CN101435222A - Steel lattice column non-cable correcting construction method - Google Patents

Steel lattice column non-cable correcting construction method Download PDF

Info

Publication number
CN101435222A
CN101435222A CNA200810229777XA CN200810229777A CN101435222A CN 101435222 A CN101435222 A CN 101435222A CN A200810229777X A CNA200810229777X A CN A200810229777XA CN 200810229777 A CN200810229777 A CN 200810229777A CN 101435222 A CN101435222 A CN 101435222A
Authority
CN
China
Prior art keywords
shaft
lattice column
column
steel lattice
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA200810229777XA
Other languages
Chinese (zh)
Inventor
田斌
杨名显
孙辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DALIAN SANCHUAN CONSTRUCTION GROUP Co Ltd
Original Assignee
DALIAN SANCHUAN CONSTRUCTION GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DALIAN SANCHUAN CONSTRUCTION GROUP Co Ltd filed Critical DALIAN SANCHUAN CONSTRUCTION GROUP Co Ltd
Priority to CNA200810229777XA priority Critical patent/CN101435222A/en
Publication of CN101435222A publication Critical patent/CN101435222A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to building construction method. A steel grid column non cable correction construction method is disclosed. the bottom elevation of a cup opening is lower than a designed elevation by 50mm; the top surface of the cup opening base is marked with axes, and the column is marked with elevation; the steel grid column is suspended in the cup opening base; jacks are put on the two axes, the steel grid column is pushed to put the column plane in position, and a steel wedge is fixed; four jacks are put at lower parts of four edges of the steel grid column feet and fall down together to reach the requirement of the column elevation, and the four edges of the steel grid column are welded with ear plates fixedly; theodolites are arranged in the two axes directions of the steel grid column, the jacks fixed on the steel grid column are adjusted to calibrate the verticality of the column, hawser cable is temporarily fixed; then the column feet concrete is poured, and the hawser cable is unfastened after reaching certain intensity. Compared with conventional calibration technology using hawser cable, the method of the invention has simple process, convenient operation, and fast construction speed, saves cost, and is not limited by the size of surrounding place.

