CN101291061B - 一种电力系统动态过程状态估计方法 - Google Patents

一种电力系统动态过程状态估计方法 Download PDF

Info

Publication number
CN101291061B
CN101291061B CN2008100988631A CN200810098863A CN101291061B CN 101291061 B CN101291061 B CN 101291061B CN 2008100988631 A CN2008100988631 A CN 2008100988631A CN 200810098863 A CN200810098863 A CN 200810098863A CN 101291061 B CN101291061 B CN 101291061B
Authority
CN
China
Prior art keywords
generator
pmu
electrical network
node
measurement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2008100988631A
Other languages
English (en)
Other versions
CN101291061A (zh
Inventor
顾全
陈松林
陈根军
王新宝
钱锋
李九虎
郑玉平
沈国荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NR Electric Co Ltd
NR Engineering Co Ltd
Original Assignee
NR Electric Co Ltd
NR Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NR Electric Co Ltd, NR Engineering Co Ltd filed Critical NR Electric Co Ltd
Priority to CN2008100988631A priority Critical patent/CN101291061B/zh
Publication of CN101291061A publication Critical patent/CN101291061A/zh
Application granted granted Critical
Publication of CN101291061B publication Critical patent/CN101291061B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/22Flexible AC transmission systems [FACTS] or power factor or reactive power compensating or correcting units

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

电力系统动态过程状态估计方法,以电网扰动前的静态状态估计结果为基础断面,引入负荷模型和发电机模型,对电网进行等效处理,在电网扰动过程中,使用同步相量测量单元PMU量测获得发电机数据,结合原电网各节点的有功和无功零注入伪量测方程,对电网各节点状态进行估计,在仅有发电厂PMU量测的条件下获得电网的动态过程状态。由于以扰动前的电网状态为基础,只对发电厂有PMU布点要求,有效解决了电网扰动条件下的状态监视问题,在同一扰动下,对连续的PMU量测断面可直接把PMU量测数据代入迭代计算,可提供电网扰动过程中的连续断面供稳定控制和分析使用,具有速度快的优点,可满足动态过程实时监视的要求。

