CN101301981B - Hoisting method - Google Patents

Hoisting method Download PDF

Info

Publication number
CN101301981B
CN101301981B CN 200810061605 CN200810061605A CN101301981B CN 101301981 B CN101301981 B CN 101301981B CN 200810061605 CN200810061605 CN 200810061605 CN 200810061605 A CN200810061605 A CN 200810061605A CN 101301981 B CN101301981 B CN 101301981B
Authority
CN
China
Prior art keywords
crane
tail
lifting
hanging device
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200810061605
Other languages
Chinese (zh)
Other versions
CN101301981A (en
Inventor
王志远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Ningbo Engineering Co Ltd
Original Assignee
China Petrochemical Corp
Sinopec Ningbo Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petrochemical Corp, Sinopec Ningbo Engineering Co Ltd filed Critical China Petrochemical Corp
Priority to CN 200810061605 priority Critical patent/CN101301981B/en
Publication of CN101301981A publication Critical patent/CN101301981A/en
Application granted granted Critical
Publication of CN101301981B publication Critical patent/CN101301981B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a lifting method which is characterized in the following steps: a) the lifting points of two sliding tail cranes are arranged under the centre of gravity of the equipment lifted and the lifting point of at least one main crane is arranged above the centre of gravity of the equipment lifted; b) the main crane is driven forward or turned to allow the equipment to become erective gradually from horizontal state and the reverse sliding tail of the equipment lifted is completed; c) two sliding tail cranes and at least one main crane are used to lift the equipment lifted in place simultaneously after the equipment lifted is completely erective. The lifting capacity of the lifting method provided by the invention is the sum of the lifting capacity of the main crane and the sliding tail crane; thus the lifting capacity of the method can be greatly increased without increasing the crane.