Description

Steel lattice column non-cable correcting construction method
One, technical field:
The present invention relates to construction techniques, particularly the correcting construction method of steel lattice column.
Two, background technology:
Heavy Type Steel Structure industry garage, because the steel work size is big, weight is big, increased very big difficulty of construction to lifting, correction, for guaranteeing the Steel Structure Installation quality, must adopt rational mounting process, bearing calibration, particularly for more apparent its importance of many limbs steel lattice column of proofreading and correct ultra-high overweight is installed.
Conventional at present installation correcting construction method is to adopt hawser
Three, summary of the invention:
The purpose of this invention is to provide a kind of steel lattice column non-cable correcting construction method, lifting speed is fast, and it is convenient to proofread and correct, precision height, easy construction.
The technical scheme that the present invention is adopted for achieving the above object is: steel lattice column non-cable correcting construction method, first step preparation of construction basis is checked and accepted: the rim of a cup basis is cleared up, check rim of a cup at the bottom of absolute altitude be lower than design elevation 50mm; The second stepping rower is annotated: mark out on reference axis, the shaft at rim of a cup basis end face and mark absolute altitude; The 3rd step lifting: steel lattice column is hung in the rim of a cup basis; The 4th step correcting plane position: lay jack on two axis, the pushing tow steel lattice column makes the post plane in place, and fixes with gad; The 5th step was proofreaied and correct absolute altitude: place four jack below steel latticework suspension column four limits, withstand on the steel lattice column bottom surface, loosen the lifting hook, four jack fall simultaneously, adhere to specification until the post absolute altitude, on steel lattice column four limits, weld fixedly steel lattice column absolute altitude of otic placode; The 6th step was proofreaied and correct verticality: lay two transits on two axis directions of steel lattice column, use adjustment to be fixed on steel pile and proofread and correct the post verticality, after meeting the requirements, use the temporary fixed steel column of cable wind rope; The 7th the step build: build the suspension column concrete then, reach design strength 90% after, take off cable wind rope.
The described second step mark: mark ± 0.00 absolute altitude line, post center line, the elongated line of shaft on shaft.
Described the 3rd step lifting: adopt crawler crane to carry out the single-point lifting.
Described the 4th step correcting plane position: the pushing tow shaft makes x axis and basic end face x dead in line on the shaft, put into steel plate in the rim of a cup and the shaft tack weld connects fixing, pushing tow shaft again, make y axis and basic top the on the shaft to the x dead in line, make the y axial location in place, put into steel plate and shaft firm welding in the same rim of a cup.
The described the 5th proofreaies and correct absolute altitude: use the jack that is laid in the steel lattice column below, the whereabouts jack when mark ± 0.00 absolute altitude reaches requirement on shaft, stops the jack that falls, and welds otic placode on shaft, fixedly the shaft absolute altitude.
Described the 6th step is proofreaied and correct verticality: on two axis directions of shaft, lay a jack respectively, lay two transits simultaneously, determine the pushing tow direction of jack by the elongated line of ink marker of observation shaft, until meeting the requirements the excision suspension hook.
The 7th step built: the suspension column concrete divides secondary to be poured into the top, and building for the first time highly is 2/3rds, and maintenance was carried out building the second time to basic end face in three days.
When job practices of the present invention lifts, do not use cable wind rope to proofread and correct and use jack correction steel lattice column, the correction difficulty is little, and correction rate is fast, the correction accuracy height; The use jack is proofreaied and correct, and both can proofread and correct steel lattice column verticality, plan-position, can proofread and correct the steel lattice column absolute altitude again; Use this worker's method to proofread and correct, before cast suspension column concrete, steel lattice column verticality, plan-position, absolute altitude change little, are convenient to secondary and check correction; The present invention is applicable to that single limb, many limbs steel lattice column of plug-in type suspension column, the installation of steel box column proofread and correct.Adopt job practices of the present invention, than traditional employing cable wind rope alignment technique, technology is simple, and is easy to operate, and speed of application is fast, saves the crane machine-team, workman's recruitment quantity, and particularly seldom occupied ground is not subjected to place size restriction on every side.Than employing cable wind rope correction of typist's errors, the energy reduction of erection time 50%, save cost 30%, economic benefit and social benefit are obvious.
Four, description of drawings:
Fig. 1 is construction process figure of the present invention.
Fig. 2 is a hoisting flow chart of the present invention.
Fig. 3 hands over horizontal frontal plane position coordinates figure for the present invention.
Fig. 4 is a correcting plane positional structure schematic diagram of the present invention.
Fig. 5 proofreaies and correct the absolute altitude structural representation for the present invention.
Fig. 6 proofreaies and correct the verticality structural representation for the present invention.
Five, the specific embodiment:
