CN101255764A CNA2008100235980A CN200810023598A CN101255764A CN 101255764 A CN101255764 A CN 101255764A CN A2008100235980 A CNA2008100235980 A CN A2008100235980A CN 200810023598 A CN200810023598 A CN 200810023598A CN 101255764 A CN101255764 A CN 101255764A
Authority
CN
China
Prior art keywords
tool
steel
high altitude
paralell
operating platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2008100235980A
Other languages
Chinese (zh)
Other versions
CN100476146C (en
Inventor
朱靖
徐国华
何浩
王霞兵
周新峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Huajian Construction Co Ltd
Original Assignee
Jiangsu Huajian Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Huajian Construction Co Ltd filed Critical Jiangsu Huajian Construction Co Ltd
Priority to CNB2008100235980A priority Critical patent/CN100476146C/en
Publication of CN101255764A publication Critical patent/CN101255764A/en
Application granted granted Critical
Publication of CN100476146C publication Critical patent/CN100476146C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

A high altitude pouring steel column internal concrete operating platform frame belongs to the technique field of the auxiliary equipment of the building structure construction. The platform frame comprises a tool falsework platform and is characterized in that a clamping bolt is provided. The tool falsework platform is laid on a steel girder which is used for facilitating to pour at least two concrete in the steel column. The clamping bolt is used for permanent connection between the tool falsework platform and the steel girder. The invention can simplify the high-difficult and high-dangerous high altitude operation to the ground. The use time of the tower crane is reduced and the ground is saved. The steel tube and buckle and the like are all common material in construction. The invention has the advantages of high recovery and use percentage, convenience to the constructor, alleviation to the labor intensity, increased construction efficiency, increased security, low cost and excellent economic property.