Description

A kind of hanging method
Technical field
The present invention relates to the equipment hoisting field, specifically refer to a kind of hanging method that uses self-propelled crane hoisting large-size equipment.
Background technology
To the lifting of some main equipments, the general both at home and abroad at present method of moving of hanging that lifts that adopts needs to use a plurality of self-propelled cranes (the following crane that all is called), is divided into the main crane and the tail crane that slips usually.The suspension centre of main crane is arranged on more than the equipment center of gravity, and the suspension centre of slide tail crane is arranged on below the equipment center of gravity.During lifting, the tail crane that slips is walked forward or is turned round, and main crane promotes suspension hook or revolution thereupon simultaneously, makes equipment upright gradually from horizontality; After equipment reaches erectility, withdraw slide tail crane, this moment, main crane was born whole weight of equipment and equipment hoisting is in place.This hanging method, the lifting ability of equipment is by the lifting ability decision of main crane, and the tail crane that slips only plays the effect of auxiliary lifting, the lifting ability is not produced directly influence, has limited the lifting ability of crane, makes the lifting ability of crane less relatively; Advantage is that to lift with crane be hoisting method the most easily, lifting setup time and lifting time all are the shortest, setup time with the crane lifting main equipment is about 7 days generally speaking, can finish in 1-2 days under some condition, and equipment hoisting all can be finished in one day.
Along with the fast development of domestic economy, equipment hoisting weight constantly increases, and lifts with general crane and hangs the method for moving and can't satisfy part main equipment lifting requirements, and alternative method is to adopt other hanging devices such as mast, gate-type hydraulic hanging system etc. to lift.This class hanging method hoisting complexity, hanging device setup time just needs about 1 month, and part is lifted on can not be finished the same day, and the lifting risk is bigger, can not satisfy short installation period requirement.
Summary of the invention
Technical matters to be solved by this invention is the present situation at prior art, a kind of hanging method of ultra-large type vertical equipment is provided, and tail crane lifts simultaneously with main crane and the while is in place by the hanging device purpose that the lifting ability increases greatly to reach the identical crane of use by slipping in hoisting process for it.
1, the present invention solves the problems of the technologies described above the technical scheme that is adopted and is: this hanging method is characterized in that comprising the steps:
A) two suspension centres that slip the tail cranes are arranged on by below the center of gravity of hanging device, the suspension centre of at least one master's crane is arranged on by more than the center of gravity of hanging device;
B) move ahead or turn round main crane, make equipment upright gradually, finish by the reverse slide tail of hanging device from horizontality;
C) by hanging device fully upright after, slip tail cranes and at least one master's crane with above-described two and will be lifted by hanging device simultaneously and put in place.
Adopt two slide tail cranes to lift the afterbody of equipment, suspension centre is arranged on below the equipment center of gravity, and with leading the head that crane is lifted equipment more than one or one, suspension centre is arranged on more than the equipment center of gravity.When beginning to lift, main crane is walked forward or is turned round, make equipment upright gradually from horizontality, oppositely finish the tail process of slipping with main crane, this and existing crane lift to hang and move method hanging device difference and be in the prior art that the upright process of equipment finishes by slipping the tail crane, after equipment is upright fully, all cranes are born weight of equipment and equipment is in place simultaneously, this point also lifts with existing crane and hangs that to move the method hanging device different, lift at existing crane and to hang in the method for moving the method hanging device, the tail crane that slips promptly breaks away from equipment after finishing the slide tail, no longer bears the weight of equipment, bears whole weight of equipment and equipment is in place by main crane; The lifting ability of hanging the method for moving that lifts existing crane depends on the lifting ability of main crane, and the lifting ability of hanging method provided by the present invention then is the lifting ability sum of main crane and slide tail crane; Therefore under the situation that does not increase crane, the lifting ability of this method but can increase greatly.
According to by the weight of hanging device, generally select for use master's crane to get final product; If big especially, also can select two master's cranes for use by hanging device weight.
The suspension centre of described slide tail crane is arranged on by the hanging device center of gravity with upper/lower positions, and the suspension centre of described master's crane is arranged on by the above position of hanging device center of gravity.The relative position of the suspension centre of slide tail crane, the suspension centre of main crane and equipment center of gravity is specifically located according to the lifting ability of slide tail crane and main crane.
The concrete of suspension centre determines that principle is: the weight that main crane is born with slip weight that the tail crane born and main crane suspension centre to by the distance of hanging device center of gravity and slide tail crane suspension centre to being inversely proportional to by the distance of hanging device center of gravity.