Description

一种电力系统动态过程状态估计方法
技术领域
本发明涉及应用电力系统同步相量测量单元PMU(Phasor Measurement Unit)量测进行状态估计的方法,具体为一种基于PMU量测的电力系统动态过程状态估计方法,对电网扰动的连续过程进行状态估计。
背景技术
电网大多数情况下,处于平稳状态,负荷变化是一个缓慢过程,EMS中的量测虽然不是同一个时刻下采集的,但由于实际电网变化较慢,采集时间产生的误差相对于表计误差较小,因此可以认为采集的是电网同一个时刻断面。静态状态估计针对一个完整电网状态进行计算,在电网正常运行方式下能够满足监视和控制的需要。
电网在扰动条件下,系统潮流发生了转移,系统处于变化过程中,这时量测的不同时性产生的误差不可忽视,而常规RTU数据有5-10秒的时差,不能反映完整一致的电网状态。例如:大机组跳闸对系统的影响可分为三个阶段:在初始瞬间,系统内其它机组按与跳闸机组电气距离远近来分配突然出现的功率缺额,距离越近承担的越多,距离越远承担的越少;随后由于这些机组输出的电功率突变,而输入机械功率不变,各机组在减速力矩的作用下出现摆动,按转动惯量的大小重新分配因机组跳闸所缺的功率,惯量较大的机组承担的比例较大;第三阶段是经过若干次功率摆动后,系统频率有所下降,网内参加一次调频的机组根据各自调速器特性最终分配功率缺额,该过程大约需要二十秒的时间。
传统的状态估计基于电网的遥测遥信,反映的是电网统一的静态断面。当出现开关变位后,通常需要等待一段时间,等遥测全部反映开关变位后的电网状态后才启动状态估计。但是这种方式有其固有的缺陷:一是等待时间不好确定,或者说难以确认是否已经等待足够的时间;二是大电网通常不断有开关变位信号,有虚假的信号和对电网状态没有影响的变位信号,有故障变位信号,设备正常操作变位信号等,这些信号影响状态估计软件的运行,使状态估计频繁处于一个等待状态。
电网故障状态下,会有大量遥信变位信号,调度员正确判断电网状态有一定困难,同时由于事故后电网运行方式发生了变化,电网潮流发生了转移,事故前的遥测量不能作为状态估计的依据,而等电网扰动消失后遥测全部更新需要一段时间,在这段时间里静态状态估计不能使用,根据变化中的厂站采集数据很难对电网运行方式作出正确判断,从而产生了电网状态监视的盲区。这段时间内调度员很难确定电网运行状态,特别是发生连续性故障时,调度员由于无法得到实时完整的运行方式,处理事故的难度很大。
基于GPS的同步相量测量单元(PMU)提供了带时标的遥测信息,这些信息为电网扰动过程状态估计提供了数据基础,同时带时标的数据为分析电网状态变化过程提供了数据基础,也是辨识电网故障和开关变位的重要数据源。但是目前安装的PMU装置比较少,只有重要厂站才会装设PMU装置,远远没有达到常规状态估计的可观测性要求。针对PMU装置的分布特点,电网动态过程估计需要研究新的状态估计方法,该方法不能依赖于常规的RTU量测,而只能使用发电厂和重要变电站的PMU装置提供的带时标数据。
发明内容
本发明要解决的问题是:当电网发生扰动后,在一段时间内常规RTU量测不能反映电网的完整运行状态,由于无法获得电网扰动过程中的完整状态而不能对扰动过程中的电网进行有效监视,而PMU量测虽可获得电压、功率、相角在扰动过程中的连续变化过程,但是目前PMU量测布点不多,不能直接满足电网状态估计可观测性的要求。
本发明的技术方案是:一种电力系统动态过程状态估计方法,以电网扰动前的静态状态估计结果为基础断面,引入负荷模型和发电机模型,对电网进行等效处理,在电网扰动过程中,使用同步相量测量单元PMU量测获得发电机数据,结合原电网各节点的有功和无功零注入伪量测方程,对电网各节点状态进行估计,在仅有发电厂PMU量测的条件下获得电网的动态过程状态。
本发明对电网进行等效处理时,每台发电机增加一个虚拟支路和虚拟发电机内节点,虚拟支路的电抗用发电机同步电抗xq表示,虚拟发电机内节点电压等于发电机虚拟电势
Figure G2008100988631D00021
虚拟发电机内节点电压
Figure G2008100988631D00022
和发电机端电压
Figure G2008100988631D00023
的相位角就等于发电机的功角,发电机机端功率量测转化为发电机虚拟支路量测,发电机功角量测转化为虚拟发电机内节点的相角量测,按此扩展网络结构,电网扰动过程中可以按照常规状态估计列出相应的PMU量测方程。
在短暂的电网动态变化过程中,电网负荷水平不发生大的变化,负荷用恒阻抗模型表示,得到扰动条件下的电网等效模型,分析量测方程:
