法
CN110067561A (zh) 下穿既有线城市地下暗挖区间施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120425

Termination date: 20181120