CN110482405A - A kind of hanging method - Google Patents
A kind of hanging method Download PDFInfo
- Publication number
- CN110482405A CN110482405A CN201910752670.1A CN201910752670A CN110482405A CN 110482405 A CN110482405 A CN 110482405A CN 201910752670 A CN201910752670 A CN 201910752670A CN 110482405 A CN110482405 A CN 110482405A
- Authority
- CN
- China
- Prior art keywords
- hanging device
- lifting part
- auxiliary
- main
- hanging
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/06—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for minimising or preventing longitudinal or transverse swinging of loads
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The present invention relates to technical field of building construction, disclose a kind of hanging method, include the following steps, main hanging device and auxiliary hanging device is arranged;The main hanging device slings the first end to lifting part, and the auxiliary hanging device slings the second end to lifting part, until reaching setting height;The auxiliary hanging device stops lifting, and the main hanging device drive is described to be rotated to lifting part, until described to lifting part state in a vertical shape.Hanging method in the present invention realizes the lifting and aerial overturning to lifting part by the cooperation of main hanging device and auxiliary hanging device in lifting, it can prevent it from generating biggish swing when lifting extra-long rod element, the stability and safety of hoisting process are improved, and operating process is simple.
Description
Technical field
The present invention relates to technical field of building construction more particularly to a kind of hanging methods.
Background technique
In building construction process, it usually needs by the member erections such as davit to high-altitude, fixed with carrying out high-altitude installation, and
And certain rod pieces need state in a vertical shape to be installed.Rod piece is usually to be in a horizontal state when being placed in ground, therefore, is being hung
Needing to be overturn during dress is vertical state, in order to subsequent installation fixation.When being lifted to rod piece, usually
The fixation of one end of rod piece is lifted by crane using a hanging device, during height is constantly raised, rod piece can gradually from
Horizontality overturning is vertical state.But when rod length is longer, the free end of rod piece is easy to happen by a relatively large margin when lifting
Swing, to cause to collide to peripheral equipment or personnel, working security is unable to get effective guarantee.
Summary of the invention
For overcome the deficiencies in the prior art, the present invention provides a kind of hanging method, passes through main hanging device in lifting
The lifting and aerial overturning to lifting part are realized in cooperation with auxiliary hanging device, can prevent its generation when lifting extra-long rod element
Biggish swing improves the stability and safety of hoisting process, and operating process is simple.
The technical solution adopted by the present invention to solve the technical problems is:
A kind of hanging method is provided, is included the following steps,
Main hanging device and auxiliary hanging device is arranged in S10;
Main hanging device described in S20 slings the first end to lifting part, and the auxiliary hanging device will be described to lifting part
Second end sling, until reach setting height;
Auxiliary hanging device described in S30 stops lifting, and the main hanging device drive is described to be rotated to lifting part, until described
To lifting part state in a vertical shape.
It as an improvement of the above technical solution, further include step S11 before step S20: will be described complete to lifting part assembly
At, and the first suspension centre is set in the first end to lifting part, in the second end to lifting part, the second suspension centre is set.
As a further improvement of the above technical scheme, further include step S40 after step S30: making described to lifting part
It is detached from the auxiliary hanging device, and will be described in lifting part transfer hanging to fixed frame.
As a further improvement of the above technical scheme, by described to lifting part transfer hanging to the side on the fixed frame
Method are as follows: third suspension centre is set in the first end, the lanyard being connected on the fixed frame is connect with the third suspension centre.
As a further improvement of the above technical scheme, the speed and institute that the main hanging device slings the first end
It is identical to state the speed that auxiliary hanging device slings the second end.
As a further improvement of the above technical scheme, the main hanging device drives described when lifting part rotation, institute
First end is stated to rotate relative to the second end.
As a further improvement of the above technical scheme, the main hanging device is mobile towards the auxiliary hanging device, or
The boom of the main hanging device is rotated towards the auxiliary hanging device.
As a further improvement of the above technical scheme, the main hanging device drives described when lifting part rotation, institute
Second end is stated to rotate relative to the first end.
As a further improvement of the above technical scheme, the auxiliary hanging device is mobile towards the main hanging device, or
The boom of the auxiliary hanging device is rotated towards the main hanging device.
