CN101392652A - Bottom column stope process - Google Patents

Bottom column stope process Download PDF

Info

Publication number
CN101392652A
CN101392652A CNA2007101130197A CN200710113019A CN101392652A CN 101392652 A CN101392652 A CN 101392652A CN A2007101130197 A CNA2007101130197 A CN A2007101130197A CN 200710113019 A CN200710113019 A CN 200710113019A CN 101392652 A CN101392652 A CN 101392652A
Authority
CN
China
Prior art keywords
stope
bottom column
slip casting
ore
filling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2007101130197A
Other languages
Chinese (zh)
Inventor
樊明玉
徐国良
刘兴义
王涛
李进鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DAYINGEZHUANG GOLD MINE ZHAOJIN MINING INDUSTRY Co Ltd
Original Assignee
DAYINGEZHUANG GOLD MINE ZHAOJIN MINING INDUSTRY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DAYINGEZHUANG GOLD MINE ZHAOJIN MINING INDUSTRY Co Ltd filed Critical DAYINGEZHUANG GOLD MINE ZHAOJIN MINING INDUSTRY Co Ltd
Priority to CNA2007101130197A priority Critical patent/CN101392652A/en
Publication of CN101392652A publication Critical patent/CN101392652A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a sill pillar stoping process. The difference of the sill pillar stoping process lies in that the sill pillar recovery process comprises the steps: (1) the arrangement of a pre-grouting drilling hole; (2) the pre-grouting; (3) the roof-contact filling in stope; and (4) the sill pillar stoping. Therefore, the process is simple, safe and highly-efficient, has low cost and high stoping rate, and is particularly suitable for the sill pillar stoping of mines.

Description

A kind of bottom column stope process
Technical field:
The present invention relates to a kind of process for stoping, particularly a kind of bottom column stope process.
Background technology:
Bottom column stope will just can carry out after next horizontal ore body has been adopted, open-assembly time generally reaches the several years, and owing to be subjected to process explosion power destructions such as haulage drift driving and mineral building back production, phenomenons such as roof fall, landslide very easily appear in reason such as pressure in the exploitation process with bearing, for both not adopting consolidated fill, do not have the concrete tailing-filled mining codes at the false end again, the bottom column stope difficulty is very big, and a lot of mines for the sake of security, can only abandon foundation and reclaim, cause resources loss.
Summary of the invention:
Purpose of the present invention will provide a kind of technology simple, safe and efficient exactly, and cost is low, the bottom column stope process that the rate of extraction is high.
The object of the present invention is achieved like this, and a kind of bottom column stope process is characterized in that may further comprise the steps:
(1) arrange pre-inlet well: when the stope of next horizontal segment is adopted to the distance haulage level 0.3-0.7 rice left and right sides, stop back production, utilize the YGZ-90 rig vertically to creep into then, penetrate ore body and surpass tailing-filled, the net degree is 1.0 * 1.0m 2To 1.5 * 1.5m 2
(2) carry out pre-slip casting: adopt cement grout, use high-pressure injection pump slip casting, the high-strength PVC pipe is a feed pipe for mortar, seamless steel pipe is a Grouting Pipe, carry out pre-slip casting, leak, use stopper as stop grouting plug at the injected hole collar extension for preventing slurries, clog with cloth near reaching Grouting Pipe on every side, after extracting Grouting Pipe out, immediately with cloth just the stopple on the stopper live, make tailings and slurries formation solid, and be full of the interior crack of foundation ore, make the glued one-tenth of ore whole.
(3) adopt the poplar top tight filling: after pre-slip casting finishes, stope is carried out top tight filling, filling should be carried out several times, and it is closely knit to guarantee that filling connects the top, for bottom column stope is laid good basis.
(4) bottom column stope: according to the thickness of foundation, divide and adopt the route type back production two~three times, first floor adopts mining advancing, for the ore deposit that falls forms enough spaces, retrusive, the safety of assurance personnel and equipment are adopted in the later ore deposit that falls, fall the ore deposit to apart from 0.5 meter in tailings face the time, finish bottom column stope.
The present invention compared with prior art has following advantage:
Owing to adopted following steps: (1) arranges pre-inlet well, and (2) carry out pre-slip casting, and (3) adopt the poplar top tight filling, (4) bottom column stope, thereby technology is simple, safe and efficient, cost is low, rate of extraction height.
The specific embodiment:
Embodiment 1:
(1) arrange pre-inlet well: when the stope of next horizontal segment is adopted to 0.5 meter left and right sides of distance haulage level, stop back production, utilize the YGZ-90 rig vertically to creep into then, penetrate ore body and surpass tailing-filled, the net degree is 1.0 * 1.0m 2
(2) carry out pre-slip casting: adopt cement grout, use high-pressure injection pump slip casting, the high-strength PVC pipe is a feed pipe for mortar, seamless steel pipe is a Grouting Pipe, carry out pre-slip casting, leak, use stopper as stop grouting plug at the injected hole collar extension for preventing slurries, clog with cloth near reaching Grouting Pipe on every side, after extracting Grouting Pipe out, immediately with cloth just the stopple on the stopper live, make tailings and slurries formation solid, and be full of the interior crack of foundation ore, make the glued one-tenth of ore whole.
(3) adopt the poplar top tight filling: after pre-slip casting finishes, stope is carried out top tight filling, filling should be carried out several times, and it is closely knit to guarantee that filling connects the top, for bottom column stope is laid good basis.
(4) bottom column stope: according to the thickness of foundation, divide and adopt the route type back production two~three times, first floor adopts mining advancing, for the ore deposit that falls forms enough spaces, retrusive, the safety of assurance personnel and equipment are adopted in the later ore deposit that falls, fall the ore deposit to apart from 0.5 meter in tailings face the time, finish bottom column stope.
Embodiment 2:
(1) arrange pre-inlet well: when the stope of next horizontal segment is adopted to 0.5 meter left and right sides of distance haulage level, stop back production, utilize the YGZ-90 rig vertically to creep into then, penetrate ore body and surpass tailing-filled, the net degree is 1.5 * 1.5m 2
(2) carry out pre-slip casting: adopt cement grout, use high-pressure injection pump slip casting, the high-strength PVC pipe is a feed pipe for mortar, seamless steel pipe is a Grouting Pipe, carry out pre-slip casting, leak, use stopper as stop grouting plug at the injected hole collar extension for preventing slurries, clog with cloth near reaching Grouting Pipe on every side, after extracting Grouting Pipe out, immediately with cloth just the stopple on the stopper live, make tailings and slurries formation solid, and be full of the interior crack of foundation ore, make the glued one-tenth of ore whole.
(3) adopt the poplar top tight filling: after pre-slip casting finishes, stope is carried out top tight filling, filling should be carried out several times, and it is closely knit to guarantee that filling connects the top, for bottom column stope is laid good basis.
(4) bottom column stope: according to the thickness of foundation, divide and adopt the route type back production two~three times, first floor adopts mining advancing, for the ore deposit that falls forms enough spaces, retrusive, the safety of assurance personnel and equipment are adopted in the later ore deposit that falls, fall the ore deposit to apart from 0.5 meter left and right sides of tailings face the time, finish bottom column stope.

