CN101446442B - Gm-ⅲ复合风管施工方法 - Google Patents

Gm-ⅲ复合风管施工方法 Download PDF

Info

Publication number
CN101446442B
CN101446442B CN2008102074377A CN200810207437A CN101446442B CN 101446442 B CN101446442 B CN 101446442B CN 2008102074377 A CN2008102074377 A CN 2008102074377A CN 200810207437 A CN200810207437 A CN 200810207437A CN 101446442 B CN101446442 B CN 101446442B
Authority
CN
China
Prior art keywords
construction method
air duct
airduct
composite air
iii
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2008102074377A
Other languages
English (en)
Other versions
CN101446442A (zh
Inventor
沈庆毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai No5 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai No5 Construction Co Ltd filed Critical Shanghai No5 Construction Co Ltd
Priority to CN2008102074377A priority Critical patent/CN101446442B/zh
Publication of CN101446442A publication Critical patent/CN101446442A/zh
Application granted granted Critical
Publication of CN101446442B publication Critical patent/CN101446442B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Duct Arrangements (AREA)

Abstract

本发明涉及通风空调系统中复合风管的施工技术领域。本发明所述的GM-III复合风管的施工方法,其步骤是:首先按照图纸和现场情况准备工料,并对板材进行清洁;然后放样切割,且切割完毕后对切割的边口进行清洁;用卷尺和直角尺对切割好的板材进行复核;其次拼装粘接预制风管;最后安装风管即可。本发明公开的施工方法技术成熟、施工简单、操作方便、质量可靠。同时施工周期短,速度快,工人熟练程度高,从而劳动生产率高,有较好的经济效益。本发明适合使用面广,能广泛应用于国防系统、工业系统、民用系统等场所。

Description

GM-III复合风管施工方法
技术领域
本发明涉及通风空调系统中复合风管的施工技术领域。
背景技术
目前的通风空调风管大多采用镀锌铁皮,而GM-III复合风管是一种代替镀锌铁皮的新型绿色环保风管,其施工工艺流程和施工要点目前尚未制定公开。
发明内容
本发明的目的就是提供GM-III复合风管的施工方法,保证GM-III复合风管的施工质量。
为达上述目的,本发明采取的具体技术方案如下:
GM-III复合风管的施工方法,其步骤如下:
a、按照图纸和现场情况准备工料,并对板材进行清洁;
b、放样切割,且切割完毕后对切割的边口进行清洁;
c、用卷尺和直角尺对切割好的板材进行复核;
d、拼装粘接;
e、安装。
上述的GM-III复合风管的施工方法,其步骤b在切割时,切割机刀片与面板成90°角,切割线应平直,风管板对角线长度误差应小于5mm;切割完毕后,对所切割的边口进行清洁。
上述的GM-III复合风管的施工方法,其步骤d在拼装粘接时优先使用自制的专用胶,也可以使用市售的各种粘接胶。所说的专用胶由氧化镁和卤片溶液混合而成,氧化镁与卤片的重量比为9-11∶5-6。在切割下毛板的接缝处上的专用胶应涂刷均匀、饱满、不缺浆。拼装粘接好后,应用捆扎带及扣子进行固定,捆扎带间距宜为0.6-0.7m。风管的四个转角应为90°角,即风管的四个面互相垂直。预制好的风管,还应填补空隙和清除余胶。当风管周长小于2m时,对角线误差不大于3mm;当周长大于2m时,对角线误差不大于5mm。风管三通、四通导流角的长度不得小于支风管宽度的二分之一。
上述的GM-III复合风管的施工方法,其步骤d在风管安装时,架设临时登高设施和安装支吊架后,首先进行干管安装、支管安装,然后进行漏光实验、局部法兰安装、局部部位法兰联接、配合装饰风口支管安装,最后进行风口镶接和系统集成。
本发明的有益效果:
本发明公开的GM-III复合风管的施工方法技术成熟、施工简单、操作方便、质量可靠。同时施工周期短,速度快,工人熟练程度高,从而劳动生产率高,有较好的经济效益。本发明适合使用面广:能广泛应用于国防系统(如:隧道、防空洞、电站、机场等)、工业系统(如:各类厂房)、民用系统(如:商场、宾馆、超市、办公楼、商住楼、图书馆、体育馆医院等)等场所。
附图说明
下面结合附图进一步说明本发明施工方法的具体步骤:
图1是本发明施工方法的流程框图
图2是本发明复合风管具体安装时的流程框图
具体实施方式
实施例1
如图1所示,首先是熟悉图纸和现场勘测,然后理出工料清单,准备工料。对所有使用风管板材进行清洁,然后放样切割,,且切割完毕后对切割的边口进行清洁。复合风管落料要点如下:
1)切割线应平直,风管板对角线长度误差应小于5mm。
2)切割完毕后,对所切割的边口进行清洁。
3)切割板与面板必须成90°角。
切割完成后进行,对切割下待拼装的板材进行复核,即复核其长宽尺寸及邻边夹角是否符合要求。
对切割好的板材进行拼装粘接。复合风管预制要点如下:
1)以重量比为10∶6准备氧化镁粉末和氧化镁卤片,将卤片用水溶解后与氧化镁粉末混合均匀。氧化镁和卤片采用市售的工业品即可。
2)待拼装毛板接缝处上的专用胶应涂刷均匀、饱满、不缺浆
3)风管预制好后,应用专用捆扎带及扣子进行固定。捆扎带间距宜为0.6m
4)风管的四个转角应为90°角
5)预制好的风管,当周长小于2m时,对角线误差不大于3mm;当周长大于2m时,对角线误差不大于5mm
6)应填补空隙和清除余胶
7)风管三通、四通导流角的长度不得小于支风管宽度的二分之一。
风管预制好后即可进行安装,其流程如图2所示。大型风管加强柱的设置见下表1:
表1
Figure B2008102074377D00041
风管安装要点如下:
1)管段定位应正确,不应多次移动,以免接触面缺胶
2)管段与管段的联结处应上下左右平直、紧密
3)联结好的风管表面应清洁,无挂胶现象
4)风管直线长度每隔20m,应设置1个伸缩节。并在伸缩节处设一个防晃支架
5)在风管的始端、末端及转角处必须设置固定支架
6)直线管段超过20m的风管,每隔20m设置一固定支架
风管吊架间距必须符合下表2所示距离:
表2
使用本发明的施工技术在上海海市大学图文信息中心、南汇疾病控制中心、天山世纪广场工程中进行实践,取得了良好的结果。工程质量获:“安装优质结构”工程奖、上海市“申安杯”工程奖、上海市“白玉兰”工程奖。