As a further improvement of the above technical scheme, the main hanging device drives described when lifting part rotation, institute
First end and the second end are stated simultaneously relative to the center rotating to lifting part.
The beneficial effects of the present invention are: the hanging method in the present invention is set in lifting by main hanging device and auxiliary lifting
The lifting and aerial overturning to lifting part are realized in standby cooperation, can prevent it from generating biggish pendulum when lifting extra-long rod element
It is dynamic, the stability and safety of hoisting process are improved, and operating process is simple.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples:
Fig. 1 is the flow chart of hanging method in first embodiment of the invention;
Fig. 2 is the schematic diagram in first embodiment of the invention to lifting part;
Fig. 3 is the schematic diagram in first embodiment of the invention after lifting part completes assembly;
Fig. 4 is the schematic diagram in first embodiment of the invention when lifting part is lifted to a certain height;
Fig. 5 is the schematic diagram in first embodiment of the invention when lifting part is overturn to a certain angle;
Fig. 6 is overturn to lifting part to the schematic diagram of vertical state in first embodiment of the invention;
Fig. 7 is the schematic diagram in first embodiment of the invention when lifting part will change hook.
Specific embodiment
This part will be described in specific embodiments of the present invention, and presently preferred embodiments of the present invention is shown in the accompanying drawings, attached
The effect of figure is the description with figure supplementary explanation book word segment, of the invention so as to intuitively, visually understand
Each technical characteristic and overall technical architecture, but it should not be understood as limiting the scope of the invention.
In the description of the present invention, if being related to orientation description, such as "upper", "lower", "front", "rear", "left", "right"
The orientation or positional relationship of equal instructions is to be based on the orientation or positional relationship shown in the drawings, be merely for convenience of the description present invention and
Simplify description, rather than the device or element of indication or suggestion meaning must have a particular orientation, with specific orientation construction
And operation, therefore be not considered as limiting the invention.When a certain feature referred to as " setting ", " fixation ", " connection " are another
One feature, it can directly be arranged, fixes, be connected to another feature, and can also be arranged indirectly, fix, be connected to
In another feature.
In the description of the present invention, if being related to " several ", one or more is meant that, if be related to " more
It is a ", it is meant that two or more, if being related to " being greater than ", " being less than ", " being more than ", should be understood as not including this number, if
Be related to " more than ", " following ", " within ", should be understood as including this number.If being related to " first ", " second ", should manage
Solution is for distinguishing technical characteristic, being not understood to indicate or imply relative importance or implicitly indicating indicated technology
The quantity of feature or the precedence relationship for implicitly indicating indicated technical characteristic.
In addition, unless otherwise defined, technical terms and scientific terms used in the present invention with technical field
The normally understood meaning of technical staff is identical.Term used in the present invention is intended merely to description specific embodiment, rather than
In order to limit the present invention.
First embodiment
Referring to Figure 1 to Figure 7, hanging method provided in this embodiment is carried out as described below.
Step 1: main hanging device and auxiliary hanging device is arranged.
It will need to be completed from main hanging device 2 with auxiliary hanging device 3 when lifting part 1 is sling.Main hanging device 2
Tower crane can be selected or truck crane or crawler crane etc. can be selected in crawler crane, auxiliary hanging device 3.It can be according to the installation site to lifting part
And the factors such as hoisting height select hanging device.
Step 2: setting height will be lifted to lifting part.
When the length of lifting part 1 is larger, it is more inconvenient to be transported to construction site, therefore, if usually first will
Then these components are placed on moulding bed 4 to construction site, are welded it with shape by the shorter component conveying of dry segment length
At meet length requirement one whole to lifting part 1.It needs to carry out seam inspection after welding, to guarantee quality.Weld seam
After flaw detection is qualified, coating is painted at position while welding.
As shown in Fig. 2, the first suspension centre 11 is arranged in the first end to lifting part 1, the second suspension centre 12 is arranged in second end.
Third suspension centre 13 is arranged in one end, and third suspension centre 13 is staggered with 11 position of the first suspension centre.Preferably, third suspension centre 13 is located at first
The opposite side of suspension centre 11.Wherein, the first suspension centre 11 cooperates jointly to realize that the lifting to lifting part 1 is turned over position with the second suspension centre 12
Turn, the first suspension centre 11 cooperates jointly with third suspension centre 13 to realize and change hook in the air.End of the above-mentioned each suspension centre distance to lifting part 1
Distance about 10m.