Compared with prior art, because having adopted a kind of many cranes (being self-propelled crane) oppositely to lift to hang, hanging method provided by the present invention moves the method lifting by hanging device, after the slide tail is finished, the tail crane that slips lifts by hanging device simultaneously with main crane, therefore under the situation of quantity that does not change crane and lifting ability, the lifting ability of hanging method provided by the present invention increases greatly, and short construction period.This law can be used for the lifting of vertical equipment, has more preceence during in particular for the lifting of ultra-large type vertical equipment.
Description of drawings
Fig. 1 is the plan view from above when main crane slips tail in the embodiment of the invention;
Fig. 2 lifts by hanging device plan view from above when in place simultaneously for main crane in the embodiment of the invention and the tail crane that slips;
Fig. 3 lifts by hanging device front plan view when in place simultaneously for main crane in the embodiment of the invention and the tail crane that slips;
Fig. 4 is that the A of Fig. 3 is to view;
Fig. 5 is the plan view from above when slipping tail crane slide tail in the Comparative Examples of the present invention;
Fig. 6 is the front plan view when main crane lifts by hanging device in the Comparative Examples of the present invention.
The specific embodiment
Embodiment describes in further detail the present invention below in conjunction with accompanying drawing.
Embodiment
As 1 to shown in Figure 4, the reactor 3 of lifting is heavy 1600 tons, 6 meters of diameters, long 56 meters.It is that main crane 1 lifts that main crane 1 adopts 1250 tons of cranes of a DEMAG CC8800 type, and according to lifting elevation drawing and lifting performance table, the specified lifting weight of crane is 832 tons.Remove 39 tons of hooks, about 20 tons of lifting rigging, the 1250 tons of maximum lifting of crane weight are 773 tons; The tail crane 2 that slips be 750 tons of cranes of two LR1750 types according to lifting elevation drawing and crane performance table, 750 tons of lifting abilities of slipping the tail cranes are 635 tons, remove 16 tons of suspension hook weight, 10 tons of lifting rigging weight, every is slipped tail crane 2 maximum lifting weight is 609 tons.In the present embodiment by the hanging device reactor from lift by crane in place all thus three cranes bear.Therefore the maximum lifting weight of main crane 1 and slide tail crane 2 is in the present embodiment:
773 tons+609 tons+609 tons=1991 tons
By calculating the hoisting point position of determining main crane 1 and slipping tail crane 2, concrete computation process is as follows: every the crane that requires according to the safety hanging device need be laid in certain safe clearance, definite master's crane 1 is born 600 tons of weight, every slide tail crane 2 is born 500 tons of weight, the suspension centre of then leading crane 1 is 1000 with slipping the suspension centre of tail crane 2 to the ratio of the distance of reactor center of gravity 4 to the distance of reactor center of gravity 4: 600=5: 3, determine the hoisting point position of main crane 1 in the suitable position of reactor center of gravity more than 4 after, can determine to slip the hoisting point position of tail crane 2 according to the ratio of above calculating, but but this process backwards calculation also double counting finally determine the suspension centre of suitable master's crane 1 and the suspension centre of slide tail crane 2.With the suspension centre of lifting skull, only need to get final product in the present embodiment according to the definite suspension centre that slips tail crane 2 of ratio as main crane 1.After having determined hoisting point position, slide tail crane 2 is fixed on by on the suspension centre of hanging device by steel rope or other riggings with the suspension hook of leading crane 1.After fixing, main crane 1 is walked forward or is turned round and oppositely finish the action of slide tail.After reactor 3 was upright, the main crane 1 and the tail crane 2 that slips were born simultaneously by the weight of hanging device and off the hook simultaneously 3 of reactors are finished the lifting task jointly on Equipment Foundations 5.Whole hoisting process can be finished in half a day.
This master's crane oppositely slips tail, main crane and the tail crane that slips and lifts the problem that has been solved the ability that lifts with the raising of limited crane resources maximum possible by the hanging method of hanging device simultaneously, has broad application prospects; Having quick, the safe characteristics of hanging device simultaneously, is the most preferably scheme of hoisting large-size vertical equipment.
Comparative Examples
To shown in Figure 6, adopt present general-duty hanging method as Fig. 5,, lift 6 meters of reactor 3 ' diameters, 56 meters of length, weigh 1600 tons by the same embodiment of hanging device.Adopt identical suspension centre setting among the embodiment, need adopt two to slip tail cranes 2 ' to reactor 3 ' slide tail, the tail crane 2 ' that slips need adopt 750 tons of cranes, and main crane 1 ' need adopt 3200 tons of cranes (according to present domestic lifting resource).In the general-duty hanging method, it is upright with reactor 3 ' to slip 2 ' walking of tail crane or revolution, remove then slip tail crane 2 ' with slip being connected of tail suspension centre, the reactor total weight is born by master's crane 1 '; The suspension hook that falls main crane 1 ' after rise on Equipment Foundations 5 ', is finished whole hoisting process with 3 ' of reactor.Owing to lift to hang to move in the method hanging device at existing crane (self-propelled crane) and slip the tail crane and only play and slip tail and must act on, upright back slips the tail crane and removes, and weight of equipment is all born by main crane, so need the tonne cooresponding big of main crane.