对于n个节点和nG个发电机的电网的等效模型,在没有任何PMU量测条件下可以列出n个节点的有功和无功零注入伪量测方程,设其中一个节点为参考节点,则电网的等效模型需要求解n+nG-1个节点电压角度,如PMU量测提供nG-1个发电机有功出力,就可以列出nG-1个量测方程,结合n个有功量测方程,可以求得电网等效模型各个节点的电压角度;
对于无功电压量测,电网的等效模型共有n+nG个母线节点电压幅值待求,根据原电网网络n个节点无功零注入伪量测方程,只要提供nG个发电机电压量测,可以得到电网的等效模型的各节点电压幅值。
PMU量测记录电网的扰动,列出PMU量测相关的有功无功量测方程,根据最小二乘原理确定有功无功目标函数,线性化处理后,得到有功无功量测修正方程,从而得到PQ解耦的基本加权最小二乘状态估计迭代修正公式,得到母线电压幅值及相角的变量和量测增益矩阵;所列电网等效模型的伪量测方程和PMU量测方程,在整个电网扰动时段内,只要没有新的扰动发生,量测方程的维数是固定的,在扰动发生开始时刻一次性的形成量测增益矩阵,在后续电网连续断面状态计算中,使用新的PMU量测数据进行迭代计算,量测母线电压幅值及相角的变化,实现扰动状态的完整估计。
对于电网的潮流计算而言,电网等效模型的发电机有功功率和虚拟节点电压是必须的,但是对于电网状态估计而言,其它类型的量测对象也可以,例如支路的功率、高压母线电压量测都可满足电网状态估计的需要。本发明可以充分使用PMU提供的发电机量测、电网母线电压幅值及相角量测和支路功率量测,对电力系统动态过程进行状态估计。
对于PMU量测可观测的节点,直接使用PMU量测进行状态估计,而不需要使用负荷模型,可适应各种PMU分布,发电机和负荷可根据实际电网情况选择合适的模型。
本发明以静态状态估计提供的扰动前电网状态为基础,在电网正常运行方式下使用静态状态估计方法,在扰动发生后启动动态过程状态估计,利用PMU量测对电网扰动过程进行估计,可获得电网完整的扰动变化过程,即使电网在扰动条件下也能获得可靠的电网状态,实现电网动态监视,由于以扰动前的电网状态为基础,对PMU布点要求不高,只对发电厂有PMU布点要求,在少量的PMU量测条件下对电网状态进行计算,有效解决了电网扰动条件下的状态监视问题,在同一扰动下,对连续的PMU量测断面可直接把PMU量测数据代入迭代计算,可提供电网扰动过程中的连续断面供稳定控制和分析使用,具有速度快的优点,可满足动态过程实时监视的要求。
附图说明
图1为单个发电机接线示意图。
图2为采用本发明的单个发电机等效模型。
图3为一个五节点系统电网示意图。
图4为采用本发明方法的图3的五节点系统电网等效模型。
图5测试网络基态潮流图。
具体实施方式
本发明根据扰动前电网状态对电网进行等效处理,扰动过程中只依靠PMU量测,同时跟踪PMU量测变化,提供电网变化过程的连续断面,实现动态过程的状态估计。在电网正常运行方式下使用静态状态估计方法,在扰动发生后启动动态过程状态估计,以电网扰动前的静态状态估计结果为基础断面,引入负荷模型和发电机模型,对电网进行等效处理,在电网扰动过程中,使用同步相量测量单元PMU量测获得发电机数据,结合原电网各节点的有功和无功零注入伪量测方程,对电网各节点状态进行估计,在仅有发电厂PMU量测的条件下可获得电网的动态过程状态。
PMU可以采集发电机的功率、电流、频率及功角δ,功角δ在电力系统稳定问题研究中占有特别重要的位置,它除了表示发电机内电势和系统电压之间的相位角,还表明了各发电机转子之间的相对运动空间位置。功角δ随时间的变化描述了各发电机转子间的相对运动,转子间的相对运动是判断各发电机是否同步运行的依据。
利用发电机同步电抗和机端电压、电流相量可以计算发电机虚拟电势和功角:
E · Q = U · + jx q i - - - ( 1 )
式中:
Figure G2008100988631D00042
为发电机虚拟电势,
Figure G2008100988631D00043
为发电机端口电压,
Figure G2008100988631D00044
为发电机端口电流,xq为发电机同步电抗。
如图1的发变组支路,发电机机端有功率和电压量测,在扰动过程中,由本发明方法发电机可以等效为图2的等效模型,增加一个虚拟支路和虚拟发电机内节点,该支路阻抗由发电机同步电抗xq表示,虚拟发电机内节点电压就等于发电机虚拟电势虚拟发电机内节点电压
Figure G2008100988631D00046
和发电机端电压
Figure G2008100988631D00047
的相位角就等于发电机的功角,发电机机端功率量测转化为发电机虚拟支路量测,发电机功角可以转化为虚拟发电机内节点的相角量测,按此扩展网络结构,电网扰动过程中可以按照常规状态估计列出相应的PMU量测方程。