Through in Dalian newly-built plane, a certain workshop, curved surface, parts dress welder field engineering on probation, the heavy four limbs steel lattice column of the high 34t of 35m has been adopted in design, adopt steel lattice column non-cable correcting construction method of the present invention, steel lattice column adopts and makes in steel work processing factory, be transported to the building site then, factory process making progress is carried out according to the site operation progress, thereby guarantees on-the-spot installation smoothly.When mounted, adopt a 150t crawler crane to lift, for preventing the influence of environment temperature to the Steel Structure Installation precision, lifting generally is arranged in to be carried out at 11 in the morning in the past.Owing to adopted the non-cable correcting technology, effectively guaranteed the installation accuracy and the speed of steel lattice column.This engineering is owing to adopted this to proofread and correct new method, make engineering steel lattice column installation accuracy height, installation rate fast, installed in one month, detect through quality monitoring, this project steel lattice column installation qualification rate is 100%, maximum perpendicular degree deviation is 4mm, and maximum absolute altitude deviation is 5mm, and the largest axis deviation is 3mm, all less than code requirement, construction overall process be in safety, stable, fast, the controllable state of high-quality, security incident does not take place than plan 20 days in advance in the duration in the work progress.Specifically work progress is as shown in Figure 1:
1, preparation of construction, basis are checked and accepted:
After base concrete intensity reaches 100% design strength, rim of a cup 4 physical dimensions, absolute altitude, axial location are checked, check requirement after, eject steel lattice column axis X, Y in length and breadth with ink fountain at basic end face, absolute altitude is than the low 50mm of design elevation, so that the adjustment of post absolute altitude is proofreaied and correct at the bottom of requiring base for post.
2, steel lattice column axis absolute altitude mark:
Before lifting, to check steel lattice column 1 length and whether meet the requirements, rustproof paint has or not destruction, at first ejects a numerical value line of ink marker with ink fountain on the elongated steel pipe on the both direction of shaft, is convenient to back in place and observes, proofreaies and correct verticality with transit.According to the capital absolute altitude, extrapolate ± 0.00 absolute altitude by drawing steel ruler, to steel lattice column ± 0.00 absolute altitude line, post center line, the elongated line of shaft position and marked on shaft with red paint, be used for post-equalization absolute altitude in place;
3, lifting:
According to single steel lattice column weight, total length, select for use the crawler crane that meets lifting requirements to lift, as selecting the 150t crawler crane in this construction for use, the single-point lifting is adopted in the embolus lifting, and the hoisting flow process as shown in Figure 2, the soft cat ladder of elder generation's colligation must carry out before lifting, is convenient to fix, during colligation, be strained and fixed firmly, when preventing to lift, the cat ladder swing, the influence lifting, this soft cat ladder is used for the decoupling device of hoist lifting hook; On the steel lattice column 1 fixedly the lifting rope position must adopt thick rubber bag to protect, prevent that lifting rope from damaging rustproof paint, lifting adopts two lifting rope bolts at capital with wire rope, prevents the steel column back rotation of slinging, and is difficult in place; When put at the steel lattice column scene, must be the close basis of capital, shaft be parallel with the crane track route, crane is positioned at capital and near a basic side, during lifting, advances to suspension column one skidding while crane plays hook, when shaft during near 90 °, stop to advance, continued hook, until shaft hold up straight after, crane retreats then, when basis during in crane radius of gyration scope, crane stops to retreat, rotate to rim of a cup 4 tops, steel lattice column 1 is slowly dropped in the rim of a cup 4, finish tentatively in place.
4, correcting plane position:
According to the x axis of steel lattice column shaft mark, pushing tow shaft on the y axis direction makes on the shaft and puts into steel plate 3 in the x axis and basic end face x rim of a cup, connect fixing with the shaft tack weld, as Fig. 3,4, according to the y axis that marks on the shaft, on the x axis direction, jack is installed again, the pushing tow shaft, make y axis and basic top the on the shaft, make the y axial location in place, put into steel plate 3 in the same rim of a cup to the x dead in line, make each steel plate and shaft firm welding, make the shaft plan-position in place.
5, proofread and correct absolute altitude:
Datum grade point according to use in the building site uses the DS3 level gauge, carries out absolute altitude and checks.Use is laid in 4 20t jack 2 of steel lattice column 1 below, and the whereabouts jack when mark ± 0.00 absolute altitude reaches requirement on shaft, stops the jack that falls, and welds otic placode, fixedly shaft absolute altitude then as shown in Figure 5 on shaft.
6, proofread and correct verticality:
As shown in Figure 6 on two axis directions of shaft, lay a 20t jack 2 respectively, lay two TDT2 transits 6 simultaneously, determine the pushing tow direction of jack by the elongated line of ink marker of observation shaft, until meeting the requirements, after having proofreaied and correct steel lattice column plan-position, absolute altitude, verticality, can extract suspension hook.
7, temporary fixed:
All proofread and correct after meet the requirements when shaft plan-position, absolute altitude, verticality, use four cable wind ropes, steel lattice column is carried out temporary fixed, and in the suspension column rim of a cup, fill in gad.
8, build the suspension column concrete:
The suspension column concrete divides secondary to be poured into the top, and building for the first time highly is 2/3rds, and maintenance was carried out building the second time to basic end face in three days.Treat that the suspension column concrete strength reaches after 90% design strength, and again cable wind rope is taken off after supporting between erection column, finish the correction construction of steel lattice column.

