CN101446090B - Method for fixation of underground storage (stock) gas well unit conjunction - Google Patents

Method for fixation of underground storage (stock) gas well unit conjunction Download PDF

Info

Publication number
CN101446090B
CN101446090B CN2008101527558A CN200810152755A CN101446090B CN 101446090 B CN101446090 B CN 101446090B CN 2008101527558 A CN2008101527558 A CN 2008101527558A CN 200810152755 A CN200810152755 A CN 200810152755A CN 101446090 B CN101446090 B CN 101446090B
Authority
CN
China
Prior art keywords
gas storage
well
storage well
fixation
outer tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2008101527558A
Other languages
Chinese (zh)
Other versions
CN101446090A (en
Inventor
牟万福
王鹏
王健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2008101527558A priority Critical patent/CN101446090B/en
Publication of CN101446090A publication Critical patent/CN101446090A/en
Application granted granted Critical
Publication of CN101446090B publication Critical patent/CN101446090B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The inventive method for fixation of underground storage (stock) gas well unit conjunction comprises the following steps of: digging a deep groove around a cluster of prepared gas storage wells with depth and area thereof being confirmed in accordance with the level of hardness and porosity of actual surface layer; laying steel rods at each gas storage well unit; fixing steel rod web layers that are mutually parallel and cross-fixed, on outer sleeves of the gas storage wells which are sleeved on peripheral of gas storage well pipes, with the welding fixation being employed in general; pouring stirred concrete in spaces around the outer sleeves of the gas storage wells and between the steel rod web layers for casting pad after fixing the steel rod web layers, and then fixing the wells subsequent to solidification thereof. The fixation method has prominent implementing effect in reinforced modification of well tube in early gas storage well, which solves the hidden safety danger caused by inferior quality of well fixation in early gas storage well. In the meantime, the fixation method has been applied in a plurality of projects that has a problem of overall subsidence during or after construction of the gas storage well due to loosened structure of the surface layer, and is also remarkable in usage, thus avoiding loss of ground personnel and property.