由静态状态估计可得到非扰动状态下全网的母线电压幅值和角度,同时获得了各个节点负荷大小及发电机出力,根据负荷节点电压可以计算各个节点的负荷等效阻抗,在短暂的电网动态变化过程中,可假设电网负荷水平不发生大的变化,并且负荷以恒阻抗模型表示,这样就可以得到扰动条件下的电网等效模型。如图3五节点系统等效表示为如图4的七节点系统,其中发电机引入了虚拟支路模型,负荷被等效为阻抗模型。
在图4等效模型中,可采用常规状态估计方法,原来五个节点都有有功和无功零注入伪量测。等效模型在没有任何PMU量测条件下可以列出五个有功量测方程,设其中一个节点为参考节点,则需要求解六个节点电压角度,显然该网络不可观测,但是如果已知发电机的有功、无功出力和电压,就可以列出相关量测方程,例如:节点1的发电机有有功、无功、电压PMU量测,可以列出如下量测方程:
PMG1=U1U6B16sin(θ16)                                (2)
QMG1=U1B16[U1-U6cos(θ16)]                           (3)
UMG1=U1                                                 (4)
式中:PMG1、QMG1、UMG1分别为发电机有功、无功、电压,由PMU量测,B16为虚拟支路导纳,U1、U6为节点1、6待求电压幅值,θ1、θ6为节点1、6待求电压相角。这样,可以利用原五节点电网网络的五个有功量测方程和(2)式求解各个节点的电压角度。对于无功电压量测方程,共有七个母线节点电压幅值待求,除了可以列出的原电网网络五个节点无功零注入伪量测方程,还需要两个发电机端口电压量测方程,也可以由PMU量测得到,进而求得等效模型的各节点电压幅值。
通过以上分析,图4电网等效模型只要通过PMU量测得到一台发电机的有功出力和各个发电机电压,就可以求得各个节点电压幅值和角度,这个结论和电网潮流计算要求一致,由于等效模型的两个虚拟发电机节点电压可由端口电压计算出来,相当于一个PV节点,一个平衡节点,也就是说,对于nG个发电机节点的电网,至少需要知道nG-1个发电机的有功功率和各个发电机端口电压,电网才可观测。
对于电网的潮流计算而言,电网等效模型的发电机有功功率和虚拟节点电压是必须的,但是对于电网状态估计而言,其它类型的量测对象也可以,例如支路的功率、高压母线电压量测都可满足电网状态估计的需要。本发明可以充分使用PMU提供的发电机量测、电网母线电压幅值及相角量测、支路功率量测,对电力系统动态过程进行状态估计。
仍以图4的等效模型为例,设节点2和节点5厂站安装了PMU装置,可以采集支路的带时标有功无功潮流:发电机有功功率PMG2、无功功率QMG2和发电机功角δMG2;UM2、UM5、θM2、θM5分别表示节点2和节点5的母线电压幅值及相角,母线电压相角以节点5为参考节点,设节点1到节点4的支路故障切除后,电网存在动态变化过程,该过程由装设在节点2、5的PMU纪录,这样可以列出PMU量测相关的有功无功量测方程如方程组(5)、(6):
θ M 2 = f ( θ 2 ) = θ 2 θ M 5 = 0 = f ( θ 5 ) = θ 5 δ MG 2 = θ 7 - θ 2 P M 23 = f ( θ 2 , θ 3 ) P M 21 = f ( θ 2 , θ 1 ) P MG 2 = f ( θ 2 , θ 7 ) P M 54 = f ( θ 5 , θ 4 ) P M 51 = f ( θ 5 , θ 1 ) - - - ( 5 )
U M 2 = g ( U 2 ) = U 2 U M 5 = g ( U 5 ) = U 5 Q M 23 = g ( U 2 , U 3 ) Q M 21 = g ( U 2 , U 1 ) Q MG 2 = g ( U 2 , U 7 ) Q M 54 = g ( U 5 , U 4 ) Q M 51 = g ( U 5 , U 1 ) - - - ( 6 )
式中:θi为待求母线电压相角,Ui为待求母线电压幅值,f(θi)为有功量测方程,g(Ui)为无功量测方程,i=1~7,表示各节点。
根据最小二乘原理可以确定有功无功目标函数为:
min J p ( θ ) = Σ i = 1 m P [ z pi - f ( θ ) σ i ] = [ z p - f ( θ ) ] T R p - 1 [ z p - f ( θ ) ] - - - ( 7 )
min J q ( U ) = Σ i = 1 m q [ z qi - g ( U ) σ i ] = [ z q - g ( U ) ] T R q - 1 [ z q - g ( U ) ] - - - ( 8 )