Claims (7)

1, steel lattice column non-cable correcting construction method is characterized in that: first step preparation of construction basis is checked and accepted: the rim of a cup basis is cleared up, check rim of a cup at the bottom of absolute altitude be lower than design elevation 50mm; The second stepping rower is annotated: mark out on reference axis, the shaft at rim of a cup basis end face and mark absolute altitude; The 3rd step lifting: steel lattice column is hung in the rim of a cup basis; The 4th step correcting plane position: lay jack on two axis, the pushing tow steel lattice column makes the post plane in place, and fixes with gad; The 5th step was proofreaied and correct absolute altitude: place four jack below steel latticework suspension column four limits, withstand on the steel lattice column bottom surface, loosen the lifting hook, four jack fall simultaneously, adhere to specification until the post absolute altitude, on steel lattice column four limits, weld fixedly steel lattice column absolute altitude of otic placode; The 6th step was proofreaied and correct verticality: lay two transits on two axis directions of steel lattice column, use adjustment to be fixed on steel pile and proofread and correct the post verticality, after meeting the requirements, use the temporary fixed steel column of cable wind rope; The 7th the step build: build the suspension column concrete then, reach design strength 90% after, take off cable wind rope.
2, steel lattice column non-cable correcting construction method according to claim 1 is characterized in that: the second step mark: mark ± 0.00 absolute altitude line, post center line, the elongated line of shaft on shaft.
3, steel lattice column non-cable correcting construction method according to claim 1 is characterized in that: the lifting of the 3rd step: adopt crawler crane to carry out the single-point lifting.
4, according to the arbitrary described steel lattice column non-cable correcting construction method of claim 1-3, it is characterized in that: the 4th step correcting plane position: the pushing tow shaft makes x axis and basic end face x dead in line on the shaft, put into steel plate in the rim of a cup and the shaft tack weld connects fixing, pushing tow shaft again, make y axis and basic top the on the shaft to the x dead in line, make the y axial location in place, put into steel plate and shaft firm welding in the same rim of a cup.
5, according to the arbitrary described steel lattice column non-cable correcting construction method of claim 1-3, it is characterized in that: the 5th proofreaies and correct absolute altitude: use the jack that is laid in the steel lattice column below, the whereabouts jack, when mark ± 0.00 absolute altitude reaches requirement on shaft, stop the jack that falls, on shaft, weld otic placode, fixedly the shaft absolute altitude.
6, according to the arbitrary described steel lattice column non-cable correcting construction method of claim 1-3, it is characterized in that: the 6th step was proofreaied and correct verticality: on two axis directions of shaft, lay a jack respectively, lay two transits simultaneously, the elongated line of ink marker by the observation shaft is determined the pushing tow direction of jack, until meeting the requirements.
7, according to the arbitrary described steel lattice column non-cable correcting construction method of claim 1-3, it is characterized in that: the 7th step built: the suspension column concrete divides secondary to be poured into the top, building for the first time highly is 2/3rds, and maintenance was carried out building the second time to basic end face in three days.
CNA200810229777XA 2008-12-12 2008-12-12 Steel lattice column non-cable correcting construction method Pending CN101435222A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA200810229777XA CN101435222A (en) 2008-12-12 2008-12-12 Steel lattice column non-cable correcting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA200810229777XA CN101435222A (en) 2008-12-12 2008-12-12 Steel lattice column non-cable correcting construction method

Publications (1)

Publication Number Publication Date
CN101435222A true CN101435222A (en) 2009-05-20

Family

ID=40709843

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA200810229777XA Pending CN101435222A (en) 2008-12-12 2008-12-12 Steel lattice column non-cable correcting construction method

Country Status (1)