Description

High altitude placing steel pole inner concrete operating platform frame
Technical field
The tool-type pin hand paralell of the structure of the tool type scaffold that the present invention relates to use in the building operations, particularly high altitude placing steel pole inner concrete belongs to the building structure construction technical field of auxiliary facilities.
Background technology
Circulation material commonly used in the building operations is set up into the tool-type pin hand paralell of typing in advance, is mainly built by vertical rod, horizon bar, fastener, scaffold floor, Dense mesh screen, baseboard etc. to connect and compose, and operating personnel fulfil assignment on pin hand platform.The steel work technology has obtained using widely at building field, girder steel-steel core concrete column framework is adopted in some building structure, this structural shape need be with regard to placing steel pole inner concrete after the steel column in the flowing water section, beam installation, and the last joint steel column, the beam that enter this flowing water section are then installed.The construction of girder steel in this structural shape-steel core concrete column framework is the key job of progress monitoring, be to save the duration, construction period girder steel-steel core concrete column framework and the cast-in-place plate of frame position often differ at least three to four layers.
High altitude placing steel pole inner concrete way in the past is that the operation hanging basket is hooked on the single steel column, the safety factor of this hanging basket itself is not high, be subjected to condition restriction during hook, volume is little, and hanging basket is installed once can only build and finished a steel column inner concrete, hanging basket need take tower crane when installing, tower crane handling number of times when therefore constructing increases, but must take tower crane when transporting concrete by hopper when placing steel pole inner concrete, because tower crane is busier, usually be connected bad, inefficiency; The number of times of last lower platform of operating personnel and steel column is more, and operating efficiency is also low, and has increased personnel's labour intensity and danger.
Summary of the invention
The objective of the invention is to overcome the deficiency that tool-type pin hand paralell that existing building operations sets up exists, a kind of high altitude placing steel pole inner concrete operating platform frame is provided, improve operating platform itself safety factor, reduce time that the handling operating platform takies tower crane, reduce number of times, reduction labour intensity and danger that operating personnel go up lower platform and steel column, increase work efficiency.
The objective of the invention is to realize by improvement to existing tool-type pin hand paralell, high altitude placing steel pole inner concrete operating platform frame, comprise tool-type pin hand paralell, it is characterized in that being provided with fastening bolt, tool-type pin hand paralell is shelved on to be convenient to build on the girder steel of at least two steel column inner concretes, fixedlys connected with fastening bolt between tool-type pin hand paralell and the girder steel.
Described tool-type pin hand paralell is provided with the three groups of horizon bars in upper, middle and lower, and three groups of horizon bars and vertical rod connect and compose framework by fastener, and middle group of horizon bar is provided with the platform that scaffold floor, baseboard constitute, and the above framework periphery of platform is provided with Dense mesh screen.Fastening bolt is made of screwed pipe, screw rod, nut, and screw rod is set in the screwed pipe, and the upper end of screw rod connects wind, and nut is arranged on the upper end of screwed pipe, and the lower end of screw rod is provided with 90 degree bending hooks, and the wind direction is identical with bending hook direction.Described horizon bar is horizontal vertical pole and the little cross bar of level.
Concrete advantage of the present invention has:
1, this paralell is assembled at the scene, simple structure, simple and direct, safe and reliable from heavy and light, power transmission, and composition material horizon bar, vertical rod are adopted
Figure A20081002359800041
48 steel pipes and fastener, scaffold floor, Dense mesh screen, baseboard etc. all are common used materials in the building operations, recyclable utilization rate height.
2, installation and fixed speed are quick and easy, and with pillar crane, wire rope, directly handling fixes with fastening bolt and to get final product to the girder steel of the mounted adjacent two Pin steel structure frames of desired area with mounted paralell.
3, once mounting can be built the concrete of finishing at least two steel columns, has reduced the service time that takies tower crane.Stand in the operating personnel on the paralell, safety belt can be lain on the upper level bar, the above framework periphery of platform is provided with Dense mesh screen, constitute good safety barrier, operating personnel are arbitrarily walking on the platform that the full shop of paralell scaffold floor constitutes, realize operate groundization, increased the convenience of constructor's safety and operation greatly, improved efficiency of construction.
4, make full use of the bearing capacity of building self, economical with materials saves space greatly.
Use the present invention, work high above the ground highly difficult, high risk can be simplified to landing, reduce the service time that takies tower crane, the convenient construction personnel reduce labor intensity, and improve efficiency of construction, increase safety, and with low cost, have excellent economy.
Description of drawings
Fig. 1 is a structural representation of the present invention;
Fig. 2 is a plane structure schematic diagram of the present invention;
Fig. 3 is a fastening bolt structural representation of the present invention;
Fig. 4 is a nut structure schematic diagram of the present invention;
Among the figure: 1 horizontal vertical pole, the little cross bar of 2 levels, 3 vertical rods, 4 fastening bolts, 5 scaffold floors, 6 baseboards, 7 Dense mesh screens, 8 girder steels, 9 bridgings, 10 screwed pipes, 11 screw rods, 12 nuts, 13 major threads, 14 minor threads.
The specific embodiment
Build tool-type pin hand paralell with horizontal vertical pole 1, the little cross bar 2 of level, vertical rod 3, bridging 9 and fastener.Horizontal vertical pole 1, the little cross bar 2 of level, vertical rod 3, bridging 9 with
Figure A20081002359800051
48 steel pipes are base material.Tool-type pin hand paralell is shelved on the girder steel 8 (girder steels of mounted adjacent two Pin steel structure frames) of being convenient to build two steel column inner concretes at least, fixedlys connected with fastening bolt 4 between tool-type pin hand paralell and the girder steel.This operating platform frame has one group of vertical rod 3, and wherein the position of four vertical rods is in the beam inboard of shelving girder steel 8 near correspondence.First group of horizontal vertical pole 1 is set in the appropriate location of vertical rod, the horizontal vertical pole of this group is shelved on the girder steel when operating platform frame uses, play finally to transmit deadweight of this operating platform frame and service load, above near the horizontal vertical pole of this group, first group of little cross bar of level is set.Second group of horizontal vertical pole 1 is set in the appropriate location of vertical rod, second group of little cross bar 2 of level is set, on the little cross bar of level, lay scaffold floor 5 and and baseboard 6 platform of standing as operating personnel near the top of the horizontal vertical pole of this group.Horizontal vertical pole 1 of one circle and the little cross bar 2 of level are set around the topmost of vertical rod, the above vertical rod of scaffold floor partly adds Dense mesh screen 7, form the guard rail of operating platform frame like this, all adopt fastener to connect between horizontal vertical pole steel pipe and each steel pipe, and can increase bridging 9 according to instructions for use.The fastening bolt 4 of four Gent systems is set on the beam outer fix paralell of shelving girder steel near correspondence.Fastening bolt is made of screwed pipe, screw rod, nut, and the screwed pipe of fastening bolt also is based on The screwed pipe 10 that 48 steel pipes are made, screwed pipe 10 is built-in can freely regulated screw rod 11, and the upper end of screw rod is provided with wind, and nut 12 is arranged on the upper port of screwed pipe, and 90 degree bending hooks are established in the lower end of screw rod, and the wind direction is with to bend the hook direction identical.The end opening major thread 13 of nut is twisted in the screwed pipe collar extension, is used for whole fastening bolt fine setting, and the minor thread suitable for reading 14 of nut is twisted on screw rod, is used for the wind screw rod is regulated.The effect of fastening bolt is to go up firm being fixed on the girder steel of tool-type pin hand paralell with being shelved on girder steel 8 (girder steels of mounted adjacent two Pin steel structure frames).As long as it is locked with the 90 degree bending hooks and the girder steel of bolt end opening by wind on the bolt and wrench that operating personnel stand on the scaffold floor, thereby entire tool formula pin hand paralell is fixed together with girder steel securely.Paralell is all finished on operating platform in all manually-operateds fixing and that throw off on the girder steel.Entire tool formula paralell can be according to using suitable length and width of needs design and height.