式中:mp为等效模型原电网的固有有功零注入伪量测和PMU相角有功量测个数,mq为固有无功零注入伪量测和PMU电压无功量测个数。对于量测矢量zp、zq,状态估计状态矢量θ、U是使目标函数Jp(θ)和Jq(U)为最小的值。对上式线性化处理后,有功无功量测修正方程分别为:
Δzp=HpΔθ                                 (9)
Δzq=HqΔU                                  (10)
式中:H矩阵为有功量测方程和无功量测方程的mp×(n+nG)及mq×(n+nG)维雅可比矩阵,nG为电网系统中发电机数量。从而得到PQ解耦的基本加权最小二乘状态估计迭代修正公式:
Δθ = [ H p T R p - 1 H p ] - 1 H p T R p - 1 Δ z p - - - ( 11 )
ΔU = [ H q T R q - 1 H q ] - 1 H q T R q - 1 Δ z q - - - ( 12 )
式中:HpTRp -1Hp和Hq TRq -1Hq都是(n+nG)×(n+nG)维量测增益矩阵即信息矩阵。
所列等效网络固有伪量测方程和PMU量测方程,在整个电网扰动时段内,只要没有新的扰动发生,量测方程维数是固定的,只要在扰动发生开始时刻一次性的形成信息矩阵,在后续连续断面计算中,只要使用新的PMU量测数据进行迭代计算,可以满足PMU量测数据实时更新要求。
为了验证本发明的可行性,对图5的七节点系统进行仿真计算,图5显示为其基态潮流,具体设备参数如下面的BPA数据所示:
/NETWORK_DATA\
BS   发电机1  16.501    999. 999.     1.01
BE   发电机2  18.001    163. 999      1.01
B    母线1    230.01
B    母线2    230.01
B    母线3    230.01    125. 70.0     20.
B    母线4    230.01    90.  40.0     10.
B    母线5    230.01    100. 55.0     20.
.L ---------------transmission lines-------------------------
L    母线1    230.母线2    230.    .0100.0850    .0440
L    母线1    230.母线3    230.    .0170.0920    .0395
L    母线1    230.母线4    230.    .0320.1610    .0765
L    母线1    230.母线5    230.    .0390.1700    .0895
L    母线2    230.母线3    230.    .0085.0720    .03725
L    母线3    230.母线4    230.    .0119.1008    .05225
L    母线4    230.母线5    230.    .0119.1008    .05225
.T-----transformers---------
T    发电机1  16.5母线1    230.         .0567         16.5242.
T    发电机2  18.0母线2    230.         .0625         18.0242.
(END)
使用BPA仿真软件对线路母线1-母线3三相短路故障进行仿真,假设第10周波故障,第15周波故障切除,获得的部分仿真结果如表1中的仿真值。
以静态潮流结果对电网进行等效处理,获得负荷阻抗模型和发电机虚拟支路模型,假设只有两台发电机装设有功、无功和电压PMU量测,应用本发明的动态过程估计方法,一次性形成雅可比矩阵,分别把35周波、55周波、115周波、175周波和235周波的发电机仿真功率和机端电压作为PMU量测带入迭代计算,获得了表1中的估计值。通过和仿真结果支路潮流比较发现,估计结果和仿真结果基本一致,表明本发明算法可行性。
通过故障仿真结果测试表明,本发明的动态过程估计方法仅利用电厂的PMU量测就能获得电网完整的状态,可有效解决当前PMU量测布点较少的问题。当某些变电站安装PMU量测时,就可以直接使用PMU量测进行估计,而不需要采用负荷模型,保证各种PMU量测条件下的可观测性。
表1仿真结果和动态过程估计值
Figure G2008100988631D00081

