CN101289858A - Pile sinking process in water for PHC pipe pile - Google Patents

Pile sinking process in water for PHC pipe pile Download PDF

Info

Publication number
CN101289858A
CN101289858A CNA2008100357916A CN200810035791A CN101289858A CN 101289858 A CN101289858 A CN 101289858A CN A2008100357916 A CNA2008100357916 A CN A2008100357916A CN 200810035791 A CN200810035791 A CN 200810035791A CN 101289858 A CN101289858 A CN 101289858A
Authority
CN
China
Prior art keywords
pile
sinking
phc
stake
gps
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2008100357916A
Other languages
Chinese (zh)
Inventor
张华�
黎亚舟
周慧杰
刘海青
项勇
陆宁海
钱雨麟
施冲
章剑果
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Hand In Third Board Second Engineering Co Ltd
China Construction Third Engineering Bureau Co Ltd
Original Assignee
CHINA COMMUNICATIONS THIRD NAVIGATIONAL BUREAU 2ND ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA COMMUNICATIONS THIRD NAVIGATIONAL BUREAU 2ND ENGINEERING Co Ltd filed Critical CHINA COMMUNICATIONS THIRD NAVIGATIONAL BUREAU 2ND ENGINEERING Co Ltd
Priority to CNA2008100357916A priority Critical patent/CN101289858A/en
Publication of CN101289858A publication Critical patent/CN101289858A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention relates to a pile-sinking method, in particular to a pile-sinking method in water area for a PHC tubular pile. The pile-sinking method for the PHC tubular pile is characterized in that the method comprises the following steps of: pile-driving preparation, wherein, the structure, the size, the weight and the underground length of the PHC tubular pile as well as geological conditions and meteorologic conditions at the place for pile sinking are analyzed, and pile-sinking equipment is selected; pile hoisting, wherein, the length of the PHC tubular pile is L, hoisting points of the pile hoisting are designed at the positions which are respectively 0.105L, 0.328L, 0.672L, and 0.895L from the bottom end; pile insertion; pile sinking, wherein, the location of the pile sinking takes the control of a theodolite as a major mode and GPS debugging as an auxiliary mode at the beginning stage, and takes GPS position as a major mode after the normal pile sinking; adopting high strength steel as driving, and adopting corrugated paper to replace the pile; and pile stabilization, wherein, the driven pile is provided with a framing scaffold. The method can better solve the phenomena such as pile top breakage, pile body cracks, overlarge pile top deviation, pile breakage and so on, caused by the prior pile-sinking method.

