CN101252262B - Beach stringing construction method - Google Patents

Beach stringing construction method Download PDF

Info

Publication number
CN101252262B
CN101252262B CN2008100232855A CN200810023285A CN101252262B CN 101252262 B CN101252262 B CN 101252262B CN 2008100232855 A CN2008100232855 A CN 2008100232855A CN 200810023285 A CN200810023285 A CN 200810023285A CN 101252262 B CN101252262 B CN 101252262B
Authority
CN
China
Prior art keywords
beach
line pole
hole
pole
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2008100232855A
Other languages
Chinese (zh)
Other versions
CN101252262A (en
Inventor
葛加君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wantong Construction Group Co Ltd
Original Assignee
葛加君
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 葛加君 filed Critical 葛加君
Priority to CN2008100232855A priority Critical patent/CN101252262B/en
Publication of CN101252262A publication Critical patent/CN101252262A/en
Application granted granted Critical
Publication of CN101252262B publication Critical patent/CN101252262B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a beach stringing method, including the steps of equipment transporting, pile and stake positioning, and wiring. The method is convenient and safe, and is capable of effectively solving the problems in beach stringing.

Description

Beach stringing construction method
Technical field:
The present invention relates to a kind of beach stringing method.
Background technology:
Along with global natural resources anxiety, imbalance between supply and demand aggravation, the develop shoals resource becomes the development topic of seashore neighbouring country.Yet the electric energy defective of beach becomes the bottleneck of marine beach development of resources again, and special beach stringing becomes a difficult problem in the project of transmitting and converting electricity.
Summary of the invention:
The object of the present invention is to provide a kind of convenience, safety to carry out the beach stringing construction method of beach stringing.
Technical solution of the present invention is:
A kind of beach stringing construction method is characterized in that: comprise the following steps:
(1) equipment transportation: when ebb, shelve marine railway in the shoal, with truck crane equipment is loaded and transported to marine railway, fair tide when treating its tidal bulge and descending to ebb, and by power-driven vessel traction location, equipment is stored on the platform to the pre-preceding equipment of preparing with crane lifting, and the line pole directly is placed on the intended target place, finishes equipment transportation target;
(2) pole stake location: utilize the ebb time, dig line pole pile foundation hole, finish a pile foundation hole, settle the single line pole with the spray of hydraulic giant slush pump, and place, online pole location, shelve amphibious formula car and boat;
(3) cable wiring manufacture: electric wire is carried out water-tight corrosion-proof by dressing device handle, be set on the line pole through support stand again, and insert tractor tug, and under the tractor tug traction, finish wiring stringing program by draught line.
Described dressing device comprises the container that water proof anticorrusion agent is housed, and container is provided with the hole of passing electric wire, adorns packing ring on the hole.Marine railway comprises the pipe layer, on the pipe layer froth bed is set, and bamboo grid layer is set on the froth bed.
The present invention is convenient, safety, can effectively solve the beach stringing construction problem.
Description of drawings:
The invention will be further described below in conjunction with drawings and Examples.
Fig. 1 is the configuration diagram of dressing device among the present invention.
Fig. 2 is the configuration diagram of marine railway.
Embodiment:
A kind of beach stringing construction method comprises the following steps:
(1) equipment transportation: when ebb, shelve marine railway in the shoal, with truck crane equipment is loaded and transported to marine railway, fair tide when treating its tidal bulge and descending to ebb, and by power-driven vessel traction location, equipment is stored on the platform to the pre-preceding equipment of preparing with crane lifting, and the line pole directly is placed on the intended target place, finishes equipment transportation target;
(2) pole stake location: utilize the ebb time, dig line pole pile foundation hole, finish a pile foundation hole, settle the single line pole with the spray of hydraulic giant slush pump, and place, online pole location, shelve amphibious formula car and boat;
(3) cable wiring manufacture: electric wire is carried out water-tight corrosion-proof by dressing device handle, be set on the line pole through support stand again, and insert tractor tug, and under the tractor tug traction, finish wiring stringing program by draught line.Described dressing device comprises the container 1 that water proof anticorrusion agent is housed, and container 1 is provided with the hole 2 of passing electric wire, dress packing ring 3 on the hole.Marine railway comprises pipe layer 4, and the pipe layer is made up of with plastic tube mixing colligation steel pipe, on the pipe layer froth bed 5 is set, and bamboo grid layer 6 is set on the froth bed.