Claims (3)

1.一种电力系统动态过程状态估计方法,其特征是以电网扰动前的静态状态估计结果为基础断面,引入负荷模型和发电机模型,对电网进行等效处理,在电网扰动过程中,使用同步相量测量单元PMU量测获得发电机数据,结合原电网各节点的有功和无功零注入伪量测方程,对电网各节点状态进行估计,在仅有发电厂PMU量测的条件下获得电网的动态过程状态:
对电网进行等效处理时,每台发电机增加一个虚拟支路和虚拟发电机内节点,虚拟支路的电抗用发电机同步电抗xq表示,虚拟发电机内节点电压等于发电机虚拟电势
Figure F2008100988631C00011
虚拟发电机内节点电压
Figure F2008100988631C00012
和发电机端电压
Figure F2008100988631C00013
的相位角就等于发电机的功角,发电机机端功率量测转化为发电机虚拟支路量测,发电机功角量测转化为虚拟发电机内节点的相角量测,按此扩展网络结构,电网扰动过程中可以按照常规状态估计列出发电机PMU量测方程;
在短暂的电网动态变化过程中,电网负荷水平不发生大的变化,负荷用恒阻抗模型表示,得到扰动条件下的电网等效模型,分析量测方程:
对于n个节点和nG个发电机的电网等效模型,在没有任何PMU量测条件下可以列出n个节点的有功和无功零注入伪量测方程,设其中一个节点为参考节点,则电网的等效模型需要求解n+nG-1个节点电压角度,如果PMU量测提供nG-1个发电机有功出力,就可以列出nG-1个量测方程,结合n个有功量测方程,可以求得电网等效模型各个节点的电压角度;
对于无功电压量测,电网的等效模型共有n+nG个母线节点电压幅值待求,根据原电网网络n个节点无功零注入伪量测方程,只要提供nG个发电机电压量测,可以得到电网的等效模型的各节点电压幅值;
PMU量测记录电网的扰动,列出PMU量测相关的有功无功量测方程,根据最小二乘原理确定有功无功目标函数,线性化处理后,得到有功无功量测修正方程,从而得到PQ解耦的基本加权最小二乘状态估计迭代修正公式,得到母线电压幅值及相角的变量和量测增益矩阵;所列电网等效模型的伪量测方程和PMU量测方程,在整个电网扰动时段内,只要没有新的扰动发生,量测方程的维数是固定的,在扰动发生开始时刻一次性的形成量测增益矩阵,在后续电网连续断面状态计算中,使用新的PMU量测数据进行迭代计算,跟踪母线电压幅值及相角的变化,实现扰动状态的完整估计。
2.根据权利要求1所述的电力系统动态过程状态估计方法,其特征是通过充分利用PMU获得发电机量测、母线电压幅值及相角量测和支路功率量测,对电力系统动态过程进行状态估计。
3.根据权利要求1所述的电力系统动态过程状态估计方法,其特征是对于PMU量测可观测的节点,直接使用PMU量测进行状态估计,而不需要使用负荷模型,可适应各种PMU分布,发电机和负荷可根据实际电网情况选择合适的模型。
CN2008100988631A 2008-05-16 2008-05-16 一种电力系统动态过程状态估计方法 Active CN101291061B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008100988631A CN101291061B (zh) 2008-05-16 2008-05-16 一种电力系统动态过程状态估计方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008100988631A CN101291061B (zh) 2008-05-16 2008-05-16 一种电力系统动态过程状态估计方法