Description

A kind of PHC pile tube pile-sinking method waterborne
Technical field
The present invention relates to a kind of pile-sinking method, particularly a kind of PHC pile tube pile-sinking method.
Background technology
Phenomenons such as crack, stake top off normal are excessive, broken pile appear in present PHC pile tube some qualitative problems of ubiquity in pile driving process as pile top break, pile body.
Summary of the invention
The object of the present invention is to provide a kind of PHC pile tube pile-sinking method waterborne, solve the problems referred to above that exist in the present pile driving process.
The present invention solves the problems of the technologies described above by the following technical solutions:
A kind of PHC pile tube pile-sinking method waterborne is characterized in that, may further comprise the steps:
Piling is prepared, and analyzes structure, size, weight, the length of burying of PHC pile tube, and the geological conditions at pile sinking place, meteorological condition are selected pile sinking equipment;
Hang stake, the PHC pile tube is long to be L, and the suspension centre design of hanging stake is at distance bottom 0.105L, 0.328L, 0.672L, 0.895L place;
Pitching pile;
Pile sinking, pile sinking are positioned at the incipient stage and are controlled to be main, GPS debugging with transit, orientate the master as with GPS behind the normal pile sinking; Adopt high-strength steel to do to adopt corrugated paper for pile for beating;
Steady stake is to the good waling of having accomplished fluently of pile holder.
Further, wave height less than 0.8 meter, do not influence under the ambient conditions that the steady and anchor hawser of boats and ships pools tightened up and got out of the way the anxious anxious ebb current that rises and carry out pile sinking.
Select different dollies for use, the situation sinking quality of pile that all the other conditions are identical is as follows:
The pile top break situation Pile top break Crack, stake top Angle, length 〉=10cm are split in the stake top Stake top spoilage
Flitch dolly (amounting to 80 of pile sinking) 2 1 8 13.8%
Strawboard dolly (amounting to 80 of pile sinking) 0 2 6 10%
Corrugated paper dolly (totally 280) 0 0 5 5.4%
Adopt the stake top of corrugated paper as dolly, pile quality is significantly better than the pile sinking quality that adopts conventional dolly.Because, using pile monkey of the same race and when beating, the size of dolly stiffness, decision when hammering, the length of hammer and stake time of contact and a hammering size of passing to.Stiffness hour, time of contact is long, and the wavelength of stress wave is big, and the hammering stress of passing to stake is little.Corrugated board is owing to exist the corrugation dead slot in the middle of it, and its stiffness obviously stiffness than traditional materials such as flitch, strawboards is little, like this, just makes when the hammering stake is pushed up, and it is less relatively that the stake top is subjected to hammering stress, makes the stake top can obtain more effectively protecting.
The specific embodiment
For technological means, creation characteristic that the present invention is realized, reach purpose and effect is easy to understand, below in conjunction with the specific embodiment, further set forth the present invention.
A kind of PHC pile tube pile-sinking method waterborne may further comprise the steps:
Piling is prepared.Analyze the geological conditions at pile sinking place, select bearing stratum, PHC pile tube how long is adopted in decision.Analyze structure, size, weight, the length of burying of PHC pile tube.Check the quality of PHC pile tube, mainly check the welding quality of crack, joint,, then will not adopt as defective in quality.Aspect meteorological condition, should be when suitable wave height (with do not influence the steady and anchor hawser of boats and ships pool tighten up be as the criterion) pile sinking, the anxious anxious ebb current that rises is got out of the way in general requirement, and attention wind-force size.The selection of pile sinking equipment, the selection of its king-pile ship should be taken all factors into consideration geological hydrology condition, the long stake of stake type, heavy, the stake ship draft of stake; The selection of plektron should be according to geological conditions and construction experience in the past, in conjunction with the requirement to the pile sinking technical indicator.
Hang stake.The PHC pile tube is long to be L, and the suspension centre design of hanging stake is at distance bottom 0.105L, 0.328L, 0.672L, 0.895L place;
Pitching pile; Aspect the layout of anchor position, correctly arrange anchor hawser position, anchorage according to the operation layout plan that casts anchor of harbour, guarantee that anchor hawser length, the anchor hawser angle under each anchor hawser stress meets the requirements.
Pile sinking, pile sinking are positioned at the incipient stage and are controlled to be main, GPS debugging with transit, orientate the master as with GPS behind the normal pile sinking.Strengthen cooperatively interacting of land personnel and ship's staff, the instant contact guaranteed the precision and the speed of pile sinking.According to Instrument measuring precision and sight line length, locate following departure and carry out plane control, to guarantee the pile sinking precision by permission.Adopt high-strength steel to do to adopt corrugated paper for pile for beating.Simultaneously, when hammer piling, pile monkey, for beating and stake should remain on the same axis replaces to beat to keep voucher, avoids producing eccentric hammering.
Pile sinking is established the caution flag in the pile sinking outermost after finishing immediately, establishes anti-collision alarm red light at night.Carry out steady stake behind the pile sinking, to the good waling of having accomplished fluently of pile holder.
More than show and described basic principle of the present invention, principal character and advantage of the present invention.The technician of the industry should understand; the present invention is not restricted to the described embodiments; that describes in the foregoing description and the manual just illustrates principle of the present invention; the present invention also has various changes and modifications without departing from the spirit and scope of the present invention, and these changes and improvements all fall in the claimed scope of the invention.The claimed scope of the present invention is defined by appending claims and equivalent thereof.

Claims (2)

1, a kind of PHC pile tube pile-sinking method waterborne is characterized in that, may further comprise the steps:
Piling is prepared, and analyzes structure, size, weight, the length of burying of PHC pile tube, and the geological conditions at pile sinking place, meteorological condition are selected pile sinking equipment;
Hang stake, the PHC pile tube is long to be L, and the suspension centre design of hanging stake is at distance bottom 0.105L, 0.328L, 0.672L, 0.895L place;
Pitching pile;
Pile sinking, pile sinking are positioned at the incipient stage and are controlled to be main, GPS debugging with transit, orientate the master as with GPS behind the normal pile sinking; Adopt high-strength steel to do to adopt corrugated paper for pile for beating;
Steady stake is to the good waling of having accomplished fluently of pile holder.
2, according to the power described a kind of PHC pile tube of claim 1 pile-sinking method waterborne, it is characterized in that: wave height less than 0.8 meter, do not influence under the ambient conditions that the steady and anchor hawser of boats and ships pool tightened up and got out of the way the anxious anxious ebb current that rises and carry out pile sinking.
CNA2008100357916A 2008-04-09 2008-04-09 Pile sinking process in water for PHC pipe pile Pending CN101289858A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2008100357916A CN101289858A (en) 2008-04-09 2008-04-09 Pile sinking process in water for PHC pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2008100357916A CN101289858A (en) 2008-04-09 2008-04-09 Pile sinking process in water for PHC pipe pile