Claims (1)

  1. A kind of bottom column stope process is characterized in that may further comprise the steps:
    (1) arrange pre-inlet well: when the stope of next horizontal segment is adopted to the distance haulage level 0.3-0.7 rice left and right sides, stop back production, utilize the YGZ-90 rig vertically to creep into then, penetrate ore body and surpass tailing-filled, the net degree is 1.0 * 1.0m 2To 1.5 * 1.5m 2
    (2) carry out pre-slip casting: adopt cement grout, use high-pressure injection pump slip casting, the high-strength PVC pipe is a feed pipe for mortar, seamless steel pipe is a Grouting Pipe, carry out pre-slip casting, leak, use stopper as stop grouting plug at the injected hole collar extension for preventing slurries, clog with cloth near reaching Grouting Pipe on every side, after extracting Grouting Pipe out, immediately with cloth just the stopple on the stopper live, make tailings and slurries formation solid, and be full of the interior crack of foundation ore, make the glued one-tenth of ore whole.
    (3) adopt the poplar top tight filling: after pre-slip casting finishes, stope is carried out top tight filling, filling should be carried out several times, and it is closely knit to guarantee that filling connects the top, for bottom column stope is laid good basis.
    (4) bottom column stope: according to the thickness of foundation, divide and adopt the route type back production two~three times, first floor adopts mining advancing, for the ore deposit that falls forms enough spaces, retrusive, the safety of assurance personnel and equipment are adopted in the later ore deposit that falls, fall the ore deposit to apart from 0.5 meter in tailings face the time, finish bottom column stope.
CNA2007101130197A 2007-09-18 2007-09-18 Bottom column stope process Pending CN101392652A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2007101130197A CN101392652A (en) 2007-09-18 2007-09-18 Bottom column stope process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2007101130197A CN101392652A (en) 2007-09-18 2007-09-18 Bottom column stope process

Publications (1)

Publication Number Publication Date
CN101392652A true CN101392652A (en) 2009-03-25

Family

ID=40493142

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2007101130197A Pending CN101392652A (en) 2007-09-18 2007-09-18 Bottom column stope process

Country Status (1)