Publications (2)

Publication Number Publication Date
CN101291061A CN101291061A (zh) 2008-10-22
CN101291061B true CN101291061B (zh) 2010-04-21

Family

ID=40035197

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008100988631A Active CN101291061B (zh) 2008-05-16 2008-05-16 一种电力系统动态过程状态估计方法

Country Status (1)

Country Link
CN (1) CN101291061B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102680762A (zh) * 2011-10-11 2012-09-19 国电联合动力技术有限公司 一种无迹卡尔曼滤波的风电场机端电压测量方法及其应用
US10103666B1 (en) 2015-11-30 2018-10-16 University Of South Florida Synchronous generator modeling and frequency control using unscented Kalman filter

Families Citing this family (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101577426B (zh) * 2009-03-19 2011-11-16 上海交通大学 适用于广域测量系统的电力系统状态估计器
CN101634670B (zh) * 2009-04-21 2014-09-17 上海申瑞继保电气有限公司 用于输电网状态估计的零支路阻抗自适应计算方法
CN101661069B (zh) * 2009-09-25 2011-07-20 北京四方继保自动化股份有限公司 不依赖状态矩阵的弱可观非pmu测点动态过程实时估计方法
CN102185308B (zh) * 2010-03-19 2013-04-03 清华大学 一种考虑零注入量测等式约束的电力系统状态估计方法
CN101917002B (zh) * 2010-07-16 2012-11-14 清华大学 基于特高压电网联络线运行状态的电压控制方法
WO2012048746A1 (de) * 2010-10-14 2012-04-19 Siemens Aktiengesellschaft Verfahren und einrichtung zum erzeugen eines zustandssignals
CN102185316B (zh) * 2011-05-24 2013-04-10 南京南瑞集团公司 基于保守原则的电力系统在线稳定分析断面数据整合方法
CN102255319B (zh) * 2011-07-15 2013-07-24 广东电网公司电力科学研究院 基于断面抽取的电网电压无功实时控制评估方法及系统
CN102255322B (zh) * 2011-07-15 2013-01-30 广东电网公司电力科学研究院 地区电网电压无功互动迭代控制方法
CN102427229B (zh) * 2011-10-18 2013-06-19 清华大学 基于修正牛顿法的带零注入约束的电力系统状态估计方法
CN102508061B (zh) * 2011-10-22 2014-02-12 东北电力大学 一种基于广域相量测量系统的功率缺额估计方法
CN102879699B (zh) * 2012-08-20 2015-07-08 中国电力科学研究院 一种变电站内变压器分接头位置的估计方法
CN102902894B (zh) * 2012-10-29 2015-04-22 东北电网有限公司 基于差异比较的调度中心pmu数据质量评估与角度误差估计方法
CN103020738A (zh) * 2012-12-17 2013-04-03 河海大学 一种基于wdse的电力系统受扰轨迹预测方法
CN103227450B (zh) * 2013-04-26 2015-05-20 国家电网公司 在线故障恢复方法及系统
CN103235187A (zh) * 2013-04-27 2013-08-07 哈尔滨电机厂有限责任公司 通过电阻法确定永磁发电机同步电抗的测试方法
CN104995811B (zh) * 2014-10-21 2017-07-28 深圳大学 交流电力网的最小相位线性有功潮流的获取方法
EP3375065A4 (en) * 2015-11-09 2019-09-04 ABB Schweiz AG PROTECTION STRATEGY FOR AN ELECTRICAL SYSTEM WITH SLIP RATE CALCULATION
CN105470980B (zh) * 2015-12-17 2021-03-02 中国电力科学研究院 一直基于电网直流换相失败下的交直流协调控制方法
CN105375484A (zh) * 2015-12-22 2016-03-02 华北电力大学 一种基于pmu的电力系统分布式动态状态估计方法
CN105843736B (zh) * 2016-03-18 2021-04-06 中国电力科学研究院 一种电力系统状态估计软件的测试方法
CN107563550B (zh) * 2017-08-23 2021-01-01 武汉大学 一种基于pmu的配电网实时分布式状态估计及pmu的优化配置方法
CN107843810B (zh) * 2017-11-01 2019-12-17 东南大学 一种基于状态估计的有源配电网故障区段在线定位方法
CN108110765B (zh) * 2018-01-20 2021-08-31 武汉西元智能科技有限公司 一种新能源与电网配合供电方法及其校验装置
CN108270226B (zh) * 2018-01-20 2021-08-31 耿秋钰 一种快速恢复供电的方法
CN110378041B (zh) * 2019-07-23 2022-05-27 广东电网有限责任公司 一种电网状态估计方法、系统、设备及计算机存储介质
CN112327047B (zh) * 2019-12-05 2022-11-15 国网辽宁省电力有限公司锦州供电公司 在变电站内实现功率同断面数据测量的方法
CN112066594A (zh) * 2020-08-31 2020-12-11 河海大学 一种基于μPMU装置的大规模电热泵有序用电控制方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7096175B2 (en) * 2001-05-21 2006-08-22 Abb Research Ltd Stability prediction for an electric power network
CN101075741A (zh) * 2007-05-15 2007-11-21 浙江大学 考虑负荷电压特性的非线性动态状态估计算法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7096175B2 (en) * 2001-05-21 2006-08-22 Abb Research Ltd Stability prediction for an electric power network
CN101075741A (zh) * 2007-05-15 2007-11-21 浙江大学 考虑负荷电压特性的非线性动态状态估计算法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李大虎等.基于SCADA/PMU混合量测的广域动态实时状态估计方法.电网技术31 6.2007,31(6),72-78.
李大虎等.基于SCADA/PMU混合量测的广域动态实时状态估计方法.电网技术31 6.2007,31(6),72-78. *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102680762A (zh) * 2011-10-11 2012-09-19 国电联合动力技术有限公司 一种无迹卡尔曼滤波的风电场机端电压测量方法及其应用
CN102680762B (zh) * 2011-10-11 2014-12-10 国电联合动力技术有限公司 一种无迹卡尔曼滤波的风电场机端电压测量方法及其应用
US10103666B1 (en) 2015-11-30 2018-10-16 University Of South Florida Synchronous generator modeling and frequency control using unscented Kalman filter