Publications (1)

Publication Number Publication Date
CN101289858A true CN101289858A (en) 2008-10-22

Family

ID=40034289

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2008100357916A Pending CN101289858A (en) 2008-04-09 2008-04-09 Pile sinking process in water for PHC pipe pile

Country Status (1)

Country Link
CN (1) CN101289858A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102134854A (en) * 2011-02-16 2011-07-27 中交二航局第四工程有限公司 Slipway underwater pile foundation and construction method thereof
CN102409680A (en) * 2011-08-12 2012-04-11 中交四航局第二工程有限公司 Underwater pile delivery technology for slipway combined pile
CN103132524A (en) * 2011-11-24 2013-06-05 五冶集团上海有限公司 Pile head crash pad of hammering pile

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102134854A (en) * 2011-02-16 2011-07-27 中交二航局第四工程有限公司 Slipway underwater pile foundation and construction method thereof
CN102134854B (en) * 2011-02-16 2012-08-22 中交二航局第四工程有限公司 Slipway underwater pile foundation and construction method thereof
CN102409680A (en) * 2011-08-12 2012-04-11 中交四航局第二工程有限公司 Underwater pile delivery technology for slipway combined pile
CN102409680B (en) * 2011-08-12 2014-04-02 中交四航局第二工程有限公司 Underwater pile delivery technology for slipway combined pile
CN103132524A (en) * 2011-11-24 2013-06-05 五冶集团上海有限公司 Pile head crash pad of hammering pile

Similar Documents

Publication Publication Date Title
CN102277878B (en) Floating foundation and construction method thereof
CN103786837A (en) Column-stabilized offshore platform with water-entrapment plates and asymmetric mooring system for support of offshore wind turbines
CN103233452B (en) The pre-splicing 1/4 cylinder transportation resources of a kind of lattice steel sheet pile large cylinder nominative sheet pile
CN102358413A (en) Installation method of full-revolving rudder propeller device with special angle
US20110214596A1 (en) Vertically installed spar and construction methods
CN105000137B (en) Covering of the fan revolution single point mooring transfusion system
CN102767176A (en) Hoisting positioning construction method of pile foundation steel reinforcement cage
CN103434989B (en) Oceanographic survey shaft-type movable lifting platform based on gear drive and method
CN102328732A (en) Offshore pile driving, pile pressing and installing united engineering ship
CN102409613B (en) Construction method for installing steel beam of plank road built along mountain and near river
CN105926628A (en) Device for underwater pile foundation construction platform convertible in floating and fixing
CN106628018A (en) Self-propelled large component transportation and installation integrated boat and construction process thereof
CN101666097A (en) Positioning settlement method of large steel suspension box or sinking well
CN101289858A (en) Pile sinking process in water for PHC pipe pile
CN206141776U (en) Large -scale component transportation of self -navigation formula installs integrative ship
CN104711930A (en) Installation and construction method for large-diameter pipe bridge on ultra-wide river way
CN102312436A (en) Steel pipe pile sinking construction technology
CN1472400A (en) Method for positioning whole floatation transported steel caisson by pre-exerting tension at anchor pier and being drilling platform
CN207985142U (en) A kind of water floated platform of quick-assembling
CN207878498U (en) A kind of tower-crane foundation structure of bridge deepwater foundation pit
CN110077534A (en) A kind of outer defeated system suitable for deep water oil storage semi-submersible type production platform
CN205804363U (en) A kind of floating, fixing convertible pile foundation in water construction platform device
CN212580085U (en) Self-stabilizing deepwater navigation mark
CN213768915U (en) Floating transportation system for dragging double-wall steel sleeve box in water
SA520420553B1 (en) Removing top decks of offshore platforms

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20090320

Address after: Postcode of No. 132 Pu circuit, Shanghai, Pudong New Area: 200122

Applicant after: China hand in the Third Board Second Engineering Co., Ltd.

Co-applicant after: China Construction Third Engineering Division Co., Ltd.

Address before: Postcode of No. 132 Pu circuit, Shanghai, Pudong New Area: 200122

Applicant before: China Communications Third Navigational Bureau 2nd Engineering Co., Ltd

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20081022