Claims (4)

1, a kind of high altitude placing steel pole inner concrete operating platform frame, comprise tool-type pin hand paralell, it is characterized in that being provided with fastening bolt, tool-type pin hand paralell is shelved on to be convenient to build on the girder steel of at least two steel column inner concretes, fixedlys connected with fastening bolt between tool-type pin hand paralell and the girder steel.
2, according to claims 1 described high altitude placing steel pole inner concrete operating platform frame, it is characterized in that described tool-type pin hand paralell is provided with the three groups of horizon bars in upper, middle and lower, three groups of horizon bars and vertical rod connect and compose framework by fastener, middle group horizon bar is provided with the platform of scaffold floor, baseboard formation, and the above framework periphery of platform is provided with Dense mesh screen.
3, according to claims 1 described high altitude placing steel pole inner concrete operating platform frame, it is characterized in that described fastening bolt is made of screwed pipe, screw rod, nut, screw rod is set in the screwed pipe, the upper end of screw rod connects wind, nut is arranged on the upper end of screwed pipe, the lower end of screw rod is provided with 90 degree bending hooks, and the wind direction is identical with bending hook direction.
4,, it is characterized in that described horizon bar is horizontal vertical pole and the little cross bar of level according to claims 2 described high altitude placing steel pole inner concrete operating platform frames.
CNB2008100235980A 2008-04-11 2008-04-11 High altitude placing steel pole inner concrete operating platform frame Active CN100476146C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2008100235980A CN100476146C (en) 2008-04-11 2008-04-11 High altitude placing steel pole inner concrete operating platform frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2008100235980A CN100476146C (en) 2008-04-11 2008-04-11 High altitude placing steel pole inner concrete operating platform frame

Publications (2)

Publication Number Publication Date
CN101255764A true CN101255764A (en) 2008-09-03
CN100476146C CN100476146C (en) 2009-04-08

Family

ID=39890837

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2008100235980A Active CN100476146C (en) 2008-04-11 2008-04-11 High altitude placing steel pole inner concrete operating platform frame

Country Status (1)

Country Link
CN (1) CN100476146C (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101858139A (en) * 2010-06-22 2010-10-13 中国核工业华兴建设有限公司 Concrete casting platform
CN102720341A (en) * 2012-06-28 2012-10-10 中建一局集团第二建筑有限公司 Frame column construction operation rack and mounting method thereof
CN102912996A (en) * 2012-11-19 2013-02-06 广州机施建设集团有限公司 Steel tube concrete column high-altitude construction safety protection system
CN103255840A (en) * 2013-04-28 2013-08-21 江苏省华建建设股份有限公司 Combined built-in fitting for concrete walls and column tie bars and installation construction method thereof
CN104131689A (en) * 2014-06-20 2014-11-05 中国建筑第四工程局有限公司 Tool stacking platform capable of being lifted and lifting method
CN105507144A (en) * 2015-12-04 2016-04-20 中交二公局第三工程有限公司 Bridge external anti-collision guardrail and safety construction method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4442638A (en) * 1982-06-21 1984-04-17 Hamilton Luke C Shelf bracket
CN2385026Y (en) * 1999-05-31 2000-06-28 曾绍强 Full-assembled lower-bearing bridged guide lifting framing scaffold
CN2801959Y (en) * 2005-06-21 2006-08-02 北京中建柏利工程技术发展有限公司 Lift type multipurpose platform
CN100577965C (en) * 2006-02-22 2010-01-06 香港理工大学 Quick distachable platform