Claims (10)

1.GM-III复合风管的施工方法,其步骤如下:
a、按照图纸和现场情况准备工料,并对板材进行清洁;
b、放样切割,且切割完毕后对切割的边口进行清洁;
c、用卷尺和直角尺对切割好的板材进行复核;
d、拼装粘接预制风管;
e、安装风管。
2.如权利要求1所述的GM-III复合风管的施工方法,其特征在于:步骤b在切割时,切割线平直,风管板对角线长度误差小于5mm。
3.如权利要求1所述的GM-III复合风管的施工方法,其特征在于:步骤b在切割时,切割机刀片与面板成90°角。
4.如权利要求1所述的GM-III复合风管的施工方法,其特征在于:步骤d在拼装粘接时使用专用胶,其氧化镁和卤片溶液混合而成。
5.如权利要求4所述的GM-III复合风管的施工方法,其特征在于:所说的氧化镁和卤片的重量比为9-11比5-6。
6.如权利要求1所述的GM-III复合风管的施工方法,其特征在于:步骤d在拼装粘接后用捆扎带或扣子进行固定,捆扎带间距为0.6-0.7米。
7.如权利要求1所述的GM-III复合风管的施工方法,其特征在于:步骤d风管预制后当风管周长小于2m时,对角线误差不大于3mm;当周长大于2m时,对角线误差不大于5mm。
8.如权利要求1所述的GM-III复合风管的施工方法,其特征在于:步骤d风管预制后风管三通、四通导流角的长度不小于支风管宽度的二分之一。
9.如权利要求1所述的GM-III复合风管的施工方法,其特征在于:步骤d在风管安装时,架设临时登高设施和安装支吊架后,首先进行干管安装、支管安装,然后进行漏光实验、局部法兰安装、局部部位法兰联接、配合装饰风口支管安装,最后进行风口镶接和系统集成。
10.如权利要求9所述的GM-III复合风管的施工方法,其特征在于:风管直线长度每隔20米设置1个伸缩节,并在伸缩节处设一个防晃支架。
CN2008102074377A 2008-12-19 2008-12-19 Gm-ⅲ复合风管施工方法 Active CN101446442B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008102074377A CN101446442B (zh) 2008-12-19 2008-12-19 Gm-ⅲ复合风管施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008102074377A CN101446442B (zh) 2008-12-19 2008-12-19 Gm-ⅲ复合风管施工方法