Claims (3)

1. a beach stringing construction method is characterized in that: comprise the following steps:
(1) equipment transportation: when ebb, shelve marine railway in the shoal, with truck crane equipment is loaded and transported to marine railway, fair tide when treating its tidal bulge and descending to ebb, and by power-driven vessel traction location, equipment is stored on the platform to the pre-preceding equipment of preparing with crane lifting, and the line pole directly is placed on the intended target place, finishes equipment transportation target; Described intended target place is meant position, preassigned pile foundation hole;
(2) pole stake location: utilize the ebb time, dig line pole pile foundation hole, finish a pile foundation hole, settle the single line pole with the spray of hydraulic giant slush pump, and place, online pole location, shelve amphibious formula car and boat; Described pile foundation hole is the hole of settling the line pole, and place, described line pole location is meant line pole arrangement position;
(3) cable wiring manufacture: electric wire is carried out water-tight corrosion-proof by dressing device handle, be set on the line pole through support stand again, and insert tractor tug, and under the tractor tug traction, finish wiring stringing program by draught line.
2. beach stringing construction method according to claim 1 is characterized in that: described dressing device comprises the container that water proof anticorrusion agent is housed, and container is provided with the hole of passing electric wire, adorns packing ring on the hole.
3. beach stringing construction method according to claim 1 is characterized in that: marine railway comprises the pipe layer, on the pipe layer froth bed is set, and bamboo grid layer is set on the froth bed.
CN2008100232855A 2008-04-01 2008-04-01 Beach stringing construction method Expired - Fee Related CN101252262B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008100232855A CN101252262B (en) 2008-04-01 2008-04-01 Beach stringing construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008100232855A CN101252262B (en) 2008-04-01 2008-04-01 Beach stringing construction method

Publications (2)

Publication Number Publication Date
CN101252262A CN101252262A (en) 2008-08-27
CN101252262B true CN101252262B (en) 2010-06-02

Family

ID=39955498

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008100232855A Expired - Fee Related CN101252262B (en) 2008-04-01 2008-04-01 Beach stringing construction method

Country Status (1)

Country Link
CN (1) CN101252262B (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5722793A (en) * 1993-04-21 1998-03-03 Coflexip Method and device for continuously laying and burying a flexible submarine conduit

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5722793A (en) * 1993-04-21 1998-03-03 Coflexip Method and device for continuously laying and burying a flexible submarine conduit

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
JP平6-74367A 1994.03.15
JP平7-298468A 1995.11.10

Also Published As

Publication number Publication date
CN101252262A (en) 2008-08-27

Similar Documents

Publication Publication Date Title
CN106035143B (en) Integrate the semi-submersible type deep-sea culture net cage of wave energy and solar power generation
CN101538844B (en) Construction method for building large-scale offshore wind farm with depth more than 2m
CN110450916A (en) A kind of wind and wave resistance floatation type sea photovoltaic power generation platform
CN207519426U (en) A kind of cultivation work ship
CN205822138U (en) A kind of offshore wind farm floating Anti-collision fender structure
CN107044379A (en) A kind of marine self-propulsion type green energy resource electric power supply apparatus
CN103015445A (en) Transition-section-free single-pile foundation construction and fan equipment installation process for shallow sea area wind farm
CN106828812B (en) Semi-submersible type deep-sea wind-powered electricity generation mounting platform and its wind power generating set integral installation method
CN102936888A (en) Self-installation type offshore booster station structure and installation method thereof
CN103661827A (en) Installation system and construction method of wind turbine assembly in sea intertidal zone
WO2021212173A1 (en) A self-propelled floating structure and method of construction
CN109911125A (en) A kind of rolling of offshore wind power foundation steel-pipe pile takes on board method
JP2009073455A (en) New method of ocean current power generation by genbu ship
CN206635654U (en) A kind of barging device of underwater narrow-bore tunnel super long type prefabricated case beam
CN206634171U (en) Semi-submersible type deep-sea wind-powered electricity generation mounting platform
CN105604058B (en) Waters Screw Anchor construction equipment
CN104773850A (en) Eutrophication treatment system capable of improving overall oxygen-restoring performance of water area
JP2012201218A (en) Method for constructing offshore wind power generation facility
CN101252262B (en) Beach stringing construction method
CN102092645A (en) Method for arranging wind power generation equipment in shallow water of intertidal zone
CN204642094U (en) Water floated building type ship
CN204490622U (en) A kind of eutrophication control system improving the overall reoxygenation ability in waters
CN201530464U (en) Special diving barge for installing shallow water wind power generating set
CN108430863A (en) The modularization Offshore Structures component of controllable relocatable module including at least one controllable relocatable module and the method for Assembling modularization Offshore Structures
CN204642060U (en) A kind of large-scale coastal waters wind power equipment installs equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: WANTONG CONSTRUCTION GROUP CO., LTD.

Free format text: FORMER OWNER: GE JIAJUN

Effective date: 20110328

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 226400 CONSTRUCTION INDUSTRY BUREAU, NO.44, RENMIN NORTH ROAD, JUEGANG TOWN, RUDONG COUNTY, JIANGSU PROVINCE TO: 226400 NO. 7, FANGQUAN ROAD, JUEGANG TOWN, RUDONG COUNTY, JIANGSU PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20110328

Address after: 226400 No. 7 Fang Quan Road, dug Town, Rudong County, Jiangsu

Patentee after: Wantong Construction Group Co Ltd

Address before: 226400 Construction Bureau, No. 44 Renmin Road, Rudong County, Jiangsu

Patentee before: Ge Jiajun

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100602

Termination date: 20140401