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101858139A (en) * 2010-06-22 2010-10-13 中国核工业华兴建设有限公司 Concrete casting platform
CN102720341A (en) * 2012-06-28 2012-10-10 中建一局集团第二建筑有限公司 Frame column construction operation rack and mounting method thereof
CN102720341B (en) * 2012-06-28 2015-04-22 中建一局集团第二建筑有限公司 Frame column construction operation rack and mounting method thereof
CN102912996A (en) * 2012-11-19 2013-02-06 广州机施建设集团有限公司 Steel tube concrete column high-altitude construction safety protection system
CN102912996B (en) * 2012-11-19 2015-03-18 广州机施建设集团有限公司 Steel tube concrete column high-altitude construction safety protection system
CN103255840A (en) * 2013-04-28 2013-08-21 江苏省华建建设股份有限公司 Combined built-in fitting for concrete walls and column tie bars and installation construction method thereof
CN103255840B (en) * 2013-04-28 2015-11-04 江苏省华建建设股份有限公司 Concrete wall, post tension rib assembly built-in fitting and construction method of installation thereof
CN104131689A (en) * 2014-06-20 2014-11-05 中国建筑第四工程局有限公司 Tool stacking platform capable of being lifted and lifting method
CN105507144A (en) * 2015-12-04 2016-04-20 中交二公局第三工程有限公司 Bridge external anti-collision guardrail and safety construction method thereof

Also Published As

Publication number Publication date
CN100476146C (en) 2009-04-08

Similar Documents

Publication Publication Date Title
CN100476146C (en) High altitude placing steel pole inner concrete operating platform frame
CN101775907A (en) Space truss structure aerial pairing integral slide installation method
CN202324571U (en) Overhanging type double-row scaffold
CN103291076A (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
CN103635643A (en) Constructing method for concrete cylinder of construction steel bar of high-rise steel structure
CN102535845A (en) Construction method of bearing frame of corridor structure
CN106193568A (en) Mobile steel truss operating platform
CN111472530A (en) Flower basket pull rod I-shaped steel cantilever bearing frame for constructional engineering and mounting method thereof
CN206581577U (en) Using housing construction builder's jack
CN105350760B (en) A kind of construction method of suspending scaffold
CN202483154U (en) High bearing capacity suspending scaffold
CN205531399U (en) Interim support frame is installed in high -order steel truss segmentation
CN203947756U (en) Exterior wall protective frame
CN212336672U (en) I-steel overhanging bearing frame of basket pull rod for constructional engineering
CN202866261U (en) Operation hanging rack for civil construction
CN102877583B (en) High-rise and ultrahigh-rise floor system
CN203499259U (en) Tool type cantilevered unloading platform
CN204491837U (en) Suspension type high-strength steel bar lifting module
CN209011528U (en) A kind of all steel attachment type raise scaffold
CN102619335A (en) Construction method of large-height small-sized cast-in-place concrete beam slab
CN201187144Y (en) Operating platform scaffold for high altitude pouring concrete in steel column
CN205777531U (en) Floor slab construction beam string shuttering supporting equipment
CN204940916U (en) A kind of Super High Core Walls Structure emergency escape passage
CN111764623A (en) Lower hanging construction platform module of high-altitude large-cantilever steel roof truss and construction method
CN206220547U (en) A kind of operating platform for steel structure column installation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: High altitude pouring of steel column inner concrete operation platform frame

Effective date of registration: 20230901

Granted publication date: 20090408

Pledgee: Bank of China Limited Yangzhou Development Zone Branch

Pledgor: JIANGSU HUAJIAN CONSTRUCTION Co.,Ltd.

Registration number: Y2023320000457