Description

The fixing means of underground storage (depositing) storage (stock) gas well unit conjunction
Technical field
The present invention relates to a kind of high pressure gas storage facilities fixing means that relates to, the fixing means of particularly a kind of underground storage (depositing) storage (stock) gas well unit conjunction.
Background technology
Along with the fast development of China's well for storage of high pressure gas new technology and the large tracts of land of nationwide are promoted, the well for storage usage quantity is more and more many, the time constantly prolongs, mode reason and cementing quality that the stratum is limit are uneven owing to cementing the well, after the indivedual gas storage wells in China different regions successively booster occurred, cause underground well casing to go out ground, cause huge injury and loss for ground staff's life and property.Domestic relevant departments and expert scholar have proposed higher safety requirements to this high pressure and inflammable and explosive storage facilities, even that is: the gas storage well cementing quality is not good, booster takes place in a year corrosion for a long time, does not also allow to go out ground.For this reason, the well cementation problem that solves underground storage (depositing) gas well is the task of top priority.
Summary of the invention
For solving the problem that exists in the above-mentioned technology, the fixing means that the purpose of this invention is to provide a kind of underground storage (depositing) storage (stock) gas well unit conjunction, be beneficial to building and in the reinforcing of the high pressure underground gas well of usefulness, particularly since during multiple complicated factor such as stratum and well cementation to the reinforcing of gas storage well; The gas storage gang of wells not good enough to cementing quality carries out second consolidation, so that it corrodes when afterwards booster taking place, can avoid the serious consequence of bringing to ground staff, national wealth fully.
For realizing goal of the invention, the fixing means of the underground storage of the present invention (depositing) storage (stock) gas well unit conjunction includes following steps:
A, around between the gas storage well gang of wells of accomplishing fluently, dig a deep trouth, its degree of depth and area are decided according to the loose hard degree of top layer matter practically, are generally 2-10 rice;
B, between each gas storage well unit, lay reinforcing bar, on the gas storage well outer tube 2 that gas storage well casing 1 periphery is with, weld the reinforcing bar stratum reticulare 4 of the cross fixation that fixedly is parallel to each other, equally spacedly on the periphery of gas storage well outer tube 2 be provided with a plurality of anchor ears 3 and reinforce, directly gas storage well outer tube 2 is held tightly the back with anchor ear 3 and be connected as a single entity with steel concrete.
C, fix reinforcing bar stratum reticulare 4 after, to around the gas storage well outer tube 2 and and reinforcing bar stratum reticulare 4 between the space in pour the concrete 5 that stirs into and pour into a mould filling, treat that it solidifies the back well cementation.
Equally spacedly on the periphery of gas storage well outer tube 2 in above-mentioned B step be provided with a plurality of anchor ears 3 and reinforce, directly gas storage well outer tube 2 is held tightly the back with anchor ear 3 and be connected as a single entity with steel concrete.
The effect that the present invention reaches be this fixing means in early days gas storage well since on the not good enough well casing that causes of cementing quality in the strengthening reconstruction of going here and there implementation result obvious, solved early stage gas storage well because the not good enough potential safety hazard that causes of cementing quality.Simultaneously, the integral body sinking problem of this fixing means in the gas storage well construction that causes owing to the surface layer short texture and after the construction use in a plurality of projects, and effect is obvious, thereby avoids the loss of ground person property.
Description of drawings
Fig. 1,2 manages two embodiment fixed structure schematic diagrames for the conjuncted table in unit of the present invention;
Fig. 3 is a unit of the present invention conjuncted gas storage well pipe fixation structure vertical view.
Among the figure: 1, gas storage well casing 2, gas storage well outer tube 3, anchor ear 4, reinforcing bar stratum reticulare 5, concrete
The specific embodiment
Reaching embodiment in conjunction with the accompanying drawings is illustrated the fixing means of underground storage of the present invention (depositing) storage (stock) gas well unit conjunction.
No matter be gas station or peak regulation station well for storage of high pressure gas, equal gas storage gang of wells of forming by gas storage well unit more than two mouthfuls, each gas storage well unit structurally is fully independently, its extent of corrosion, all be not quite similar service life, the possibility that booster particularly takes place simultaneously is zero substantially, and since its buried underground hardly may be as the above-ground storage tank chain-react, stratum storage power in addition, endergonic huge ability, so, improve the fixing means that has designed a kind of underground storage (depositing) storage (stock) gas well unit conjunction based on this characteristic.This method can be together in series with whole gas storage gang of wells gas station or peak regulation by steel concrete, because of involving other gas storage well that booster does not take place, corrosion generation booster involves the unlikely ground of going out to reach as if certain a bite gas storage well, make the energy of cumulative be released and absorb, thereby thereby avoid the loss of ground person property to realize the purpose of invention underground.
As shown in Figure 1, 2, 3, the fixing means step of underground storage of the present invention (depositing) storage (stock) gas well unit conjunction is achieved in that
A, around between the gas storage well gang of wells of accomplishing fluently, dig a deep trouth, its degree of depth and area are decided according to the loose hard degree of top layer matter practically, are generally 2-10 rice;
B, lay reinforcing bar between each gas storage well unit, the reinforcing bar stratum reticulare 4 of the cross fixation that fixedly is parallel to each other on the gas storage well outer tube 2 that gas storage well casing 1 periphery is with generally adopts welding fixing;
C, fix reinforcing bar stratum reticulare 4 after, to around the gas storage well outer tube 2 and and reinforcing bar stratum reticulare 4 between the space in pour the concrete 5 that stirs into and pour into a mould filling, treat that it solidifies the back well cementation.
Equally spacedly on the periphery of gas storage well outer tube 2 in above-mentioned B step be provided with a plurality of anchor ears 3 and reinforce.Directly gas storage well outer tube 2 being held tightly the back with anchor ear 3 is connected as a single entity with steel concrete.

Claims (1)

1. fixing means that the well for storage unit is conjuncted, this method includes following steps:
A, around between the gas storage well gang of wells of accomplishing fluently, dig the deep trouth of a 2-10 rice, its concrete degree of depth and area are decided according to the loose hard degree of actual face of land soil property;
B, between each gas storage well unit, lay reinforcing bar, go up the parallel each other reinforcing bar stratum reticulare (4) of welding multilayer at the gas storage well outer tube (2) that gas storage well casing (1) periphery is with, every layer of reinforcing bar cross fixation is on gas storage well outer tube (2), and the equally spaced a plurality of anchor ears (3) that are provided with are reinforced on the periphery of gas storage well outer tube (2);
C, fix reinforcing bar stratum reticulare (4) after, to around the gas storage well outer tube (2) and and reinforcing bar stratum reticulare (4) between the space in pour the concrete (5) that stirs into and pour into a mould filling, treat that it solidifies the gas storage well outer tube of directly being held tightly by anchor ear (3) back (2) and is connected as a single entity with steel concrete, well cementation.
CN2008101527558A 2008-10-31 2008-10-31 Method for fixation of underground storage (stock) gas well unit conjunction Expired - Fee Related CN101446090B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008101527558A CN101446090B (en) 2008-10-31 2008-10-31 Method for fixation of underground storage (stock) gas well unit conjunction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008101527558A CN101446090B (en) 2008-10-31 2008-10-31 Method for fixation of underground storage (stock) gas well unit conjunction