Also Published As

Publication number Publication date
CN101291061A (zh) 2008-10-22

Similar Documents

Publication Publication Date Title
CN101291061B (zh) 一种电力系统动态过程状态估计方法
CN101750562B (zh) 基于潮流方程灵敏度分析的非pmu测点动态过程估计方法
CN101900777B (zh) 电力系统监测方法及其装置
Chakrabortty et al. A measurement-based framework for dynamic equivalencing of large power systems using wide-area phasor measurements
Sexauer et al. Phasor measurement units for the distribution grid: Necessity and benefits
CN101924364B (zh) 变电站-调度中心两级分布式电网的非线性状态估计方法
US10733901B2 (en) Dynamic dispatcher training simulator
CN101305283B (zh) 用于验证状态估计计算的准确性的方法和设备
CN102298671A (zh) 一种实现电网故障重演的仿真方法
Cordova et al. Fault location identification in smart distribution networks with distributed generation
CN103840452A (zh) 一种引入pmu量测信息的大电网状态估计方法
Artale et al. Smart interface devices for distributed generation in smart grids: The case of islanding
Schweitzer et al. Real-time power system control using synchrophasors
CN100554976C (zh) 基于同步相量测量的区域电压稳定性监视方法
Schweitzer et al. Real-world synchrophasor solutions
CN109581103A (zh) 基于广域监测的电网谐波源定位方法
CN108802570A (zh) 一种用于交直流混联微电网的故障检测系统及检测方法
CN102902894B (zh) 基于差异比较的调度中心pmu数据质量评估与角度误差估计方法
La Scala et al. Development of applications in WAMS and WACS: an international cooperation experience
CN102946099B (zh) 一种多机互联电力系统的暂态功角稳定性实时判别的方法
Saitoh GPS synchronized measurement applications in Japan
Amin et al. Wide area measurement system for smart grid applications involving hybrid energy sources
Min Phasor measurement applications in China
Ponci et al. Instrumentation and measurement testing in the real-time lab for automation of complex power systems
Liu et al. Fault detection and location of microgrid based on distributed decision

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant