CN101298763B - Method for closure of dam - Google Patents
Method for closure of dam Download PDFInfo
- Publication number
- CN101298763B CN101298763B CN200710040361A CN200710040361A CN101298763B CN 101298763 B CN101298763 B CN 101298763B CN 200710040361 A CN200710040361 A CN 200710040361A CN 200710040361 A CN200710040361 A CN 200710040361A CN 101298763 B CN101298763 B CN 101298763B
- Authority
- CN
- China
- Prior art keywords
- bag
- filling
- mud
- son
- female
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
- Y02A10/11—Hard structures, e.g. dams, dykes or breakwaters
Landscapes
- Revetment (AREA)
Abstract
The invention discloses a method for folding a dyke, characterized in that the method uses a primary-secondary bag, the primary-secondary bag comprises a primary bag to which two secondary bags are connected, first of all, the primary bag is filled up to dispose at a folding opening; when folding, the secondary bags are filled up in the first place to be higher than the primary bag for blocking or cutting off upper water stream of the primary bag; flow speed of the water stream on top of the primary bag is reduced and then a mud bag is disposed on the primary bag to fill the sands, afterwards, the empty mud bag is disposed on the filled mud bag and filled with the sands; the mud bags can be sequentially superposed together by repeatedly filling up the mud bags to fold the opening of the dyke. The method of the invention can be applied to folding the dyke.
Description
Technical field
The present invention relates to the method for closure of dam.
Background technology
The corral engineering more often adopts the construction method of the flat stifled closure of filling bag at present.In closure work, by keeping suitable mouth door, when Dang Wei district water level declines to the mouth door weir crest depth of water 0.5m left and right sides with ebb tide, begin artificial water middle berth bag filling construction, because the weir crest flow rate of water flow is general bigger, and must be in a hurry with trend, therefore often difficulty of construction is big, has subject matter:
If flow velocity surpasses 0.5m/s during closure, have a strong impact on bagging laying personnel's construction safety, bagging also is difficult in place, greatly increases closure difficulty and risk;
Cloth bag begins packing stage, and is little than flow action with the frictional resistance of lower floor bagging, and sliding phenomenon often takes place, so usually need to adopt the large scale bagging, affects the closure progress, also uneconomical;
For rapid uplift closure section is cut off the water supply, also normal the employing cut off the water supply with a very fast filling lifting of little filling bag earlier, or elder generation's construction sealing rock mound (being commonly called as the swallow nest) has slowed down a mouthful door weir crest flow velocity before the Longkou, but exists equally, speed of application is slow, uneconomic problem.
Summary of the invention:
The objective of the invention is for a kind of construction safety is provided, speed of application is fast, economic closure method.
For achieving the above object, the present invention has adopted following technical scheme:
A kind of method of closure of dam, it is characterized in that: use a kind of protection composite bag, described protection composite bag comprises a female bag, be connected with two son bags on female bag, at first the filling of mother's bag is placed on the Longkou, elder generation's filling bag during closure, make the son bag be higher than female bag, stop or block the upper current of female bag, reduce female bag top flow rate of water flow, filling mud bag is positioned on female bag is filled into sand, empty mud bag is positioned on the good mud bag of filling again, to be filled into sand in the empty mud bag, repetition filling mud bag can make the mud bag of filling stack up successively the dykes and dams Longkou is joined the two sections of a bridge, etc.
Preferably, described son bag is positioned at female bag both sides, and make son bag and female bag horizontally, the son bag highly is higher than female bag after the filling, at first the filling of mother's bag is placed on the Longkou, and filling bag makes the son bag become concave shape with protection composite bag then, the mud bag is stacked between two son bags is filled into sand, empty mud bag is positioned on the good mud bag of filling, will be filled into sand in the empty mud bag, repetition filling mud bag can make the mud bag of filling stack up successively the dykes and dams Longkou is joined the two sections of a bridge, etc.。
Preferably, described son bag is positioned on female bag, two son bags after the filling become the ridge shape, at first the filling of mother's bag is placed on the Longkou, filling bag makes two son bags become the ridge shape again, the mud bag is positioned between two son bags is filled into sand, empty mud bag is positioned on the good mud bag of filling again, to be filled into sand in the empty mud bag, repetition filling mud bag can make the mud bag of filling stack up successively the dykes and dams Longkou is joined the two sections of a bridge, etc.