Publications (2)

Publication Number Publication Date
CN101446090A CN101446090A (en) 2009-06-03
CN101446090B true CN101446090B (en) 2010-10-13

Family

ID=40741953

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008101527558A Expired - Fee Related CN101446090B (en) 2008-10-31 2008-10-31 Method for fixation of underground storage (stock) gas well unit conjunction

Country Status (1)

Country Link
CN (1) CN101446090B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101846239B (en) * 2010-04-23 2012-11-21 自贡力源科技有限公司 Reinforcing device for underground gas storage well of high-pressure fuel gas and reinforcing and processing method
CN106870929A (en) * 2017-01-19 2017-06-20 四川鼎胜能源设备科技有限公司 High pressure underground gas well fixing device and gas storage well overall structure and fixing means
CN106968714A (en) * 2017-05-03 2017-07-21 四川鼎胜能源设备科技有限公司 High pressure underground gas well emits supervising device and monitoring method on sinking
CN107461603B (en) * 2017-09-21 2019-10-11 西安交通大学 The hot dry rock reheating compressed-air energy-storage system of gas storage heat accumulation one
CN109610609B (en) * 2018-12-19 2021-07-27 中冶南方工程技术有限公司 Integral intercepting ditch of tunnel portal

Also Published As

Publication number Publication date
CN101446090A (en) 2009-06-03

Similar Documents

Publication Publication Date Title
CN101446090B (en) Method for fixation of underground storage (stock) gas well unit conjunction
AU2014407470B2 (en) Underground steel-concrete structure pipeline with spiral composite reinforcement ring on inner wall and manufacturing method thereof
CN102162255B (en) Method for reinforcing existing pile foundation in collapsed loess area by slip casting
CN209780920U (en) Supporting construction in subway tunnel construction in-process field entrance and exit secretly dig tunnel
CN204059403U (en) A kind of low embankment existing gas pipeline insulation blocking structure
CN205711788U (en) A kind of underground piping protection is contained
CN104179194A (en) Integrated pipe trench in soft soil stratum and construction method of integrated pipe trench
CN110836121A (en) Anti-floating reinforcing structure of operated subway tunnel and construction method
CN107794942A (en) Riverbed comprehensive pipe gallery structure and its construction method are worn under one kind
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN203547753U (en) Profile steel concrete shaft wall base
CN203222795U (en) Manual hole digging pile
CN203429648U (en) Large steel cylinder cofferdam structure
US11821316B1 (en) System and construction method of single-layer lining tunnel structure based on mine-tunnelling method
CN210768831U (en) Rigid-flexible combined supporting structure applied to weak surrounding rock tunnel
CN105544620A (en) Damping ditch with pressure relief device and shockproof plates and construction method for damping ditch
CN206308700U (en) A kind of Traffic Engineering Construction slope protection device
CN104294859A (en) Stability judgment method of foundation pit basal-heave resistant system
CN108104113A (en) Exceeded ruggedized construction and construction method are deformed for friction pile in work progress
CN210461993U (en) Composite pipeline for improving strength and anti-deformation capability of ultra-deep buried steel pipe pipeline
CN113089651A (en) Long spiral drilling pressure irrigation energy pile structure and construction method thereof
CN104652426B (en) A kind of saline soil area waterglass anticorrosion pile foundation construction method
CN201330388Y (en) Pumped storage power station buried steel bifurcated pipe and wall rock union forced structure
CN106812538A (en) Built-in type magnesium iron framework-reinforced concrete combination tunnel wallboard
Zhang et al. Construction applicability of mechanical methods for connecting aisle in the bohai mudstone stratum with high water pressure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101013

Termination date: 20211031

CF01 Termination of patent right due to non-payment of annual fee