As shown in figure 3, will be connected on the boom 21 of main hanging device 2 when after lifting part 1 completes assembly on moulding bed 4
Wirerope 22 bind at the first suspension centre 11.The wirerope 32 connected on the boom 31 of auxiliary hanging device 3 is bound second
At suspension centre 12.
Main hanging device 2 is lifted by crane with auxiliary hanging device 3, makes to be detached to lifting part 1 and moulding bed 4, until reaching setting height.
Need to only meet will not encounter ground in its bottom end when overturning when lifting part 1 under the setting height.To lifting part 1 by main lifting
Equipment 2 is sling simultaneously with auxiliary hanging device 3, can be limited its generation and significantly be swung, to improve the safety of lifting process.
At this point, main hanging device 2 and auxiliary hanging device 3 need to keep synchronous to shift position, pullled in order to avoid being formed between each other.
As shown in Figure 4, it is preferred that speed that main hanging device 2 slings the first suspension centre 11 and auxiliary hanging device 3 are by second
The speed that suspension centre 12 is sling is identical.Horizontality is remained in uphill process to lifting part 1, to make to lifting part 1
Movement in lifting only straight up, can be further improved the stability and safety of lifting process.
Step 3: auxiliary hanging device stops working, main hanging device drives described to lifting part rotation.
As shown in figs. 5 and 6, will be after lifting part 1 be lifted to setting height, auxiliary hanging device 3 stops lifting, and master hangs
Installing standby 2 drives to be rotated to lifting part 1, will gradually be overturn by horizontality to vertical state to lifting part 1.
In above-mentioned switching process, the boom 21 of main hanging device 2 needs gradually to rotate towards auxiliary hanging device 3, so that
It (is connect with auxiliary hanging device 3 to the first end (one end being connect with main hanging device 2) on lifting part 1 relative to second end
One end) it rotates clockwise.In the process, the rotation that remains a constant speed is needed, to improve stability and safety.When turning over certain angle
After degree, to lifting part 1 by state in a vertical shape, that is, overturning is completed.
Later, make to be detached to lifting part 1 and auxiliary hanging device 3, by main hanging device 2 continue will to be hung to lifting part 1 to
Near installation site.Crosshead is provided at position to be installed, operator enters crosshead and carries out changing hook operation.Such as Fig. 7
It is shown, the binding of the lanyard on fixed frame 56 will be connected at the third suspension centre 13 to lifting part 1.Then, main hanging device 2
Wirerope 22 is begun to decline, so that being gradually transferred on fixed frame 5 to 1 weight of lifting part.When the weight to lifting part 1 turns completely
It moves on fixed frame 5, after the wirerope 22 of main hanging device 2 does not stress, the wirerope 22 on main hanging device 2 is unclamped,
Make to completely disengage to lifting part 1 and main hanging device 2.
After being adjusted with the position that lanyard 6 treats lifting part 1, it is fixed in place to be installed.It is carried out in order to prevent
It swings, can be fixed in components such as the practical cable wind ropes in its bottom, in order to the installation of subsequent parts.
Second embodiment
The present embodiment is the alternate embodiment of first embodiment, in the present embodiment, is made to the first end phase on lifting part 1
When for second end rotation, main hanging device 2 can be made mobile towards auxiliary hanging device 3, main hanging device 2 is gradually reduced and is hung with auxiliary
Installing standby the distance between 3.Main hanging device 2 need to remain a constant speed advance, to improve stability and safety.
3rd embodiment
The present embodiment is the alternate embodiment of first embodiment, in the present embodiment, is made to the first end phase on lifting part 1
When for second end rotation, the boom 21 of main hanging device 2 can be made gradually to rotate towards auxiliary hanging device 3, meanwhile, make main lifting
Equipment 2 is mobile towards auxiliary hanging device 3.
Fourth embodiment
The present embodiment is the alternate embodiment of first embodiment, in the present embodiment, make the boom 31 of auxiliary hanging device 3 by
Gradually towards main hanging device 2 rotate so as to the second end (one end being connect with auxiliary hanging device 3) on lifting part 1 relative to
First end (one end connecting with main hanging device 2) rotates clockwise.In the process, the rotation that remains a constant speed is needed, to improve
Stability and safety.
5th embodiment
The present embodiment is the alternate embodiment of fourth embodiment, in the present embodiment, so as to the second end on lifting part 1
When relative to first end rotation, auxiliary hanging device 3 can be made mobile towards main hanging device 2, be gradually reduced main hanging device 2 with it is auxiliary
The distance between hanging device 3.Auxiliary hanging device 3 need to remain a constant speed advance, to improve stability and safety.
Sixth embodiment
The present embodiment is the alternate embodiment of fourth embodiment, in the present embodiment, is made to the second end phase on lifting part 1
When for first end rotation, the boom 31 of auxiliary hanging device 3 can be made to rotate towards main hanging device 2, meanwhile, set auxiliary lifting
Standby 3 is mobile towards main hanging device 2.
7th embodiment
The present embodiment is the alternate embodiment of first embodiment, in the present embodiment, is made when lifting part 1 is overturn, can be with
It rotates the boom 21 of main hanging device 2 gradually towards auxiliary hanging device 3, and keeps main hanging device 2 mobile towards auxiliary hanging device 3,
Meanwhile rotate the boom of auxiliary hanging device 3 towards main hanging device 2, and keep auxiliary hanging device 3 mobile towards main hanging device 2, from
And make first end and second end to lifting part 1 simultaneously relative to the center rotating to lifting part 1.
It is to be illustrated to what preferable implementation of the invention carried out, but the present invention is not limited to the embodiment, institute above
The technical staff in category field can also make various equivalent deformation or replacement without departing from the purpose of the present invention.In addition,
In the absence of conflict, the feature in the embodiment of the present invention and embodiment can be combined with each other.
Claims (10)
1. a kind of hanging method, which is characterized in that include the following steps,
Main hanging device and auxiliary hanging device is arranged in S 10;
Main hanging device described in S20 slings the first end to lifting part, and the auxiliary hanging device is by lifting part
Two ends are sling, until reaching setting height;
Auxiliary hanging device described in S30 stops lifting, and the main hanging device drive is described to be rotated to lifting part, until described wait hang
Piece installing state in a vertical shape.
2. hanging method according to claim 1, which is characterized in that further include step S11 before step S20: will be described
It is completed to lifting part assembly, and the first suspension centre is set in the first end to lifting part, in the second end to lifting part
Second suspension centre is set.
3. hanging method according to claim 1, which is characterized in that further include step S40 after step S30: making described
It is detached to lifting part and the auxiliary hanging device, and will be described in lifting part transfer hanging to fixed frame.
4. hanging method according to claim 3, which is characterized in that will be described to lifting part transfer hanging to the fixation
Method on frame are as follows: third suspension centre is set in the first end, the lanyard being connected on the fixed frame and the third are hung
Point connection.
5. hanging method according to claim 1, which is characterized in that the main hanging device sling the first end
Speed is identical as the speed that the auxiliary hanging device slings the second end.
6. hanging method according to claim 1, which is characterized in that the main hanging device drives described to lifting part turn
When dynamic, the first end is rotated relative to the second end.
7. hanging method according to claim 6, which is characterized in that the main hanging device is moved towards the auxiliary hanging device
The boom of the dynamic or described main hanging device is rotated towards the auxiliary hanging device.
8. hanging method according to claim 1, which is characterized in that the main hanging device drives described to lifting part turn
When dynamic, the second end is rotated relative to the first end.
9. hanging method according to claim 8, which is characterized in that the auxiliary hanging device is moved towards the main hanging device
The boom of the dynamic or described auxiliary hanging device is rotated towards the main hanging device.