Owing to adopted above scheme, the beneficial effect that the present invention is possessed is, son bag after the filling is higher than female bag, can stop or block current, reduce mother's bag top flow rate of water flow, make female bag top stack the easy construction of filling mud bag, safety, quick: the son bag can at first form buffering to current, reduce current washing away filling bag, guarantee workmen's safety, therefore also can improve speed of application, and the closure cost is low.
Description of drawings
Fig. 1 is the protection composite bag structure place schematic diagram in the first embodiment of the invention;
Fig. 2 is the protection composite bag structural representation in the second embodiment of the invention.
The specific embodiment
Below in conjunction with embodiment the present invention is further described.
As shown in Figure 1, a kind of method of closure of dam, it is characterized in that: use a kind of protection composite bag, described protection composite bag comprises a female bag 1, be connected with son bag 2 on female bag 1, described son bag 2 is positioned at female bag 1 both sides, son bag 2 is horizontal with mother's bag 1, son bag 2 highly is higher than female bag 1, son bag 2 after the filling forms concave shape with female bag 1, at first 1 filling of mother's bag is placed on the Longkou, refills son bag 2 and make son bag 2 make protection composite bag become concave shape, again mud bag 3 is positioned between two son bags, sand is filled in the mud bag 3, empty mud bag is positioned on the good mud bag of filling, will be filled into sand in the empty mud bag, repetition filling mud bag can make the mud bag of filling stack up successively the dykes and dams Longkou is joined the two sections of a bridge, etc.
Be illustrated in figure 2 as second embodiment of the invention, described son bag 2 is positioned on female bag 1, two son bags 2 after the filling form the ridge shape, at first 1 filling of mother's bag is placed on the Longkou, refills son bag 2 and make 2 one-tenth ridge shapes of two son bags, again mud bag 3 is positioned between two son bags 2, sand is filled in the mud bag 3, empty mud bag is positioned on the good mud bag of filling, will be filled into sand in the empty mud bag, repetition filling mud bag can make the mud bag of filling stack up successively the dykes and dams Longkou is joined the two sections of a bridge, etc.
Protection composite bag among the present invention and filling mud bag can adopt the high-strength compound geotextiles to make.
Claims (3)
1. the method for a closure of dam, it is characterized in that: use a kind of protection composite bag, described protection composite bag comprises a female bag, be connected with two son bags on female bag, at first the filling of mother's bag is placed on the Longkou, elder generation's filling bag during closure, make the son bag be higher than female bag, stop or block the upper current of female bag, reduce female bag top flow rate of water flow, the mud bag is positioned on female bag is filled into sand, empty mud bag is positioned on the good mud bag of filling again, to be filled into sand in the empty mud bag, repeat the filling mud bag good mud bag that can make filling and stack up successively the dykes and dams Longkou is joined the two sections of a bridge, etc.
2. the method for closure of dam according to claim 1, it is characterized in that, described son bag is positioned at female bag both sides, and make son bag and female bag horizontally, the son bag highly is higher than female bag after the filling, at first the filling of mother's bag is placed on the Longkou, filling bag makes protection composite bag become concave shape then, again the mud bag is stacked between two son bags and is filled into sand, empty mud bag is positioned on the good mud bag of filling again, to be filled into sand in the empty mud bag, repeat the filling mud bag good mud bag that can make filling and stack up successively the dykes and dams Longkou is joined the two sections of a bridge, etc.
3. the method for closure of dam according to claim 1, it is characterized in that, described son bag is positioned on female bag, two son bags after the filling become the ridge shape, at first the filling of mother's bag is placed on the Longkou, filling bag makes two son bags become the ridge shape again, again the mud bag is positioned between two son bags and is filled into sand, empty mud bag is positioned on the good mud bag of filling again, to be filled into sand in the empty mud bag, repeat the filling mud bag good mud bag that can make filling and stack up successively the dykes and dams Longkou is joined the two sections of a bridge, etc.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200710040361A CN101298763B (en) | 2007-04-30 | 2007-04-30 | Method for closure of dam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200710040361A CN101298763B (en) | 2007-04-30 | 2007-04-30 | Method for closure of dam |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101298763A CN101298763A (en) | 2008-11-05 |
CN101298763B true CN101298763B (en) | 2010-05-19 |
Family
ID=40078698
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN200710040361A Active CN101298763B (en) | 2007-04-30 | 2007-04-30 | Method for closure of dam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101298763B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104179186A (en) * | 2013-05-21 | 2014-12-03 | 山东省水利科学研究院 | Still water dumping filling blocking method for seawall |
CN107476257A (en) * | 2017-09-30 | 2017-12-15 | 潘文安 | A kind of dike breach and the method for blocking of cofferdam closure |
CN112502093A (en) * | 2020-12-25 | 2021-03-16 | 浙江省围海建设集团股份有限公司 | Sand-filled pipe bag type seawall closure control method |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2434338Y (en) * | 1999-10-17 | 2001-06-13 | 董禹全 | Dam bag |
CN1324971A (en) * | 2000-05-19 | 2001-12-05 | 武汉水利电力大学 | Floating and choking river-damming method |
CN1488816A (en) * | 2003-08-20 | 2004-04-14 | 陆晓升 | Master-slave type pipe bag and construction process thereof |
-
2007
- 2007-04-30 CN CN200710040361A patent/CN101298763B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2434338Y (en) * | 1999-10-17 | 2001-06-13 | 董禹全 | Dam bag |
CN1324971A (en) * | 2000-05-19 | 2001-12-05 | 武汉水利电力大学 | Floating and choking river-damming method |
CN1488816A (en) * | 2003-08-20 | 2004-04-14 | 陆晓升 | Master-slave type pipe bag and construction process thereof |
Non-Patent Citations (4)
Title |
---|
JP特开2001-40629A 2001.02.13 |
JP特开2005-207018A 2005.08.04 |
胡军庆等.上海南汇东滩促淤圈围(四期)工程1#龙口合拢技术的探讨.皖西学院学报20 5.2004,20(5),61-65. |
胡军庆等.上海南汇东滩促淤圈围(四期)工程1#龙口合拢技术的探讨.皖西学院学报20 5.2004,20(5),61-65. * |
Also Published As
Publication number | Publication date |
---|---|
CN101298763A (en) | 2008-11-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101298763B (en) | Method for closure of dam | |
CN104695380A (en) | Revetment structure composed of plastic steel plate piles and concrete | |
CN107059786B (en) | A kind of floating wall of movable embankment protection | |
CN106638486B (en) | High-tech zones cut-pff wall and gallery stage construction method | |
CN204626402U (en) | A kind of intermediate anchoring structure for the long slope seepage control layer of super large liquid storage tank | |
CN202945572U (en) | Foldable self-balancing water retaining wall | |
CN104141285A (en) | Seepage-proofing seawall | |
CN202787190U (en) | Frame used in riprap closure method for high flow rate closure gap | |
CN104863097A (en) | Flexible sand stop curtain structure | |
CN103147422A (en) | Earth-rock dam breaking overtopping field test method | |
CN203096696U (en) | High and low composite backwater weir | |
CN203654232U (en) | Enclosure closure gap protection structure applicable to deep beaches | |
CN205444090U (en) | Flip trajectory bucket worker's supplementary energy dissipation revetment structure | |
CN202416338U (en) | Foundation for novel grating dam | |
CN101768941A (en) | Diversion channel closure advancing dike of upstream cofferdam arranged on river channel | |
CN203487506U (en) | Water-absorbing rapid-hardening water retaining auxiliary dike | |
CN204174576U (en) | Antiseepage sea wall | |
CN105714740B (en) | Dyke fast blockage equipment | |
CN2700398Y (en) | Multifunctional flood prevention bag | |
CN208121699U (en) | A kind of lift shuts off caisson | |
CN207405584U (en) | A kind of checkdam for hydraulic and hydroelectric engineering | |
CN203890952U (en) | Spur dike structure suitable for stable river bed of mountain river | |
CN208219678U (en) | A kind of TGXG with auxetic effect | |
CN202849996U (en) | Hinge type mold bag | |
CN1563595A (en) | Harness method for dredging riverway containing much fluvial sand |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |