CN101298765B - Novel single pillar structure and mounting method thereof - Google Patents

Novel single pillar structure and mounting method thereof Download PDF

Info

Publication number
CN101298765B
CN101298765B CN2007101414930A CN200710141493A CN101298765B CN 101298765 B CN101298765 B CN 101298765B CN 2007101414930 A CN2007101414930 A CN 2007101414930A CN 200710141493 A CN200710141493 A CN 200710141493A CN 101298765 B CN101298765 B CN 101298765B
Authority
CN
China
Prior art keywords
pile
suction
new single
suction pile
pillar structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2007101414930A
Other languages
Chinese (zh)
Other versions
CN101298765A (en
Inventor
王翎羽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Neptune Offshore Engineering Development Co ltd
Original Assignee
HAIWANGXING OCEAN ENGINEERING TECHNOLOGY Co LTD TIANJIN CITY
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HAIWANGXING OCEAN ENGINEERING TECHNOLOGY Co LTD TIANJIN CITY filed Critical HAIWANGXING OCEAN ENGINEERING TECHNOLOGY Co LTD TIANJIN CITY
Priority to CN2007101414930A priority Critical patent/CN101298765B/en
Publication of CN101298765A publication Critical patent/CN101298765A/en
Application granted granted Critical
Publication of CN101298765B publication Critical patent/CN101298765B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

A new single post structure and an installation method thereof are disclosed, the structure is composed by a suction pile + driven pile 8, a central vertical post 9 and a small platform 10, characterized in that the structure adopts a combination basic of suction type + driven type, the small platform 10 forms an integrative structure with the central vertical post 9 by welding. A central guide cylinder 3 is located in centre of the cylinder body 1, upper end is higher than a top cover 2 with a bell-mouthed shape, the lower end is horizontal to bottom end of the cylinder body 1. A mud-cleaning jetting ring 7 is provided in middle of a lower rib plate 5 of the central guide cylinder 3 and a grouting jetting ring is provided in the middle of the central guide cylinder 3. The top cover 2 is provided with a pump hole 12 for installing an underwater pump 13 or a pneumatic pump. The invention has the advantages that the new single post structure varies P-Y curve of surface layer soil, which is in favour of reduction of displacement under horizontal force, and meanwhile enhances structural intensity of the post. During the construction, the combination basic of the new single post structure lessens hoisting weight, in the meantime, the suction pile assists and positions the driven pile.

Description

A kind of new single pillar structure and mounting method thereof
Technical field
The invention belongs to the innovation of marine single pillar structure pattern in ocean engineering field and mounting method thereof.
Background technology
At present in ocean engineering extensive use two class single pillar structures are arranged, a class is the driven pile rod structure, another kind of is the suction pile rod structure.Characteristic according to earth resistance, the bearing capacity of topsoil is very weak, and the driven pile rod structure is elongated shape, therefore it is being subjected to the natural environment masterpiece time spent can produce big horizontal movement at Ni Mianchu, cause driven pile rod structure fatigue to make its damage easily, also need erection device less important work when driven pile is constructed simultaneously at sea, but the characteristics of this class formation are the offshore construction technology maturations; The suction pile has then improved the supporting capacity of topsoil by self structure, but because the suction pile rod structure is stubby shape, be subjected to the natural environment masterpiece time spent can cause structure to be toppled, but the characteristics of this class formation are offshore construction duration weak points and can reuse.In addition, suction pile rod structure form and special marine suction sinking method adapt.Do the time spent at above-mentioned two class single pillar structures in the external force of experiencing certainly and all have weak point.
Summary of the invention
For optimizing structure and remedying the defective separately of two class single pillar structures, effectively reduce use to the offshore construction resource, the invention provides a kind of new single pillar structure and mounting method thereof.This single pillar structure has the suction pile concurrently and squeezes into the pattern of pile two class formations, by wirerope with suction pile with driven pile links into an integrated entity or split lifting entry is transferred.This single pillar structure is because the structural shape that itself is had, corresponding offshore installation method is also special---and be suction sinking method and the associating of squeezing into method, structure is by forming the suction seal condition from the mud of reentrying, and can in suction pile suction sinking penetration process, finish leveling and clear mud, after injection puts in place, make driven pile injection ocean bottom soil desired depth with pile hammer, grouting makes driven pile and suction pile be consolidated into one then, improve driven pile and suction pile deficiency separately, improve single pillar structure and bear the ability of environmental forces, and reached the use that reduces the offshore construction resource.
The technical solution adopted for the present invention to solve the technical problems is: new single pillar structure by cylindrical shell, top cover, centre pilot tube, go up floor, ring is dashed in floor, grouting spray down, clear mud spray is formed towards ring, driven pile, gin pole and chain-wales, it is characterized in that adopting suction type+squeeze into the commbined foundations of formula, between cylindrical shell and the centre pilot tube by top cover, go up floor and following floor connects as one structure (abbreviation suction pile).The centre pilot tube is positioned at cylindrical shell central authorities, and the upper end exceeds top cover, becomes the horn mouth shape, is used for the pitching pile guiding of driven pile, and the lower end flushes with the cylindrical shell bottom.The place is provided with mud spray clearly and dashes ring in the middle of the following floor of centre pilot tube, and the upper end is connected with high-pressure pump when the suction pile injection; The place is provided with the grouting spray and dashes ring in the middle of the centre pilot tube, and the upper end supports the grouting pump on the ship to be connected with construction.Top cover is provided with pumping hole, is used for the pump that extracts water in the suction pile is installed, as submersible pump or air-powered pump.When new single pillar structure is at sea installed, can transport by barge loading, crane ship lifting entry, rely on deadweight to make suction pile go into mud and reach the initial sealing condition, start clear mud spray and dash the high-pressure pump of ring, remove the soil plug in the centre pilot tube, and extract water in the suction pile, make suction pile in injection ocean bottom soil process, finish clear mud in the centre pilot tube by submersible pump.This process can draw water submersible pump or water filling by control suction pile top pump valve system, and that adjusts suction pile goes into the mud degree of depth and levelness.After suction pile puts in place, carry out piling work, after driven pile reaches pre-provisioning request, can carry out the grouting operation between suction pile and the driven pile, at last gin pole is installed on the driven pile together with chain-wales.
The invention has the beneficial effects as follows that new single pillar structure is big at the native counter-force P of Ni Mianchu P-Y curve, help reducing the displacement under the horizontal force action, also improved the structural strength of stake simultaneously.In construction, new single pillar structure can and be squeezed into pile with suction pile and lift respectively, reduces to lift weight, has reduced the requirement to crane ship, and suction pile rises driven pile and sets upright positioning action simultaneously, need not the erection device of driven pile.
Description of drawings
The invention will be further described below in conjunction with drawings and Examples.
Fig. 1 is elevation of the present invention and sectional view;
Fig. 2 is that schematic diagram is transferred in one lifting entry of the present invention;
Fig. 3 is that the present invention installs schematic diagram.
Wherein: the 1-cylindrical shell; The 2-top cover; 3-centre pilot tube; The last floor of 4-; Floor under the 5-; Ring is dashed in 6-grouting spray; Ring is dashed in the clear mud spray of 7-; The 8-driven pile; The 9-gin pole; The 10-chain-wales; The 11-pile follower; The 12-pumping hole; The 13-submersible pump; The 14-crane barge; The 15-water surface; 16-soil.
The specific embodiment
New single pillar structure is seen Fig. 1, by cylindrical shell 1, top cover 2, centre pilot tube 3, go up floor 4, ring 6 is dashed in floor 5, grouting spray down, clear mud spray is dashed ring 7, driven pile 8, gin pole 9, chain-wales 10 and pumping hole 12 and formed, driven pile 8 is positioned at centre pilot tube 3, and gin pole 9 is connected with driven pile 8 with chain-wales 10; Top cover 2 end faces are provided with pumping hole 12, and submersible pump 13 or air-powered pump are installed in its top.
New single pillar structure one lifting entry is transferred and is seen Fig. 2, and transferred to seabed mud face by sling suction pile, driven pile 8 and pile follower 11 and submersible pump 13 of crane barge 14 this moment, and make suction pile and driven pile 8 basic initial penetration into mud reach air-proof condition by deadweight.
New single pillar structure is by extracting the water in the suction pile, make in the suction pile injection ocean bottom soil 16, in injection soil 16 processes, the pump valve system draws water or water filling submersible pump 13 by control suction pile top, adjust suction pile and go into the mud degree of depth and levelness, water under high pressure sprays towards 7 pairs of center guide cylinders of ring, 3 interior soil by clear mud and fills in the row removing simultaneously.After the suction pile injection puts in place, with pile hammer impact pile follower 11 make driven pile 8 also injection to soil 16 desired depths, dashing ring 6 by grouting spray then is in the milk toward the annular space between centre pilot tube 3 inwalls and driven pile 8 outer walls, at last gin pole 9 is mounted on the driven pile 8 together with chain-wales 10, sees Fig. 3.

Claims (6)

1. new single pillar structure, by cylindrical shell, top cover, centre pilot tube, go up floor, ring is dashed in floor, grouting spray down, clear mud spray is formed towards ring, driven pile, gin pole and chain-wales, its feature adopts suction type+squeeze into commbined foundations of formula, chain-wales and the gin pole structure that is welded as a whole.
2. new single pillar structure according to claim 1 is characterized in that the centre pilot tube inwall of said suction pile and the annular space between the driven pile outer wall are one by cement-grouting consolidation.
3. new single pillar structure according to claim 1 is characterized in that said suction pile top is provided with pumping hole, is used for installing the pump that extracts water in the suction pile.
4. new single pillar structure according to claim 1 is characterized in that the centre pilot drum outer wall of said suction pile is adorned 2 sprays towards ring, and one is used for removing the soil plug, and another is used for being in the milk.
5. new single pillar structure according to claim 1 is characterized in that said suction type+squeeze into the commbined foundations of formula, and is big at the native counter-force P of Ni Mianchu P-Y curve, helps reducing the displacement under the horizontal force action, also improved the structural strength of stake simultaneously.
6. according to the mounting method of the described new single pillar structure of claim 1 to 5, it is characterized in that two kinds of job practicess that the marine pile foundation engineering of commbined foundations collection of said employing suction type+squeeze into formula is installed, it is suction sinking method and the installation of uniting of squeezing into method: at first crane ship lifting suction pile entry, rely on deadweight to make suction pile go into mud and reach the initial sealing condition, submersible pump extracts the water in the suction pile, make suction pile in injection ocean bottom soil process, finish clear mud in the centre pilot tube, after suction pile puts in place, carry out piling work, after driven pile reaches pre-provisioning request, can carry out the grouting operation between suction pile and the driven pile, finish the construction on basis.
CN2007101414930A 2007-08-27 2007-08-27 Novel single pillar structure and mounting method thereof Expired - Fee Related CN101298765B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2007101414930A CN101298765B (en) 2007-08-27 2007-08-27 Novel single pillar structure and mounting method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2007101414930A CN101298765B (en) 2007-08-27 2007-08-27 Novel single pillar structure and mounting method thereof

Publications (2)

Publication Number Publication Date
CN101298765A CN101298765A (en) 2008-11-05
CN101298765B true CN101298765B (en) 2010-04-21

Family

ID=40078700

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2007101414930A Expired - Fee Related CN101298765B (en) 2007-08-27 2007-08-27 Novel single pillar structure and mounting method thereof

Country Status (1)

Country Link
CN (1) CN101298765B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101879932B (en) * 2009-05-08 2013-03-06 中国海洋石油总公司 Method for lengthening and lading steel piles of large deepwater jacket
BRPI1105774B1 (en) * 2010-10-19 2020-08-11 Horton Wison Deepwater, Inc OFFSHORE STRUCTURE FOR DRILLING AND / OR PRODUCTION OF A SUBMARINE WELL AND METHOD
CN103911978B (en) * 2014-03-24 2016-08-17 广州中国科学院工业技术研究院 A kind of marine prefabricated platform and installation method thereof
CN104805817B (en) * 2015-01-12 2016-11-09 烟台中集来福士海洋工程有限公司 Self-elevating ocean platform and immersible pump tower thereof
CN107090844A (en) * 2017-05-19 2017-08-25 中交第三航务工程局有限公司 Offshore wind farm grouped piles cap composite foundation and construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1016199B (en) * 1989-06-03 1992-04-08 渤海石油公司工程设计公司 Training subsidence foundation and subsidence technology for under sea working
GB2341409A (en) * 1998-09-08 2000-03-15 John Stephen Baross Supporting a pipeline above the seabed
CN1317160C (en) * 2002-02-26 2007-05-23 天津市海王星海上工程技术有限公司 Self-installed suction anchor

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1016199B (en) * 1989-06-03 1992-04-08 渤海石油公司工程设计公司 Training subsidence foundation and subsidence technology for under sea working
GB2341409A (en) * 1998-09-08 2000-03-15 John Stephen Baross Supporting a pipeline above the seabed
CN1317160C (en) * 2002-02-26 2007-05-23 天津市海王星海上工程技术有限公司 Self-installed suction anchor