10. hanging method according to claim 1, which is characterized in that the main hanging device drives described to lifting part
When rotation, the first end and the second end are simultaneously relative to the center rotating to lifting part.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910752670.1A CN110482405A (en) | 2019-08-15 | 2019-08-15 | A kind of hanging method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910752670.1A CN110482405A (en) | 2019-08-15 | 2019-08-15 | A kind of hanging method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110482405A true CN110482405A (en) | 2019-11-22 |
Family
ID=68551138
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910752670.1A Pending CN110482405A (en) | 2019-08-15 | 2019-08-15 | A kind of hanging method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110482405A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112027913A (en) * | 2020-05-28 | 2020-12-04 | 中国核工业第五建设有限公司 | Rod piece hoisting system |
CN112299232A (en) * | 2020-11-16 | 2021-02-02 | 中核机械工程有限公司 | Method for hoisting L-shaped tower-attached pipeline on top of large-scale tower equipment by using single main lifting lug |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101301981A (en) * | 2008-05-23 | 2008-11-12 | 中国石油化工集团公司 | Hoisting method |
CN101759101A (en) * | 2008-12-24 | 2010-06-30 | 上海市基础工程公司 | Asymmetrical structure air posture adjusting method |
CN103058054A (en) * | 2012-12-27 | 2013-04-24 | 三一重工股份有限公司 | Tail device and tail dragging method |
CN103072893A (en) * | 2013-01-17 | 2013-05-01 | 中国核工业二三建设有限公司 | Tool and device for overturning vertical equipment in nuclear power plant |
CN103241652A (en) * | 2013-05-31 | 2013-08-14 | 中国海洋石油总公司 | Overturning process of heavy equipment |
-
2019
- 2019-08-15 CN CN201910752670.1A patent/CN110482405A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101301981A (en) * | 2008-05-23 | 2008-11-12 | 中国石油化工集团公司 | Hoisting method |
CN101759101A (en) * | 2008-12-24 | 2010-06-30 | 上海市基础工程公司 | Asymmetrical structure air posture adjusting method |
CN103058054A (en) * | 2012-12-27 | 2013-04-24 | 三一重工股份有限公司 | Tail device and tail dragging method |
CN103072893A (en) * | 2013-01-17 | 2013-05-01 | 中国核工业二三建设有限公司 | Tool and device for overturning vertical equipment in nuclear power plant |
CN103241652A (en) * | 2013-05-31 | 2013-08-14 | 中国海洋石油总公司 | Overturning process of heavy equipment |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112027913A (en) * | 2020-05-28 | 2020-12-04 | 中国核工业第五建设有限公司 | Rod piece hoisting system |
CN112299232A (en) * | 2020-11-16 | 2021-02-02 | 中核机械工程有限公司 | Method for hoisting L-shaped tower-attached pipeline on top of large-scale tower equipment by using single main lifting lug |
CN112299232B (en) * | 2020-11-16 | 2023-10-13 | 中核机械工程有限公司 | Method for hoisting tower top L-shaped tower-attached pipeline of large-scale tower equipment by single main lifting lug |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103848360B (en) | A kind of group tower tower crane being provided with packaged type balance weight system | |
CN202346637U (en) | Holding rod of double-flat-arm spinning self-lifting seat | |
CN109231023B (en) | Method for installing jib system of portal crane | |
CN103832933B (en) | A kind of group tower tower crane with auxiliary | |
CN110482405A (en) | A kind of hanging method | |
CN102730552A (en) | Special hold hoop equipment for complete machine installation of marine fan | |
CN206590793U (en) | Connect arm assembly and the movable arm tower crane comprising the device in the air | |
CN104963521B (en) | A kind of system and construction method for head tower integral hoisting rotation | |
CN107215784A (en) | The crane of Split rotary crane is installed | |
CN201952153U (en) | Portable detachable hoisting equipment | |
CN202296907U (en) | Suspension arm balanced movable arm tower crane capable of luffing based on steel rope traction | |
CN203359781U (en) | Hoisting device adopting clamp ring hoisting lug to hoist tower equipment | |
CN206088728U (en) | Novel large -scale gallows of taking a trial run | |
CN108408667A (en) | Broken line type girder truss rod piece Quick overturning device and its method for turning | |
CN106429788A (en) | Method for lifting cabin | |
CN210480628U (en) | Rotatory hoist of two-way self-balancing | |
CN212712478U (en) | Dismounting device for cargo boom and balance arm of tower crane | |
CN107253487A (en) | Fold mountain region derrick car and detection folds mountain region derrick car | |
CN203474321U (en) | Tower crane used for constructing and erecting electric transmission line iron towers | |
CN209306810U (en) | Scale beam type counter-jib suspender | |
CN106586822A (en) | Lifting tool | |
CN207330175U (en) | Detachable gin pole | |
CN103084817B (en) | The installation method of industry cylindrical furnace radiating furnace tube | |
CN207932896U (en) | Ring beam and ring rail integral hoisting tool | |
CN208532061U (en) | A kind of derrick crane convenient for construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191122 |