Country Link
CN (1) CN101392652A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102011589A (en) * 2010-10-29 2011-04-13 中钢集团马鞍山矿山研究院有限公司 Stope bottom structure suitable for underground two-step mining and production process thereof
CN102011590A (en) * 2010-10-29 2011-04-13 中钢集团马鞍山矿山研究院有限公司 Mine down-hole double-stope bottom structure
CN102619516A (en) * 2012-04-26 2012-08-01 鞍钢集团矿业公司 Top-filled pillarless vertical end-wall sublevel caving method extraction technique
CN102619515A (en) * 2012-04-26 2012-08-01 鞍钢集团矿业公司 Top-filled high-end-wall pillarless sublevel caving method extraction technique
CN102619518A (en) * 2012-04-26 2012-08-01 鞍钢集团矿业公司 Ore drawing technique for controlling fluidity of ore rocks via pillarless cornice end-wall sublevel caving method
CN102619514A (en) * 2012-04-26 2012-08-01 鞍钢集团矿业公司 Top-filled pillarless cornice end-wall sublevel caving method extraction technique
CN110043263A (en) * 2019-05-24 2019-07-23 福州大学 Low-angle dip based on subregion Pre-control roof is crushed mineral deposit medium-length hole enhanced recovery method

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102011589A (en) * 2010-10-29 2011-04-13 中钢集团马鞍山矿山研究院有限公司 Stope bottom structure suitable for underground two-step mining and production process thereof
CN102011590A (en) * 2010-10-29 2011-04-13 中钢集团马鞍山矿山研究院有限公司 Mine down-hole double-stope bottom structure
CN102619516A (en) * 2012-04-26 2012-08-01 鞍钢集团矿业公司 Top-filled pillarless vertical end-wall sublevel caving method extraction technique
CN102619515A (en) * 2012-04-26 2012-08-01 鞍钢集团矿业公司 Top-filled high-end-wall pillarless sublevel caving method extraction technique
CN102619518A (en) * 2012-04-26 2012-08-01 鞍钢集团矿业公司 Ore drawing technique for controlling fluidity of ore rocks via pillarless cornice end-wall sublevel caving method
CN102619514A (en) * 2012-04-26 2012-08-01 鞍钢集团矿业公司 Top-filled pillarless cornice end-wall sublevel caving method extraction technique
CN102619518B (en) * 2012-04-26 2014-01-08 鞍钢集团矿业公司 Ore drawing technique for controlling fluidity of ore rocks via pillarless cornice end-wall sublevel caving method
CN102619514B (en) * 2012-04-26 2014-01-08 鞍钢集团矿业公司 Top-filled pillarless cornice end-wall sublevel caving method extraction technique
CN102619515B (en) * 2012-04-26 2014-01-08 鞍钢集团矿业公司 Top-filled high-end-wall pillarless sublevel caving method extraction technique
CN110043263A (en) * 2019-05-24 2019-07-23 福州大学 Low-angle dip based on subregion Pre-control roof is crushed mineral deposit medium-length hole enhanced recovery method
CN110043263B (en) * 2019-05-24 2024-01-30 福州大学 Zone pre-control roof-based medium-deep hole reinforcement mining method for gently-inclined broken ore deposit

Similar Documents

Publication Publication Date Title
CN102635392B (en) Co-extraction method for pillar-less coal and gas of advanced entry-retaining construction extraction engineering
CN101392652A (en) Bottom column stope process
CN100554642C (en) A kind of method of long-wall integrated-extraction reclaiming room-type coal column mining
CN104832178A (en) A layering and partially filling coal mining method of thick seams
CN104763434B (en) A kind of without coal column double lanes driving method
CN101608552A (en) The seat earth aquifer reinforces and protects the method for water barrier in reinforcing process
CN107035405B (en) One kind cutting top pressure relief method for the double filling wall constructions of gob side entry retaining
CN103821558A (en) Coal mine gob filling mining system and gob-side entry retaining filling process
CN102086765B (en) High-sublevel multi-layer mining method of ultrathin copper ore body
CN103244123B (en) High-dipping medium thick ore body mining method
CN104358573B (en) The stage open stope of big thick ore body and stage avalanche combined mining method
CN104763466B (en) Method for detecting active diffusion radius of covered rock separation grouting filling slurry
CN104533452A (en) Sectional type grouting reinforcement method for underground coal mine fragmentized coal bodies
CN109595029B (en) Goaf partial stowage supporting structure and its construction method under the conditions of tight roof
CN109869152B (en) Mining method for reserved roadway of coal and gas outburst coal seam
RU2333363C1 (en) Method of monitoring gas emission during mining operations in series of highly gaseous coal seams
CN104975868A (en) Top plate high-position boring large-diameter long-drill-hole gas extraction method based on directional drilling
CN108798769A (en) Item adopts goaf integrated synthesis and administers construction method
CN110067592A (en) Top plate gas cooperative control method based on tight roof ground fracturing
CN106050302A (en) Constructing system and method for coal mine permanent sealing wall
CN102926754B (en) Two-tunneling bidirectional stripping two-step pre-support mining method
CN104727847A (en) Non chain pillar gob-side entry retaining method with filling wall self-erasure
CN106522955A (en) Studding recovery method for reconstructing covering layer through dead zone wastefill and top surrounding rock spallation collaboratively
CN110566226A (en) shallow-consolidation deep-injection supporting method for rapid excavation of broken roof large-section roadway
CN116517617A (en) Coal gangue-based waste underground stoping roadway chamber filling method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20090325