Claims (3)

1. a hanging method is characterized in that comprising the steps:
A) two suspension centres that slip the tail cranes are arranged on by below the center of gravity of hanging device, the suspension centre of at least one master's crane is arranged on by more than the center of gravity of hanging device;
B) move ahead or turn round main crane, make by hanging device uprightly gradually, finish by the reverse slide tail of hanging device from horizontality;
C) by hanging device fully upright after, slip tail cranes and at least one master's crane with two and will be lifted by hanging device simultaneously and put in place.
2. hanging method according to claim 1 is characterized in that: described master's crane is according to selected for use one or two by the weight of hanging device.
3. hanging method according to claim 2 is characterized in that: definite principle of suspension centre is the weight that main crane is born: weight=slides tail crane suspension centre that the tail crane that slips is born is to by the distance of hanging device center of gravity: lead the crane suspension centre to by the distance of hanging device center of gravity.
CN 200810061605 2008-05-23 2008-05-23 Hoisting method Expired - Fee Related CN101301981B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200810061605 CN101301981B (en) 2008-05-23 2008-05-23 Hoisting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200810061605 CN101301981B (en) 2008-05-23 2008-05-23 Hoisting method

Publications (2)

Publication Number Publication Date
CN101301981A CN101301981A (en) 2008-11-12
CN101301981B true CN101301981B (en) 2010-06-02

Family

ID=40112120

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200810061605 Expired - Fee Related CN101301981B (en) 2008-05-23 2008-05-23 Hoisting method

Country Status (1)

Country Link
CN (1) CN101301981B (en)

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101830393A (en) * 2010-05-21 2010-09-15 中国石化集团第五建设公司 Hoisting method of thin-wall long and thin large-size equipment
CN102556855B (en) * 2012-02-22 2014-02-12 徐工集团工程机械股份有限公司 Deformable super-tonnage crawler crane and combining method thereof
CN102674136A (en) * 2012-05-09 2012-09-19 中国海洋石油总公司 Lifting method for large-scale tower equipment
CN103588081A (en) * 2012-08-13 2014-02-19 中国石油天然气集团公司 Hoisting method for equipment inapplicable to conventional hoisting process
CN102926799B (en) * 2012-10-24 2016-01-27 广东省工业设备安装公司重庆分公司 Underground construction main equipment hoisting transportation method
CN103058054B (en) * 2012-12-27 2014-11-19 三一重工股份有限公司 Tail device and tail dragging method
CN103303793B (en) * 2013-06-08 2015-04-29 中石化第十建设有限公司 Lifting mechanism suitable for tail end lifting operation of vertical equipment
CN103449301B (en) * 2013-09-22 2015-02-11 中石化南京工程有限公司 Overturning and lifting method for major-diameter superheavy end socket
CN103663101A (en) * 2014-01-07 2014-03-26 国核工程有限公司 Method for lifting voltage stabilizer of nuclear power station
CN103935909B (en) * 2014-04-15 2016-06-29 中石化宁波工程有限公司 A kind of crane rotates location hanging method
CN104477755B (en) * 2014-12-24 2017-01-18 中国化学工程第三建设有限公司 Method for rapidly hoisting suspended type vertical vessel
CN105152030A (en) * 2015-06-26 2015-12-16 中化二建集团有限公司 Method for hoisting Fischer-Tropsch synthesis reactor by taking gantry crane as main crane and achieving tail lifting through single gantry
CN107758507B (en) * 2016-08-19 2019-06-04 中石化重型起重运输工程有限责任公司 The hanging method of annular-pipe reactor
CN109319660B (en) * 2018-10-23 2020-03-17 中建一局集团第一建筑有限公司 Hoisting process of giant acrylic plate
CN110255361B (en) * 2019-07-12 2024-04-30 山西省安装集团股份有限公司 Double-sliding lifting device for water-cooled wall of boiler and application method of double-sliding lifting device
CN110482405A (en) * 2019-08-15 2019-11-22 中建钢构有限公司 A kind of hanging method
CN110921580A (en) * 2019-10-22 2020-03-27 沪东中华造船(集团)有限公司 Row column hoisting method
CN111302228B (en) * 2020-04-25 2021-03-30 中国有色金属工业第六冶金建设有限公司 Hoisting method for hoisting large barrel by multiple masts based on wind condition
CN111846141B (en) * 2020-05-29 2022-08-30 招商局金陵船舶(南京)有限公司 Method for hoisting high-load liquefied gas carrier tank by using crane with low hoisting capacity