Country Link
CN (1) CN101435222A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101818575A (en) * 2010-02-10 2010-09-01 中国建筑第七工程局有限公司 Construction technology of cross-shaped profile steel column
CN104929372A (en) * 2015-06-12 2015-09-23 山西四建集团有限公司 Construction method for accurate steel pipe column installation
CN105863042A (en) * 2015-01-19 2016-08-17 江苏沪宁钢机股份有限公司 All-steel structure building and construction method thereof
CN106193630A (en) * 2016-07-05 2016-12-07 中国十九冶集团有限公司 Prefabricated Concrete bent columns hoisting alignment instrument
CN111119497A (en) * 2019-12-30 2020-05-08 倡创(上海)咨询管理事务所 Super-large box-type steel column installation system and construction method
CN111502120A (en) * 2020-04-28 2020-08-07 中铁六局集团有限公司 Construction method for hoisting platform steel stand column
CN112727107A (en) * 2020-12-25 2021-04-30 上海二十冶建设有限公司 Construction method for quickly adjusting position of axis in steel column installation and in-place

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101818575A (en) * 2010-02-10 2010-09-01 中国建筑第七工程局有限公司 Construction technology of cross-shaped profile steel column
CN105863042A (en) * 2015-01-19 2016-08-17 江苏沪宁钢机股份有限公司 All-steel structure building and construction method thereof
CN104929372A (en) * 2015-06-12 2015-09-23 山西四建集团有限公司 Construction method for accurate steel pipe column installation
CN104929372B (en) * 2015-06-12 2017-05-17 山西四建集团有限公司 Construction method for accurate steel pipe column installation
CN106193630A (en) * 2016-07-05 2016-12-07 中国十九冶集团有限公司 Prefabricated Concrete bent columns hoisting alignment instrument
CN111119497A (en) * 2019-12-30 2020-05-08 倡创(上海)咨询管理事务所 Super-large box-type steel column installation system and construction method
CN111119497B (en) * 2019-12-30 2023-11-03 倡创(上海)咨询管理事务所 Ultra-large box-type steel column installation system and construction method
CN111502120A (en) * 2020-04-28 2020-08-07 中铁六局集团有限公司 Construction method for hoisting platform steel stand column
CN112727107A (en) * 2020-12-25 2021-04-30 上海二十冶建设有限公司 Construction method for quickly adjusting position of axis in steel column installation and in-place

Similar Documents

Publication Publication Date Title
CN101435222A (en) Steel lattice column non-cable correcting construction method
CN106395628B (en) A kind of method of the aerial group pair of heavy tower equipment segmental hoisting
CN103291076B (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
CN102434003B (en) Heavy battened steel column construction process
CN101691815B (en) Fast hoisting-aligning method for Large-sized steel frames, and steel frame base structure
CN108678388B (en) Short mast multi-point integral lifting construction method for large-capacity circular storage tank
CN107013038A (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN112211103A (en) Special safe construction process for assembling and installing coal conveying trestle steel truss
CN203066095U (en) Assembled single-wall steel hanging box
CN116607795A (en) Steel column hoisting and positioning aid and positioning method
CN102777044B (en) Hoisting method of steel-structured spraying layer of urea prilling tower
CN105781205B (en) A kind of guider in place of the aerial group pair of heavy tower equipment segmental hoisting
CN111485573A (en) Transmission project prefabricated foundation installation and iron tower assembly coherent construction method
CN105350560A (en) Marine wind-finding radar foundation structure and installation method thereof
CN102615492A (en) Hoisting butt joint method of tower-like containers
CN111502120A (en) Construction method for hoisting platform steel stand column
CN202544423U (en) Hoisting structure of supporting steel column
CN211172058U (en) Island type breakwater navigation light pile foundation with maintenance channel
CN201495556U (en) Structure for quickly hoisting and centering base of large steel frame
CN203497150U (en) Scaffold for hatch coaming of ship
CN203486787U (en) Integral lifting device for cabinet top of Wiggins coal gas cabinet
CN112227369B (en) Cover-excavation top-down construction permanent steel pipe stand column installation construction method
CN115492403A (en) Combined type precise positioning construction device for tower footing steel latticed column
CN205224073U (en) Mould is fixed to contact net
CN211114863U (en) Well is from climbing concrete cloth system architecture

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Open date: 20090520