Publications (2)

Publication Number Publication Date
CN101446442A CN101446442A (zh) 2009-06-03
CN101446442B true CN101446442B (zh) 2011-03-30

Family

ID=40742234

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008102074377A Active CN101446442B (zh) 2008-12-19 2008-12-19 Gm-ⅲ复合风管施工方法

Country Status (1)

Country Link
CN (1) CN101446442B (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110425713A (zh) * 2019-07-16 2019-11-08 上海一建安装工程有限公司 不同介质管道变径时偏心异径管的安装方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003106631A (ja) * 2001-10-01 2003-04-09 Toshiba Corp ダクト交換時の据付方法
CN2711611Y (zh) * 2004-07-28 2005-07-20 上海康靖工业成套设备安装有限公司 空调风管连接装置
CN1268866C (zh) * 2003-05-30 2006-08-09 支亮 一种通风管道制作、连接方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003106631A (ja) * 2001-10-01 2003-04-09 Toshiba Corp ダクト交換時の据付方法
CN1268866C (zh) * 2003-05-30 2006-08-09 支亮 一种通风管道制作、连接方法
CN2711611Y (zh) * 2004-07-28 2005-07-20 上海康靖工业成套设备安装有限公司 空调风管连接装置

Also Published As

Publication number Publication date
CN101446442A (zh) 2009-06-03

Similar Documents

Publication Publication Date Title
CN204901084U (zh) 一种基于bim的预制一体化装配式组合支架
CN110440429B (zh) 地铁拱形顶通风管道装配施工方法
CN105804298B (zh) 一种蜂窝状的外凸型不规则幕墙的施工方法
CN108591634B (zh) 机制玻镁复合板风管施工工法
CN101446442B (zh) Gm-ⅲ复合风管施工方法
CN108222398A (zh) 一种装配式石材外装饰围护墙板模板及其预制工艺
CN207176922U (zh) 一种模块化建筑
CN108999417A (zh) 一种干挂式幕墙的安装方法
CN203878746U (zh) 一种组装式轻型房屋
CN205224367U (zh) 房屋屋顶系统
CN212358796U (zh) 一种应急工程组合式屋面
CN210713208U (zh) 一种变电站装配式一体化警卫室
CN203821903U (zh) 一种拼装式配电房
CN113653290A (zh) 中置式连接的玻镁复合板对拼回风夹道施工工法
CN204826205U (zh) 一种由标准周转房组合成大房间的结构
CN207320742U (zh) 一种角度可调的电缆桥架连接件
CN209145011U (zh) 用于施工临建的装配式钢结构模块
CN201933811U (zh) 一种无框架型箱式变电站
CN207988157U (zh) 预制隔墙连接节点
Harrell et al. Building enclosure design for modular construction
CN204960089U (zh) 一种新型预制楼板
CN105370048A (zh) 一种超高超长蒸压轻质加气混凝土板墙体的施工方法
JP2011145049A (ja) 多層階建物における冷媒配管工法と冷媒配管ユニット
CN207296480U (zh) 一种装配式别墅
CN218714701U (zh) 一种排水立管封包设计结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
DD01 Delivery of document by public notice

Addressee: Jie Wenxia

Document name: Notification to Go Through Formalities of Registration

C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: SHANGHAI CONSTRUCTION NO.5 GROUP CO., LTD.

Free format text: FORMER NAME: SHANGHAI NO.5 BUILDING CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 200063 1000 Cao Yang Road, Shanghai

Patentee after: Shanghai Construction NO.5 (Group) Co., Ltd.

Address before: 200063 1000 Cao Yang Road, Shanghai

Patentee before: Shanghai No.5 Construction Co., Ltd.