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1438165A (en) * 2002-12-30 2003-08-27 苏安 Device for adjusting pitch-posture of suspended article
CN2578300Y (en) * 2002-10-31 2003-10-08 方锦全 Simple hoister
CN101003347A (en) * 2007-01-18 2007-07-25 卫华集团有限公司 Equipment for balancing outofstep sustained center of crane
EP1880971A2 (en) * 2006-07-18 2008-01-23 Liebherr-Werk Nenzing GmbH Method for controlling the orientation of a crane load

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2578300Y (en) * 2002-10-31 2003-10-08 方锦全 Simple hoister
CN1438165A (en) * 2002-12-30 2003-08-27 苏安 Device for adjusting pitch-posture of suspended article
EP1880971A2 (en) * 2006-07-18 2008-01-23 Liebherr-Werk Nenzing GmbH Method for controlling the orientation of a crane load
CN101003347A (en) * 2007-01-18 2007-07-25 卫华集团有限公司 Equipment for balancing outofstep sustained center of crane

Also Published As

Publication number Publication date
CN101301981A (en) 2008-11-12

Similar Documents

Publication Publication Date Title
CN101301981B (en) Hoisting method
CN205045698U (en) Reinforcement cage hoisting utensil
CN204624970U (en) Indoor hoisting simple lifting tool
CN101994318B (en) Lifting frame, hoisting system and hoisting method for vertically and rotatably hoisting steel reinforcement cage
CN103397629B (en) The disposable construction method for hanging of overlength reinforcing cage
CN203845712U (en) Heavy-duty equipment hoisting device
CN203173684U (en) Component for hoisting reinforcement cage
CN108946475B (en) Overturning and hoisting system and method for horizontal equipment
CN101284626A (en) Additional weight hoisting method
CN202030434U (en) Large-span whole-section hoisting sling for steel box girder
CN202390116U (en) High-intensity small-tonnage hoist
CN201722053U (en) Hoisting mechanism used for upright column hoisting
CN104401865B (en) Steel billet handling appliance
CN201762053U (en) Simple automatic hoisting rod
CN203402809U (en) Three-group vertical connection pulley block series connection type hanging row
CN201943006U (en) Main tower zone movable bracket for assisting non-variable amplitude girder erecting crane to erect steel box girders
CN105317031B (en) A kind of ship lift main equipment room bridge main beam hanging method
CN211769762U (en) Concrete box girder steel reinforcement cage integral hoisting device
CN203319500U (en) Reinforcing cage abutting-joint adjusting device
CN203129148U (en) Panel slide mold with walking devices
CN204022373U (en) For pushing tow temporary supporting part, remove the hanging device of use
CN207090834U (en) Cable boom hoisting
CN105671245B (en) A kind of method of utilization hoist engine flip-over type installing converter
CN203923910U (en) A kind of instrument for bridge board lifting
CN204802837U (en) Platform sling promotes structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Free format text: FORMER OWNER: NINGBO ENGINEERING CO., LTD., SINOPEC

Effective date: 20121015

Owner name: SINOPEC NINGBO ENGINEERING COMPANY LIMITED

Free format text: FORMER OWNER: CHINA PETROCHEMICAL GROUP CORPORATION

Effective date: 20121015

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 100088 CHAOYANG, BEIJING TO: 315103 NINGBO, ZHEJIANG PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20121015

Address after: 315103 Ningbo high tech Zone, Zhejiang, academician Road, No. 660

Patentee after: SINOPEC NINGBO ENGINEERING Co.,Ltd.

Address before: 100088, No. six, Xin Xin Street East, Beijing, Chaoyang District

Patentee before: CHINA PETROLEUM & CHEMICAL Corp.

Patentee before: SINOPEC NINGBO ENGINEERING Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100602