Also Published As

Publication number Publication date
CN101298765A (en) 2008-11-05

Similar Documents

Publication Publication Date Title
CN107542101B (en) Construction method of offshore four-buoy-buoyancy tank combined foundation structure
CN107653895B (en) Combined offshore six-buoy buoyancy tank foundation structure and construction method thereof
CN107630461B (en) Combined offshore four-buoy buoyancy tank foundation structure and construction method thereof
CN200971492Y (en) Pile submarine drilling basal disc with suction
CN101298765B (en) Novel single pillar structure and mounting method thereof
CN108316338B (en) Suction injection type arc-shaped steel anchor
CN102383431B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN101255701A (en) At-sea composite foundation
CN111456075A (en) Pile barrel composite truss type offshore wind turbine foundation and construction process thereof
CN113417311A (en) Offshore wind power multi-cylinder jacket foundation construction method
CN103015455B (en) Bridge pile-bucket combined foundation and construction method thereof
CN105401577A (en) Suction type pile shoe suitable for self-lifting platform and mounting method
CN113404081A (en) Suction bucket foundation structure assisting sinking by using high-frequency vibration device and construction method thereof
CN110258571A (en) A kind of bored concrete pile pipe sinking pressure grouting construction method
CN103031853B (en) Seabed oil storage system
CN216739729U (en) Self-elevating platform suction pile shoe device suitable for silt operation
CN109306706B (en) Main and auxiliary barrel seabed injection device and construction method thereof
CN210797617U (en) Pile barrel composite truss type offshore wind turbine foundation
CN103572770B (en) A kind of stake case hydraulic structures and construction method thereof
CN201347191Y (en) Suction pile type ocean floor drilling novel basal disc
CN202176267U (en) Novel suction pile type seabed drilling base plate
CN201883448U (en) Mixed foundation on sea
CN103556972A (en) Self-installed ocean floor drilling template and installation method thereof
CN102953709A (en) Novel suction pile type subsea drilling template
CN203755335U (en) Negative-pressure bucket-shaped basic structure of offshore wind turbine with pile-type steel framework

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Novel single pillar structure and mounting method thereof

Effective date of registration: 20130724

Granted publication date: 20100421

Pledgee: Bank of Shanghai Limited by Share Ltd. Tianjin branch

Pledgor: Tianjin Neptune Offshore Engineering Development Co.,Ltd.|WUDI HAIZHONG FLEXIBLE PIPE MANUFACTURING CO.,LTD.

Registration number: 2013990000500

PLDC Enforcement, change and cancellation of contracts on pledge of patent right or utility model
C56 Change in the name or address of the patentee

Owner name: NEPTUNE OFFSHORE ENGINEERING DEVELOPMENT CO., LTD.

Free format text: FORMER NAME: HAIWANGXING OCEAN ENGINEERING TECHNOLOGY CO., LTD, TIANJIN CITY

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 300384 Tianjin City, Nankai District Huayuan Industrial Park Road No. 1 Industrial Park E block 6 layer

Patentee after: NEPTUNE OFFSHORE ENGINEERING DEVELOPMENT Co.,Ltd.

Address before: 300384 Tianjin City, Nankai District Huayuan Industrial Park Road No. 1 Industrial Park E block 6 layer

Patentee before: Tianjin Neptune Offshore Engineering Development Co.,Ltd.

PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20141119

Granted publication date: 20100421

Pledgee: Bank of Shanghai Limited by Share Ltd. Tianjin branch

Pledgor: NEPTUNE OFFSHORE ENGINEERING DEVELOPMENT Co.,Ltd.|WUDI HAIZHONG FLEXIBLE PIPE MANUFACTURING CO.,LTD.

Registration number: 2013990000500

PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Novel single pillar structure and mounting method thereof

Effective date of registration: 20141120

Granted publication date: 20100421

Pledgee: Bank of Shanghai Limited by Share Ltd. Tianjin branch

Pledgor: NEPTUNE OFFSHORE ENGINEERING DEVELOPMENT Co.,Ltd.

Registration number: 2014990000973

PLDC Enforcement, change and cancellation of contracts on pledge of patent right or utility model
PM01 Change of the registration of the contract for pledge of patent right

Change date: 20141119

Registration number: 2013990000500

Pledgor after: NEPTUNE OFFSHORE ENGINEERING DEVELOPMENT Co.,Ltd.

Pledgor after: WUDI HAIZHONG FLEXIBLE PIPE MANUFACTURING CO.,LTD.

Pledgor before: Tianjin Neptune Offshore Engineering Development Co.,Ltd.

Pledgor before: WUDI HAIZHONG FLEXIBLE PIPE MANUFACTURING CO.,LTD.

PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20160108

Granted publication date: 20100421

Pledgee: Bank of Shanghai Limited by Share Ltd. Tianjin branch

Pledgor: NEPTUNE OFFSHORE ENGINEERING DEVELOPMENT Co.,Ltd.

Registration number: 2014990000973

PLDC Enforcement, change and cancellation of contracts on pledge of patent right or utility model
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Novel single pillar structure and mounting method thereof

Effective date of registration: 20160125

Granted publication date: 20100421

Pledgee: Bank of Shanghai Limited by Share Ltd. Tianjin branch

Pledgor: NEPTUNE OFFSHORE ENGINEERING DEVELOPMENT Co.,Ltd.

Registration number: 2016120000003

PLDC Enforcement, change and cancellation of contracts on pledge of patent right or utility model
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20170527

Granted publication date: 20100421

Pledgee: Bank of Shanghai Limited by Share Ltd. Tianjin branch

Pledgor: NEPTUNE OFFSHORE ENGINEERING DEVELOPMENT Co.,Ltd.

Registration number: 2016120000003

PC01 Cancellation of the registration of the contract for pledge of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100421

CF01 Termination of patent right due to non-payment of annual fee